P00001 SECTION C -PERFORMANCE WORK STATEMENT REDSTONE JOC.pdf

PDF 681 KB Posted

Attached to
FBI REDSTONE JOB ORDER CONTRACT
Solicitation number
15F06725R0000021
Issued by

About this file

This document is a Statement of Work (SOW) for a Job Order Contract (JOC) for the Federal Bureau of Investigation (FBI) at Redstone Arsenal in Alabama. The contract will support construction, alteration, and repair of industrial, commercial, office, and utility projects through a Job Order Contract system using the Gordian® JOC Solution. The contractor will be responsible for project management, planning, estimating, labor, transportation, materials, equipment, and supervision for various construction tasks, with a 1-year base period and up to 4 option periods.

Key requirements include providing a Program Manager with 15 years of construction experience, a Project Manager with 8 years of experience, a Superintendent, a Quality Control Manager, and an Estimator. The contractor must comply with multiple safety, environmental, and security regulations, including OSHA standards, EPA requirements, and FBI security protocols. The contract includes provisions for preparing Task Order proposals, using a Construction Task Catalog® (CTC®) with preset unit prices, and submitting detailed documentation for each project. The total contract value is not to exceed $11.5M or a 5-year term, with a minimum guarantee of $50,000, and is a competitive local 8(a) set-aside limited to businesses within a 50-mile radius of FBI Redstone.

View the file

Other files

File Type Posted
Industry Day Slides.pptx PPTX presentation
15F06725R0000021 P00001 Redstone Job Order Contract.pdf PDF
Using The Construction Task Catalog.pdf PDF
Redstone JOC Site Visit Roster.pdf PDF
P00001 SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
Building A Tie Off5.JPG JPG image
07_61_14.00_20_TB-23.0-Roof_Anchor_Sys TECH 1 roof tie-offs.pdf PDF
Building A Tie Off4.JPG JPG image
Building A Tie Off6.JPG JPG image
Non-Disclosure Agreement.pdf PDF
Attachment H - Questions and Answers.pdf PDF
Building A Tie Off1.JPG JPG image
Building A Tie Off3.JPG JPG image
SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
SECTION M - Evaluation Criteria.pdf PDF
15F06725R0000021 Redstone Job Order Contract.pdf PDF
Seed Project - SOW Window Washing.pdf PDF
Attachment N FD-816 Access of Non-FBI Personnel to FBI Facilities Background Data Information Form.pdf PDF
Attachment F - Surety Form.pdf PDF
Attachment J - FD-857a NDA.pdf PDF
Attachment B - Joint Venture Partner Form.pdf PDF
SECTION C -STATEMENT OF WORK REDSTONE JOC.pdf PDF
Attachment G - Financial Questionnaire.pdf PDF
Attachment L - RSA Badge Request Form.pdf PDF
Attachment E - Acquisition Risk Questions.pdf PDF
Attachment I - Ethics Fact Sheet.pdf PDF
Attachment S VR-219 Unlocked JOC Site Visit 20240530.xlsx XLSX spreadsheet
Attachment K - LAR_SF_85_Completion_Guide.pdf PDF
Attachment M - SF-85 FBI LAR Form.pdf PDF
15F06725R0000021 Redstone Job Order Contract.pdf PDF
Attachment O Coeffecient Explained.pdf PDF
Attachment C - Past Performance Questionaire.pdf PDF
SECTION M - Evaluation Criteria.pdf PDF
Attachment Q Vendor_Request_Form_.pdf PDF
Attachment P Wage Determination AL20240090 (as of 14 Mar 25).pdf PDF
Attachment R JOC 5 Step Process.pdf PDF
SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
Attachment A - Construction Task Catalog - Redstone Jan. 2025.pdf PDF
Attachment D - Past Performance Information (PPI) Contract Reference Sheet.pdf PDF
Attachment H - Questions Template.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FEDERAL BUREAU OF INVESTIGATION

Statement of Work for

Huntsville Job Order Contract

Facilities & Logistics Services Division

Redstone Facilities Services Section

08 January 2025 30 April 2025

FBI at Redstone

Redstone Arsenal, AL

PROPERTY OF THE UNITED STATES GOVERNMENT

UNCLASSIFIED//FOR OFFICIAL USE ONLY (FOUO)

Copying, dissemination, or distribution of these drawings, plans, or specifications to unauthorized recipients is prohibited. Do not remove this notice.

Properly destroy or return documents when no longer needed.

C-2

UNCLASSIFIED//FOUO

C.1 INTRODUCTION

The FBI requires continued Job Order Contract (JOC) services to support the FBI at Redstone.

The FBI necessitates JOC services to support construction, alteration, and repair of industrial, commercial, office, and utility projects at various FBI facilities on Redstone Arsenal, Alabama.

The FBI needs project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, minimal drawings, and other associated tasks necessary to fulfill the construction requirements of each JOC Task Order (TO).

Contract documents include a Construction Task Catalog® (CTC®) containing Prepriced tasks for construction work with preset unit prices. All unit prices are based on local labor, material, and equipment costs and are for the direct cost of construction.

Bidders will bid two adjustment factors to be applied to the unit prices: one adjustment factor for performing work during standard working hours (see Section C.4.1) and a second adjustment factor for performing work during nonstandard working hours (see Section C.4.2). These adjustment factors apply to every Prepriced task in the CTC®. Bidders will also bid a Non-

Prepriced adjustment factor to be applied to Non-Prepriced work.

This contract provides for a 1-year Base Period and up to 4 Option Periods. All TOs issued during any term of this contract shall be valid and in effect notwithstanding that the Detailed Scope of

Work (DSOW) may be performed, payments may be made, and the guarantee period may continue, after such period has expired. All terms and conditions of the contract apply to each TO.

As projects are assigned, the Contractor will attend Joint Scope Meetings with the Government to review and discuss the proposed work. The Government will prepare a DSOW and issue a TO

Request for Proposal (TORP) to the Contractor. The Contractor will then prepare a TO proposal including a price proposal, construction schedule, list of proposed subcontractors, and other requested documentation.

