This document provides details for a federal solicitation seeking construction services for a VA healthcare facility project. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22 is soliciting bids for construction work at the VA Phoenix Healthcare System located at 650 East Indian School Road in Phoenix, Arizona. The project involves Electronic Health Records Modernization infrastructure upgrades and will be performed in a functioning hospital environment. The magnitude of the construction project is estimated between $10,000,000 and $20,000,000. All work must be performed according to applicable building codes and the terms of the solicitation. This procurement is set aside 100% for Service-Disabled Veteran-Owned Small Businesses listed as verified on Vendor Information Pages. An Invitation for Bid will be issued on June 3, 2021 via sam.gov and include site visit details. Questions should be directed to the named contracting specialist.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26221B0007 AMENDMENT 0004 7-13-21.pdf | ||
| 36C26221B0007 AMENDMENT 0003 7-07-21.pdf | ||
| AMENDMENT 0003 - ATTACHMENT MI903 - Mechanical and Electrical Schedules.pdf | ||
| 36C26221B0007 AMENDMENT 0002 7-02-21.pdf | ||
| 36C26221B0007 AMENDMENT 0001 6-30-21.pdf | ||
| Attachment B_ Wage Determination.pdf | ||
| Attachment D2_ Drawings 2 of 12.pdf | ||
| Attachment D3_ Drawings 3 of 12.pdf | ||
| Attachment D5_ Drawings 5 of 12.pdf | ||
| Attachment D9_ Drawings 9 of 12.pdf | ||
| Attachment D4_ Drawings 4 of 12.pdf | ||
| Attachment D10_ Drawings 10 of 12.pdf | ||
| Attachment D11_ Drawings 11 of 12.pdf | ||
| Attachment A_ Campus Map.pptx | PPTX presentation | |
| Attachment D1_ Drawings 1 of 12.pdf | ||
| Attachment D12_ Drawings 12 of 12.pdf | ||
| 36C26221B0007_1.docx | DOCX document | |
| Attachment D6_ Drawings 6 of 12.pdf | ||
| Attachment D7_ Drawings 7 of 12.pdf | ||
| Attachment D8_ Drawings 8 of 12.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRONIC HEALTH RECORD
MODERIZATION (EHRM)
INFRASTRUCTURE UPGRADES
Construction Documents
100% Set Specifications
PVAHCS - Carl T Hayden Medical Center 650 E Indian School Road Phoenix Arizona 85012
DVA Project No.644-20-201
APRIL 28, 2021
ClarkGarrett_jlabo80 Snapshot
EHRM Infrastructure Upgrades
Project No. 644-20-201
Consultants Directory 00 01 03 - 1
SECTION 00 01 03
CONSULTANTS DIRECTORY
PART 1 - GENERAL
1.1 PROJECT LISTING
A. Architect
Concourse Federal Group
123 South Royal Street Alexandria, Virginia 22314
B. Structural Engineer
Greg P. Luth & Associates, Inc.
3350 Scott Blvd, Bldg 48 Santa Clara, CA 95054
C. Fire Protection
Coffman Engineers
8171 Maple Lawn Blvd #250 Fulton, MD 20759
D. Mechanical and Electrical Engineer
DHE Engineering
3300 N. Central Avenue 3300 Tower Suite, 1520 Phoenix, Arizona 85012
E. Telecommunications
Olympus CM
4365 E Pecos Road, Suite 120 Gilbert, Arizona 85297
PART 2 - PRODUCTS (Not Used)
PART 3 - EXCECUTION (Not Used)
Consultants Directory 00 01 03 - 2
THIS PAGE INTENTIONALLY LEFT BLANK
Table of Contents
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES
DIVISION 00 - SPECIAL SECTIONS
00 01 03 Consultants Directory
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements
01 26 13 Requests for Interpretation
01 32 16.15 Project Schedules
01 33 23 Shop Drawings, Product Data, and Samples
01 35 26 Safety Requirements
01 42 19 Reference Standards
01 45 00 Quality Control
01 45 29 Testing Laboratory Services
01 45 35 Special Inspections
01 57 19 Temporary Environmental Controls
01 58 16 Temporary Interior Signage
01 74 19 Construction Waste Management
01 81 13 Sustainable Construction Requirements
01 91 00 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
02 41 19 Selective Demolition
02 82 11 Traditional Asbestos Abatement
02 82 13.19 Asbestos Floor Tile and Mastic Abatement
