This is a Questions and Answers document for federal contract opportunity 140P2026R0020, Amendment 01/2.5.26, for MEVE 317500, Replace Morefield Waterlines. The document contains 89 official responses to contractor inquiries regarding proposal submission requirements, technical specifications, and project execution details.

Proposal and Administrative Requirements: Offerors must submit one electronic copy of each volume. Previously completed Past Performance Questionnaires are acceptable. Subcontractor Reference forms and a preprinted form for Key Personnel Resumes are not required. The Hazardous Materials Identification Listing form is not required. The Limit on Subcontracting form (B08_Attach_14) is required. The Schedule of Values must be submitted for the single line item with major work components including general requirements, site work, utilities, structural and building systems, interior and exterior construction, and project closeout. Both page 9 of the RFP and Attachment 05 (Excel price schedule) must be completed. The Quality Control Manager may dual-hat as the Site Safety and Health Officer, while the Superintendent must remain independent. Safety requirements are excluded from the five-page Management Approach limit. Key trades must be relevant to scope; Mason, Mechanical Services, and Electrical Services should be omitted if not applicable.

Technical and Project Execution Requirements: This is a firm fixed price contract with no quantity overruns eligible for equitable adjustment. The 4,500-foot HDD segment designated to avoid sensitive cultural resources must remain directionally drilled; open-cut areas may be changed to directional drilling with technical approach documentation. Contractor-furnished work includes temporary access roads, trench shoring, dewatering, utility potholing, and spoil disposal to legal off-site areas. HDD plan and profile submittals require approval before drilling operations; contingency plans addressing inadvertent returns, drilling fluid loss, obstructions, and subsurface conditions are required. Flexible Steel pipe with 2,250 and 3,000 PSI ratings and NSF 61 liners are specified; Vent-O-Mat RBX air release valves rated to 750 PSI are acceptable. Silt fencing (not soil berms) is required per stormwater pollution prevention specifications. The existing 6-inch stainless steel pipe is Schedule 80 (some Schedule 40); approximately 270 linear feet of carrier pipe casing is required in rockfall deposit areas with centralizers mandated. Pressure testing is required pre and post pullback per specifications 40 05 28, 40 05 00, 33 05 07, and 33 11 13. Trench backfill compaction must achieve 95% under surfacing and 85% under natural areas, tested minimum once every 500 linear feet at 2-foot vertical intervals starting 6 inches above pipe to finish subgrade. The Notice to Proceed is anticipated March 1, 2026, with proposal due date extended to February 26, 2026. The project budget is estimated at $5 million to $10 million, with funding confirmed available.

View the file

Other files

File Type Posted
Attach_23_Answers_to_Questions_Amendment_02_2_12_26_0002.pdf PDF
Sol_140P2026R0020_Amd_0002.pdf PDF
Attach_22_MEVE_317500_Attendance_from_Site_Visit_0001.pdf PDF
Attach_21_Boring_Profiles_0001.pdf PDF
Sol_140P2026R0020_Amd_0001.pdf PDF
B08_Attach_12_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.pdf PDF
B08_Attach_06_Solit_PSP_Cover.pdf PDF
B08_Attach_02_MEVE_317500_Geotechnical_Investigation_Report_092123.pdf PDF
B08_Attach_16_MEVE_-_31750_Morefield_Plan_C9_No_Arc.pdf PDF
B08_Attach_13_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Soliciation_140P2026R0020_revision_January_9_2026.pdf PDF
B08_Attach_03_MEVE-317500_Morefield_Plans.pdf PDF
B08_Attach_07_Solit_Construction_SF1442_REQD_RELEASED_v2_Jan2025.pdf PDF
B08_Attach_08_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Attach_05_MEVE_317500_Price_Schedule_041224_BLANK.xlsx XLSX spreadsheet
B08_Attach_19_MEVE_-_317500-Morefiled_Pland_C16.pdf PDF
B08_Attach_04_-_Wage_Determination.pdf PDF
B08_Attach_18_MEVE_-_317500-Morefiled_Pland_C14.pdf PDF
B08_Attach_10_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attach_17_MEVE_-_31750_Morefield_Plan_C30_No_Arc.pdf PDF
B08_Attach_11_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf PDF
B08_Attach_14_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD.xlsx XLSX spreadsheet
Sol_140P2026R0020.pdf PDF
B08_Attach_01_MEVE_317500___Specifications.pdf PDF
B08_Attach_09_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attach_15_MEVE_-_31750_Morefield_Plan_C8_No_Arc.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2026R0020 / Amendment 01/2.5.26

MEVE 317500, Replace Morefield Waterlines

Question No.