The value of the price proposal shall be determined by summing the total of the following calculation for each Prepriced task:

𝑈𝑛𝑖𝑡 𝑃𝑟𝑖𝑐𝑒 𝑥 𝑄𝑢𝑎𝑛𝑖𝑡𝑦 𝑥 𝐴𝑑𝑗𝑢𝑠𝑡𝑚𝑒𝑛𝑡 𝐹𝑎𝑐𝑡𝑜𝑟 + 𝑉𝑎𝑙𝑢𝑒 𝑜𝑓 𝑁𝑜𝑛 𝑃𝑟𝑒𝑝𝑟𝑖𝑐𝑒𝑑 𝑇𝑎𝑠𝑘𝑠

The TO price shall equal the value of the approved price proposal.

If the TO proposal is found to be complete and accurate, the Government may issue a TO to the

Contractor.

A TO will reference the DSOW and set forth the TO completion time and price. The Contractor will be paid the TO price for completing all required elements of the DSOW within the TO completion time.

Extra work, credits, and deletions will be contained in a Supplemental TO.

C-3

C.2 CONTRACTOR COEFFICIENT

For the life of the contract, in each TO, the Contractor shall provide certain labor, equipment, materials, and rentals/fees that are considered field overhead and therefore part of the Contractor’s coefficient. Those requirements and responsibilities are identified throughout this Statement of

Work (SOW). Note that where notification of a coefficient requirement/responsibility is stated, all associated subparagraphs are also applicable as part of the coefficient. Other coefficient statements within these subparagraphs refer to additional requirement/responsibilities. A consolidated, but not exhaustive, list of applicable coefficient requirements/responsibilities is provided in Technical

Exhibit (TE)-1, “Applicable Contractor Coefficient Requirements and Responsibilitiesi.”

C.3 APPLICABLE CODES, REGULATIONS, AND STANDARDS

All work under this contract shall comply with the most current Local, State, and Federal

Regulations, including any subsequent updates as they occur. The latest edition of building codes and regulations shall be followed for all designs, construction, and materials under this contract.

If there is a conflict between the codes and/or regulations and these contract specifications, the most stringent requirements shall govern. The Contractor shall maintain a copy of each of these documents for use during the term of this contract.

The most current versions of the FBI at Redstone Campus Design Guideii, Redstone Construction

Standards Guideiii Volumes 1 and 2, and the Unified Facilities Criteria 3-580iv shall be used in the preparation and execution of all work under this contract.

Publications listed within this document form a part of this specification to the extent referenced.

The publications are referred to in the text by basic designation only.

C.3.1 CODE OF FEDERAL REGULATIONS (CFR)

C.3.1.1 OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA)

Both the Occupation, Safety and Health Administration (OSHA) General Industry Safety and

Health Standards (29 Code of Federal Regulations [CFR] 1910v), Publication V2206, OSHA

Construction 3 Industry Standards (29 CFR 1926vi) and EM 385-1-1vii are applicable. One source of these regulations is OSHA Publication 2207viii, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety and health. They are for sale by the Superintendent of Documents, US Government Publishing Office, Washington, DC 20402.

C.3.1.2 US ARMY CORPS OF ENGINEERS (USACE) ENGINEERING MANUAL (EM) 385 1-1

EM 385-1-1 is a set of regulations developed by the U.S. Army Corps of Engineers (USACE). It details safety and health requirements for construction contract work related to military or government projects.

https://dojfbi.sharepoint.us/Teams/000086/Shared%20Documents/Forms/AllItems.aspx?id=%2FTeams%2F000086%2FShared%20Documents%2F200%20Facility%20Standards%2F020%20Design%20and%20Construction%20Stds%20Guides%2F04%20Redstone%20Arsenal%2FA%20RSA%5FCampus%5FDesign%5FCurrent%2FRSA%5FCampus%5FDesign%5FGuide%5Fv21%5F0%5F30%5FSEP%5F2020%2Epdf&parent=%2FTeams%2F000086%2FShared%20Documents%2F200%20Facility%20Standards%2F020%20Design%20and%20Construction%20Stds%20Guides%2F04%20Redstone%20Arsenal%2FA%20RSA%5FCampus%5FDesign%5FCurrent https://dojfbi.sharepoint.us/Teams/000862/ProjectManagementDocuments/Forms/AllItems.aspx?id=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FQT%2FStandards%2FQuantico%20Guides%2F02%2DQuantico%20Information%20Received%2F20%2DMasterplan%20and%20Other%20References%2FFBI%20Redstone%20Arsenal%20%2D%20Construction%20Standards%20Guide%20Vol%201%20%2D%2021%2E0%2Epdf&parent=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FQT%2FStandards%2FQuantico%20Guides%2F02%2DQuantico%20Information%20Received%2F20%2DMasterplan%20and%20Other%20References https://dojfbi.sharepoint.us/Teams/000862/ProjectManagementDocuments/Forms/AllItems.aspx?id=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FQT%2FStandards%2FQuantico%20Guides%2F02%2DQuantico%20Information%20Received%2F20%2DMasterplan%20and%20Other%20References%2FFBI%20Redstone%20Arsenal%20%2D%20Construction%20Standards%20Guide%20Vol%201%20%2D%2021%2E0%2Epdf&parent=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FQT%2FStandards%2FQuantico%20Guides%2F02%2DQuantico%20Information%20Received%2F20%2DMasterplan%20and%20Other%20References https://www.osha.gov/ https://www.osha.gov/general-industry https://www.osha.gov/general-industry https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.gpo.gov/ https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf

C-4

C.3.1.3 FED-STD-313F SAFETY DATA SHEETS (SDS)

The Contractor shall prepare and submit a copy of all required Safety Data Sheets (SDS) to the

FBI for each TO issued against this contract.

Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds are prohibited, Department of the Army (DA) Circular 40-83-4ix.

Hazardous Materials refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910 and to others as additionally defined in FED-STD-313Fx and EM 385 1-1

Chapter 6 (Hazardous or Toxic Agents and Environments).

