36C26221B0007 AMENDMENT 0001 6-30-21.pdf
PDF 2 MB Posted
- Attached to
- Z2DZ--644-20-201 EHRM Phoenix Construction Federal contract opportunity
- Solicitation number
- 36C26221B0007_1
About this file
This federal contract opportunity announcement solicits construction services for an Electronic Health Records Modernization Infrastructure Upgrades project at the VA Phoenix Healthcare System located in Phoenix, Arizona. The solicitation seeks general construction, alterations, mechanical, electrical and utility system work including necessary demolition and removal of existing structures. Work will be performed in a functioning hospital environment. The project value is estimated between $10-20 million. The requirement is set aside 100% for Service-Disabled Veteran-Owned Small Businesses. The North American Industry Classification code is 236220 for Commercial and Institutional Building Construction. The solicitation number is 36C26221B0007_1 and will be issued on or around June 3, 2021 via beta.sam.gov. A mandatory site visit will be scheduled. Interested parties should contact the point of contact, Steven J. Covell, for any questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26221B0007 AMENDMENT 0004 7-13-21.pdf | ||
| 36C26221B0007 AMENDMENT 0003 7-07-21.pdf | ||
| AMENDMENT 0003 - ATTACHMENT MI903 - Mechanical and Electrical Schedules.pdf | ||
| 36C26221B0007 AMENDMENT 0002 7-02-21.pdf | ||
| Attachment D4_ Drawings 4 of 12.pdf | ||
| Attachment D10_ Drawings 10 of 12.pdf | ||
| Attachment D11_ Drawings 11 of 12.pdf | ||
| Attachment B_ Wage Determination.pdf | ||
| Attachment D2_ Drawings 2 of 12.pdf | ||
| Attachment D3_ Drawings 3 of 12.pdf | ||
| Attachment D5_ Drawings 5 of 12.pdf | ||
| Attachment D9_ Drawings 9 of 12.pdf | ||
| Attachment A_ Campus Map.pptx | PPTX presentation | |
| Attachment D1_ Drawings 1 of 12.pdf | ||
| Attachment D12_ Drawings 12 of 12.pdf | ||
| 36C26221B0007_1.docx | DOCX document | |
| Attachment D6_ Drawings 6 of 12.pdf | ||
| Attachment D7_ Drawings 7 of 12.pdf | ||
| Attachment D8_ Drawings 8 of 12.pdf | ||
| Attachment C_ Specifications.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 36
0001 6-30-2021
644-20-201
00262
Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
00262
Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
To all Offerors/Bidders
36C26221B0007
06-04-2021
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 7-14-2021, 2:00PM (PDT)
Amendment 0001 of Solicitation 36C26221B0007 is issued to provide responses to RFI's received (enclosed).
Note that bids are to be submitted electronically via email to steve.covell@va.gov.
The bid due date has been extended until July 14, 2021 at 2:00PM (PDT).
A virtual public bid opening will be held on Wednesday, July 14, 2021 at 2:15PM (PDT) via phone (voice only).
To join the public bid opening dial: 1-213-282-6316, Conference ID: 319 481 78#
PVAHCS ‐ Carl T Hayden Medical Center
EHRM Infrastructure Upgrades
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
1 08 71 10 Please verify what keyway the facility requires. The facility uses Medeco cores. None
2 07 81 00 2.1 A.1 This is referencing mineral wool applied fireproofing. Other products are not listed.
Please reference sheet 01‐GI002 Code Analysis
Structural frame is listed with UL Design Y719.
This design is for Monokee Applied fireproofing.
Is Monokote an acceptable product to install?
Please provide UL design for tube steel with mineral fiber.
Utilize sheet 01‐GI002 Code Analysis and
Minimum Fire Resistive Requirements listed on sheet 01‐SG001 and details on sheet 01‐AE532.
Disregard any references to Mineral wool applied fireproofing.
None
3 08‐TN401 Bold is new equipment and shaded is existing. TR
0600 has bold 96U PP but states they are existing. Please clarify. (This also applys to multiple drawings.)
Reference keynote 4 ‐ "It is the responsibility for the division 27 contractor to tone and test all existing CAT5 cabling." CAT5 and below cabling shall be replaced with CAT6A. Tone cabling for location/investigation and replacing purposes.
CAT5 PP to be replaced with 6A as applicable.
None
4 All Confirming that unless the TR legend states to install new Cat6A cabling the existing cabling will remain reguardless of the cable category, other that WAP cabling that will be upgrade to Cat6A?
All Category 5 and below cabling shall be replaced with CAT6A.
None
5 08‐TN402.1 Note 4 states to tone and test all existing cabling
(if applicable) Are we to include to tone and test all existing cabling that is not being replaced that has a bold PP? And relable if necessary?
Tone and test only CAT5 and below cabling that will be replaced. Tone cabling for location/investigation and replacing purposes.
None
6 All Drawings state to locate and replace existing
WAP locations Is there a standard quantity we are to use for the WAP cabling locations, like 10 per TR or something as the actual quantity is unknow.
Division 27 contractor shall provide heat map per floor and determine required new WAP locations per TDR.
None
7 N/A Because the rooms being repurposed weren’t shown to us, they at the jobsite suggested they take pictures of these room ceilings. I need pictures of the following rooms:
BLDG 1, Basement
TR, TRS‐000A
TR MECH, TRS‐000B
TRS ELEC, TRS‐000C
BLDG 1, 1ST FLOOR
TR, TRS‐100A
TR MECH, TRS‐100B
TRS ELEC, TRS‐100C
DATA CENTER, 1809
TRC, 115
TR, 1221A
TR 105, 1151
TR, 1321A
TR, K132
BLDG 2
TR, 1124
Photographic information taken by A/E Team will be made available to Bidders as a courtesy only and are not part of the Bidding or Contract
Documents. Representative photos of various room/ceiling conditions included with the RFI document.
Photos accessible at https://awensolutions.sharepoint.com/:f:/ s/AwenAE/EhV‐
Z6_7nOZPixNdzhyuTTgBUjf3loiFLS7kBpnm k8yQMg?e=VN4IjI
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments cont.