Sheet or

Reference Question Official Response - DSC

SF1442 block 13a states “Original and 1 copies”; however, Section L, paragraphs E.1. and F.1. state, “Submit (1) one electronic copy.” Please confirm that only one electronic copy of each volume is required.

This is confirmation that only one electronic copy of each volume is required.

Section L, Volume I, Factor 6 requires offerors to submit a Past Performance Questionnaire (PPQ) or a CPARS evaluation report. Can offerors submit a previously completed PPQ rather than requesting that a reference complete new PPQ form? This will help reduce the burden on references by requiring them to complete a separate, distinct PPQ form for each procurement effort.

A previously submitted Past Performance Questionnaire can be submitted.

Solicitation Attachment “B08_Attach_06_Solit_PSP_Cover” includes a reference to “2.

Subcontractor Reference” within the Technical Volume I. While contractors are required to identify Key Trades for Mason, Mechanical Services and Electrical Services, there are no requirements to provide reference or experience for subcontractors. Can the government please confirm that Subcontractor Reference forms are not required to be completed as part of the proposal response?

This is confirmation that Subcontractor Reference forms are not required.

Solicitation Attachment “B08_Attach_06_Solit_PSP_Cover” includes a reference to “3. Key Personnel Qualifications” within the Technical Volume I. However, Section L, Volume I, Factor 5 – Key Personnel Experience states, “There is no preprinted form for this submittal.”

Can the government please confirm that this form is not required to be used for key personnel resumes?

This is confirmation that there is no required form for Key Personnel Resumes.

Solicitation Attachment “B08_Attach_06_Solit_PSP_Cover” includes a reference to “5.

Hazardous Materials Identification Listing” within the Business and Price Volume II.

However, these forms were not issued on SAM.gov. Can the government please confirm that this form is not required to be completed as part of the proposal response?

This is confirmation that Hazardous Materials Identification Listing form is not required.

Solicitation Attachment “B08_Attach_12_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25” was provided on SAM.gov, but there are no instructions included in Sections L and M directing offerors to complete this form with the proposal submission. Can the government please confirm that this form is not required to be completed as part of the proposal response?

This form is requitred if any proposed equals for products are included in the propsal.

Solicitation Attachment “B08_Attach_14_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD“ was provided on SAM.gov, but there are no instructions included in Sections L and M directing offerors to complete and return this form with the proposal submission. Can the government please confirm that this form is not required to be completed as part of the proposal response?

B08_Attach_14_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD is required as part of the proposal response.

Question No.

Sheet or

Reference Question Official Response - DSC

Section H Special Requirement 3: Key Personnel identifies four key personnel positions, including Job Site Superintendent, Job Site Quality Control Manager and Job Site Safety Manager. Furthermore, Section L, Volume I, Factor 5 – Key Personnel Experience, identifies that key personnel resumes be provided for the Superintendent, On-site Quality Control Specialist and On-site Safety Specialist positions. Is it acceptable for the Safety Manager/Specialist role to be dual-hatted with either the Quality Control Manager/Specialist or the Superintendent?

Yes, QCM may also act as SSHO. Superintendent shall only perform superintendence of the project.

Section B, RFP page 9 of 84, provides a Bid Schedule for this project. Within the instructions on page 9, the RFP states, “Please complete Attachment XX Contract Price Schedule (include this sentence if not using table below).” Although not referenced in this statement, a separate Excel file (Attachment 05) was also provided with the Bid Schedule. Furthermore, Section L, Volume II states, “SECTION B CONTRACT PRICE SCHEDULE or ATTACHMENT X CONTRACT PRICE SCHEDULE.” Can the government please clarify if offerors should complete page 9 of the RFP or the separate Excel attachment?

Complete page 9 of the RFP and attachement 05 (B08_Attach 05_MEVE 317500 Price Schedule

041224 BLANK).

Section L, RFP page 81 of 84, Other Submittals, states, “Include the following submittals not related to any evaluation factors in Volume I.” Can the government please clarify if any additional submittals are required to be included within this section of an offeror’s response?

No additional submittals are required.