The most common hazardous materials include asbestos, lead-based paint, polychlorinated biphenyls (PCB), explosives, and radioactive material, among others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, pipe coverings, vinyl floor tile and/or its associated materials. The Contractor shall adhere to regulations and standards

IAW the USEPA Clean Air Act (CAA), USEPA Toxic Substances Control Act, USEPA

National Emission Standards for Hazardous Air Pollutants (NESHAP), and USEPA 40 CFR 763

Subpart I.

C.4 WORK TYPES

C.4.1 STANDARD WORK

Standard work hours are defined as the period from 6:00 a.m. to 6:00 p.m. CST, Monday through

Friday, excluding Federal holidays. All work shall be performed during this period unless otherwise authorized by the Contracting Officer (CO) and approved at least 48 hours in advance unless otherwise specified in the TO. Access to work sites may be restricted to this period due to mission requirements.

C.4.2 NONSTANDARD WORK

Nonstandard work is defined as the period outside of Standard Work, Section C.4.1. The nonstandard coefficient may be used to account for loss of productivity while working in secure areas, for TOs to be accomplished on weekends and during nonstandard hours only, and to accelerate a TO to include multiple shifts both during standard hours and nonstandard hours. Only work specified by the CO, prior to issuance of a TO, or subsequent modification that identifies work requiring nonstandard work hours, shall be multiplied by the nonstandard coefficient.

C.4.3 MINIMAL DESIGN

The Government will require a conventional design developed up to 35% stage for renovation and repair projects (project dependent). If the design requires the services of a registered architect or engineer and if the SOW does not specifically require design services, it is outside the parameters of minimum design. The Contractor is then responsible for submitting documentation that substantiates the proposed approach. The Government shall only provide basic concept design, sketches, and/or drawing(s) information for a specific work requirement. The Contractor must demonstrate design capabilities of providing quality, cost effective minimal design for multiple https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/laws-regs/regulations/standardnumber/1910 http://everyspec.com/FED-STD/FED-STD-313F_55842/

C-5

TOs simultaneously, which shall comply with Government requirements and all applicable building codes and governing authorities. The Contractor will be provided with the Government’s initial concept design and SOW for each TO. The Contractor shall then be responsible for further development of the Government’s concept design to a point where the Contractor’s designs/drawings clearly indicate the proposed method of accomplishing the work, as well as the description, size, and location of all proposed elements of the work. The Contractor’s design must fully comply with the Government’s concept design requirements as well as all governing codes, Unified Facilities Guide Specification, and the FBI at Redstone Campus Design Guide and

Redstone Arsenal Construction Standards Guide which will be provided at award in a portable document format (PDF). The Contractor is expected to use recognized industry standard practices in determining proposed design materials and methods unless the Government specifies otherwise.

C.5 CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS AND SERVICES

The Contractor shall not employ persons for work on this contract if such employee is identified to the Contractor by the CO as a potential threat to health, safety, security, general well-being, or operational missions of the installation and its population. Where reading, understanding, and discussing safety and environmental warnings are an integral part of a contract employee's duties, that employee will be able to understand, read, write, and speak English (speaking skills are not required where a Contractor employee is hearing impaired).

C.5.1 PERSONNEL

C.5.1.1 PROGRAM MANAGER

The Program Manager shall have a minimum of 15 years of construction related services and either superintendence or senior construction management experience. They must possess a program management certification from an accredited source with a program as rigorous as Program

Management Institute (PMI). The PMI programs require at least 2,500 contract hours prior to receiving the Program Manager certifications plus extensive courses of study. The Program

Manager for the JOC shall have positive past performance overseeing multiple projects of varying complexity with successful completion of those projects on time and within budget. The Program

Manager shall have the ability to commit the Contractor, respond to all the various types of service support for the JOC and not delay proposal responses to the Government. The Program Manager shall coordinate all Contractor personnel and tasks and facilitate any required conflict resolution measures.

C.5.1.2 Project Manager (PM)

The Project Manager (PM) shall have a minimum of 8 years’ experience in JOC type tasks, be able to handle multiple job orders simultaneously, maintain cost, schedule, and risk levels in accordance with (IAW) industry and Governmental standards. The PM shall have some project management training with completion certifications to handle projects in the value of $5,000-$1.5 million and be ready to stand in for the Program Manager for short periods of time (not to exceed 2 weeks).

A Project Management Professional or Licensed Professional Engineer would be considered, however, individuals with certifications, such as PMI, will receive greater preference in conjunction with relevant prior work experience.