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete
DIVISION 04 – MASONRY
Division Not Used
DIVISION 05 – METALS
05 12 00 Structural Steel Framing
05 40 00 Cold-Formed Metal Framing
05 50 00 Metal Fabrications
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry
06 12 13 Structural Panel Concrete Subfloor Systems
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation
07 22 00 Rood and Deck Insulation
07 24 00 Exterior Insulation and Finish Systems
07 27 26
07 51 00
07 54 19
Fluid-Applied Membrane Air Barrier, Vapor Permeable
Roof Repair
Polyvinyl-Chloride (PVC) Roofing
07 60 00
07 72 13
07 81 00
Flashing and Sheet Metal
Manufactured Curbs
Applied Fireproofing
07 84 00 Firestopping
07 92 00 Joint Sealants
07 95 13 Expansion Joint Cover Assemblies
00 01 10-3
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Frames
08 14 00 Interior Wood Doors
08 31 13 Access Doors and Frames
08 71 00 Door Hardware
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes
09 06 00 Schedule for Finishes
09 22 16 Non-Structural Metal Framing
09 29 00 Gypsum Board
09 62 80 Static Control Fluid-Applied ESD Epoxy Flooring
09 65 13 Resilient Base and Accessories
09 91 00 Painting
DIVISION 10 – SPECIALTIES
10 44 00 Fire-Protection Specialties
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components
13 34 19 Pre-engineered Metal Buildings
DIVISION 14– CONVEYING EQUIPMENT
00 01 10-4
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing
22 05 12 General Motor Requirements for Plumbing Equipment
22 05 19 Meters and Gages for Plumbing Piping
22 05 23 General Duty Valves for Plumbing Piping
22 07 11 Plumbing Insulation
22 11 00 Facility Water Distribution
22 14 00 Facility Storm Drainage
22 31 11 Water Softeners
22 67 19.16 Reverse-Osmosis Water Equipment
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam Generation
23 05 11 Common Work Results for HVAC
23 05 93 Testing, Adjusting, and Balancing for HVAC
23 09 23 Direct-Digital Control System for HVAC
23 21 13 Hydronic Piping
23 21 23 Hydronic Pumps
23 23 00
23 07 11
23 31 00
Refrigerant Piping
HVAC and Boiler Plant Insulation
HVAC Ducts and Casings
23 36 00 Air Terminal Units
23 37 00 Air Outlets and Inlets
23 81 23 Computer-Room Air-Conditioners
23 81 43 Air-Source Unitary Heat Pumps
00 01 10-5
SECTION NO. DIVISION AND SECTION TITLES
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33 Raceway and Boxes for Electrical Systems
26 05 39 Underfloor Raceways for Electrical Systems
26 05 73 Overcurrent Protective Device Coordination Study
26 08 00 Commissioning of Electrical Systems
26 09 23 Lighting Controls
26 22 00 Low-Voltage Transformers
26 24 16 Panelboards
26 27 26 Wiring Devices
26 29 21 Enclosed Switches and Circuit Breakers
26 41 00 Facility Lightning Protection
26 51 00 Interior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations
27 05 26 Grounding and Bonding for Communications Systems
27 05 33 Raceways and Boxes for Communications Systems
27 08 00 Commissioning of Communications Systems
27 10 00 Control, Communication and Signal Wiring
27 11 00 Communications Equipment Room Fittings
27 15 00 Communications Structured Cabling
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00
28 13 00
28 23 00
Fire Detection and Alarm
Physical Access Control System
Video Surveillance
00 01 10-6
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
PROJECT GENERAL
GI000 COVER SHEET
GI002 SHEET INDEX
GI003 PROJECT INFORMATION AND SYMBOLS
GI004 ARCHITECTURAL ABBREVIATIONS & SYMBOLS
GI101 CONSTRUCTION SEQUENCE - SITE
GS101 CAMPUS MAP
09.1-FIRE ALARM
FA001 FIRE ALARM GENERAL NOTES
09.2-FIRE PROTECTION
FP001 FIRE PROTECTION GENERAL NOTES AND DETAILS
10-PLUMBING
PI001 PLUMBING SYMBOLS AND LEGEND
PK501 PLUMBING DETAILS
PK601 PLUMBING RISER DIAGRAM
PK602 STORM WATER RISER DIAGRAM
12-MECHANICAL
MI001 MECHANICAL ABBREVIATIONS, SYMBOLS, AND LEGENDS