Section L, Volume II, Section B Contract Price Schedule instructions state, “Also provide a separate Schedule of Values (SOV) for each line item in the Section B Contract Price Schedule.” Since there is only one CLIN, is a SOV still required to be submitted?

Yes, the SOV is required for the single line item.

12 Is there any possiblity of splitting the 4400ft bore into two segments?

See 33 05 07 - 1.1(a)(2) Unlikely. The 4500 HDD segmenet was selected and engineered to avoid sensative cultural and natural resources. Contractor shall follow section 33 05 07 for guidance and required submittals in 33 05 07 (1.9)(C)(a).

Factor 3 Management Approach is limited to 5 pages yet establishes requirements for four distinct areas, including Capacity, Roles and Responsibilities, Risk Mitigation and Safety.

The response to the Safety requirement alone will exceed 5 pages since it requires an overview of the Company Safety Program, a resume for the Project Safety Manager, a copy of OSHA Logs for the past three calendar years and a statement from the insurance company with the current Experience Modification Rate (EMR). Can the government respectfully consider excluding the safety requirements from the 5-page limit specified for Factor 3 Management Approach?

Yes. Safety will be excluded from the 5 page requirement.

RFP page 81 of 84, Volume II, 3. Contents, Section B states, “Also provide a separate Schedule of Values (SOV) for each line item in the Section B Contract Price Schedule.” As there is only one line item on the bid schedule, are the major work components’ breakdown on the SOV to equal the single CLIN’s lump sum total?

Yes.

Reference Question Official Response - DSC

RFP page 81 of 84, Volume II, 3. Contents, Section B states, “Also provide a separate Schedule of Values (SOV) for each line item in the Section B Contract Price Schedule. Each SOV shall show the line-item price broken down by major work components.” Can the government please clarify what major work components offerors are required to submit in the

SOV?

Major work components should include general requirements, site work, utilities, structural and building systems, interior and exterior construction, and project closeout.

Attachment 1: Section 33 05 07, Horizontal Directional Drilling, para 1.8 Qualifications, sets forth experience requirements (excerpt below). The required information in this specification section does not align with the Section L requirements established in Factor 4 – Project Experience and Factor 6 Past Performance. Factor 4 does not require offerors to submit “Project Experience” forms for the key trades. Furthermore, Section H, Key Trades, does not include horizontal directional drilling (HDD). Can the government please confirm that offerors are not required to address the HDD project experience requirements outlined in Section 33 05 07, Horizontal Directional Drilling, para 1.8 Qualifications in the proposal response?

Section 33 05 07, Horizontal Directional Drilling, para 1.8 excerpt: 1. List of previously completed projects in which the Contractor has completed at least three (3) installations of at least 6-inch nominal diameter plastic pipes (high density polyethylene (HDPE), Fusible PVC, or Flex Steel) with a minimum length of 2,000 feet each within the past 3 years. One of these projects must be at least 4,000 feet in length. One of these projects must include an entry to exit elevation differential of at least 500 feet in which Drilling Fluids were successfully maintained within the Borehole without Inadvertent Returns. Include project name, length, diameter, pipe material, and soil conditions for the drill; and two project references, with project descriptions, and current name and phone number for the references; the project budget; and the project owner. Qualifying projects must have been completed by the Contractor.

Section 33 05 07 is not a preaward requirement, section 33 05 07 is a contract requirement.

Reference section L of the soliciation for technical proposal.

Attachment 1: Section 33 05 07, Horizontal Directional Drilling (HDD), para 1.8 Qualifications, sets forth requirements for names and experience resumes for key field personnel. Included within these requirements are a Driller, a Superintendent, Tracking System personnel, Drilling Fluid control personnel, and a Fusion Technician. However, Section L, Factor 5 – Key Personnel Experience, does not require offerors to submit qualifications for HDD personnel. Can the government please confirm that offerors are not required to submit resumes for the HDD key field personnel identified in Section 33 05 07, Horizontal Directional Drilling (HDD), para 1.8 Qualifications in the proposal response?

Section 33 05 07 is not a preaward requirement, section 33 05 07 is a contract requirement.

Reference section L of the soliciation for technical proposal.

Can you please provide additional details regarding the fencing requirements? The plans reference both silt fencing and hog-wire–type fencing, and I’d like to confirm the intent for each. Specifically, which areas require silt fencing versus hog-wire fencing, and are there any installation details or limits we should be aware of?