BLDG 8, Basement
TR, A000
TR, A0115
1ST FLOOR
TR, A1428
TR, A1218
TR, A1034
2ND FLOOR
TR, 2208
TR, A2021
TR, A2448
BLDG 14
TR, 14‐3
BLDG 21
TR, 100
TR, 108
TR, 0110
BLDG 24
TR, 117B
BLDG 27
TR, 128
BLDG 28
TR, 112
BLDG 29
TR, 1066
cont.
BLDG 31
1ST FLOOR
TR, 1039
2ND FLOOR
TR, 2039
BLDG 34
1ST FLOOR
TR, 1039
2ND FLOOR
TR, 2034
8 N/A Are manually generated redline drawings sufficient for on site as builts?
Field as‐built drawings shall be maintained per
01 00 08/1.10A, also refer to sections 22 05 11, 23 05 11, 23 21 13, 23 21 23, 27 05 11, 27 15 00, and 28 13 00 for additional requirements.
None
9 N/A Is pre‐installation FAT testing a requirement? Yes None
10 27 08 00 Is DAS a requirement for this project? No None
11 N/A Will the factory reel test satisfy copper and fiber reel test requirements?
Yes None
12 N/A Do all head end devices have to have an energy star seal?
No None
13 N/A Are cabling numbers and locations TBD by discovery process matching to existing?
Yes None
14 N/A Does existing overhead pathway have capacity to accommodate all new cabling?
It is the responsibility of the Division 27 contractor to utilize existing pathways where possible. New pathways may need to be installed in tight areas.
None
15 N/A Does all cabling have to be in conduit when it exits the main pathway (basket or tray)?
No. Only when over hard‐lid ceilings or is inaccessible for more that 8' in distance
None
16 N/A Is the use of J‐hooks for data cabling acceptable once the cabling has exited the cable tray?
Yes None
17 02‐TN401 Does any/all new access control have to be C‐
Cure 9000 to be compatible with existing C‐Cure
9000 denoted on drawing 02‐TN401 (page 234)?
Yes None
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
18 01 00 00 1.3 B 01 00 00 1.3 B “ALTERNATE NO.1: BASE BID
except deletes IDF room humidification.” Please provide additional clarification so that we can price this alternate correctly. Does this alternate remove the total balance of the system including water softening, RO system as well as the humidifiers?
Yes this Alternate deletes the water softening, RO system, piping, and humidifiers.
None
19 N/A Is the controls contractor required to furnish flow meters?
Controls Contractor shall furnish flow meters. None
20 N/A Will x‐ray or GPR be required for any coring that is to take place at the facility?
Refer to 270511/3.1‐B3, this would apply to other trades penetrating a PT slab.
None
21 N/A Please identify what RO piping is to be designated as “low pressure” and what is to be over 75 psi
All supply RO piping shall be stainless steel type
316L. All backwash and drain RO piping shall be stainless steel type 304.
None
22 N/A What is the pipe flushing / cleaning requirements for this project per system?
All plumbing piping, equipment, and components shall be flushed and disinfected in accordance with AWWA C651, see specifications.
None
23 N/A Who is the preferred water treatment vendor for this facility? Please provide contact info
Bernie Peacock with Western Water
Technologies, Inc.
None
24 N/A Can a detail for drip troughs be provided? Please provide minimum requirements for drip trough such as material, gage, dimensions, proper installation, etc.
Refer to Sheet MK503, detail D1. Use 18‐22 gauge for thickness.
MK503 reissued
25 N/A Will drip troughs require sensor or alarms for water detection?
No, leak detection tape will suffice. None
26 N/A Can a plumbing equipment / fixture schedule per building be furnished?
No plumbing fixtures are being installed, fixture schedule is not needed.
None
27 N/A Can a piping detail for CRAC unit hookup be provided?
Refer to Installer/User guide for piping detail None
28 N/A Can a P&ID be furnished for HVAC and plumbing systems?
Please clarify. None
29 N/A Will a pre read of any systems be required for test and balance? Please list pre read requirements
See attached TAB scope of work document See attached memo
30 N/A Please clearly define test and balance scope expected for this project
See response to RFI 29. See attached memo
31 MK601 What is “DPT” referring to on sheet MK601 shown on third floor of south tower diagram?
Differential pressure transmitter None
32 N/A Is controls contractor responsible for furnishing and installing of leak detection tape?
Yes None
33 General
Requirements
Can facility define what areas will be required to work specific hours, days, times, etc.? It was stated during job walk that certain areas would be restricted to specific days and times to accommodate hospital patients and staff, please clarify
The OR and SPS are generally shut down for 2 weeks annually, usually in August. Work for those areas will likely be restricted to this 2 week period. No more than 2 rooms per inpatient ward can be taken simultaneously, with work in the inpatient wards occurring during the day.
Admin space can be done off‐hours when inpatient ward work is not available. Mental health facilities will need to be specifically coordinated as well, but will likely be daytime work.
None
34 N/A Can hot taps be utilized for this project? Yes, please coordinate with VA None
35 N/A Will equipment connected to ductwork that is to be tapped be required to be shut down during duct tap?
Air handlers do not need to be shut down for installation of Terminal Units.
None
36 N/A Will special ICRA requirements have to be made for duct tie ins?
Yes None
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
37 N/A Please provide equipment schedules to include all HVAC equipment in each building
Refer to sheet MI901 ‐ MI903, for all equipment in all buildings. For example, CU‐23‐2 means it is
Tag CU in building 23 and it is #2
None
38 N/A Will existing doors in rooms / closets that will house new humidifier equipment require door seals or other to properly climatize new space?
Yes, refer to Architectural Door schedules on sheet A601 for each building.
None
39 N/A Can 3‐way valve detail be furnished for any HVAC or other equipment requiring a 3‐way valve?
See sheet MK104 for the 3‐way valve location.