MK501 MECHANICAL DETAILS
MK502 MECHANICAL DETAILS
MK503 MECHANICAL DETAILS
MK601 MECHANICAL RISER DIAGRAMS
MJ501 CONTROLS
MJ502 RO SKID MONITORING CONTROLS
MJ503 ROOM 0119 CONTROLS SCHEMATIC
MI901 MECHANICAL AND ELECTRICAL SCHEDULES
MI902 MECHANICAL MATERIALS
MI903 MECHANICAL AND ELECTRICAL SCHEDULES
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 2
13-ELECTRICAL
EI001 ELECTRICAL ABREVIATIONS, SYMBOLS, AND LEGENDS
15-TELECOMMUNICATIONS
TN501 TYPICAL DETAILS
TN502 TYPICAL DETAILS
TN503 TYPICAL DETAILS
TN504 TYPICAL DETAILS
TN601 FIBER OPTIC BACKBONE RISER DIAGRAM - BUILDING 1
TN602 FIBER OPTIC BACKBONE RISER DIAGRAM - BUILDINGS 2 / 8
BLDG 01
01-GENERAL
01-GI001 COVER SHEET
01-GI002 GENERAL NOTES, CODE REQUIREMENTS, AND SHEET INDEX
01-GC001 SEQUENCING NOTES
01-GC100 SEQUENCING PLAN - BASEMENT
01-GC101 SEQUENCING PLAN - 1ST FLOOR
01-GC102 SEQUENCING PLAN - 2ND FLOOR
01-GC103 SEQUENCING PLAN - 3RD FLOOR
01-GC104 SEQUENCING PLAN - 4TH FLOOR
01-GC105 SEQUENCING PLAN - 5TH FLOOR
01-GC106 SEQUENCING PLAN - 6TH FLOOR
01-GC107 SEQUENCING PLAN - 7TH FLOOR
07-STRUCTURAL
01-SG001 GENERAL NOTES
01-SG002 LEGEND, SHEET LIST & ABBREVIATIONS
01-SG003 LOAD KEY
01-SG004 AXONOMETRIC VIEW
01-SF103 REFERENCE PLAN - 3RD FLOOR
01-SF151 ENLARGED REFERENCE PLAN - 3RD FLOOR
01-SF351 SOUTH TR TOWER SECTIONS AND ELEVATIONS
01-SF352 NORTH TR TOWER SECTIONS AND ELEVATIONS
01-SF401 SOUTH IDF TOWER PLAN
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 3
01-SF402 NORTH IDF TOWER PLAN
01-SF501 STEEL POD DETAILS
01-SF502 STEEL STRONGBACK DETAILS
01-SF503 CFS DETAILS
01-SF504 CONCRETE DETAILS
01-SF505 EQUIPMENT ANCHORAGE DETAILS
08-ARCHITECTURAL
01-AE100 REFERENCE PLAN - BASEMENT
01-AE101 REFERENCE PLAN - 1ST FLOOR
01-AE102 REFERENCE PLAN - 2ND FLOOR
01-AE103 REFERENCE PLAN - 3RD FLOOR
01-AE104 REFERENCE PLAN - 4TH FLOOR
01-AE105 REFERENCE PLAN - 5TH FLOOR
01-AE106 REFERENCE PLAN - 6TH FLOOR
01-AE107 REFERENCE PLAN - 7TH FLOOR
01-AE108 REFERENCE PLAN - PENTHOUSE
01-AE201 EXTERIOR ELEVATIONS
01-AE202 EXTERIOR ELEVATIONS
01-AE351 SOUTH TOWER SECTIONS
01-AE352 NORTH TOWER SECTIONS
01-AE361 ENLARGED SECTIONS
01-AE362 ENLARGED SECTIONS
01-AE363 ENLARGED SECTIONS
01-AE371 ENLARGED SECTIONS
01-AD404 ENLARGED DEMOLITION PLANS
01-AD405 ENLARGED DEMOLITION PLANS
01-AE401 ENLARGED PLANS SOUTH TR TOWER
01-AE402 ENLARGED PLANS SOUTH TR TOWER
01-AE403 ENLARGED PLANS NORTH TR TOWER
01-AE404 ENLARGED PLANS
01-AE405 ENLARGED PLANS
01-AE406 ENLARGED PLANS
01-AE411 PLAN DETAILS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 4
01-AE451 INTERIOR ELEVATIONS
01-AE452 INTERIOR ELEVATIONS
01-AE453 INTERIOR ELEVATIONS
01-AE454 INTERIOR ELEVATIONS
01-AE511 EXTERIOR DETAILS
01-AE512 EXTERIOR DETAILS
01-AE513 ROOF DETAILS
01-AE521 DOOR DETAILS
01-AE531 WALL TYPES
01-AE532 FIRE PROTECTION DETAILS
01-AE533 INTERIOR DETAILS
01-AE601 SCHEDULES
01-AE901 PERSPECTIVE VIEW
09-FIRE ALARM
01-FA151 FIRE ALARM PLAN - 1ST FLOOR
01-FA152 FIRE ALARM PLAN - 2ND FLOOR
01-FA153 FIRE ALARM PLAN - 3RD FLOOR
01-FA154 FIRE ALARM PLAN - 4TH FLOOR
01-FA155 FIRE ALARM PLAN - 5TH FLOOR
01-FA156 FIRE ALARM PLAN - 6TH FLOOR
09-FIRE PROTECTION
01-FP150 FIRE PROTECTION PLAN - BASEMENT
01-FP151.1 FIRE PROTECTION PLAN - 1ST FLOOR
01-FP151.2 FIRE PROTECTION PLAN - 1ST FLOOR
01-FP151.3 FIRE PROTECTION PLAN - 1ST FLOOR
01-FP151.4 FIRE PROTECTION PLAN - 1ST FLOOR
01-FP152 FIRE PROTECTION PLAN - 2ND FLOOR
01-FP153 FIRE PROTECTION PLAN - 3RD FLOOR
01-FP154 FIRE PROTECTION PLAN - 4TH FLOOR
01-FP155 FIRE PROTECTION PLAN - 5TH FLOOR
01-FP156 FIRE PROTECTION PLAN - 6TH FLOOR
10-PLUMBING
01-P100 PLUMBING PIPING PLAN - BASEMENT
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 5
01-P101 PLUMBING PIPING PLAN - 1ST FLOOR
01-P102 PLUMBING PIPING PLAN - 2ND FLOOR
01-P103 PLUMBING PIPING PLAN - 3RD FLOOR
01-P104 PLUMBING PIPING PLAN - 4TH FLOOR