Reference 01 57 23 - Temporary Stormwater Pollution prevention. Contractor responsible for stormwater pollution prevention. Plans indicate locations for silt fence. Silt fence details are provided for incorporation into the SWPPP. Contractor is responsible for determining BMP method per 01 57 23 (2.1)(a)

Instead of installing silt fencing, could the contractor construct soil berms for erosion and sediment control?

No.

Lump Sum Quantity Risk Please confirm whether the lump-sum contract requires the Contractor to assume full quantity risk for trenching, HDD, rock excavation, and restoration, or if quantity overruns may be eligible for equitable adjustment.

Project is a firm fixed price contract.

Reference Question Official Response - DSC

Installation Method Flexibility Are the delineated limits of open trench versus HDD installation prescriptive, or may the Contractor adjust installation methods based on field conditions with approval and without penalty?

Areas delinated to be directionally drilled shall remain directionally drilled due to sensative cultural resources. Areas deliniated as open cut may be changed to directional drilling. Any planned changes to the open vs. HDD shall be communicated in the technical approach section of the proposal.

Temporary Access Roads Please confirm whether temporary access road construction, maintenance, and final restoration are included in the base bid scope or addressed separately.

Project is firm fixed price contract. All work shall be priced in accordance with the contarct line item scheudle provided. All work required to sucessfully complete the project shall be considered base bid.

Internal Phasing Will the Owner allow internal phasing of work (installation, testing, restoration) provided overall project milestones are maintained?

Yes. See 01 11 00.

Seasonal / Visitor Restrictions Are there additional seasonal, visitor-related, or park-specific restrictions not listed in the specifications that may limit construction operations?

Restrictions are referenced in division 01.

Note: The main park road (mesa top ruins road) is maintained during the winter by NPS. access may be limited after snow accumulation while NPS road crews clear snow. Roads to morefield camp ground and tank are not regularly maintained, access and maintenance can be coordinated through park during construction. "offroad" sections of the 4x4 trail and switch backs will not be maintained by NPS and are not recommended for travel during winter due potential for natural and cultural resource damage. All requests for access to inaccessable areas will be evaluated and considered on a case by case basis prioritizing preservation of natural and cultural resources.

Quality Control and material testing:

Will subcontractor be required to provide QAQC services?

Quality control requirements are presented under 01 40 00. Consult specification for specific inspection and third party testing requirements.

Bill of materials Will a BOM be issued prior to bid due date?

No.

Extended & Weekend Work If required to maintain schedule, will weekend or extended-hour work be permitted with prior approval? Who will be responsible for notifying the Park Superintendent if extended work hours are required?

Subject to park and contracting officer approval. See 01 11 00 (1.7). Contractor responsibilities are identified in 01 11 00.

Haul Routes & Load Limits Beyond the stated 20,000 lb/axle restriction, are there additional haul route limitations or delivery restrictions that bidders should account for? This also applies to bridge restrictions.

Will you please provide the rules and regulations that can be obtained from the office of the park superintendent?

follow state DOT and Federal Highways permitting requirements. Axle load is limited to 20k per axle to prevent road damage. If oversized loads are needed, submit permit and haul plan to COR for approval.

EXCAVATION, TRENCHING & ROCK

Rock Excavation Risk Are estimated quantities or alignment segments subject to rock excavation available for bidder reference, and will differing site conditions related to rock be considered for adjustment?

Two Geotechnical Reports were completed with the following dates 01-28-22 and 09-21-23.

Estimated quantities will not be provided. Contract is firm fixed price.

Shoring & Dewatering Please confirm that all trench shoring, dewatering, and excavation safety systems are considered Contractor means and methods with no separate pay item.

Project is firm fixed price contract. All work shall be priced in accordance with the contarct line item scheudle provided. All work required to sucessfully complete the project shall be considered base bid.

Reference Question Official Response - DSC

Spoil Disposal Will spoil disposal areas be designated by NPS, or is hauling and disposal entirely Contractor-furnished?

Dispose in a legal off site disposal area per 01 74 19 and 33 05 07

HORIZONTAL DIRECTIONAL DRILLING (HDD)

HDD Alignment Criteria Are HDD profiles, depths, and entry/exit points shown on the drawings conceptual or mandatory? May Contractors propose alternate profiles that meet performance requirements?

see 33 05 07.

