Attch 4 - Price Sheet.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Seoul Chancery, Consular, IMOT, PCC, IPC, and ESO Outbuilding Roof Replacements
Solicitation number
19AQMM26R0342_Seoul_Roof_Replacements_RFP
Issued by

About this file

This is a Price Sheet template in Excel format for the Seoul Chancery, Consular, IMOT, PCC, IPC, and ESO Outbuilding Roof Replacements design-bid-build project. The price sheet serves as the pricing submission document for contractors responding to the Request for Proposal issued by the Department of State Office of Acquisition Management. Contractors are required to complete this template as part of their proposal submission, with proposals due by September 7, 2026 at 3:00 PM ET. The pricing template establishes the structured format through which bidders will present their cost estimates for the roof replacement work at the US Embassy Seoul facilities in South Korea.

The specific pricing line items, cost categories, and submission requirements contained within this Excel workbook are not detailed in the available information, but this template is a standard appendix document used to ensure consistent and comparable pricing submissions across all proposals received for this design-bid-build project.

View the file

Other files

File Type Posted
19AQMM26R0342 A003.pdf PDF
Attch 4 - Price Sheet (Revised).xlsx XLSX spreadsheet
Attch 1 - OBC Roof Replacement Specifications (Amendment 01).pdf PDF
QandA 1.docx DOCX document
19AQMM26R0342 A002.pdf PDF
Attch 7 - Info For Offerors 1.docx DOCX document
19AQMM26R0342 A001.pdf PDF
Attch 2 - OBC Roof Replacement Drawings.pdf PDF
Attch 3 - PPQ.docx DOCX document
Attch 6 - Public Release of Information 20250219.pdf PDF
Attch 5 - Bidders DD-254.pdf PDF
19AQMM26R0342.pdf PDF
Attch 1 - OBC Roof Replacement Specifications.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE CONTRACT

Attachment 4 - Price Sheet
LABOR TYPE: CLEARED AMERICAN
POST: SEOUL. SOUTH KOREA
PROJECT NUMBER: FWP 608
PROJECT TITLE: OBC ROOF REPLACEMENT
ITEM OF WORKQUANTITYUNITSMATERIAL COSTLABOR & EQUIPMENT COSTTOTAL
PER UNITSUBTOTALPER UNITSUBTOTAL
OBC - Roof Area A - Hot Rubberized PMR
Mobilization / Demobilization1Lump Sum$ - 0$ - 0$ - 0
Roof System Demolition/Disposal13,000Square Feet$ - 0$ - 0$ - 0
Hot Rubberized Membrane13,000Square Feet$ - 0$ - 0$ - 0
Drain Board / Fabric13,000Square Feet$ - 0$ - 0$ - 0
New Insulation13,000Square Feet$ - 0$ - 0$ - 0
New Concrete Pavers13,000Square Feet$ - 0$ - 0$ - 0
Penetration Flashing30Each$ - 0$ - 0$ - 0
Base Flashing and Counterflashing1,000Linear Feet$ - 0$ - 0$ - 0
Metal Edge1,000Linear Feet$ - 0$ - 0$ - 0
Equipment / Curb Flashing500Linear Feet$ - 0$ - 0$ - 0
Miscellaneous HVAC/Electrical Work1Lump Sum$ - 0$ - 0$ - 0
Equipment / Piping Supports25Each$ - 0$ - 0$ - 0
Roof Drains/Parts4Each$ - 0$ - 0$ - 0
Scuppers/Downspouts8Each$ - 0$ - 0$ - 0
Sealant500Linear Feet$ - 0$ - 0$ - 0
Painting1Lump Sum$ - 0$ - 0$ - 0
Subtotal - Materials and Labor$ - 0$ - 0$ - 0
OBC PENTHOUSE ROOFs - Roof Area B - PMMA Coating
Surface Preperation2,000Square Feet$ - 0$ - 0$ - 0
PMMA Reinforced Liquid Roof Membrane2,000Square Feet$ - 0$ - 0$ - 0
Metal Edge / Misc. Metal Flashing500Lineal Feet$ - 0$ - 0$ - 0
Roof Drains3Each$ - 0$ - 0$ - 0
Painting (Penthouse + Bulkhead Façade)1Lump Sum$ - 0$ - 0$ - 0
Misc. Sealant1Lump Sum$ - 0$ - 0$ - 0
Subtotal - Materials and Labor$ - 0$ - 0$ - 0
CON Roof - Roof Areas C, D, E - Hot Rubberized PMR
Roof System Demolition/Disposal6,500Square Feet$ - 0$ - 0$ - 0
Hot Rubberized Membrane6,500Square Feet$ - 0$ - 0$ - 0
Drain Board / Fabric6,500Square Feet$ - 0$ - 0$ - 0
New Insulation6,500Square Feet$ - 0$ - 0$ - 0
New Concrete Pavers6,500Square Feet$ - 0$ - 0$ - 0
Penetration Flashing30Each$ - 0$ - 0$ - 0
Base Flashing and Counterflashing500Linear Feet$ - 0$ - 0$ - 0
Metal Edge500Linear Feet$ - 0$ - 0$ - 0
Equipment / Curb Flashing250Linear Feet$ - 0$ - 0$ - 0
Miscellaneous HVAC/Electrical Work1Lump Sum$ - 0$ - 0$ - 0
Equipment / Piping Supports25Each$ - 0$ - 0$ - 0
Roof Drains/Parts4Each$ - 0$ - 0$ - 0
Scuppers/Downspouts15Each$ - 0$ - 0$ - 0
Sealant500Linear Feet$ - 0$ - 0$ - 0
Painting1Lump Sum$ - 0$ - 0$ - 0
Subtotal - Materials and Labor$ - 0$ - 0$ - 0
IMOT, PCC, IPC, ESO Roofs - Roof Areas F, G, H, J - PMMA Coating
Surface Preperation4,000Square Feet$ - 0$ - 0$ - 0
PMMA Reinforced Liquid Roof Membrane4,000Square Feet$ - 0$ - 0$ - 0
Metal Edge / Misc. Metal Flashing1,000Lineal Feet$ - 0$ - 0$ - 0
Roof Drains5Each$ - 0$ - 0$ - 0
Painting1Lump Sum$ - 0$ - 0$ - 0
Misc. Sealant1Lump Sum$ - 0$ - 0$ - 0
Subtotal - Materials and Labor$ - 0$ - 0$ - 0

SUBTOTAL ALL ROOF AREAS - Materials & Labor $ - 0 $ - 0 $ - 0

INDIRECT COSTS
Shipping1Lump Sum$ 100,000.00
DBA1Lump Sum$ 50,000.00
Taxes & InsuranceLabor$ - 0
OverheadSubtotal - M&L$ - 0
ProfitALL$ - 0
ContingencyALL$ - 0
Subtotal - Indirect Costs$ 150,000.00

SUBTOTAL - ESTIMATED PROJECT COST (M&L + IND.Costs) w/o Travel $ 150,000.00

TRAVEL EXPENSES
Visas & Immunizations (10 Crew)10Each$ - 0
Airfare (10 Crew x $4000 R/T)10Each$ - 0
Lodging (10 Crew x $245/Day)150Calendar Days$ 2,450.00$ 367,500.00
M&IE (10 Crew x $119/Day150Calendar Days$ 1,190.00$ 178,500.00
Local Transportation1Lump Sum$ - 0
Subtotal - Travel Expenses$ 546,000.00
TOTAL ESTIMATED PROJECT COST$ 696,000.00
$ 696,000.00