01-P105 PLUMBING PIPING PLAN - 5TH FLOOR
01-P106 PLUMBING PIPING PLAN - 6TH FLOOR
01-P107 PLUMBING PIPING PLAN - 7TH FLOOR
01-PP401 ENLARGED PLUMBING PIPING PLANS SOUTH TR TOWER
01-PP402 ENLARGED PLUMBING PIPING PLANS SOUTH TR TOWER
01-PP403 ENLARGED PLUMBING PIPING PLANS NORTH TR TOWER
01-PP404 ENLARGED PLUMBING PLANS
01-PP405.1 ENLARGED PLUMBING PLANS
01-PP405.2 ENLARGED PLUMBING PLANS
01-PP407 ENLARGED PLUMBING PIPING PLANS
01-PD401 ENLARGED PLUMBING DRAIN AND VENT PLANS SOUTH TR TOWER
01-PD402 ENLARGED PLUMBING DRAIN AND VENT PLANS SOUTH TR TOWER
01-PD403 ENLARGED PLUMBING DRAIN AND VENT PLANS NORTH TR TOWER
12-MECHANICAL
01-M100 MECHANICAL HVAC OVERALL PLAN - BASEMENT
01-M101 MECHANICAL HVAC OVERALL PLAN - 1ST FLOOR
01-M102 MECHANICAL HVAC OVERALL PLAN - 2ND FLOOR
01-M103 MECHANICAL HVAC OVERALL PLAN - 3RD FLOOR
01-M104 MECHANICAL HVAC OVERALL PLAN - 4TH FLOOR
01-M105 MECHANICAL HVAC OVERALL PLAN - 5TH FLOOR
01-M106 MECHANICAL HVAC OVERALL PLAN - 6TH FLOOR
01-M107 MECHANICAL HVAC OVERALL PLAN - 7TH FLOOR
01-MH152 MECHANICAL HVAC PLAN - 2ND FLOOR
01-MD401 ENLARGED DEMOLITION MECHANICAL HVAC PLANS SOUTH TR
TOWER
01-MH401 ENLARGED MECHANICAL HVAC PLANS SOUTH TR TOWER
01-MH402 ENLARGED MECHANICAL HVAC PLANS SOUTH TR TOWER
01-MH403 ENLARGED MECHANICAL HVAC PLANS NORTH TR TOWER
01-MH404 ENLARGED MECHANICAL HVAC PLANS - 1ST FLOOR
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 6
01-MH405.1 ENLARGED MECHANICAL HVAC PLANS - 1ST FLOOR
01-MH405.2 ENLARGED MECHANICAL HVAC PLANS - 1ST FLOOR
01-MH405.3 ENLARGED MECHANICAL HVAC PLANS - 1ST FLOOR
01-MP401 ENLARGED MECHANICAL PIPING PLANS SOUTH TR TOWER
01-MP402 ENLARGED MECHANICAL PIPING PLANS SOUTH TR TOWER
01-MP403.1 ENLARGED MECHANICAL PIPING PLANS NORTH TR TOWER
01-MP403.2 ENLARGED DEMOLITION MECHANICAL HVAC PLANS SOUTH TR
TOWER
01-MP404 ENLARGED MECHANICAL PIPING PLANS - 1ST FLOOR
01-MP405.1 ENLARGED MECHANICAL PIPING PLANS - 2ND FLOOR
01-MP405.2 MECHANICAL PIPING PLANS - DATA CENTER
01-MP405.3 MECHANICAL PIPING PLANS - 2ND FLOOR
13-ELECTRICAL
01-E100 ELECTRICAL POWER PLAN - BASEMENT
01-E101 ELECTRICAL POWER PLAN - 1ST FLOOR
01-E102 ELECTRICAL POWER PLAN - 2ND FLOOR
01-E103 ELECTRICAL POWER PLAN - 3RD FLOOR
01-E104 ELECTRICAL POWER PLAN - 4TH FLOOR
01-E105 ELECTRICAL POWER PLAN - 5TH FLOOR
01-E106 ELECTRICAL POWER PLAN - 6TH FLOOR
01-E107 ELECTRICAL POWER PLAN - 7TH FLOOR
01-EL401 ENLARGED ELECTRICAL LIGHTING PLANS SOUTH TR TOWER
01-EL402 ENLARGED ELECTRICAL LIGHTING PLANS SOUTH TR TOWER
01-EL403 ENLARGED ELECTRICAL LIGHTING PLANS NORTH TR TOWER
01-EL404 ENLARGED ELECTRICAL LIGHTING PLANS
01-EL405.1 ENLARGED ELECTRICAL LIGHTING PLANS
01-EL406.1 ENLARGED ELECTRICAL LIGHTING PLANS
01-EL406.2 ENLARGED ELECTRICAL LIGHTING PLANS
01-EP401 ENLARGED ELECTRICAL POWER PLANS SOUTH TR TOWER
01-EP402 ENLARGED ELECTRICAL POWER PLANS SOUTH TR TOWER
01-EP403 ENLARGED ELECTRICAL POWER PLANS NORTH TR TOWER
01-EP404 ENLARGED ELECTRICAL POWER PLANS
01-EP405.1 ENLARGED ELECTRICAL POWER PLANS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 7
01-EP405.2 ENLARGED ELECTRICAL POWER PLANS
01-EP405.3 ENLARGED ELECTRICAL POWER PLANS
01-EP406 ENLARGED ELECTRICAL POWER PLANS
01-EP406.1 ELECTRICAL POWER PLANS - 2ND FLOOR
01-EP408 ENLARGED POWER PLANS NORTH AND SOUTH TR TOWERS
01-EK601 ELECTRICAL PANEL SCHEDULES
01-EK602 ELECTRICAL PANEL SCHEDULES
01-EK603 ELECTRICAL PANEL SCHEDULES
01-EK604 ELECTRICAL PANEL SCHEDULES
01-EK605 ELECTRICAL PANEL SCHEDULES
01-EK606 ELECTRICAL PANEL SCHEDULES
01-EK607 ELECTRICAL PANEL SCHEDULES
01-EK608 ELECTRICAL PANEL SCHEDULES
01-EK609 ELECTRICAL PANEL SCHEDULES
01-EK610 ELECTRICAL PANEL SCHEDULES
01-EK611 ELECTRICAL PANEL SCHEDULES
01-EJ601 ELECTRICAL ONE-LINE DIAGRAM - CRITICAL
01-EJ602 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
15-TELECOMMUNICATIONS
01-TN100 TELECOM AND SECURITY PLAN - BASEMENT