The HDD plan and profile provided in the Construction Drawings shall be reviewed and confirmation shall be provided that the HDD plan and profile can be reasonably constructed with the Contractor proposed means and methods within the tolerances specified

HDD Alignment Criteria The longer HDD has multiple PIs throughout, making the drawn alignments not constructable.

Can the alignment be moved to accommodate a “drillable” curve?

see 33 05 07.

The HDD plan and profile provided in the Construction Drawings shall be reviewed and confirmation shall be provided that the HDD plan and profile can be reasonably constructed with the Contractor proposed means and methods within the tolerances specified

HDD Alignment Criteria What (if any) are the lessons learned from previous installations of HDD?

see 33 05 07.

The HDD plan and profile provided in the Construction Drawings shall be reviewed and confirmation shall be provided that the HDD plan and profile can be reasonably constructed with the Contractor proposed means and methods within the tolerances specified herein

HDD Alignment Criteria Are there any restrictions on the product pipe, for these longer line pulls? Will it need to be coupled in the bore?

Reference 33 05 07 (2.2) Carrier Pipe: Carrier Pipe shall be as shown on the Drawings and shall be specifically capable of installation by HDD method. Increase the thickness the Carrier Pipe or grade of pipe material at the Contractors discretion and sole expense.

Contractor shall confirm coupling requirements with pipe supplier and manufacturer per the specifications 33 05 07 and 40 05 28.

HDD Alignment Criteria What size casing will be required and how much? If so, Will Centralizers be required for the carrier pipe?

Reference 33 05 07 (2.2) Carrier Pipe: Carrier Pipe shall be as shown on the Drawings and shall be specifically capable of installation by HDD method. Increase the thickness the Carrier Pipe or grade of pipe material at the Contractors discretion and sole expense.

Carrier pipe will be required through rockfall deposits in the HDD installations. Known areas include approximately 270 LF at the upper end of the long HDD segment up the mesa. Sizing and grade shall be proposed by the contractor and submitted for review/approval. Centralizers will be required for any carrier pipe installations.

HDD Alignment Criteria Will an engineered design and bore profile need to be approved prior to any drilling operations?

Yes, submittal requirements are detailed in 33 05 07 1.8.A & 1.9.A.

HDD Alignment Criteria Will bore sections require a pressure test pre and post pullback?

Yes per specifications 40 05 28, 40 05 00, 33 05 07, and 33 11 13.

HDD Alignment Criteria Will tree clearing be allowed at HDD TUA?

vegetation may be cleared in the areas delinated as limites of disturbance. Tree removal shall be approved by NPS prior to removal.

Reference Question Official Response - DSC

HDD Alignment Criteria Will hydrovac services be required full time during drilling operations?

Reference 33 05 07

HDD Refusal / Frac-Out In the event of HDD refusal or inadvertent returns, will alternate installation methods be treated as a change in scope?

Reference 33 05 07 and 01 26 01

11. Contingency plans for the following scenarios are required and shall include, measures that will be taken to minimize probability of the below scenarios, observations that may indicate the presence of the scenario occurring, and possible actions that may be taken in the event the scenario occurs:

a. Procedures, Drilling Fluids, or tooling considering the subsurface conditions identified in the Geotechnical Investigation Report including materials ranging from rockfall deposits with large sandstone boulders to shale bedrock.

b. Inadvertent Fluid Return (IR). The plan shall specifically address methods and procedures to minimize the possibility of an IR. The plan shall also address how drilling fluids will be contained in the event of an IR.

c. Loss of Drilling Fluid circulation

d. Obstruction encountered during Pilot Bore drilling or Reaming

e. Difficulty removing spoil from lower elevation conductor casing

f. Broken drill pipe

g. Broken Carrier Pipe during Carrier Pipe positioning or Pullback

h. Carrier Pipe stoppage during pipe pull back due to Borehole collapse.

i. Utility strike or damage to an existing utility

j. Line or grade outside specified tolerances

k. Unforeseen subsurface conditions.

HDD

What is the largest annular space allowable for the HDD sections?

Reference 33 05 07 - Contractor responsible for annular sizing to manange drilling fluid, pressures, torque, etc. Reference minimum pilot/ drill ratio in section 2.1

UTILITIES, SHUTDOWNS & TIE-INS

Fire Hydrants and ARV’s In the specifications it references Fire Hydrants and ARV’s, after reviewing the alignment sheets, there are only isolation valves with drains on this line. Where are the Fire Hydrants and ARV’s located in reference to the line?

