B08_Attach_01_MEVE_317500___Specifications.pdf

PDF 4 MB Posted

Attached to
MEVE 317500, Replace Morefield Waterlines, Mesa Ve
Solicitation number
140P2026R0020
Issued by

About this file

This is a comprehensive project specification document for the Replace Morefield Waterlines project at Mesa Verde National Park in Colorado. The project involves designing and constructing approximately 5 miles of high-pressure water line in the Morefield housing and campground area, utilizing a combination of open trench and horizontal directional drilling (HDD) installations. The waterline replacement will include surfacing restoration, site restoration, upgrading air release valves, adding isolation valves, incorporating drainage components, and improving tank connections.

The specifications detail technical requirements for pipe materials (6-inch Spoolable Composite Pipe with 2,250 or 3,000 psi pressure ratings), installation methods, testing protocols, and environmental considerations. The project will involve complex HDD installations with lengths of approximately 1,500 and 4,500 feet, requiring precise geological navigation through varying terrain including rockfall deposits and shale bedrock. Key technical specifications include specific requirements for pipe materials, valve installations, air release valves, and comprehensive testing and disinfection procedures for the potable water system. The project is being managed by the National Park Service's Midwest Region, with construction anticipated to occur in August 2025.

View the file

Other files

File Type Posted
Attach_23_Answers_to_Questions_Amendment_02_2_12_26_0002.pdf PDF
Sol_140P2026R0020_Amd_0002.pdf PDF
Attach_20_Answers_to_Questions_Amendment_01_2_5_26_0001.pdf PDF
Attach_22_MEVE_317500_Attendance_from_Site_Visit_0001.pdf PDF
Attach_21_Boring_Profiles_0001.pdf PDF
Sol_140P2026R0020_Amd_0001.pdf PDF
B08_Attach_12_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.pdf PDF
B08_Attach_06_Solit_PSP_Cover.pdf PDF
B08_Attach_02_MEVE_317500_Geotechnical_Investigation_Report_092123.pdf PDF
B08_Attach_16_MEVE_-_31750_Morefield_Plan_C9_No_Arc.pdf PDF
B08_Attach_13_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Soliciation_140P2026R0020_revision_January_9_2026.pdf PDF
B08_Attach_03_MEVE-317500_Morefield_Plans.pdf PDF
B08_Attach_07_Solit_Construction_SF1442_REQD_RELEASED_v2_Jan2025.pdf PDF
B08_Attach_08_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Attach_05_MEVE_317500_Price_Schedule_041224_BLANK.xlsx XLSX spreadsheet
B08_Attach_19_MEVE_-_317500-Morefiled_Pland_C16.pdf PDF
B08_Attach_04_-_Wage_Determination.pdf PDF
B08_Attach_18_MEVE_-_317500-Morefiled_Pland_C14.pdf PDF
B08_Attach_10_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attach_17_MEVE_-_31750_Morefield_Plan_C30_No_Arc.pdf PDF
B08_Attach_11_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf PDF
B08_Attach_14_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD.xlsx XLSX spreadsheet
Sol_140P2026R0020.pdf PDF
B08_Attach_09_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attach_15_MEVE_-_31750_Morefield_Plan_C8_No_Arc.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MESA VERDE

NATIONAL PARK

Colorado

MOREFIELD

WATER LINE REPLACEMENT

MEVE

PMIS NO. 317500

PROJECT SPECIFICATIONS

(Construction Documents)

NATIONAL PARK SERVICE

MIDWEST REGION

August 2025

THIS PAGE INTENTIONALLY LEFT BLANK

MEVE - 317500 00 01 10 - 1

Table of Contents

TABLE OF CONTENTS

DIVISION 00 — PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 - SEALS AND SIGNATURES