Basis of Design "Griswold Controls UR3
Unimizier: 3‐way valve"
3 way valve basis of design
40 N/A Are check valves required at pumped condensate lines?
Yes, all pumps shall require check valves None
41 N/A Can air device schedule be provided per building where applicable?
See sheet MI902 for the scheduled Diffusers, Registers, and Grilles
42 N/A Can a detailed scope pertaining to test and balance be furnished? Test and balance has traditionally been difficult and costly at that particular facility due to vague scopes and no clear delineation between TAB for new work and what effects the conditions of the current system may play on work to be balanced. Please furnish a clear scope for test and balance requirements under this solicitation
See response to RFI 29. 3 way valve basis of design
43 01 91 00 What is the extent of commissioning assistance required for contractor and subcontractors involved with this project? Is there a predetermined amount of time expected from each trade? Commissioning has traditionally been a very long and costly process at this facility when involving the HVAC and controls system.
For the purposes of fairness in pricing can a predetermined amount of labor be figured into the commissioning process such as is traditionally done with owner training requirements?
Commissioning is NOT required for this project, omit section 01 91 00 in it's entirety and all references to commissioning requirements throughout the specification. Refer to individual sections for startup, training, and demonstration requirements.
None
44 01 91 00 What subcontractors will be required to assist with commissioning and to what extent is this expected per trade? For the purposes of fairness in pricing can a predetermined amount of labor be figured into the commissioning process such as is traditionally done with owner training requirements?
See response to RFI 43. None
45 N/A Are hot taps or line stops expected for pipe connections into existing systems or will system be shut down and drained for tie ins?
Hot taps allowed per VA. Coordinate with VA for hot tap or shut down of system.
None
46 N/A Can a clear water treatment scope be furnished for this solicitation? Example: how much glycol is expected to be replaced for system drain down?
Coordinate with VA facilities and water treatment vendor. As for glycol, there is not glycol being used.
None
47 N/A Who is responsible for chemical treatment cost if system is drained down for new work under this solicitation?
Coordinate with VA representative None
48 22 14 00 Will chlorination or other sterilization be required for plumbing systems? If so, please clarify extent of this scope
Refer to 22 14 00/3.3 and 3.6/C None
49 MK503 Sheet MK503 shows a rainwater bubbler box detail. Is this detail expected to be used for this project? If so where is this being installed?
See sheet 37‐MP401 None
50 N/A Please confirm that no fire dampers will be required for this project
No fire dampers required. None
51 N/A Will any backing need to be installed behind drywall for surface mount equipment?
Yes, provide backing per detail F5/01‐AE533.
Where equipment is mounted to existing walls, Unistrut support spanning at least three studs my be used at Contractor's option.
None
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
52 N/A Will noise and vibration control be required for
MEP systems? If so, can specs and scope be furnished?
Yes, see spec section 23 05 41 New Section(s)
23 05 41
53 01 91 00 Is the commissioning process going to require a single person from each trade to be involved or will multiple representatives be required? If multiple is required, please list how many for each trade?
See response to RFI 43. None
54 01 91 00 Is phased commissioning expected for this project? How many commissioning trips should be figured by each contractor / subcontractor for pricing purposes?
See response to RFI 43. None
55 N/A Please provide hydraulic calculations for the existing sprinkler system.
Full hydraulic calculations for the existing system are not available. Design to be based on annual fire pump test information provided on Sheet
FP001.
None
56 N/A Please confirm that the existing fire sprinkler system will support the required extensions to the new IDF towers.
Confirmed. The existing sprinkler system is capable of supporting the extension of sprinklers into the new IDF towers. Note that the sprinkler subcontractor is responsible for providing hydraulic calculations to support their chosen design.
None
57 N/A Please provide pictures of room 0119 in building
1 where the RO tank and pump equipment will be located.
Refer to response to RFI# 7. None
58 07 84 00 Will 3rd part[y] firestopping inspections be required?
Yes, refer to 07 84 00/1.5‐C None
59 N/A Superintendent/SSHO Do not understand what's being asked None
60 N/A How many full time bodies are required for this project?
As many as the Contractor deems necessary to complete the Work within the stipulated time.
None
61 01‐GI002, Note 2 Regarding 01‐GI002 metal works note 2, please confirm the finish requirement for the structural steel framing related to the new building towers.
Disregard Metal Works note 1 and 2. Structural steel shall be shop primed per
05 12 00/2.4B.
None
62 01‐GC001 Sheet 01‐GC001 Building 01, Group 5, Data center note 10 says that an existing rack must be removed and reinstalled to demolish the existing
Liebert unit. Will the VA or the contractor be required to remove and reinstall this rack?
The contractor will be required to remove and reinstall this rack.
None
63 01‐GC001 Sheet 01‐GC001 Building 01, Group 2, Floors 2‐6 notes list durations for some features of work, are these durations suggestions, or does the
Government require these features to be completed in the stated durations?
These durations are suggestions only and not mandated by the VA.
None
64 01‐AE101
01‐GI002
The abatement keynote legend on sheet 01‐
AE101 mentions asbestos containing material to be removed from the ceiling and references sheet 01‐GI0002 for the quantities and details.
The callout is shown on the page for corridor
1231A on sheet 01‐AE101, however No details or information is provided on sheet 01‐GI0002 for ceilings. Please Clarify. This corridor scope does not appear to be related to this project
Abatement in Corridor 1231A was inadvertently omitted from the abatement schedule. There is approximately 263 square feet of ACM (texture over white plaster near elevator S5) that requires abatement.
Reissued sheet
01‐GI002
65 N/A Will the Division 27 contractor be required to provide heat mapping showing new wireless locations and coverage for this project? An example location of this is called out on sheet 01‐
TN100 general note 4.
Division 27 contractor to provide heat map per floor and determine required new WAP locations per TDR.
None
66 N/A Please provide locations of all of the existing
Wireless access points and quantities if they are to be rewired as part of this solicitation.
Division 27 contractor to provide heat map per floor and determine required new WAP locations per TDR.
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
67 02‐PP402 Is the 4” concrete equipment pad shown on sheet 02‐PP402 detail F4 existing, or will a new pad be required? If the pad is new, please provide plans for the new pad, as well as existing grade details, and details for attachment to the existing surface.
This will be a new equipment pad. Details to follow.
MK504 reissued
68 02‐PP402 Please provide elevations and a piping stand detail for note 3 on sheet 02PP402.