01-TN101 TELECOM AND SECURITY PLAN - 1ST FLOOR
01-TN102 TELECOM AND SECURITY PLAN - 2ND FLOOR
01-TN103 TELECOM AND SECURITY PLAN - 3RD FLOOR
01-TN104 TELECOM AND SECURITY PLAN - 4TH FLOOR
01-TN105 TELECOM AND SECURITY PLAN - 5TH FLOOR
01-TN106 TELECOM AND SECURITY PLAN - 6TH FLOOR
01-TN401 ENLARGED PLANS SOUTH TR TOWER
01-TN402 ENLARGED PLANS SOUTH TR TOWER
01-TN403 ENLARGED PLANS NORTH TR TOWER
01-TN404 ENLARGED PLANS
01-TN405 ENLARGED PLANS
01-TN406 RACK ELEVATIONS
01-TN407 RACK ELEVATIONS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 8
01-TN408 RACK ELEVATIONS
01-TN409 RACK ELEVATIONS
01-TN410 RACK ELEVATIONS
BLDG 02
01.0-GENERAL
02-GI001 COVER SHEET
01.1-GENERAL
02-GC101 SEQUENCING PLAN
08-ARCHITECTURAL
02-AE101 REFERENCE FLOOR PLAN
02-AE102 REFERENCE ROOF PLAN
02-AE401 ENLARGED PLANS AND INTERIOR ELEVATIONS
02-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
02-FP101 FIRE PROTECTION FLOOR PLAN
10-PLUMBING
02-PP101 PLUMBING PIPING PLAN
02-PP401 ENLARGED PLUMBING PIPING PLAN
02-PP402 ENLARGED PLUMBING PIPING PLAN - WATER SOFTENER SYSTEM
02-PP403 ENLARGED PLUMBING PIPING PLAN - WATER SOFTENER SYSTEM
12-MECHANICAL
02-MH101 MECHANICAL HVAC PLAN
02-MH401 ENLARGED MECHANICAL HVAC PLANS
02-MP401 ENLARGED MECHANICAL PIPING PLAN
13-ELECTRICAL
02-EP101 ELECTRICAL POWER PLAN
02-EP401 ENLARGED ELECTRICAL POWER PLAN
02-EK601 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
15-TELECOMMUNICATIONS
02-TN101 TELECOM AND SECURITY PLAN
02-TN401 ENLARGED TR PLANS & RACK ELEVATIONS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 9
BLDG 08
01-GENERAL
08-GI001 COVER SHEET
08-GC100 SEQUENCING PLAN BASEMENT
08-GC101 SEQUENCING PLAN 1ST FLOOR
08-GC102 SEQUENCING PLAN 2ND FLOOR
08-ARCHITECTURAL
08-AE100 REFERENCE FLOOR PLAN BASEMENT
08-AE101 REFERENCE FLOOR PLAN 1ST FLOOR
08-AE102 REFERENCE FLOOR PLAN 2ND FLOOR
08-AE401 ENLARGED PLANS - BASEMENT
08-AE402 ENLARGED PLANS - 1ST FLOOR
08-AE403 ENLARGED PLANS - 2ND FLOOR
08-AE451 INTERIOR ELEVATIONS
08-AE452 INTERIOR ELEVATIONS
08-AE453 INTERIOR ELEVATIONS
08-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
08-FP100 FIRE PROTECTION PLAN - BASEMENT
08-FP101 FIRE PROTECTION PLAN - 1ST FLOOR
08-FP102 FIRE PROTECTION PLAN - 2ND FLOOR
10-PLUMBING
08-PP100 PLUMBING PIPING PLAN - BASEMENT
08-PP101 PLUMBING PIPING PLAN - 1ST FLOOR
08-PP102 PLUMBING PIPING PLAN - 2ND FLOOR
08-PP401 ENLARGED PLUMBING PIPING PLANS - BASEMENT
08-PP402 ENLARGED PLUMBING PIPING PLANS - 1ST FLOOR
08-PP403 ENLARGED PLUMBING PIPING PLANS - 2ND FLOOR
12-MECHANICAL
08-MH100 MECHANICAL HVAC PLAN - BASEMENT
08-MH101 MECHANICAL HVAC PLAN - 1ST FLOOR
08-MH102 MECHANICAL HVAC PLAN - 2ND FLOOR
08-MD401 DEMOLITION MECHANICAL HVAC PLAN - 1ST FLOOR
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 10
08-MD402 DEMOLITION MECHANICAL HVAC PLAN - 2ND FLOOR
08-MH401 ENLARGED MECHANICAL HVAC PLAN - BASEMENT
08-MH402 ENLARGED MECHANICAL HVAC PLAN - 1ST FLOOR
08-MH403 ENLARGED MECHANICAL HVAC PLAN - 2ND FLOOR
08-MP401 ENLARGED MECHANICAL PIPING PLAN - BASEMENT
08-MP402 ENLARGED MECHANICAL PIPING PLAN - 1ST FLOOR
08-MP403 ENLARGED MECHANICAL PIPING PLAN - 2ND FLOOR
13-ELECTRICAL
08-EP100 ELECTRICAL POWER PLAN - BASEMENT
08-EP101 ELECTRICAL POWER PLAN - 1ST FLOOR
08-EP102 ELECTRICAL POWER PLAN - 2ND FLOOR
08-EP401 ENLARGED ELECTRICAL POWER PLANS
08-EP402 ENLARGED ELECTRICAL POWER PLANS
08-EP403 ENLARGED ELECTRICAL POWER PLANS
08-EK601 ELECTRICAL ONE-LINE DIAGRAMS - CRITICAL
08-EJ601 ELECTRICAL PANEL SCHEDULES
15-TELECOMMUNICATIONS
08-TN100 TELECOM AND SECURITY PLAN - BASEMENT
08-TN101 TELECOM AND SECURITY PLAN - 1ST FLOOR
08-TN102 TELECOM AND SECURITY PLAN - 2ND FLOOR
08-TN401 ENLARGED TR PLANS & RACK ELEVATIONS
08-TN402 ENLARGED TR PLANS
08-TN402.1 ENLARGED TR PLANS
08-TN403 ENLARGED TR PLANS
08-TN403.1 RACK ELEVATIONS
BLDG 13
01-GENERAL
13-GI001 COVER SHEET
08-ARCHITECTURAL
13-AE101 FLOOR/SEQUENCING PLAN