Follow Morefield Plans. Combination air release and vacuum release valves exist on the alighnment.

Specification on existing stainless steel What is the size/ spec on the existing Stainless-steel pipe we are to connect Flex steel to?

Existing Stainless Steel Pipe is 6" Diameter Schedule 80. Some locations may also be 6" Schedule 40.

Existing line Will the existing line that need to be removed prior to the new line installation?

See Sheet G1 Note 5.

Shutdown Execution Will night work be permitted to execute tie-ins within the allowable shutdown durations specified in the contract?

Subject to park and contracting officer approval in emergency situations See 01 11 00 (1.7).

Contractor responsibilities are identified in 01 11 00. Night work may be denied due to neighborhood impacts, natural/ cultural compliance, nps staffing or other factors.

Temporary Water Service Are temporary bypass pumping or water supply systems during shutdowns Contractor-furnished, or will these be provided by the Owner? Is there an expectation that there will be utility interruptions during this project? If there will be interruptions that affect the government employees and visitors, who will be responsible for temporary utilities to be provided during shutdowns?

Temporary utility interruptions are acceptable provided they are communicated to the park and COR in accordance with 01 11 (1.7)(c). System capacity for outages varies by time and date. at the time of requrest, the COR will provide the contractor with the available water capacity and usage rates/ restrictions that may be inacted. Any outages that exceed the limitations set by the park will be the contractor's responsibility to resolve.

Reference Question Official Response - DSC

Utility Potholing Please clarify the extent of exploratory potholing required prior to excavation and whether this work is included in the base bid.

Project is firm fixed price contract. All work shall be priced in accordance with the contarct line item scheudle provided. All work required to sucessfully complete the project shall be considered base bid.

ENVIRONMENTAL, WILDLIFE & ARCHAEOLOGICAL COMPLIANCE

Dust Control Will a full time dust control operation need to be incorporated into estimate?

Reference 01 35 05.

Professional Arborist Will the removal of 8” Diameter trees need to be replaced with two 4” diameter trees? How will we need to quantify this in our proposal?

Confine construction activities to limits of disturbance. All vegetation removal shall be approved by the Contracting Officer prior to removal. Tree and shrub disturbances shall be minimized to the greatest extent possible. Replanting of any removed trees/ shrubs is not required provided the requirements set within the specificiation and this reponse are met.

Monitoring Requirements Will full-time environmental and/or archaeological monitoring be required during excavation or HDD activities?

See 01 31 00 (1.8)(a)

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

Archaeological Monitoring will be provided by the government per 01 35 13.22

Archaeological Work Stoppage If work is suspended due to unanticipated archaeological discoveries, will standby costs for labor and equipment be compensable?

Refer to 01 26 01 and FAR 52.236 and FAR 52.242 IF work is suspended for any reason, consult FAR 52.242.

RESTORATION, TESTING & ACCEPTANCE

Restoration Standards Must restoration standard match existing conditions or comply with new standards indicated in the contract documents?

see 32 92 00.

Pressure Testing Please clarify if the existing segments that are tying into the flexsteel will be need to be pressure tested? This also includes the Isolations valve stations.

see 40 05 00 (3.4)

Pressure Testing Will the water used for the hydrotest be able to stay in the line or will it need to be disposed and hauled off?

see 40 05 00 (3.5)

Acceptance Criteria Please provide acceptance criteria for trench compaction, pavement restoration, and final surface tolerances.

Trench Backfill shall be compacted to 95% under surfacing and 85% under natural areas per Specification 312333,3.5.B. Contractors testing firm shall test the trench backfill at minimum once every 500LF, starting 6” above the pipe test every 2’ vertically up to finish subgrade elevation, minimum of 3 tests every 500 LF. Additional testing may be required by the COR if operations do not appear to be consistent or if there are failing tests. Pavement restoration is per specification

Reference Question Official Response - DSC

The specifications call out for the spoolable composite pipe and associated fittings to be rated to 2,500 PSI and 3,000 PSI with an NSF 61 rated inner liner. After speaking with manufacturers it does not appear that this is possible in a 6" diameter pipe. Also, no NSF 61 rated air valves appear to meet this pressure requirement either. Can you please confirm the pressure rating on this project and provide a list of approved manufacturers for the pipe and fittings?