https://dojfbi.sharepoint.us/Teams/000086/Shared%20Documents/Forms/AllItems.aspx?id=%2FTeams%2F000086%2FShared%20Documents%2F200%20Facility%20Standards%2F020%20Design%20and%20Construction%20Stds%20Guides%2F04%20Redstone%20Arsenal%2FA%20RSA%5FCampus%5FDesign%5FCurrent%2FRSA%5FCampus%5FDesign%5FGuide%5Fv21%5F0%5F30%5FSEP%5F2020%2Epdf&parent=%2FTeams%2F000086%2FShared%20Documents%2F200%20Facility%20Standards%2F020%20Design%20and%20Construction%20Stds%20Guides%2F04%20Redstone%20Arsenal%2FA%20RSA%5FCampus%5FDesign%5FCurrent https://dojfbi.sharepoint.us/Teams/000862/ProjectManagementDocuments/Forms/AllItems.aspx?id=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FRSA%2FProgram%2F02%20Procedures%2C%20Standards%2C%20and%20Templates%2F02%20Standards%2FRSA%5FConstruction%5FStandards%5FGuide%5FVol%5FI%5F21%5F0%2Epdf&parent=%2FTeams%2F000862%2FProjectManagementDocuments%2FOwn%2FRSA%2FProgram%2F02%20Procedures%2C%20Standards%2C%20and%20Templates%2F02%20Standards https://www.pmi.org/?s_kwcid=AL!8620!3!697044720949!e!!g!!program%20management%20institute&utm_job_number=36&utm_region_name=north_america&utm_funnel_stage=customer_acquisition&utm_marketing_channel=paid_media&utm_marketing_subchannel=search_ppc_branded&utm_start_date=05052024&utm_end_date=12312024&utm_source=google&utm_custom_field_one=pmi_branded_core_north_america&utm_custom_field_two=brand_na_brand_nontrademark&utm_custom_field_three=697044720949&utm_custom_field_four=program%20management%20institute&utm_custom_field_five=e&gad_source=1&gclid=CjwKCAjw_4S3BhAAEiwA_64YhtjayuNnzKEQ8YQuynPH3z2lHqIYD6eK7SAFn8hOVksiMLWVbxWTMRoChv4QAvD_BwE https://www.pmi.org/?s_kwcid=AL!8620!3!697044720949!e!!g!!program%20management%20institute&utm_job_number=36&utm_region_name=north_america&utm_funnel_stage=customer_acquisition&utm_marketing_channel=paid_media&utm_marketing_subchannel=search_ppc_branded&utm_start_date=05052024&utm_end_date=12312024&utm_source=google&utm_custom_field_one=pmi_branded_core_north_america&utm_custom_field_two=brand_na_brand_nontrademark&utm_custom_field_three=697044720949&utm_custom_field_four=program%20management%20institute&utm_custom_field_five=e&gad_source=1&gclid=CjwKCAjw_4S3BhAAEiwA_64YhtjayuNnzKEQ8YQuynPH3z2lHqIYD6eK7SAFn8hOVksiMLWVbxWTMRoChv4QAvD_BwE

C-6

The PM shall respond to a standard TO within 48 hours and within 2 hours for an Emergency TO.

C.5.1.3 SUPERINTENDENT

The Superintendent shall have a minimum of 10 years’ experience in JOC type tasks, be able to handle multiple job orders simultaneously, maintain cost, schedule, and risk levels IAW industry and Governmental standards. The Superintendent shall be experienced in multi-skill trade integration for project completion and communicate project status to the PM and the Government.

The Superintendent shall have some project management training with completion certifications to handle projects in the value of $5,000 to $1.5M and be ready to stand in for the PM for short periods of time (not to exceed 2 weeks).

C.5.1.4 SAFETY OFFICER (SO)/LEVEL 1 SITE SAFETY HEALTH OFFICER (SSHO)

As outlined in the USACE Safety and Health Requirements Manual (EM 385-1-1) the Level 1 Site

Safety Health Officer (SSHO) shall:

• Be a full-time responsibility.

• The SSHO shall be present at the project site, located so they have full mobility and reasonable access to all major work operations during the shift.

• Report to a senior corporate safety official, senior PM, or corporate official.

Per EM 385-1-1, all Level 1 SSHOs must receive OSHA 30-hour general industry or construction safety training. Training may be web-based if permitted by OSHA. In lieu of formal OSHA-30 training, SOH training covering the subjects of the OSHA 30-hour course and this Statement of

Work (SOW) may be accepted by the CO in coordination with the local SSHO having jurisdiction over the work. The local SSHO will evaluate the proposed equivalent training for applicability to the contract SOW being performed. In addition, the SSHO is required to have proof of employment for one of the following:

• Five years of cumulative construction industry safety experience in the last 10 years in supervising/managing or implementing a Safety, Occupational, and Health (SOH) program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.

• If the SSHO has a safety-related degree, third-party, nationally accredited (e.g., American

National Standards Institute [ANSI], National Commission for Certifying Agencies

[NCCA], or Council on Engineering and Scientific Specialty Boards [CESB]) SOH-related certification or designation requiring a minimum of 3 years of experience to obtain, only 3 years of experience are needed.

The SSHO shall maintain competency through 24 hours of documented formal, or online safety and health related coursework within the past 5 years. The initial SOH training (OSHA 30-hour) does not meet the 24-hour competency training requirement. Hours spent as an instructor for SOH related training (e.g., teaching an OSHA 10- or 30-hour class, or a 4-hour fall protection end user training) can be considered for hours spent training, however each course can only be used for https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.ansi.org/ https://www.ansi.org/ https://assess.com/ncca-accreditation/?gad_source=1&gclid=CjwKCAjw_4S3BhAAEiwA_64YhhMslqHwJrsSNVvAdLwymvHHOGcxZdYsLgbwA8Xs5vG8IhR5VYbToxoCiPEQAvD_BwE https://assess.com/ncca-accreditation/?gad_source=1&gclid=CjwKCAjw_4S3BhAAEiwA_64YhhMslqHwJrsSNVvAdLwymvHHOGcxZdYsLgbwA8Xs5vG8IhR5VYbToxoCiPEQAvD_BwE https://www.cesb.org/

C-7 hours once. For example, instructing a 4-hour fall protection end user course training three times a year only counts for 4 hours of training.

For projects with multiple shifts, an Alternate SSHO as identified in the Activity Hazard Analysis

(AHA) will be assigned to ensure SSHO coverage for the project at all times work activities are being conducted. Note that the Alternate SSHO must meet the same requirements and assume the responsibilities of the project SSHO. Responsibilities of the SSHO are located in EM 385 1-1

Chapter 2-4.b. The Alternate SSHO is referenced in EM 385 1-1 Chapter 2-4.9 Note that if additional SSHO(s) are used on a project site or required due to contract requirements, multiple shifts, etc. the alternate SSHO(s) must abide by the same roles and responsibilities and assist the primary SSHO in the performance of the duties outlined above. Definitions for Alternate SSHO and SSHO can be found in EM 385 1-1 Chapter 2.

Per, EM 385-1-1, f the Level 1 SSHO must be off-site for a period longer than 24 hours/one day, an additional/alternate Level 1 SSHO must be at the site of work to fulfill the same roles and responsibilities when work is performed.

The Contractor’s project management team, with the assistance of the SSHO, is responsible for managing, communicating, implementing, and enforcing compliance with the Contractor's

Accident Prevention Program (APP) and other accepted safety and health submittals.