12-MECHANICAL
13-MP101 MECHANICAL PIPING PLAN
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 11
13-ELECTRICAL
13-EP101 ELECTRICAL POWER PLAN
13-EJ601 ELECTRICAL ONE-LINE DIAGRAM - CRITICAL
15-TELECOMMUNICATIONS
13-TN101 TELECOM PLAN
BLDG 14
14-GI001 COVER SHEET
08-ARCHITECTURAL
14-AE101 FLOOR/SEQUENCING PLANS
14-AE351 WALL SECTIONS
14-AE451 INTERIOR ELEVATIONS
14-AE521 DOOR DETAILS
14-AE531 WALL TYPES
14-AE532 MISCELLANEOUS DETAILS
14-AE601 SCHEDULES
09-FIRE PROTECTION
14-FP101 FIRE PROTECTION PLAN
10-PLUMBING
14-PP101 PLUMBING PIPING PLAN
12-MECHANICAL
14-MP101 MECHANICAL PIPING PLAN
13-ELECTRICAL
14-EP101 ELECTRICAL POWER PLAN
14-EJ601 ELECTRICAL ONE-LINE DIAGRAM
15-TELECOMMUNICATIONS
14-TN101 TELECOM AND SECURITY PLAN
BLDG 21
21-GI001 COVER SHEET
21-GC101 SEQUENCING PLAN
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 12
08-ARCHITECTURAL
21-AE101 REFERENCE FLOOR PLAN
21-AE102 REFERENCE ROOF PLAN
21-AE401 ENLARGED PLANS
21-AE451 INTERIOR ELEVATIONS
21-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
21-FP101 FIRE PROTECTION PLAN
10-PLUMBING
21-PP101 PLUMBING PIPING PLAN
21-PP401 ENLARGED PLUMBING PIPING PLAN
12-MECHANICAL
21-MH101 MECHANICAL HVAC PLAN
21-MH401 ENLARGED MECHANICAL HVAC PLANS
13-ELECTRICAL
21-EP101 ELECTRICAL POWER PLAN
21-EP401 ENLARGED ELECTRICAL POWER PLANS
21-EJ601 ELECTRICAL ONE-LINE DIAGRAM
15-TELECOMMUNICATIONS
21-TN101 TELECOM AND SECURITY PLAN
21-TN401 ENLARGED TR PLANS & RACK ELEVATIONS
BLDG 24
24-GI001 COVER SHEET
08-ARCHITECTURAL
24-AE101 REFERENCE/SEQUENCING PLANS
24-AE401 ENLARGED PLANS
24-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
24-FP101 FIRE PROTECTION PLAN
10-PLUMBING
24-PP401 ENLARGED PLUMBING PIPING PLANS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 13
12-MECHANICAL
24-MH401 ENLARGED MECHANICAL HVAC PLAN
13-ELECTRICAL
24-EP101 ELECTRICAL POWER PLAN
24-EP401 ENLARGED ELECTRICAL POWER PLAN
24-EJ601 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
15-TELECOMMUNICATIONS
24-TN101 TELECOM AND SECURITY PLAN
24-TN401 ENLARGED TR PLAN & RACK ELEVATIONS
BLDG 27
27-GI001 COVER SHEET
08-ARCHITECTURAL
27-AE101 REFERENCE/SEQUENCING PLANS
27-AE401 ENLARGED PLANS
27-AE601 MISCELLANEOUS DETAIL AND SCHEDULES
09-FIRE PROTECTION
27-FP101 FIRE PROTECTION PLAN
10-PLUMBING
27-PP401 ENLARGED PLUMBING PIPING PLAN
12-MECHANICAL
27-MH401 ENLARGED MECHANICAL HVAC PLAN
13-ELECTRICAL
27-EP101 ELECTRICAL POWER PLAN
27-EP401 ENLARGED ELECTRICAL POWER PLAN
27-EJ601 ELECTRICAL ONE-LINE DIAGRAM
15-TELECOMMUNICATIONS
27-TN101 TELECOM AND SECURITY PLAN
27-TN401 ENLARGED TR PLAN & RACK ELEVATIONS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 14
BLDG 28
01-GENERAL
28-GI001 COVER SHEET
08-ARCHITECTURAL
28-AE101 REFERENCE/SEQUENCING PLAN
28-AE401 ENLARGED PLANS
28-AE601 MISCELLANEOUS DETAIL AND SCHEDULES
09-FIRE PROTECTION
28-FP101 FIRE PROTECTION PLAN
10-PLUMBING
28-PP401 ENLARGED PLUMBING PIPING PLAN
12-MECHANICAL
28-MH401 ENLARGED MECHANICAL HVAC PLAN
13-ELECTRICAL
28-EP101 ELECTRICAL POWER PLAN
28-EP401 ENLARGED ELECTRICAL POWER PLAN
28-EJ601 ELECTRICAL ONE-LINE DIAGRAM - CRITICAL
15-TELECOMMUNICATIONS
28-TN101 TELECOM AND SECURITY PLAN
28-TN401 ENLARGED IDF PLANS & RACK ELEVATIONS
BLDG 29
29-GI001 COVER SHEET
08-ARCHITECTURAL
29-AE101 REFERENCE/SEQUENCING PLAN
29-AE102 REFERENCE PLAN - ROOF
29-AE401 ENLARGED PLANS
29-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
29-FP101 FIRE PROTECTION PLAN
10-PLUMBING
29-PP401 ENLARGED PLUMBING PIPING PLAN
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 15
12-MECHANICAL
29-MH401 ENLARGED MECHANICAL HVAC PLANS
13-ELECTRICAL
29-EP101 ELECTICAL POWER PLAN
29-EP401 ENLARGED ELECTRICAL POWER PLANS
29-EJ601 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
15-TELECOMMUNICATIONS
29-TN101 TELECOM AND SECURITY PLAN
29-TN401 ENLARGED TR PLANS & RACK ELEVATIONS