Details to follow. MK504 reissued
69 02‐EP401/F3 Can the new electrical circuits feeding the water softener on sheet 02‐EP401 detail F3 be routed overhead on the pipe stands with the new piping?
Electrical conduits can be routed at the same elevation with the plumbing piping; however, they need to be independently supported from the plumbing piping stands.
None
70 01‐PP407 The Elliptical RO water storage tank is shown on sheet 01‐PP407 with dimensions of
142”x84”x55”. Please provide an access route from exterior loading area and routing into room
0119 in the basement.
Coordinate route with VA None
71 01 00 00‐5 L.1 In 01 00 00‐5 L.1. It states the contractor shall maintain a minimum temp of 4 degrees C (40 degrees F) for every building/site that we occupy, this temperature seems significantly low, what are the normal operating temperatures of the facility or is this applicable?
Omit Article L, Contractor is not responsible for maintaining HVAC in areas where work in being done. System will be maintain by the facility at current operating temperatures.
None
72 Will the VA clarify if the Site Superintendent, if duly qualified, may also serve in the roles of CQC and SSHO for this project or if a separate individual will be required for either of those two roles?
See FAR 52.236‐13 Accident Prevention None
73 During the site visit, the necessity of multiple shifts was stressed to meet the POP, will the
SSHO, Superintendent, CQC roles need to be represented in all shifts?
See FAR 52.236‐13 Accident Prevention None
74 Telecom floor plan sheets
General Note #3 on the telecommunications floor plan drawing sheets indicates that Div 27 contractor is responsible “to investigate and locate (tone and test) all existing Category 5 cabling section cabling…” Since it appears that all existing Cat 5 cable will be removed and replaced as part of the scope of this project, does the Div
27 contractor need to tone and test the Cat 5 cable?
No. Tone cabling for location/investigation and replacing purposes.
None
75 Telecom floor plan sheets
General Note #4 on the telecommunications floor plan drawing sheets indicates that Div 27 contractor is responsible “to provide heat mapping showing new wireless locations and coverage.” Is this an actual requirement for the
Div 27 contractor?
Yes. Division 27 contractor to provide heat map per floor and determine required new WAP locations per TDR.
None
76 Please clarify the meaning of the meaning of and required work effort for cables/TRs identified as
“REMEDIATE IN PLACE on the telecommunications floor plan drawings.
TDR's to remain in place and existing CAT5 cabling is to be replaced with CAT6A.
None
77 08‐TN401 Bold is new equipment and shaded is existing. TR
0600 has bold 96U PP but states they are existing. Please clarify. (This also applies to multiple drawings.)
Refer to response to RFI#3 None
78 All Confirming that unless the TR legend states to install new Cat6A cabling the existing cabling will remain regardless of the cable category, other that WAP cabling that will be upgrade to Cat6A?
Refer to response to RFI#4 None
79 08‐TN402.1 Note 4 states to tone and test all existing cabling
(if applicable) Are we to include to tone and test all existing cabling that is not being replaced that has a bold PP? And relabel if necessary?
Refer to response to RFI#5 None
80 All Drawings state to locate and replace existing
WAP locations Is there a standard quantity we are to use for the WAP cabling locations, like 10 per TR or something as the actual quantity is unknow.
Refer to response to RFI#6 None
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
81 08‐TN401 Reference Drawing 08‐TN401: Bold is new equipment and shaded is existing. TR 0600 has bold 96U PP but states they are existing. Please clarify. (this also applies to multiple drawings).
Refer to response to RFI#3 None
82 All All Drawings: Confirming that unless the TR legend states to install new Cat6A cabling the existing cabling will remain regardless of the cable category, other than WAP cabling that will be upgraded to CAT6A. Please confirm or advise.
Refer to response to RFI#4 None
83 08‐TN402.1 Reference Drawing 08‐TN402.1: Note 4 states to tone and test all existing cabling (if applicable).
Are we to tone and test all existing cabling that is not being replaced that has a bold PP? And relabel if necessary?
Refer to response to RFI#5 None
84 All All Drawings: Drawings state to locate and replace existing WAP locations. Is there a standard quantity we are to use for the WAP cabling locations, such as 10 per TR for example?
The actual quantity is unknown, so we need a quantity to use for bidding purposes. Please advise.
Refer to response to RFI#6 None
85 01‐GI002
07 81 00 2.1 A.1
This is referencing mineral wool applied fireproofing. Other products are not listed.
Please reference sheet 01‐GI002 Code Analysis
Structural frame is listed with UL Design Y719.
This design is for Monokee Applied fireproofing.
Is Monokote an acceptable product to install?
Please provide UL design for tube steel with mineral fiber.
Refer to response to RFI #2 None
86 Are there any revisions to the Performance Work
Statement
Attached Performance Work Statement dated
6/10/2021, replaces all others issued to date
Preformance Work Statement 6/10/21
87 01 91 00 Is commissioning required for this project? No, commissioning is NOT required for this project, omit section 01 91 00 in it's entirety and all references to commissioning requirements throughout the specification. Refer to individual sections for startup, training, and demonstration requirements.
None
88 Is there an existing Physical Access Control
System (PACS) in place, or will this be a new stand alone system for future expansion?
An existing Physical Access control system is in place. This is an extension of that system.
None
89 Is there an existing Video Assessment and
Surveillance System (VASS)in place, or will this be a new stand alone system for future expansion?
An existing Video Assessment and Surveillance
System is in place. This is an extension of that system.
None
90 01‐AE601, 01‐
AD404, 01‐AE404
There are several rooms in Bldg.1 that are not listed on the finish schedule 01‐AE601; however the floor plan 01‐AE604 Rooms 1321A Detail C3, 1151 Detail C6, 1221A Detail F6 & 2207&2008A are all showing either epoxy finish or tile finish.
Are these rooms to be included in our bid price?
No 01‐AE604 sheet found. Follow key note 02 41
00.A2 as typical for all TR's in each bldg. Floor finish for all TR's called out in Keynote 09 62
80.A1. For rooms 2207 and 2008A follow detail
C1 on 01‐AE404. This information supercedes contrary information on the finish schedule.
Project No. 644‐20‐201
JUNE 30, 2021
RFI # Drawing/Spec
Reference
Question Response Attachments
91 Muliple Keyed
Notes.