Per EM 385 1-1 Chapter 2-4.b(3), the SSHO shall conduct daily inspections according to EM

385 1-1 Chapter 2-5.b, “Contractor SOH Inspections,” and maintain an SOH deficiency tracking system according to EM 385 1-1 Chapter 2-8.f(3), “Deficiency Log and Hazard Tracking

System.”

The SSHO is responsible for the daily inspection of the jobsite to identify key issues that may affect the safety of the Contractors and Government employees. These duties include, but are not limited to:

• Attending all pre-construction conferences, tail-gate meetings, and pre-work meetings, to include preparatory meetings and periodic in-progress meetings.

• Conducting ongoing evaluations of the APP throughout the life of the project to ensure it is current and site-specific.

• Maintaining applicable safety reference material at the site of work including SDS, APP, manufacturer instructions, etc.

• Ensuring all project personnel comply with SOH requirements.

• Providing and keeping a record of site safety orientation and indoctrination training for all project personnel, including subcontractors.

C-8

• Reviewing daily logs documenting compliance with OSHA and other governing laws and regulations.

• Reporting and investigating all accidents and near misses.

C.5.1.5 QUALITY CONTROL MANAGER (QCM)

The Contractor shall provide a Quality Control Manager (QCM) to provide quality control during active TOs. The QCM shall perform a minimum of 2 daily site visits to each active project site to ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are IAW the approved construction drawings, shop drawings, and material submittals. The QCM shall submit daily field notes recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, and prepare quality control reports.

C.5.1.6 ESTIMATOR

The Estimator shall have a minimum of 10 years’ experience with 4 years of TO estimating or TO type contracting experience. It is a requirement that the Estimator must sign off on all eGordian®

CTC® proposals prior to review by the Government.

C.5.1.7 SUBCONTRACTORS

The PM shall have the ability to manage and control multiple subcontractors at multiple work sites.

The Contractor shall schedule all jobs and adequately staff all construction sites to ensure all projects are completed as efficiently as possible and that no site is left idle for more than 7 calendar days. The PM shall provide to the CO a completed Statement and Acknowledgement Form (SF

1413xi) within 7 calendar days after any subcontractor award regardless of tier (IAW FAR 52-222-

11xii). Subcontractors shall be selected from within a 50-mile radius of FBI at Redstone. If the required subcontracting trade/specialty is not able to be obtained within the 50-mile radius the

Contractor shall locate and submit a subcontractor to the Government for approval.

C.5.1.8 PARTNERING

To accomplish this contract most effectively, the Government requests the formation of a cohesive partnership with the Contractor and its subcontractors. The partnership will draw on the strength of each organization to achieve a quality project done right the first time, within the budget, on schedule, and without any safety mishaps. Formal Contractor and subcontractor partnering sessions are required to foster this partnership with the Government. The Contractor shall have agreements with subcontractors that all proposals will be developed using the eGordian® CTC®.

subcontractors will have the ability to access the CTC® and submit their task lines to the Contractor for use in the Contractor’s proposal to the Government.

https://www.gsa.gov/system/files/2023-10/SF1413-23.pdf https://www.gsa.gov/system/files/2023-10/SF1413-23.pdf https://www.acquisition.gov/far/52.222-11 https://www.acquisition.gov/far/52.222-11

C-9

C.5.2 PROFESSIONAL, TECHNICIAN, AND CRAFTSMAN QUALIFICATIONS

The PM shall ensure all employees, including subcontractor employees, have valid licensing/certifications to accomplish applicable contract requirements before starting work under this Contract. Additionally, the pm shall ensure all employees are compliant with all Federal, State, and Local regulations and environmental requirements or laws, are qualified, competent, and capable of handling all assigned tasks. The following qualifications are not all inclusive.

C.5.2.1 TECHNICAL COMPETENCE

All PMs, QCMs and Project Superintendents shall have the minimum years of experience performing in that function as stated above, and all nonprofessional and/or technician project managers shall have relevant experience in the discipline they are designing.

C.6 PROGRAMS

C.6.1 QUALITY CONTROL PROGRAM

All labor, equipment, materials, and rentals/fees required to provide the Quality Control Program shall be at no additional cost to the Government and are considered field overhead, therefore part of the Contractor’s coefficient.

C.6.1.1 QUALITY CONTROL PLAN (QCP)

In compliance with the FAR 52.246-4xiii the Contractor shall provide a Quality Control Plan (QCP) with their proposal that contains, at a minimum, the items listed in Section C.6.2. The QCP shall become a compliance document for all work accomplished under all TOs. Any subsequent modifications shall be submitted to the CO for acceptance before implementation.

C.6.2 MINIMUM REQUIREMENTS

C.6.2.1 INSPECTION SYSTEM

The Contractor shall provide a description of the inspection system that covers all tasks and services required to perform work on each TO. The description shall include specifics as to the areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, submission of a quality control inspection schedule, and the title and organizational placement of the inspectors. Additionally, control procedures for any Government provided keys or lock combinations shall be included.

C.6.2.2 IDENTIFICATION AND PREVENTION METHODS

The Contractor shall provide a description of the methods to be used for identifying discrepancies, eliminating negative trends, and preventing defects in the quality of work performed.

https://www.acquisition.gov/far/52.246-4

C-10

C.6.2.3 DOCUMENTATION

The Contractor shall provide a description of the records kept to document inspections and corrective, or preventive actions taken. The records of inspections shall be maintained and made available to the Government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract. At a minimum, daily

Superintendent production reports and all QCM inspections must be performed and documented within the system of record. Copies of inspection reports and daily reports for all active projects shall be supplied to the CO and COR on a weekly basis.