BLDG 31
31-GI001 COVER SHEET
08-ARCHITECTURAL
31-AE101 REFERENCE/SEQUENCING PLAN - 1ST FLOOR
31-AE102 REFERENCE/SEQUENCING PLAN - 2ND FLOOR
31-AE401 ENLARGED PLANS
31-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIREPROTECTION
31-FP101 FIRE PROTECTION PLAN - 1ST FLOOR
31-FP102 FIRE PROTECTION PLAN - 2ND FLOOR
10-PLUMBING
31-PP101 PLUMBING PIPING PLAN - 1ST FLOOR
31-PP102 PLUMBING PIPING PLAN - 2ND FLOOR
31-PP401 ENLARGED PLUMBING PIPING PLANS
12-MECHANICAL
31-MH101 MECHANICAL HVAC PLAN - 1ST FLOOR
31-MH102 MECHANICAL HVAC PLAN - 2ND FLOOR
31-MH401 ENLARGED MECHANICAL HVAC PLANS
13-ELECTRICAL
31-EP101 ELECTRICAL POWER PLAN - 1ST FLOOR
31-EP102 ELECTRICAL POWER PLAN - 2ND FLOOR
31-EP401 ENLARGED ELECTRICAL POWER PLANS
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 16
31-EJ601 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
15-TELECOMMUNICATIONS
31-TN101 TELECOM AND SECURITY PLAN - 1ST FLOOR
31-TN102 TELECOM AND SECURITY PLAN - 2ND FLOOR
31-TN401 ENLARGED TR PLANS & RACK ELEVATIONS
31-TN402 ENLARGED TR PLANS & RACK ELEVATIONS
BLDG 34
34-GI001 COVER SHEET
34-GC101 SEQUENCING PLAN - 1ST FLOOR
34-GC102 SEQUENCING PLAN - 2ND FLOOR
08-ARCHITECTURAL
34-AE101 REFERENCE PLAN - 1ST FLOOR
34-AE102 REFERENCE PLAN - 2ND FLOOR
34-AE401 ENLARGED PLANS
34-AE451 INTERIOR ELEVATIONS
34-AE601 MISCELLANEOUS DETAILS AND SCHEDULES
09-FIRE PROTECTION
34-FP101 FIRE PROTECTION PLAN - 1ST FLOOR
34-FP102 FIRE PROTECTION PLAN - 2ND FLOOR
10-PLUMBING
34-PP101 PLUMBING PIPING PLAN - 1ST FLOOR
34-PP102 PLUMBING PIPING PLAN - 2ND FLOOR
34-PP401 ENLARGED PLUMBING PIPING PLANS
12-MECHANICAL
34-MP101 MECHANICAL PIPING PLAN - 1ST FLOOR
34-MP102 MECHANICAL PIPING PLAN - 2ND FLOOR
34-MP401 ENLARGED MECHANICAL PIPING PLANS
13-ELECTRICAL
34-EP401 ENLARGED ELECTRICAL POWER PLANS
34-EJ601 ELECTRICAL ONE-LINE DIAGRAM - NORMAL
Project No. 644-20-201
APRIL 28, 2021
List of Drawing Sheets - 00 01 15 - 17
15-TELECOMMUNICATIONS
34-TN101 TELECOM AND SECURITY PLAN -1ST FLOOR
34-TN102 TELECOM AND SECURITY PLAN -2ND FLOOR
34-TN401 ENLARGED IDF PLANS & RACK ELEVATIONS
34-TN402 ENLARGED IDF PLANS & RACK ELEVATIONS
BLDG 37
37-GI001 COVER SHEET
08-ARCHITECTURAL
37-AE101 REFERENCE FLOOR PLAN - PARKING STRUCTURE
37-AE401 FLOOR/SEQUENCING PLAN - PARKING STRUCTURE
09-FIRE PROTECTION
37-FP101 FIRE PROTECTION PLAN - PARKING STRUCTURE
10-PLUMBING
37-PP401 ENLARGED PLUMBING PIPING PLAN - PARKING STRUCTURE
12-MECHANICAL
37-MP401 ENLARGED MECHANICAL PIPING PLAN - PARKING STRUCTURE
13-ELECTRICAL
37-EP101 ENLARGED ELECTRICAL PLAN - PARKING STRUCTURE
37-EP401 ELECTRICAL ONE-LINE DIAGRAM
TOTAL NUMBER OF SHEETS: 415
Project No. 644-20-201
List of Drawing Sheets - 00 01 15 - 18
THIS PAGE INTENTIONALLY LEFT BLANK
General Requirements
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including selective demolition in existing structures, and furnish labor and materials and perform work for PVAHCS - Carl T Hayden Medical Center, EHRM Infrastructure Upgrades as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
C. Offices of Concourse Federal Group/Awen Solutions Group, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, alterations, necessary selective removal of portions of existing structures and construction and certain other items.
B. ALTERNATE NO.1: BASE BID except deletes IDF room humidification.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
01 00 00 -2
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded
01 00 00 -3 and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software
(EDMS).
8. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
9. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
1.6 ACCESS TO SITE
A. General: Contractor have limited use of Project site within the Contract limits indicated for construction operations as shown on Drawings and as specified by requirements of this Section. In addition Contractor's use of project site is limited only by Owner's right to perform work or to retain other contractors on portions of this project.