Update for all parties: To any and all Keyed Notes within the drawings that reference a specific Legend, Detail, or
Schedule sheet please use the following sheet name changes:
1). PJ000 is now PI001
2). PK101 is now PK501
3). PK102 is now PK601
4). PK103 is now PK602
5). MJ000 is now MI001
6). MK101 is now MK501 (Mechanical Details changed to 500 series)
7). MK104 is now MK601
8). MK105 is now MJ501
9). MK106 is now MJ502
10). MK107 is now MJ503
11). MI001 is now MI901 (Schedules changed to
900 series)
12). EJ000 is now EI001
13). Electrical One‐Line Diagrams were EK601.
They are now EJ601 (for all buildings)
14). Electrical Panel Schedules were EJ601. They are now EJ501 (for all buildings)
TAB Scope Clarification
Project: VA PHX EHRM Project No: 00961.00
Date of Issue: 06/25/2021
Purpose: To better define the scope of work regarding the Test and Air Balance portion of this project.
All additions, corrections and clarifications are to be submitted to DHE Engineering within five days of receipt.
1. Pre-Construction: Anywhere a new Terminal Unit is being added or removed, rebalancing will need to take place. Prior to demolition there will be multiple airflow readings that need to be taken. First, perform a traverse reading in the duct mains upstream of where the work will take place. Next, perform airflow measurements on all diffusers and grilles downstream of where the traverse measurement was taken.
Once these measurements have been taken, submit to A/E team for their records.
2. Post-Construction: After construction is complete rebalancing will need to take place to ensure the spaces around the renovated rooms are left as they were prior to construction. Perform another traverse airflow measurement at the same spot as the traverse taken during pre-construction. Balance the system or adjust airflow from the Air Handler as needed to match the airflow that was acquired during the pre construction measurement. The same will need to be performed for all the diffusers and grilles that had pre construction airflow readings. Verify that the post construction measurement for all diffusers and grilles matches the pre construction measurements, adjust system as needed to acquire the correct airflow readings.
END OF REPORT
ACTUATED VALVES 1/2" – 3" UNIMIZER®:3-WAY
7/20 This specification © 2020 Griswold Controls F-5396J
1700 Barranca Parkway, Irvine, CA 92606
(949) 559-6000 Fax (949) 559-6088 www.GriswoldControls.com
SPECIFICATIONS
Static Pressure/Temp: 360 PSI / -4F to 250F (600 WOG) Service: Chilled water, hot water, up to 50%
Glycol, or contact factory for additional fluids.
Flow Optimizer: Glass Filled Polymer Body Material: Forged Brass ASTM B283-06 End Connections: Brass – NPT or BSP Field Repairable Stem: Dual Teflon seals and EPDM O-ring Stem Seals: EPDM O-Rings Ball Valve: Nickel-plated brass ball Ball Seals: Teflon Seals with EPDM O-Rings Angle of Rotation: 0-90 Installation: Valve can be installed in mixing or diverting installations.
Leakage Rate: A Port: ANSI Class IV; B: Port: Class III
DIMENSIONS & WEIGHTS (NOMINAL) (measured in inches and lbs unless noted) All dimensions are for planning purposes only and may change without notice.
SIZE
MODEL
NO.
THROUGH Cv
A:LENGTH B:HEIGHT C:LENGTH D:DEPTH
(NOT
SHOWN)
E:
HANDLE
F:HEIGHT G:HEIGHT
WEIGHT
FNPT BSP FNPT BSP FNPT BSP FNPT BSP FNPT BSP
1/2" UR3A_ 0.33, 0.59, 1.0, 2.4, 4.3, 8.0 2.7 2.7 3.4 3.4 7.0 7.0 3.0 2.0 9.5 9.5 2.0 2.0 1.6
3/4” UR3B_ 0.40, 0.66, 1.3, 2.4, 3.8, 7.0, 11.0 2.8 2.8 3.4 3.4 6.5 6.5 3.0 2.0 8.9 8.9 2.0 2.0 1.6
1” UR3C_
0.40, 0.65, 1.3, 2.3, 3.5, 10.0 2.8 2.8 3.4 3.4 7.3 7.3
3.0 2.0
9.6 9.6 2.1 2.1 1.6
8.6 3.0 3.0 3.9 3.9 6.8 6.8 9.9 9.9 2.4 2.4 2.3
4.5, 14.9, 22.3, 30.8 4.3 4.3 4.1 4.1 7.8 7.8 10.9 10.9 3.3 3.3 3.6
1-1/4” UR3D_
4.1, 8.7, 19.4 3.0 3.0 3.9 3.9 6.8 6.8
3.0 2.0
9.9 9.9 2.4 2.4 3.3
12.7, 26.8, 34.1 3.6 3.6 4.1 4.1 7.3 7.3 10.4 10.4 2.8 2.8 3.5
1-1/2” UR3E_
4.0, 8.3, 13.4, 32.0 3.4 3.4 4.1 4.1 7.8 7.8
3.0 2.0
10.9 10.9 2.7 2.7 3.6
23.5, 61.1 4.0 4.0 4.6 4.6 7.3 7.3 11.1 11.1 3.2 3.2 5.2
2” UR3F_
23.9, 38.2, 56.7 4.0 4.0 4.6 4.6 7.3 7.3
3.0 2.0
11.1 11.1 3.2 3.2 5.2
82.6, 108.5 5.0 5.0 5.9 5.9 7.8 7.8 12.4 12.4 3.8 3.8 8.5
2-1/2” UR3G_ 38.1, 74.1, 99.5 5.3 5.3 5.9 5.9 7.8 7.8 3.0 2.0 12.4 12.4 4.1 4.1 9.1
3"1 UR3H_ 75, 100, 125, 150, 175, 200 9.4 9.4 4.5 N/A2 10.1 10.1 7.1 2.0 12.3 12.3 2.8 N/A2 23.0
NOTES
1 Valve shown is 1/2" to 2-1/2". 3" valve has bypass port in Z plane.
2 Not available in 3" size.
A C
B
G
F
E
Valves shown are 1/2"-2-1/2".