C.6.2.4 DRAWINGS

The Contractor shall maintain “As-Built” record drawings during the progress of the job to serve as a record of all changes and corrections from the original layout on the drawings. Locations of all sub-surface utility lines shall be detailed on the record drawings. To ensure all buried or hidden items may be determined in the future, the drawings shall show their location using offset dimensions to two permanent fixtures or landmarks. This marking method shall be used to locate the end of each run and all changes in direction. Valves, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a known reference point. The average depth of the item shall be recorded. Final “As-Built” record drawings shall be stored in the system of record and submitted to the CO and COR upon project completion in both hard copy and on

CD. Failure to maintain record drawings may result in retention from progress payments, and notation on the performance evaluation of record. Shop drawings shall be submitted for projects

(particularly fire alarms/sprinkler plans) with a “red marked” version to be submitted to the COR for final approval.

C.6.2.5 BUILDING INFORMATION MODELING (BIM)

The Contractor to produce/modify BIM As-Builts to reflect changes for facilities that have BIM

As-Built models.

C.6.2.6 MATERIALS

The Contractor shall provide material lists to include trade names, brand names, model number, and ratings (if appropriate) for all materials necessary for a complete job. Material submittals shall be provided for all proposed materials in the form of cut sheets. No materials shall be installed without prior written approval of the CO or the COR. Any materials installed without prior approval shall be removed and replaced at no cost to the Government if deemed unacceptable. All

Operations and Maintenance (O&M) manuals and product warranty information shall be delivered to the COR electronically at the completion of each TO.

C-11

C.6.2.7 AUTHORITY HAVING JURISDICTION (AHJ)

The Contractor shall follow the “Authority Having Jurisdiction” (AHJ) for fire alarm and sprinkler requirements when modifying existing spaces within a building. Project designs shall be submitted for AHJ review at least 15 business days before TO approval.

C.6.2.8 PROGRAM OF REQUIREMENTS (POR)

Projects occurring in existing FBI facilities and/or on the FBI Campus. The Contractor shall obtain the Program of Requirements (POR), if applicable, from the Owner and ensure design and construction compliance with the POR. The Contractor shall ensure design and construction within existing FBI facilities are compliant with the most recent published version of the FBI at Redstone

Campus Design Guide.

C.6.2.9 DESIGNS

The Contractor shall have at least one hardcopy full set of 100% designs on the project site while work is being performed. The size shall be no less than Arch D (24″ x 36″).

C.6.2.10 CONCEPTUAL DESIGN

Conceptual design effort is defined as the capability to provide shop drawings and preliminary specifications of the type routinely developed in commercial practice and/or as provided and supplemented by industry. This includes pre-engineered building manufacturers, major heating ventilating and air conditioning (HVAC) equipment suppliers, fire suppression system suppliers, etc.

C.6.3 HEALTH AND SAFETY PROGRAMS

All labor, equipment, materials, and rentals/fees required to provide the Health and Safety

Programs shall be at no additional cost to the Government and are considered field overhead, therefore part of the Contractor’s coefficient.

C.6.3.1 NON-COMPLIANCE ACTIONS

The CO will notify the Contractor of any non-compliance of health or safety requirements, and the required action to be taken (notification delivered to the Contractor representative at the worksite shall be deemed sufficient). The Contractor shall take immediate corrective action to rectify all violations. If the Contractor fails, or refuses to promptly comply, the CO may issue a Stop Work

Order ceasing all, or part of the work for a stop work order issued for non-compliance actions, until satisfactory corrective action has been taken. The Contractor shall not claim costs, damages, or time extensions due to Stop Work Orders based on non-compliance with health or safety requirements.

C-12

C.6.3.2 US ARMY CORPS OF ENGINEERS MANUAL, EM 385-1-1, SAFETY AND HEALTH

REQUIREMENTS MANUAL

The Contractor shall comply with all pertinent provisions of the most current version of the

USACE Manual, EM 385-1-1, Safety and Health Requirements Manual. The Contractor

(including subcontractors) is responsible for compliance with the provisions of this manual.

C.6.3.3 ACCIDENT PREVENTION PLAN (APP)

Per EM 385-1-1, an Accident Prevention Plan (APP) is “a written site-specific SOH plan that documents project, contract, and job-specific potential hazards in the workplace, and the company policies, controls, and work practices that will be used to minimize those hazards.” The

APP must be developed by a CP (Competent Person(s)) and reviewed and approved by the prime contractor and corporate safety official. Upon contractor approval, the plan must be submitted to the CO or COR for review and acceptance prior to the performance of any work. No contract work can begin without a CO or COR accepted APP. APPs must include the following:

(1) The APP must be written in English and articulate the specific work, work process, equipment, and materials to be used, hazards pertaining to the contract work, and the control measures that will be implemented. Follow the mandatory ENG Form 6293

(Accident Prevention Plan Worksheet).

(2) It is understood that at the time of APP submission, there may be unknown portions of the work. Include all known information in the APP prior to the start of work. Project-specific information that is yet to be known (for example, subcontractors to be used, type of fall protection to be used at a certain point in time, specific cranes or other load handling equipment (LHE) to be brought at the site of work, must be added and submitted prior to each preparatory phase/meeting, along with the appropriate AHAs. (See EM 385-1-1 referenced Engineer Forms.)

(3) The SSHO must conduct on-going evaluations and updates of the APP throughout the life of the project to ensure it is up to date and site specific. Changes, revisions, and updates to the APP must be reviewed and approved by the contractor and submitted to the CO or COR for acceptance.

• Include measures to be taken to control potential hazards associated with materials, services, or equipment provided by vendors, contractors, subcontractors, etc.

• Address any unusual or unique aspects or hazards of the project or activity.

(4) The completed APP (reviewed and approved by the contractor and accepted by the CO or

COR) must be always available on the site of work and be accessible to all employees. At minimum, a copy of the most current APP EM 385-1-1 must be posted on the SOH bulletin board, or a notice posted on the board stating the location of the plan.

https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.nae.usace.army.mil/Portals/74/docs/Contracting/2024/APP-24Q0097.pdf?ver=VRDdnNX4Y_s7CrKoxKGLXA%3D%3D https://www.nae.usace.army.mil/Portals/74/docs/Contracting/2024/APP-24Q0097.pdf?ver=VRDdnNX4Y_s7CrKoxKGLXA%3D%3D https://www.publications.usace.army.mil/USACE-Publications/Engineer-Forms/

C-13

C.6.3.4 EMERGENCY PLANS. Emergency plans ensure employee safety in case of fire, inclement weather, or other emergencies at the project location must be prepared, in writing, and reviewed with all affected employees. Emergency plans must be tested to ensure their effectiveness.

(1) Plans must include evacuation procedures, routes, and rally points; the identification of critical plant operations and procedures for employees who operate critical plant operations

(for example, gas line shut down, electrical systems, etc.); employee accountability following evacuation; rescue and medical duties; means of reporting emergencies; and points of contact.

(2) Onsite emergency planning must be coordinated with off-site emergency support.

Documentation of specific onsite emergency services is also required and can include written agreements, memoranda for record, telephone conversation logs, etc. The contractor must offer an onsite orientation of the project and associated hazards to the emergency services provider.

(3) Emergency alert systems must be developed, tested, and used to alert all persons likely to be affected by existing or imminent disasters and to alert and summon emergency responders.

(4) Emergency telephone numbers and reporting instructions for ambulance, physician, hospital, fire, and police must be clearly communicated to all employees and posted at the site of work.

(5) Employees working alone in remote locations must be provided an effective means of emergency communications (for example, cellular phone, two-way radios, land-line telephones, remote employee tracking devices/GPS, or other).

• The selected communications must be readily available (easily within the immediate reach) of the employee and be tested prior to the start of work to verify effective operation at the site of work.

• Develop an employee check-in/check-out communication process to ensure employee safety.

C.6.3.5 ACTIVITY HAZARD ANALYSIS (AHA)

C.6.3.5.1 Risk management is a business process that requires planning to ensure risk is reduced to an acceptable level prior to performing work activities. Risk management provides consistent and systematic identification and communication of risks, consequences, and potential actions to mitigate those risks. Unidentified and unmanaged hazards and their associated risks impede successful missions, undermine readiness, decrease morale, and deplete resources. A properly documented risk assessment serves as evidence that leadership decision-making was based on sound judgment and reasonable principles. Leadership and

C-14 management at every level must exercise risk management. Risk management must be integrated into all phases of work to ensure risk decisions are made at the appropriate level, no unnecessary risk is taken, and the process is applied consciously. Effective risk management requires the following steps.

(1) Identify all potential hazards associated with the task prior to work.

(2) Assess identified hazards to determine probability and potential severity of occurrence (that is, risk).

(3) Develop adequate controls to mitigate hazard and reduce probability and risk.

(4) Implement controls to ensure all workers know, understand, and implement required controls to reduce risk.

(5) Continuously supervise and evaluate controls to ensure they are fully implemented, adequate, and effective at reducing risk. When needed, stop work to make corrections, modify, or add more controls, to ensure risk is managed. Note. There are many tools to aid with risk management implementation. One of these tools is the AHA.

C.6.3.5.2 Hazard Mitigation. Analysis of hazards and implementation of control measures is a vital element to the risk management process and reducing the residual risk to an acceptable level. Use the following hierarchy of controls, listed from most effective to decreasing effectiveness, to identify control measures to be implemented to eliminate or control hazards to an acceptable level: (2-6.b) EM 385-1-1 Note. There may be some situations or activities when more than one control measure or level of controls may need to be implemented to adequately control the hazard(s) to an acceptable level.

(1) Elimination/Substitution. Elimination/substitution involves removing the hazard from the work area. This may be accomplished by modifying structures, changing work processes, or substituting equipment so that persons are not exposed to the hazard(s).

(2) Engineering Controls. Engineering controls isolate or separate the hazard(s) from the general work area and personnel exposure. A common engineering control is physical barriers that prevent contact/exposure to the hazard(s) (for example, guardrails, machine guards, containment).

(3) Administrative Controls. Administrative controls involve work practices or procedures to govern/control the way persons work so that hazardous situations or conditions can be avoided. A common example of an administrative control is training, in that persons are trained in proper procedures so that they do not subject themselves or others to hazards.

C-15

(4) PPE. PPE is equipment worn or used by persons performing work with hazards to minimize the effects of exposure to the hazard(s). PPE includes hard hats, safety glasses, safety shoes, hearing protection, respirators, etc. (See chapter 5) Note.

PPE should not be used as the only protection against a hazard. It should only be used after attempt has been made to implement higher level controls, or as a subsequent control to provide an additional layer of protection.

C.6.3.5.3 Risk Acceptance. Acceptance of risk is a serious matter; therefore, the appropriate level of leadership must accept the overall residual risk associated with a task before its commencement. Residual risk must be communicated and accepted by the proper authority before beginning the activity. Note: The proper authority may be different in each scenario and is based on the scope of work, hazards, and associated risk.

C.6.3.5.4 Activities that require an AHA must not begin until the AHA with the identified

RAC has been reviewed, accepted, and signed by the proper approval authority.

C.6.3.5.5 Prime contractors must establish an internal process that outlines appropriate acceptance authority based on each level of residual risk. The risk acceptance process and acceptance authority personnel must be included in the APP. Note.

USACE does not accept contractor risk. EM 385-1-1.

C.6.3.6 AHA MINIMUM REQUIREMENTS

C.6.3.6.1 AHAs must be prepared and documented for all field, laboratory, industrial, and maintenance activities performed. Before beginning each work activity, task, or

DFOW, an initial AHA must be prepared to ensure minimum safety requirements are adequately addressed. In developing the AHA for a particular activity, the writer(s) (that is, CPs) should draw upon the expertise (for example, knowledge, skills, and experience) of the employees, supervisors, and SOH personnel.

Additional AHA requirements may be found in other applicable chapters of this manual. See paragraph 6 of each chapter of this manual. Note. JSAs, JHAs, or similar Risk Management assessment tools are considered equivalent to, and acceptable substitutes for AHAs as long as the data collected is the same as that required by the AHA.

C.6.3.6.2 AHAs must be provided to and reviewed by all involved employees prior to starting the task. Each employee must document their review with a signature on the AHA or an additional signature sheet. Provide copies of signed AHAs to the CO or COR upon request.

C.6.3.6.3 AHAs must be readily available onsite (for example, office trailer) and accessible onsite by all employees for a period of 12 months, or for contracted work, the length of the contract. Workers/crews must have in their possession the current

AHA that reflects current site conditions, personnel, equipment, control measures, etc. while the work is being performed.

C.6.3.6.4 AHAs must include the following:

C-16

• Identify the activity/task/DFOW name, contractor name and contract number, project location, date of AHA development, name, and title of AHA preparer, and name and title of AHA acceptance authority.

• Define the steps to be performed for the activity/task/DFOW and the work sequences (for example, site conditions, materials, personnel) needed. Job steps should be detailed so that the reader clearly understands how that job will be accomplished (for example, how the part will be installed or removed, anticipated voltages, quantities of chemicals utilized, equipment utilized to accomplish the task, heights being accessed or trenched).

• List all potential hazards associated with each specific job step.

• List all controls required to mitigate hazards according to paragraph 2-6.a. If one layer of control cannot fully eliminate or reduce hazards to an acceptable level, put additional controls in place to reduce risk to an acceptable level (that is, low or medium where possible).

• Assign a RAC to each job step, to identify the residual risk that remains after controls have been applied.

• Assign an overall RAC to the AHA. The overall RAC must not be lower than the highest job step RAC on the AHA.

C.6.3.6.5 Identify the equipment needed, training requirements needed of involved personnel, and any inspection requirements necessary for the activity/task/DFOW. Employer will designate, in writing (for example, certification, company letter) any required

CP(s) and QP(s) by name for a particular activity (for example, excavation, confined space, scaffolding, fall protection, lead removal, asbestos abatement, other activities as specified by OSHA and this manual), and provide proof of competency/qualification.

C.6.3.6.6 Activities that require an AHA must not begin until the AHA with RAC has been reviewed and accepted by the proper acceptance authority. Note. Contractors must submit their accepted AHAs to the CO or COR for review and acceptance to ensure contractual requirements are met.

C.6.3.6.7 Updates to the AHA. The AHA must be modified as necessary to address changing site conditions, operations, or change of CPs or QPs.

• If the initial RAC increases due to a change made to the AHA, resubmit the AHA for acceptance prior to the start of work.

• Changes or updates to an AHA that do not increase the RAC are not required to be resubmitted for acceptance.

• If the AHA needs to be revised, work should not resume until revision is complete and provided to and reviewed by all involved employees prior to starting the task.

C-17

• If the work has been stopped due to safety non-compliance with this manual, APP, AHA, etc. and the AHA needs to be revised, work should not resume until revision is complete and accepted and employees have re-reviewed. Note. For a non-mandatory formatted outline of an AHA, see ENG Form 6206.

C.6.3.7 RECORDS/NOTIFICATION

The Contractor shall maintain accurate records and notify the CO in the prescribed manner of, all exposure data, accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies, and equipment incident to work performed under this contract.

C.6.4 ENVIRONMENTAL PROGRAMS

C.6.4.1 ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT (ADEM)

REQUIREMENTS FOR CONSTRUCTION STORMWATER MANAGEMENT

For any proposed construction/alteration actions performed on FBI at Redstone properties, the following requirements must be met prior to project implementation.

C.6.4.2 CONSTRUCTION GENERAL PERMIT

The US Environmental Protection Agency (USEPA) Clean Water Actxiv and Federal regulations require construction site operators to obtain National Pollutant Discharge Elimination System

(NPDES) permit coverage for regulated land disturbances and associated discharges of stormwater runoff to State waters. Effective April 1, 2021, ADEM established General NPDES Permit No.

ALR100000xv for discharges associated with regulated construction activity that will result in land disturbance equal to or greater than one acre or from construction activities involving less than one acre and which are part of a common plan of development or sale equal to or greater than one acre.

Construction site operators/owners seeking coverage under this general permit must submit a

Notice of Intent (NOI) IAW the permit requirements. Operators/owners of all regulated construction sites must implement and maintain effective erosion and sediment controls IAW a

Construction Best Management Practices Plan (CBMPP) prepared and certified by a Qualified

Credentialed Professional (QCP).

For priority construction sites, the CBMPP must be submitted to ADEM for review along with the

NOI. Priority construction sites include:

• Discharges to a waterbody which is listed on the most recently approved Section 303(d) of the USEPA Clean Water Act of impaired waters for turbidity, siltation, or sedimentation.

• Any waterbody for which a Total Maximum Daily Load (TMDL) has been finalized or approved by USEPA for turbidity, siltation, or sedimentation.

• Any waterbody assigned the Outstanding Alabama Water use classification IAW ADEM

Admin. Chapter 335-6-10-.09xvi.

https://adem.alabama.gov/default.cnt https://www.epa.gov/ https://www.epa.gov/laws-regulations/summary-clean-water-act https://www.epa.gov/npdes https://www.epa.gov/npdes https://adem.alabama.gov/programs/water/waterforms/ALR21CGP.pdf https://adem.alabama.gov/programs/water/waterforms/ALR21CGP.pdf https://www.epa.gov/tmdl https://adem.alabama.gov/newsEvents/notices/jul21/pdfs/7triennialreview.pdf https://adem.alabama.gov/newsEvents/notices/jul21/pdfs/7triennialreview.pdf

C-18

• Any waterbody assigned a special designation in accordance with ADEM Admin. Chapter

335-6-10-.10xvii.

A QCP or Qualified Credentialed Inspector (QCI) shall conduct regular inspections, as stated in the permit requirements, of regulated construction activities to ensure effective erosion and sediment controls are being maintained. In certain circumstances, the QCI or QCP must also monitor construction site discharges for turbidity. ADEM Form 23xviii shall be utilized for documentation of NPDES compliance inspection. On December 1, 2009, the USEPA published

Effluent Limit Guidelines (ELG)xix and New Source Performance Standards (NSPS)xx for regulated construction sites. The regulation went into effect on February 1, 2010.