Attachment R JOC 5 Step Process.pdf

PDF 131 KB Posted

Attached to
FBI REDSTONE JOB ORDER CONTRACT
Solicitation number
15F06725R0000021
Issued by

About this file

The document is a detailed 5-Step Process guide for a Job Order Contract (JOC) that outlines the workflow between an Owner and Contractor for project execution. The process includes: 1) Joint Scope Meeting where the Owner and Contractor inspect the site and discuss work details, 2) Detailed Scope of Work preparation by the Owner, 3) Price Proposal submission by the Contractor using appropriate tasks and quantities, 4) Price Proposal Review by the Owner, and 5) Job Order Issuance after satisfactory review and submission of required documents. Pre-work steps emphasize thorough information gathering, site inspection, bringing necessary tools, potentially involving subcontractors, and asking detailed questions. A key procedural note indicates that an Independent Government Estimate (IGE) must be completed by the government before receiving or reviewing the price proposal.

View the file

Other files

File Type Posted
Industry Day Slides.pptx PPTX presentation
15F06725R0000021 P00001 Redstone Job Order Contract.pdf PDF
P00001 SECTION C -PERFORMANCE WORK STATEMENT REDSTONE JOC.pdf PDF
Using The Construction Task Catalog.pdf PDF
Redstone JOC Site Visit Roster.pdf PDF
P00001 SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
Building A Tie Off5.JPG JPG image
07_61_14.00_20_TB-23.0-Roof_Anchor_Sys TECH 1 roof tie-offs.pdf PDF
Building A Tie Off4.JPG JPG image
Building A Tie Off6.JPG JPG image
Non-Disclosure Agreement.pdf PDF
Attachment H - Questions and Answers.pdf PDF
Building A Tie Off1.JPG JPG image
Building A Tie Off3.JPG JPG image
SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
SECTION M - Evaluation Criteria.pdf PDF
15F06725R0000021 Redstone Job Order Contract.pdf PDF
Seed Project - SOW Window Washing.pdf PDF
Attachment N FD-816 Access of Non-FBI Personnel to FBI Facilities Background Data Information Form.pdf PDF
Attachment F - Surety Form.pdf PDF
Attachment J - FD-857a NDA.pdf PDF
Attachment B - Joint Venture Partner Form.pdf PDF
SECTION C -STATEMENT OF WORK REDSTONE JOC.pdf PDF
Attachment G - Financial Questionnaire.pdf PDF
Attachment L - RSA Badge Request Form.pdf PDF
Attachment E - Acquisition Risk Questions.pdf PDF
Attachment I - Ethics Fact Sheet.pdf PDF
Attachment S VR-219 Unlocked JOC Site Visit 20240530.xlsx XLSX spreadsheet
Attachment K - LAR_SF_85_Completion_Guide.pdf PDF
Attachment M - SF-85 FBI LAR Form.pdf PDF
15F06725R0000021 Redstone Job Order Contract.pdf PDF
Attachment O Coeffecient Explained.pdf PDF
Attachment C - Past Performance Questionaire.pdf PDF
SECTION M - Evaluation Criteria.pdf PDF
Attachment Q Vendor_Request_Form_.pdf PDF
Attachment P Wage Determination AL20240090 (as of 14 Mar 25).pdf PDF
SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
Attachment A - Construction Task Catalog - Redstone Jan. 2025.pdf PDF
Attachment D - Past Performance Information (PPI) Contract Reference Sheet.pdf PDF
Attachment H - Questions Template.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5 Step Process

1. Joint Scope Meeting The Owner schedules a Joint Scope Meeting at the site with the Contractor and others to agree on the details of the work to be performed. This meeting allows the Contractor to inspect the site and ask questions before submitting a Price Proposal, helping to eliminate misunderstandings and mistakes. This upfront, open communication often results in more cost-effective, collaborative solutions.

2. Detailed Scope of Work The Owner prepares a Detailed Scope of Work that describes the work the Contractor will perform. The Detailed Scope of Work will be sent along with the Request for Proposal to the Contractor.

3. Price Proposal The Contractor prepares a Price Proposal by selecting the appropriate Tasks from the CTC and enters the appropriate quantities. The Contractor submits the Price Proposal along with a construction schedule showing the Job Order Completion Time and a list of proposed local subcontractors.

4. Price Proposal Review The Owner reviews the Price Proposal to ensure the Contractor has selected the appropriate tasks and the correct quantities and asks the Contractor to make any required changes.

5. Job Order Issued Once the Owner is 100 percent satisfied with the Price Proposal, construction schedule, proposed subcontractors and has received and approved any other required documents (e.g. bonds, certificates of insurance, etc.), the Owner can issue a Job Order to the Contractor. The Job Order will require the Contractor to complete the Detailed Scope of Work within the Job Order Completion Time for the Job Order Price which is the value of the approved Price Proposal.

PRE-work -

• Information gathering – go to the site and get the details of what is happening – o Design work? Drawings?

• Put together a brief scope of work prior to site walk / Joint Scope Meeting – don’t rush through this, bring tools – ladder, tape measures; check ceilings, check outlets – o Depending on job, bring subcontractors.

o Ask questions

• Site Walk / Joint Scope meeting - Meeting – don’t rush through this, bring tools – ladder, tape measures; check ceilings, check outlets – o Depending on job, bring subcontractors.

o Ask questions

• IGE needs to be done by government before receiving/viewing price proposal

File details come from the government source that posted it. Updated .