3" valve has bypass port in Z plane www.GriswoldControls.com
THROUGH Cv SELECTION AND FLOW RATE TABLE (GPM)
LINE
SIZE
MODEL
NO.
THROUGH
Cv
FULL3
PORT
CLOSE
OFFP4
FLOWRATE (GPM) @ DIFFERENTIAL PRESSURE (PSI)
2-Position
HVAC Apps
HVAC Modulating Apps
Cv5
0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 7.0 10.0
1/2"
UR3AA_ A=0.33
50 PSI
0.2 0.33 0.4 0.5 0.5 0.6 0.6 0.7 0.7 0.7 0.9 1.0
UR3AB_ B=0.59 0.4 0.59 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.3 1.6 1.9
UR3AC_ C=1.0 0.7 1.0 1.2 1.4 1.6 1.7 1.9 2.0 2.1 2.2 2.6 3.2
UR3AD_ D=2.4 1.7 2.4 2.9 3.4 3.8 4.2 4.5 4.8 5.1 5.4 6.3 7.6
UR3AE_ E=4.3 3.0 4.3 5.3 6.1 6.8 7.4 8.0 8.6 9.1 9.6 11.4 13.6
UR3AF_ F=8.0 5.7 8.0 9.8 11.3 12.6 13.9 15.0 16.0 17.0 17.9 21.2 25.3
3/4"
UR3BA_ A=0.40
50 PSI
0.3 0.40 0.5 0.6 0.6 0.7 0.7 0.8 0.8 0.9 1.1 1.3
UR3BB_ B=0.66 0.5 0.66 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.7 2.1
UR3BC_ C=1.3 0.9 1.3 1.6 1.8 2.1 2.3 2.4 2.6 2.8 2.9 3.4 4.1
UR3BD_ D=2.4 1.7 2.4 2.9 3.4 3.8 4.2 4.5 4.8 5.1 5.4 6.3 7.6
UR3BE_ E=3.8 2.7 3.8 4.7 5.4 6.0 6.6 7.1 7.6 8.1 8.5 10.1 12.0
UR3BG_ G=7.0 4.9 7.0 8.6 9.9 11.1 12.1 13.1 14.0 14.8 15.7 18.5 22.1
UR3BF_ F=11.0 7.8 11.0 13.5 15.6 17.4 19.1 20.6 22.0 23.3 24.6 29.1 34.8
1"
UR3CA_ A=0.40
50 PSI
0.3 0.40 0.5 0.6 0.6 0.7 0.7 0.8 0.8 0.9 1.1 1.3
UR3CB_ B=0.65 0.5 0.65 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.7 2.1
UR3CC_ C=1.3 0.9 1.3 1.6 1.8 2.1 2.3 2.4 2.6 2.8 2.9 3.4 4.1
UR3CD_ D=2.3 1.6 2.3 2.8 3.3 3.6 4.0 4.3 4.6 4.9 5.1 6.1 7.3
UR3CE_ E=3.5 2.5 3.5 4.3 4.9 5.5 6.1 6.5 7.0 7.4 7.8 9.3 11.1
UR3CF_ F=10.0 7.1 10.0 12.2 14.1 15.8 17.3 18.7 20.0 21.2 22.4 26.5 31.6
UR3CG_ G=8.6 6.1 8.6 10.5 12.1 13.6 14.9 16.1 17.2 18.2 19.2 22.7 27.2
UR3CH_ H=22.3 15.8 22.3 27.3 31.5 35.3 38.6 41.7 44.6 47.3 49.9 59.0 70.5
UR3CJ_ J=14.9 10.5 14.9 18.2 21.1 23.6 25.8 27.9 29.8 31.6 33.3 39.4 47.1
UR3CK_ K=4.5 3.2 4.5 5.5 6.4 7.1 7.8 8.4 9.0 9.5 10.1 11.9 14.2
UR3CM_ M=30.8 21.8 30.8 37.7 43.6 48.7 53.3 57.6 61.6 65.3 68.9 81.5 97.4
1-1/4"
UR3DB_ B=19.4
40 PSI
13.7 19.4 23.8 27.4 30.7 33.6 36.3 38.8 41.2 43.4 51.3 61.3
UR3DC_ C=12.7 9.0 12.7 15.6 18.0 20.1 22.0 23.8 25.4 26.9 28.4 33.6 40.2
UR3DD_ D=4.1 2.9 4.1 5.0 5.7 6.4 7.0 7.6 8.1 8.6 9.1 10.7 12.8
UR3DE_ E=8.7 6.1 8.7 10.6 12.3 13.7 15.0 16.2 17.3 18.4 19.4 22.9 27.4
UR3DF_ F=34.1 24.1 34.1 41.8 48.2 53.9 59.1 63.8 68.2 72.3 76.2 90.2 107.8
UR3DG_ G=26.8 19.0 26.8 32.8 37.9 42.4 46.4 50.1 53.6 56.9 59.9 70.9 84.7
1-1/2"
UR3EA_ A=13.4
40 PSI
9.5 13.4 16.4 18.9 21.1 23.2 25.0 26.7 28.4 29.9 35.4 42.3
UR3EB_ B=4.0 2.8 4.0 4.9 5.7 6.4 7.0 7.5 8.1 8.5 9.0 10.7 12.7
UR3EC_ C=8.3 5.8 8.3 10.1 11.7 13.1 14.3 15.5 16.5 17.5 18.5 21.9 26.1
UR3ED_ D=32.0 22.6 32.0 39.2 45.3 50.6 55.5 59.9 64.0 67.9 71.6 84.7 101.3
UR3EE_ E=23.5 16.6 23.5 28.8 33.3 37.2 40.8 44.0 47.1 49.9 52.6 62.3 74.4
UR3EF_ F=61.1 43.2 61.1 74.8 86.4 96.6 105.8 114.3 122.2 129.6 136.6 161.6 193.2
2"
UR3FA_ A=23.9
40 PSI
16.9 23.9 29.3 33.8 37.8 41.4 44.7 47.8 50.7 53.4 63.2 75.6
UR3FB_ B=56.7 40.1 56.7 69.4 80.2 89.7 98.2 106.1 113.4 120.3 126.8 150.0 179.3
UR3FC_ C=38.2 27.0 38.2 46.8 54.0 60.4 66.2 71.5 76.4 81.0 85.4 101.1 120.8
UR3FD_ D=108.5 76.7 108.5 132.9 153.4 171.6 187.9 203 217 230 243 287 343
UR3FE_ E=82.6 58.4 82.6 101.2 116.8 130.6 143.1 154.5 165.2 175.2 184.7 219 261
2-1/2"
UR3GA_ A=38.1
40 PSI
26.9 38.1 46.7 53.9 60.2 66.0 71.3 76.2 80.8 85.2 100.8 120.5
UR3GC_ C=74.1 52.4 74.1 90.8 104.8 117.2 128.3 138.6 148.2 157.2 165.7 196.1 234
UR3GB_ B=99.5 70.4 99.5 121.9 140.7 157.3 172.3 186.1 199.0 211 223 263 315
3"