DIVISION 01 — GENERAL REQUIREMENTS

01 11 00 - SUMMARY OF WORK

01 26 01 - CONTRACT MODIFICATION PROCEDURES

01 27 00 - DEFINITION OF CONTRACT LINE ITEMS

01 31 00 - PROJECT MANAGEMENT AND COORDINATION

01 32 16 - CONSTRUCTION SCHEDULE

01 33 23 - SUBMITTAL PROCEDURES

01 35 05 - ENVIRONMENTAL PROTECTION AND SPECIAL CONTROLS

01 35 13.22 - ARCHEOLOGICAL PROTECTION

01 35 23 - SAFETY REQUIREMENTS

01 40 00 - QUALITY REQUIREMENTS

01 50 00 - TEMPORARY FACILITIES AND CONTROLS

01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION

01 67 00 - PRODUCT REQUIREMENTS

01 73 20 - OPENINGS AND PENETRATIONS IN CONSTRUCTION

01 73 29 - CUTTING AND PATCHING

01 73 40 - EXECUTION

01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 - CLOSEOUT PROCEDURES

01 78 23 - OPERATION AND MAINTENANCE DATA

01 79 00 - DEMONSTRATION AND TRAINING

DIVISION 02 — EXISTING CONDITIONS

02 41 00 - DEMOLITION

DIVISION 31 — EARTHWORK

31 10 00 - SITE CLEARING

31 23 17 - ROCK EXCAVATION

31 23 33 - TRENCHING, BACKFILLING, AND COMPACTING FOR UTILITIES

31 37 00 - RIPRAP

DIVISION 32 — EXTERIOR IMPROVEMENTS

32 12 16 - ASPHALTIC CONCRETE VEHICULAR PAVING

32 91 13 - TOPSOILING AND FINISHED GRADING

32 92 00 - SEEDING, SODDING AND LANDSCAPING

DIVISION 33 — UTILITIES

33 05 07 - HORIZONTAL DIRECTIONAL DRILLING

33 05 15 - PRECAST CONCRETE UTILITY STRUCTURES

33 11 13 - WATER MAIN CONSTRUCTION

MEVE - 317500 00 01 10 - 2

Table of Contents

33 12 19 - FIRE HYDRANT

DIVISION 40 — PROCESS INTERCONNECTIONS

40 05 00 - PIPE AND PIPE FITTINGS - BASIC REQUIREMENTS

40 05 28 - PIPE - SPOOLABLE COMPOSITE

40 05 51 - VALVES - BASIC REQUIREMENTS

40 05 52 - MISCELLANEOUS VALVES

40 05 61 - GATE VALVES

D I V I S I O N 0 0

PROCUREMENT AND CONTRACTING

REQUIREMENTS

MEVE - 317500 00 01 07 - 1

SEALS AND SIGNATURES

00 01 07 - SEALS AND SIGNATURES

Owner Name: National Park Service

Facility or Site Name: Mesa Verde National Park

Project Name: Morefield Water Line

Project or Contract Designation: PMIS No. 317500

Engineer: HDR

Brandon W. Luster, PE

License No. 41014

The seal and signature to the left applies to the all

Specifications divisions and sections of this project manual.

Engineer’s seal and signature does not apply to the documents that comprise Division 00, Bidding and

Contracting Requirements.

It is a violation of applicable laws and regulations governing professional licensing and registration for any person, unless acting under the direction of the licensed and registered design professional(s) indicated above, to alter in any way the Specifications in this project manual.

END OF SEALS AND SIGNATURES

D I V I S I O N 0 1

GENERAL REQUIREMENTS

MEVE - 317500 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Contractor Use of Site

4. Public Use of Site

5. Conduct of Operations

6. Work Restrictions

7. Special Construction Requirements

8. Soils Investigation Report

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: This project is located at Mesa Verde National Park in Cortez, Colorado.

Main project areas include the Morefield housing area/campground.

B. The Work consists of: This project will include the design and construction of 5 miles of high-pressure water line at the Morefield area. Waterline replacement will be accomplished with a combination of open trench and horizontal directional drilling (HDD) installations. Replace-ment will include surfacing restoration, site restoration, upgrading air release valves, additional isolation valves, incorporating drains at low points in alignments, tank connections, drainage culvert repairs, drainage crossing upgrades, temporary construction access road improvements.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in a minimum of 1 phase for work Morefield area. The contractor shall provide a proposed phasing plan to NPS as a submittal. The project will be considered one project in regards to substantial completion with all work in the Morefield area needing to be substantially complete before NPS will consider the project substantially complete.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb por-tions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to Construction limits indicated on the draw-ings.

