This document is a Task Group Instruction (TGI) for repairing deck covering on the USS SHOUP (DDG-86), specifically in the Central Control Station and Damage Control Central area (1-268-0-C). The repair involves replacing 77 square feet of existing chemical-resistant flooring with a new chemical-resistant flooring system specified as MIL-PRF-32584, Type IV, in Navy blue color with white flake. An additional 83 square feet of deck plating, including vertical structural surfaces, will also be treated.
The work includes removal of existing equipment, installation of new flooring, and surface preparation. The SRF-JRMC (Ship Repair Facility-Japan Regional Maintenance Center) will provide supporting services such as crane and rigging, utility services, safety inspections, and quality assurance inspections. The task is scheduled for July 2025, with specific start and completion dates to be determined by the TGI POP (Period of Performance) List. A potential asbestos hazard is noted, and the work will follow specific procedural requirements from referenced standard items.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
16-JUL-2025 1119
20.14.15.2.9020 (September 2024) ICN: 38KC265402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-268-0-C DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC2 66311
CU PHASE TITLE: *F/O – REPAIR DECK COVERING IN 1-268-0-C
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
EM044217
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
KANO, DAISUKE 231A 3152430098 05-JUL-2025
APPROVED BY: CODE: PHONE: DATE:
KOMATSU, SHUUHEI 231A 3152436786 07-JUL-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM04-4217
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 1-268-0-C 1 U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
654A1102
1. SCOPE/PURPOSE:
1.1 Title: Deck Covering in 1-268-0-C; repair
1.2 Location of Work:
1.2.1 Central Control Station and Damage Control Central (1-268-0-C)
1.3 Identification:
1.3.1 Quantity (77 SF), Chemical-Resistant Floorings System [Existing] Remarks: See Sketch Enclosure-01 for location detail.
1.3.2 Quantity (77 SF), Chemical-Resistant Floorings System
Specification: MIL-PRF-32584, Type IV Color: 706 Navy blue color coat with white flake
TGI Short Form
16-JUL-2025 1119
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KC265402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-268-0-C DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC2 66311
CU PHASE TITLE: *F/O – REPAIR DECK COVERING IN 1-268-0-C
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1.3.3 Quantity (83 SF), Deck Plating including vertical structural surface up to height of One inch from complete chemical-resistant floorings system level
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Asbestos Hazard
1.6 Contractor work start date: See TGI POP List
1.7 Contractor work completion date: See TGI POP List
2. PROCEDURE:
2.1 Accomplish the requirements of 009-026 of Ref. No. One, including Attachment C, for removal of each existing equipment listed in 1.3.1 and installation of each new equipment listed in 1.3.2.
2.1.1 Accomplish the requirements of 009-032 of Ref. No. One, including Table 3, Line(s) 6, Column(s) A, B, and D, for each area listed in 1.3.3. Primer must conform to MIL-PRF-23236, Type V, VI, or VII.
2.2 Notes:
2.2.1 Planner: Code 231A D. Kano, 243-0098
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN EM04-4217 is related to this TGI.
2.3 Government Furnished Material (GFM): None.
2.4 SRF-JRMC will provide the following service work: (TGI No. 38KC265402S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbol(s).
16-JUL-2025 1119
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KC265402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-268-0-C DC A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-86 USS SHOUP KC2 66311
CU PHASE TITLE: *F/O – REPAIR DECK COVERING IN 1-268-0-C
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
ATTACHMENT LIST
TITLE FILE NAME SAVED DATE
ENCLOSURE-01 38KC265402A01-Sketch.pdf 05-JUL-2025 0000
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38KC265402 KEY OP: A01
LOCATION MAP OF REPLACEMENT
DECK COVERING AREA IN CCS (1-268-0-C)
38KC265402A01
SKETCH
ENCLOSURE-01 SHEET 1 of 1