UR3HA_ A=75.0
70 PSI
53.0 75.0 91.9 106.1 118.6 129.9 140.3 150.0 159.1 167.7 198.4 237
UR3HB_ B=100.0 70.7 100.0 122.5 141.4 158.1 173.2 187.1 200 212 223 264 316
UR3HC_ C=125.0 88.4 125.0 153.1 176.8 197.6 216 234 250 265 279 331 395
UR3HD_ D=150.0 106.0 150.0 183.7 212 237 260 281 300 318 335 397 474
UR3HE_ E=175.0 123.7 175.0 214 247 277 303 327 350 371 391 463 553
UR3HF_ F=200.0 141.4 200 245 283 316 346 374 400 424 447 529 632
NOTES
3 These valves are full port and do not have the Optimizer insert.
4 Close-Off Pressures measured with 35 in-lb. actuator. The “Close Off Pressure” is the maximum allowable pressure drop across the valve body when the valve is fully closed. (Do not use actuators with torques higher than 90 in-lbs) 5 The Cv is the gallons of water per minute (gpm) at 60°F that the valve will pass at 1 PSI pressure drop. Hence the 1.0 PSI pressure differential column in the table above is equivalent to the Cv value.
www.GriswoldControls.com
MODEL NUMBER SELECTION
PIPING CONFIGURATIONS
Our 3-Way ball allows the same 3-Way valve to be installed in either a mixing or diverting configuration without sacrificing any performance or Cv. (Valve shown is 1/2"-2-1/2". 3"-6” valve has bypass port in Z plane.)
ACTUATOR SELECTION
The Griswold Controls Universal Mounting Plate on all 1/2" to 3" valves is compatible with the following actuators besides the actuators detailed in the following tables. Contact the factory if you have a different model number not listed below.6.
Honeywell: ML6161D2006, ML6174D2009, ML7161A2008, ML7174A2001, ML6185A1000, ML6185C1008, ML8185A1008, ML8185C1006, ML7285A1007, ML7285C1005, MN6105, MN7510, MN7520, MN6110
Schneider Electric: MF40-6083, MA40-7043, MA40-7043-501, MA40-7040, MA40-7040-
501, MF40-7043, MF40-7043-501, MS40-7043, MS40-7043-501
Johnson Controls: M9106-AGA2, M9106-AGC2, M9106-GGA2, M9106-GGC2, M9206-
AGA2, M9206-AGC2, M9206-GGA2, M9206-GGC2, M9104-AGA-2S, M9208-GGA-2,
M9208-GGA-3
Belimo: LM24, LM24S, LF24, LF24S, LF120, LF120S, LF24-3, LF24-3S, LM24SR, LF24SR, LF24SRS, LMB24-SR-T, LMB24-3-T
Neptronic: BBT-24, BBT-1000, BBT-1060, BBT-1021, BBT-1080, BBTHV-1100, BBTHV-
1160, BBTHV-1120, BBTHV-1180, BBM2000A, BBM2060A
NOTES
6 Do not use actuators capable of torques higher than 90 in-lbs.
U R 3
Select a Line Size: A=1/2", B=3/4", C=1", D=1-1/4", E=1-1/2", F=2", G=2-1/2", H=3"
T= Optional 3" x 3"
Aluminum Hanging ID Tag
Select a Through Cv from "Flow Rate Table"
Select Type: F=FNPT, B=BSP2
M
Insert Actuator Model Number. If Actuator is supplied by others, insert "1" for Neptronic, "2" for Johnson Controls, "3" for Schneider Electric, "4" for Honeywell, "5" for Siemens, "6" for Belimo, "7" for KMC Controls
Select Ball and Stem: B=Standard www.GriswoldControls.com
SUITABLE FOR 1/2" TO 3" VALVES
SIEMENS GDE131.1P GDE161.1P GMA121.1P GMA131.1P GMA161.1P
Power Supply 24Vac 24Vac 24Vac/dc 24Vac/dc 24Vac/dc Torque 44 in-lb 44 in-lb 62 in-lb 62 in-lb 62 in-lb Control Signal: On/Off Control Signal: 3 Point Control Signal: Modulating
0–10 VDC
Speed 90 sec 90 sec 90 sec 90 sec 90 sec Fail Safe (Spring Return) Operating Power 3.3 VA 3.3 VA 5 VA 5 VA 5 VA Mounting Components 9656-250 9656-250 9656-250 9656-250 9656-250 Weight 1.1 pounds 1.1 pounds 3.0 pounds 3.0 pounds 3.0 pounds
Wiring Diagram
Where 6 is CW and 7 is CCW
SUITABLE FOR 1/2" TO 3/4" VALVES ONLY
SUITABLE FOR 1/2" TO 3" VALVES
KMC CONTROLS MEP-4201 MEP-4255 MEP-4252
Power Supply 24 Vac/dc 100-240 Vac 24 Vac/dc Torque 25 in-lb 25 in-lb 25 in-lb Control Signal: On/Off Control Signal: 3 Point
Control Signal:
Modulating
2-10VDC
Speed <35 sec <25 sec <50 sec Fail Safe (Capacitor) Operating Power 6 VA 6 VA 6 VA Mounting Components 9656-248 9656-248 9656-248 Weight 1.1 pounds 1.5 pounds 1.5 pounds Wiring Diagram See actuator cover for wiring diagram
KMC CONTROLS MEP-4001 MEP-4002 MEP-4554 MEP-4555 MEP-4501
MEP-4552
(formerly
MEP-5372)
MEP-4551
(formerly
MEP-5373)
MCP-
36315000
Power Supply 24 Vac 24 Vac 24 Vac/dc 100-240
Vac 24 Vac 24 Vac 24 Vac Pneumatic
Torque 40 in-lb 40 in-lb 45 in-lb 45 in-lb 40 in-lb 45 in-lb 45 in-lb 59 in-lb Control Signal: On/Off Control Signal: 3 Point
Control Signal:
Modulating
2-10VDC
Modulating
2-10VDC
8-13 psi
Speed 90 sec 90 sec <35 sec <25 sec <35 sec 50 sec 90 sec Fail Safe (Capacitor) Operating Power 2 VA 4 VA 6 VA 6 VA 6 VA 6 VA 6 VA Mounting Components 9656-250 9656-250 9656-248 9656-248 9656-248 9656-250 9656-250 9656-852 Weight 1.1 pounds 1.1 pounds 1.5pounds 1.5 pounds 1.1 pounds 3.0 pounds 3.0 pounds 1.5 pounds Wiring Diagram See actuator cover for wiring diagram
PERFORMANCE WORK STATEMENT
EHRM Upgrades ‐ Construction
644‐20‐201
THE PHOENIX ARIZONA VETERAN ADMINISTRATION HEALTH CARE SYSTEM (PVAHCS)
Carl T. Hayden Medical Center
650 E. Indian School Road
Phoenix, AZ 85012
06/10/2021
The contract and/or services will not include performance or provision or portion therefore (installation, service, storage, use, sharing, or distribution), involving Veteran or individually identifiable information, including any of 18 HIPAA identifiers, PHI, PII, and/or information that is sensitive.
Prepared by:
Rich Casey, Capital Program Supervisor
Scope