We know FlexSteel has 6" pipe meeting all the requirements for both 2,250 psi and 3,000 psi composite pipe. Vent-O-Mat RBX, Double Orifice with Anti Shock orifice is one supplier we had found for the air release valves. Per Spec 40 05 52 the working pressure requirement for the air release valves is 750psi.

58 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? SSHO can be shared with QCM. All other positions are independent.

Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Period of performance is fixed.

60 Please provide the site visit attendee sign in sheet. See document "B01_MEVE_317500_Attendance from Site Visit"

Please provide bidding quantities for deteriorated underlayment (roofing)/base course (paving).

Quantities will not be provided.

Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

Park can provide water in limited quantities. Subject to authorizition, park needs and current water demand which vary seasonally. For unrestricted bulk fill, use offsite water.

63 Does this project require phasing? See 01 11 00.

64 Is this project tax exempt? No.

65 When do you anticipate on site work starting?

see solicitation 140P2026R0020 rev 1 pg. 79 of 84. Notice to Proceed for Schedule shall be March 1, 2026.

66 Is permitting required? See Division 01 31 00

Is any landscaping restoration required for this project? For example; topsoil, seeding, and fertilizer.

See 32 92 00.

68 Please provide staking data points for the project. Control Points are listed on sheet G1. Alignment data is provided on sheet C2.

69 Are red, yellow, and blue tops required? Contractor to verify location of all underground utilities. (33 11 13)

Reference Question Official Response - DSC

Please clarify what corrosion protection system is required for the composite and stainless steel waterline in corrosive soil zones (coatings, wraps, encasement, or cathodic protection).

Existing lines have cathodic protections in place. New water line is corrosion resistant, no additional protections are specified if HDPE is intact. Should steel become exposed the pipe shall be repaired or replaced in accordance with the manufacturer's specification.

I noticed in the Special Requirements to list four key trades. Those trades are listed at Mason, Mechanical Services, Electrical Services, and Other. Is it necessary to includes these trads since Mason, Mechanical Services, & Electrical Services are not applicable to this scope of work?

Key trades shall be relevant to the scope of work. Omit references to Mason, Mechanical, Electrical and Other.

Per Flexsteel technical recommendation, an annulus test is recommended when working in current design SOW. This will ensure 100% shield integrity and successful Flexsteel product install with engineered report. Can we consider planning for annulus testing per Flexsteel's recommendation?

see 33 05 07.

The HDD plan and profile provided in the Construction Drawings shall be reviewed and confirmation shall be provided that the HDD plan and profile can be reasonably constructed with the Contractor proposed means and methods within the tolerances specified by the manfuacturer.

Please ensure all manufacturer required tests are performed.

Can we receive more clarifications on asphalt paving locations? We do not see any specific locations on the drawings vs the Geotech report.

Paving locations are limited to those areas disturbed or damaged during construction.

Is the contractor allowed to utilize two-track roads to access ROW across the project as feasible?

Yes, vehicle traffic is permitted on the switch back roads and High Clearnance 4x4 Road accessing the switch back road form the visitor center. Vehicles shall remain on designated routes within the

LOD.

75 SPECS 017823 – What all trainings are required from these specifications? See O&M Requirements spreadsheet in 01 78 23.

Bore #2 (4,462’) Clarification Requests - Per drawing sub-sheet C38, the HDD set up area is identified. Per our Drilling Engineer, more space is needed. Is there any way the pipe exit area can move closer to 168+00 station to allow for more work area space and staging for successful bore? What are the client’s recommendations for more space.

No. Significant Archaeology exists in this location. if needed additional space may be allocated closer to 169+00 and 170+00. Expansion of the LOD request can be made once exact needs are presented by the contractor but space is limited by cultural resources and topography.

Bore #2 (4,462’) Clarification Requests - Casing – Use poly instead of steel?

a.33 05 07-10 Horizontal Directional Drilling: 2.2 E Wash-Over Casing shall confirm to

ASTM A252 Grade 2 Steel and be manufactured specifically for the method of installation b.Flexsteel recommendation is HDPE casing compared to steel for various technical reasons.

Contractor can propose an alternate casing pipe type for review/approval after award. If HDPE can meet casing requirements per specifications it may be considered. See 'submittal procedures' 01 33 23 (1.3)(E)

Reference Question Official Response - DSC

Bore #2 (4,462’) Clarification Requests - Casing – Use slick bore (not using casing) instead of poly or steel?

a.Per appendix A in specifications, bore calls for 12” ream pass. If slick bore is allowed, will this 12” minimum still be required?