MEVE - 317500 01 11 00 - 2

B. Storage of Materials: Confine storage of materials to staging areas shown on the plans and con-firmed with NPS.

C. Parking: Confine parking to designated locations within the construction limits.

D. Stockpiling: Confine stockpiling to staging areas shown on the plans and approved by NPS

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or stor-age of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp: Establishment of a camp within park will not be permitted.

H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load re-strictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. There is a parkwide load restriction on park roads of 20,000 lb/axle.

I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and cal-endar restrictions as outlined.

1.5 PUBLIC USE OF SITE

A. Morefield alignment is mostly out of the publicly used areas of the park. When the boring is occurring for the upper segment the contractor shall have an approved traffic control plan in place prior to beginning work.

MEVE - 317500 01 11 00 - 3

1.6 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and reg-ulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit re-quests 2 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construc-tion site or within the park unless approved by the Contracting Officer.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend & Holiday Hours: 7 a.m. to 5 p.m. Contractor must submit a request in writing a minimum of 48 hours in advance of weekend work and request must be approved by the CO prior to working.

2. Early Morning Hours: Confirm any restrictions with the CO prior to construction.

3. Hours for loud construction activities: Confirm requirements with the CO prior to con-struction.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Govern-ment or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permis-sion.

3. Hours and length of Utility Shutdowns: Shutdowns of the Morefield line for cross over connections between the existing and new system shall be coordinated with the park for exact timing and be a maximum of 10 hrs at a time. Off peak (October to April) shut-downs for up to 5 days will be allowed with advance coordination with Park staff.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes.

MEVE - 317500 01 11 00 - 4

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the Construction Management Representa-tive (CMR) will be used for purposes of managing communication and documents during con-struction stage.

1.9 SOILS INVESTIGATION REPORT

A. The report Geotechnical Investigation Report by Lithos Engineering is included with this pack-age.

B. In case of conflict between report and drawings or specifications, the drawings and specifica-tions govern.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 11 00

MEVE - 317500 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

MEVE - 317500 01 26 01 - 2

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General

Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

MEVE - 317500 01 26 01 - 3

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project. Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A.

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for

Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

MEVE - 317500 01 26 01 - 4

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe

Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a

Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|

MEVE - 317500 01 26 01 - 5

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense

Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army

Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit………………10.00%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above).

It is the responsibility of the partners to decide on division of revenue.

MEVE - 317500 01 26 01 - 6

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

MEVE - 317500 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

C. All Contract line items will be considered as one in determining substantial completion and start of warranty period.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1 - Replace Morefield Waterline

1. This item consists of construction of the new Morefield water lines using NPS standards.

Major components include new water lines with both open trench and horizontal directional drilling (HDD) installations, replacement of valves, roadway resurfacing, erosion control, and drainage improvements.

2. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

MEVE - 317500 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on

Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 35 05 “Environmental Protection and Special Controls” for coordinating environmental requirements of the Contract.

3. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

4. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

5. Section 01 79 00 “Demonstration and Training” for coordinating training requirements for Government staff on new equipment.

1.2 DEFINITIONS

A. Authority Having Jurisdiction

B. Construction Permits – Contractor Provided

C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

MEVE - 317500 01 31 00 - 2

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Refer to 01 40 00 “Quality Requirements”.

2. Provide Method of Procedure for all outages and coordination with NPS; provide step-by-step procedure, timelines, and critical involvement required by Contractor and NPS.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base

Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

MEVE - 317500 01 31 00 - 3

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).

3. Number of Copies: Submit 2 opaque copies of each submittal. Contracting Officer (CO) will return 1 copy.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Sections.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Review: Contracting Officer (CO) will review coordination drawings to confirm that the

Work is being coordinated, but not for the details of the coordination, which are

Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform

Contractor, who shall make changes as directed and resubmit.

2. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Preparation Format: AutoCad.dwg, Version 2018, operating in Microsoft Windows operating system, also provide GIS shapefiles of any proposed work that may affect work limits or boundaries

3. File Submittal Format: Submit or post coordination drawing files using Portable

Document Format (PDF) file format.

4. Contracting Officer (CO) will furnish Contractor one set of digital data files

(AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer (CO) will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

MEVE - 317500 01 31 00 - 4

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (UPPP).

11. Contractors Commissioning Plan.

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

E. All items listed must be provided to the CO before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction

Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the

CO will consider other contractual remedies. Work shall not commence until written Notice to

Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIS)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

MEVE - 317500 01 31 00 - 5

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the project website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select

“CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of CO's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the

Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT WEB SITE

A. Use the Project website for communication throughout the contract period. The Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

MEVE - 317500 01 31 00 - 6

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not suitable to be shared using the Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the Project website and shall be coordinated with the Project team as appropriate.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, CO will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. Project website.

17. Acceptance/rejection of work.

18. Progress meetings.

19. Submittal procedures.

20. Environmental requirements.

21. Permit requirements.

22. As-constructed drawings/operation and maintenance (O&M) manuals.

23. Saturday, Sunday, holiday and night work.

24. Reference materials.

25. Value engineering.

26. Schedule of Values.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

MEVE - 317500 01 31 00 - 7

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, 3-phase Inspections, Accessibility, etc.).

g. Inspections of work in progress and projected Special inspections.

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

l. Review and Mitigation of Project Risks.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of agency(ies) with jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

MEVE - 317500 01 31 00 - 8

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the

Work and reconvene the conference at earliest feasible date.

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the

Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).

d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Noise & Acoustics Management.

4. Temporary Storm Water Pollution Prevention Environmental Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

MEVE - 317500 01 31 00 - 9

4. Pollution Prevention (P2) practices: Submit evidence of participation in P2 programs illustrating familiarity with P2 practices.

5. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of CO.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved WMP, IAQ Management Plan, SWPPP and EA..

1.9 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the

Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The

Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, the Contractor will not be considered an agent of the

Government. Therefore, the Contractor will comply with the appropriate Federal, State and local laws.

B. Government Furnished Permits: During the development of the project’s design the permits listed below were negotiated and agreed to by the Government. The terms and provisions of these permits shall be adhered to for the duration specified in each permit. Contractor shall comply with terms of permits.

1. Clean Water Act Section 404 with Rivers and Harbors Act Section 10, Structures or

Work in or Affecting Navigable Waters permit from the U.S. Army Corps of Engineers

C. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits will be required for the contract’s chosen means and methods. The list shall not be considered complete, as it is the responsibility of the contractor to determine means and methods, and obtain the required permits. It is the responsibility of the Contractor to obtain all permits required to legally conduct the work.

1. Over-An-Acre Pollution Prevention Permit – CDPHE Construction Activity General

Permit (CGP) for Stormwater with accompanying SWPPP.

2. Oversize/Overweight Transportation Permit – CDOT Oversize/Overweight Permit.

3. Montezuma County – Utility Permit in County ROW

D. Coordination with Agency with Jurisdiction Issuing Permits:

1. Coordination: Contact the Agency with Jurisdiction as needed sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

E. Administrative Procedures:

MEVE - 317500 01 31 00 - 10

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency with Jurisdiction issuing permits, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.

2. Supply all needed information to Agency with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.

3. Upload permits to the project website or other means as directed by the Contracting

Officer when the permits are obtained.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 31 00

MEVE - 317500 01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The

Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. Critical Path Method (CPM): Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships.

Network calculations determine when activities can be performed and the critical path of

Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the

Contractor, but is jointly owned.

MEVE - 317500 01 32 16 - 2

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be posted on the NPS DSC

SharePoint project website, provided in the native electronic file format. It is the intent of the

Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference, submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule. Schedule and Sequencing plans must be submitted by the contractor for approval by the CO a minimum of 2 weeks prior to the Pre-Construction Meeting.

D. CPM Reports: Concurrent with CPM schedule, submit 3 paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or…

This is the start of the file's text. The full file is on GovTribe.