This is an informational document for offerors participating in a Request for Proposal (RFP) for roof replacement services at the U.S. Embassy Seoul and related facilities in South Korea. The project encompasses roof replacements for the Chancery, Consular, IMOT, PCC, IPC, and ESO Outbuilding structures using a Design-Bid-Build delivery method. The Department of State Office of Acquisition Management is the contracting agency for this federal contract opportunity.

Key submission dates include a mandatory site visit scheduled for August 18-20, 2026, with questions from offerors due by August 26, 2026. Proposals must be submitted by September 7, 2026, at 3:00 PM Eastern Time. The RFP was subject to at least one amendment (Amendment 1) that updated Section J to include this attachment, and Revision 1 re-uploaded Attachment 2 to the solicitation package. Offerors should reference all current attachments and amendments when preparing their proposals for this international roofing project.

View the file

Other files

File Type Posted
19AQMM26R0342 A003.pdf PDF
Attch 4 - Price Sheet (Revised).xlsx XLSX spreadsheet
Attch 1 - OBC Roof Replacement Specifications (Amendment 01).pdf PDF
QandA 1.docx DOCX document
19AQMM26R0342 A002.pdf PDF
19AQMM26R0342 A001.pdf PDF
Attch 2 - OBC Roof Replacement Drawings.pdf PDF
Attch 4 - Price Sheet.xlsx XLSX spreadsheet
Attch 3 - PPQ.docx DOCX document
Attch 6 - Public Release of Information 20250219.pdf PDF
Attch 5 - Bidders DD-254.pdf PDF
19AQMM26R0342.pdf PDF
Attch 1 - OBC Roof Replacement Specifications.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof & Façade Management Program

OBO/CFSM/FMS/PS

INFORMATION FOR OFFERORS No. 1

DATE:August 26, 2026
POST:Seoul, South Korea
SUBJECT:OBC Compound Roof Replacement

This Information for Offerors is to provide answers to questions posed by the bidders and to provide supplemental information to the bidders. This information is non-binding and is not part of the Contract Documents.

Existing OBC Roof Deck:

· Existing thickness of roof deck is 8” of two-way flat concrete slab (OBC Upper Roof only).

OBC Elevation Height:

· Approximately 27.8 Meters (91’) from grade to top of parapet.

On-Site Logistics:

· 2-3 20’ containers can be stored on-site for duration of project. Alternative warehouse/storage location for bulk materials cannot be provided by Embassy and will need to be arranged by roofing contractor if needed.

· Weather:

· Dry Season: March-June , August-October

· Wet Season: June-July, November-March

· Motorpool bathrooms may be available for roofing contractor use. Subject to further confirmation closer to mobilization.

· Crane can be used and must be parked on the street next to the Consular CAC (with the police buses). Will require local permit.

GSO Meeting & Shipping Logistics:

· Visa requirements: 90 days in-country, then must depart country in order to reset 90-day clock. Contractor responsibility to fully verify all visa entry/exit requirements. Please note, starting January 2027, an e-visa (K-ETA) must be filled out and submitted before traveling to South Korea.

· General Shipping Timeline: 4 weeks from US on average.

· Customs Clearance Timeline: 7 days to clear South Korean Customs on average.

· Hazmat items can be shipped to South Korea.

· 10% tax on construction goods purchased locally.

RSO Meeting:

· RSO Escort Ratio US Cleared Americans to Uncleared/Locals

· 1:2 on Chancery Upper Roof and CAA spaces.

· 1:5 on Chancery Low Roofs (Consular, Annex, etc.)

· 1:10 in Parking Lot

· Fasteners must be shipped secure. Contractors to procure fasteners in US, send to OBO Roof Program for secure shipping.

· Picture badges will be issued to Cleared American contractor crew members.

· Crane OK to be left in compound parking lot overnight if on weekends.

· Coordination with multiple OBO/Post offices required for temporary moving and relocation of rooftop equipment. Will require two-week look ahead schedules during construction.

POST Provided Information:

· Nearby/Recommend Hotels:

· Westin Josun (within 1 mile of Chancery)

· The Plaza (within 1 mile of Chancery)

· Lotte Hotel (within 1 mile of Chancery)

· Four Seasons (within 1 mile of Chancery)

· Courtyard Marriott Myeongdong

· The Shilla Seoul

· Conrad

· Fairmont

· Dragon City – Novotel Suites & Grand Mercure (1.8km away from Annex)

· Grand Hyatt

· Mondrian (near Yongsan Embassy housing)

· Novotel Ambassador Dongdaemun

· Grand Intercontinental Seoul Parnas

· Sofitel Ambassador

· Local Contractors:

· Forklift and Crane Rental Company:

· Company name: Joonggi Call

www.0409-0409.com
Tel:1660-0404

· Long-Stay / Serviced Apartments in Seoul:

· Container Laydown / Material Staging Location On-Site:

· Concrete Paver Plant/Manufacturer:

END OF INFORMATION FOR OFFERORS No. 1 image2.png image3.png image4.png image1.png