B.08 RFP_Att#5_Scope_for_Independent_Structural_Proofing.pdf

PDF 136 KB Posted

Attached to
Water Supply Storage System Bazum Village, Armenia (Design-Build Construction)
Solicitation number
W912GB26RA030
Issued by

About this file

This is an attachment to a Design Build Statement of Work (SOW) that establishes the scope for independent structural proofing services required for construction projects.

The contractor must engage an independent, licensed structural proofing engineer at the contractor's expense to review and stamp all structural calculations and drawings prior to final design submittal. The proofing engineer must be licensed in the host nation for the appropriate discipline (concrete, steel, timber) and maintain objectivity from the Designer of Record (DOR), with all conflicts of interest disclosed to the Contracting Officer Representative (COR). The proofing scope includes verification of structural design calculations and fire protection measures; review of structural execution drawings such as reinforcement, steel, and shop drawings; and for high seismic zones, review of non-structural component anchorage and bracing shown on non-structural sheets. The contractor is responsible for ensuring the proofing meets all applicable building codes and host nation permitting requirements.

Deliverables at final design stage consist of proofing reports documenting the effort with detailed information on the proofing engineer credentials, project description, structural system details, design assumptions (gravity loads, environmental loads, seismic loads, soil data), applicable codes, technical findings, and a final statement confirming completion with no structural concerns. The contractor must also submit complete red-lined proofed calculations and drawings stamped and signed by the Independent Proofing Engineer, with all proofing remarks addressed in the final design documents. Final drawings must include a remark confirming that all independent proofing remarks have been resolved.

View the file

Other files

File Type Posted
Solicitation Amendment W912GB26RA0300002 SF 30.pdf PDF
Solicitation Amendment W912GB26RA0300001 SF 30.pdf PDF
B.08 RFP Att#17 - Section 01 22 00 Price & Payment Proceedures_14AUG2026.docx DOCX document
B.08 RFP_Att#2b_Conceptual Site Plan_Option-2.pdf PDF
B.08 RFP_Att#3_DedicationPlaque.pdf PDF
B.08 RFP_Att#7_SOW_30Jul2026.pdf PDF
B.08 RFP_Att#9 - Bank Letter of Guarantee (BLG) Template.docx DOCX document
B.08 RFP_Att#14 - Past Performance Information Sheet.docx DOCX document
B.08 RFP_Att#16 - Bazum Price Schedule.docx DOCX document
Solicitation - W912GB26RA030.pdf PDF
B.08 RFP_Att#2a_Conceptual Site Plan_Option-1.pdf PDF
B.08 RFP_Att#13 - JV Offeror Information Page.docx DOCX document
B.08 RFP_Att#15 - Past Performance Questionnaire (PPQ).pdf PDF
B.08 RFP_Att#1_Site Location Map.pdf PDF
B.08 RFP_Att#4_01-2016 Preparation of Structural Calculations English+German.pdf PDF
B.08 RFP_Att#8 - Bank Letter of Assurance (BLA) Template.docx DOCX document
B.08 RFP_ATT#12 - Past Performance Overview Spreadsheet_23JUL2026.xlsx XLSX spreadsheet
B.08 RFP_Att#6-_Full Spec Binder.pdf PDF
B.08 RFP_Att#10 - Site Visit Registration Spreadsheet.xlsx XLSX spreadsheet
B.08 RFP_Att#11 - Letter of Commitment Forms.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT TO DESIGN BUILD SOW – SCOPE FOR INDEPENDENT STRUCTURAL PROOFING

CENAU‐EDD OCT 2023

Page | 1

I. General scope

The structural calculations and drawings must be proofed by an independent proofing engineer, licensed as required for structural design in the host nation (HN) of the appropriate discipline(s)

(ie. Concrete, steel timber) at the Contractor’s expense. A complete set of proofed and stamped structural design documents as well as the final structural proofing report must be submitted with the Corrected Final design submittal. For this purpose the Contractor must coordinate early enough with the selected proofing engineer. Contractor is responsible for ensuring proofing meets all requirements of the applicable building code, and as applicable meets all requirements necessary to achieve HN permitting. The proofing engineer must be objective and independent from DOR. All conflicts of interest between the proofing engineer and the DOR must be disclosed to the COR prior to the start of the proofing process.

II. Specific scope: The proofing effort includes:

1. Proofing of the Structural Design Calculations and the verifications of structural fire protection.

2. Proofing of structural execution drawings, including but not limited to: Reinforcement drawings, structural steel drawings, structural shop drawings, etc.

3. For high seismic zones proofing of structural execution drawings shown in non‐structural sheets, including but not limited to: Anchorage and bracing of non‐structural components (electrical, mechanical, architectural, fire protection, etc)

III. Deliverables: This task shall include the following deliverables at the final design stage:

1. Proofing Report(s):

The proofing report(s) need(s) to clearly document the proofing effort.

The report shall list as a minimum:

A. Name, title, and address of proofing engineer

Name, title, and address of designer of record

B. Project name and location

C. Complete list of proofed documents

If the proofing effort consists of different review phases the report shall be updated with each phase listing all proofed documents with dates of proofing effort.

D. Project description

E. Description of the structural system, including but not limited to: Foundation system, vertical forces resisting system, lateral forces resisting system, structural materials, etc.

F. Structural assumptions including but not limited to:

‐ Gravity Loads (dead load, live load, etc.).

‐ Environmental loads (wind, snow, rain, ice, etc.).

‐ Seismic loads and seismic design information (seismic zone, seismic design category, base shear, design spectrum, etc.).

‐ Soil data (allowable bearing capacity, subgrade reaction modulus, lateral earth pressures, etc.).

G. Applicable codes and regulations

H. Findings:

‐ Interim proofing reports shall list in detail the technical findings and the required

ATTACHMENT TO DESIGN BUILD SOW – SCOPE FOR INDEPENDENT STRUCTURAL PROOFING

CENAU‐EDD OCT 2023

Page | 2 actions

‐ Final proofing reports shall document that all findings are addressed within the final design package.

If items still need to be addressed during execution, the report shall state so.

I. Final statement: The final statement shall summarize the proofing effort. If the proofing effort is completed the statement shall state that the proofing effort is completed and that there are no structural concerns against the execution in accordance with the proofed documents

J. Stamp and signature

2. Calculations:

Complete set of red lined proofed structural calculations with proofing remarks provided to the Contractor Designer of Record during the proofing process.

The set shall be stamped and signed on the title page by the Independent Proofing Engineer.

3. Drawings

Complete set of structural red lined drawings with proofing remarks.

The set be stamped and signed on the title page by the Independent Proofing Engineer remarks provided to the Contractor Designer of Record during the proofing process.

IV. Final design documents:

The Contractor DOR shall demonstrate at the final design submittal that all structural proofing remarks are addressed within the final design documents. The final drawings shall receive a remark indicating that the independent proofing remarks are addressed.