Contractor can propose an alternate to casing for review/approval after award. If slick borer can meet casing requirements per specifications it may be considered. See 'submittal procedures' 01 33 23 (1.3)(E)

Bore #2 (4,462’) Clarification Requests - What are the client’s concerns if any about preloading the Flexsteel inside the casing prior to pulling the casing through the bore section?

Per our drilling engineer the best recommendation for a successful bore is to preload the casing specifically from station 123+00 to 77+00 across the entire ROW.

See specification 33 05 07.

The Contractor shall submit any proposed changes to the plan orientation per the specifcation prior to beginning HDD work. Due to resource concerns the bore needs to terminate in the shown drilling setup area around station 169+00-170+00.

Bore #2 (4,462’) Clarification Requests - Per drilling engineer recommendations, extensive dirt work will need to be completed to ensure a successful bore of bore #2. What are the expectations and requirements for the extensive dirt work needing to be done and the carbon footprint of change behind the extensive dirt work? This question is directly related to the boring lay down area at 170+00.

The Contractor will need to submit their excavation plan within the boring lay down area for approval prior to work in that area per specification 33 05 07. Excavation monitor requirements are called out in the Division 01 specifications also.

Bore #2 (4,462’) Clarification Requests - What are the stipulations behind using the Mesa Top Ruins Road for pipe staging and other necessary steps to complete bore 2 successfully?

Can the road be completely closed for a certain amount of time or can half of the road be closed for an extensive amount of time if contractor provides sufficient road traffic.

Mesa Top Ruins Road cannot be completely closed. Half of the road can be closed with appropriate traffic control with delays not exceeding 15 mins, 24/7. Any damage to roadway from staging of material will need to be repaired to match existing condition

Requesting a bid date be extension for 2 weeks or longer, do to increment weather the week of 01/ 19/2026 delayed a site visit. 1A Do to subcontractors and or suppliers our company has reached out to requesting sub-quotes or materials quotes are unaware of the project being out to bid. Most have requested additional time or days in order to prepare quotes. We have been contacting said companies starting on January 15, 2026 for quotes.

An extension is granted and the proposal due date is now 2/26/2026.

Concerning the budget stated or shown on Sol 140P2026R0020 of 5 to 10 million is this corrected?

The rough order Magnitude of this project is between $5M-$10M.

The elevation shown on the profile plans for the 6 inch pipe being installed by HDD method, Will NPS, DSC Contracting Services consider changing the HDD pipe elevation to 4 foot of cover to the top of pipe, similar to the open trench elevation as shown on the water line profile plan sheets on the HDD drawing?

No.

The following stations the existing 6 Inch line appears to be in conflict with the new 6 inch waterline, elevations and pipe locations, if the waterline cannot be shut down for more than 1 to 2 hours what are acceptable means and methods to install the new waterline if conflicts of this nature between existing and new waterline. The following stations are estimated 52+75 to 53+00, 61+00 to 62+00, 67+50 to 68+25, 70+75 to 74+25 and 75+50 to 76+20.

Review the plans, none of the locations listed have the new waterline closer than 10' from the existing water line. There is a crossing identified at approximately 47+90 with callouts to adjust grade of the new line as needed to provide 1' of clearance.

Reference Question Official Response - DSC

On page 5 (V) of the Geotechnical report the last paragraph states 1400 l f of existing roadway will need to be removed and replace, please state what plan sheet this work is located at.

Follow plans and specs. Geotech report is provided for subsurface reference only.

Based on the solicitation, it states: “This is currently an unfunded requirement with a high expectation that funds will be available. When and if funds become available, a contract will be awarded at that time.”

Could you please clarify whether funding is currently available for this project, or if this solicitation is being issued to establish project pricing in anticipation of funding prior to award?

Funding is available for this project.

Who will be responsible for conducting all final inspections? If inspections will not be conducted by a single entity, please clarify which inspections will be required and by whom.

Final inspections will be conducted by the government.

Who is managing this project? Is the project being managed directly by the National Park Service, or by a third-party representative?

The project is being managed by the National Park Service. It is anticipated that a Contruction Managment Representative will be contracted for assistance and oversight.