1. Do not disturb portions of the site beyond areas in which the Work is indicated and allow for Owner occupancy and public use of adjacent spaces.
B. Driveways, Walkways and Entrances: Keep driveways, parking garage, loading areas, and entrances serving premises clear and available at all times to the Medical Center employees, patients, visitors and emergency vehicles. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances by construction operations.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain existing adjacent building and portions of existing building affected by construction operations in a weathertight condition throughout construction period. Take precautions to protect the building, its occupants and the public during the construction period.
1. Repair damage caused by construction operations. provisions.
D. Parking: No parking will be available on site. The Contractor, Contractor's employees Sub-contractor’s and Sub-contractor’s employees shall make their own arrangements for vehicle parking off site.
01 00 00 -4
1.7 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in
01 00 00 -5 absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Sequencing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week.
Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
a. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate sequencing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such sequencing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR, and Contractor, as indicated on the sequencing plans.
J. All Buildings will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment.
These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction staging area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F)
01 00 00 -6 at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for Medical Center at all times.
Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR and Chief of Facilities Management. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to the following for additional requirements:
a. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
b. Section 27 05 11, REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS
c. Section 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY
AND SECURITY
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the
COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
01 00 00 -7
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped, or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be always open to traffic with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from selective demolition of buildings or structures, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed.
Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 00 -8
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE
CONDITIONS" (FAR 52.236-2).
1.10 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR and Chief of Facilities Management within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.11 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit one set in digital form MS Word, Excel, etc.), un-protected and fully editable and one set in Portable Document Format (PDF) un-protected, searchable and printable of the warranty management plan, submit sample to COR for approval. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract.
The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product
01 00 00 -9 warranty period. A joint 4 month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer.
Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers, or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
01 00 00 -10
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor…