This document is a template for a Problem Notification Report (PNR) related to a federal contract opportunity. The template calls for details about the nature, source and impact of any problems, as well as required corrective actions and anticipated costs. It is to be submitted to the FEDSIM Contracting Officer's Representative when a scheduled delivery under task order number 47QFCA2XXXXXX will be late. The related federal contract opportunity is a Request for Proposal from the General Services Administration for the Sesame Street for Military Families program, solicitation number 47QFCA23R0050. Responses to the solicitation are due based on the standard proposal process and terms defined in the solicitation documentation.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G
PROBLEM NOTIFICATION REPORT (PNR) TEMPLATE
| Task Order Number: |
| 47QFCA2XXXXXX |
| FEDSIM COR was verbally notified on: |
| [Notify the FEDSIM COR as soon as it becomes apparent that a scheduled delivery will be late.] |
| Date PNR Submitted: |
| [insert Month Day, Year] |
Nature and Source of Problem:
[Provide a detailed description of the nature and source of the problem. Attach additional pages, if necessary.]
Is action required by the Government?
Yes/No [If Yes, describe Government action required and date required.]
Will the problem impact delivery schedule?
Yes/No [If Yes, identify which deliverables will be affected and extent of the delay, the rationale for late delivery, and overall project impact.]
Can required delivery be brought back on schedule?
Yes/No [Explain]
Describe corrective action needed to resolve problems:
[Provide a detailed description of corrective action needed to resolve the problem. Attach additional pages, if necessary.]
When will corrective action be completed?
[Provide the new delivery schedule and anticipated completion date.]
Are increased costs anticipated?
Yes/No [If Yes, identify the amount and nature of the increased costs anticipated and define Government responsibility for problems and costs.]
FEDSIM is a Client Support Center housed within GSA, FAS, AAS Page 1 of 1 Template Version 01-31-22 image1.png image2.png