Construction Hospital operations shall not be unexpectedly impacted during this project. All impacted shall be planned with the COR as an outage (See more information in part 11 below). Patient care cannot be compromised during this project; therefore, it is highly likely construction will require carefully coordinated phasing to not impact patient care. Minor outages may be permitted if no reasonable alternatives exist but must be planned and approved in advance of the requested date. See below for more details.
Successful outcomes include, but not limited to, the following requirements:
NOTE: Requirements are the roadmap to the outcomes.
Requirements begin with the CFM Program Guide for Construction and reference to the design Technical Information Library (TIL).
1) Work Hours – Normal work hours are Monday through Friday, 0630-1630. Times for weekend work and evening work, if required, will be agreed upon by the contractor and
COR.
2) Submittals – Contractor shall use Submittal Exchange (or equal) as a means of communicating with the VA. Submittal Exchange shall be provided within 72 hours after award.
3) Daily Reports – Contractor shall provide a daily report. The daily report shall include any safety issues, personnel onsite and the company they work for along with the hours worked.
a. The daily reports shall be provided to the COR within 24 hours of each workday.
b. The safety inspection form shall have the project number, project start date, project end date and an area for the date and initials by the contractor’s safety officer.
c. The safety inspection form shall be filled out by the contractor’s safety officer at the beginning and end of each workday.
d. The Contractor shall comply with ICRA and ILSM requirements during construction.
4) Schedule of Values (SOV) – Contractor’s Schedule of Values shall be submitted within 48 hours after award of the contract.
a. The SOV will be broken down by phase of construction and CSI division of work and materials.
b. The cost of the General Conditions per day must also be presented on contractors the Schedule of Values.
c. The Schedule of Values is to be presented as a submittal for the VA COR review and Contracting Officer’s written approval.
d. Contractor to provide a detailed cost schedule for each section within the specification’s table of contents, provided in MS Excel format.
5) Outages – The scheduled timing of all outages requires a 21 calendar days’ written notice to the VA’s Contracting Officer’s Representative (COR). This overrides the 7 and 15 day outage timeframes in the specifications.
a. All work closing down any section of the hospital shall be considered an outage.
b. Any work impacting the telecommunications of part of the facility shall be considered an outage.
c. Written notice shall include:
i. Details of the work being performed including tasks and personnel performing the work.
ii. All changes to the ILSM and ICRA. Work with the COR to identify these.
iii. Duration of the outage, times, and dates.
d. All outages shall be approved in writing by the COR 14 days’ in advance.
e. The priority for performing any outages are as follows:
i. Weekends between 0630 and 1500
ii. After 1630 on weekdays
iii. After 1500 on weekends
iv. During normal work hours
f. The contractor cannot perform the outage without written approval by the COR.
6) Vacating the Area – Before mobilization the VA will clear all movable items and equipment they will salvage.
a. The remaining serviceable and usable items will be removed by the contractor.
The VA reserves the right to claim any serviceable/usable items. Items not claimed by the VA will be the responsibility of the contractor to remove from the facility campus.
7) Pre-Construction Meeting – The pre-construction meeting shall be held before mobilization between, the contractor’s management, contractor’s site superintendent, contractor’s safety officer, VA contracting officer and VA contracting officers’ representative.
a. All training of clinician and maintenance personnel required shall be identified in writing by the contractor, prior the pre-construction meeting.
b. Identification is defined as listing the specification section, training requirements, personnel (company) performing the training and including the training in the overall project schedule.
c. All warranty items shall be identified in writing by the contractor no later than 50% of the project schedules completion.
d. A complete testing plan shall be provided at the pre-construction meeting.
i. Plan will list out all testing in the specifications and approximate percentage of project completion for when the test shall take place.
e. At the pre-construction meeting, the contractor shall submit to the VA, the critical path for the project, validating their review of the guide listed above.
8) Inspecting Personnel – Along with personnel listed in the requirements, during installation, the following items will be inspected by the personnel below and the COR before being covered/sealed:
a) Electrical work –Electrical Shop Supervisor
b) Mechanical work –HVAC Shop Supervisor
c) Plumbing work - Plumbing Shop Supervisor
d) Structural work – COR/AE
e) Data/Telecom/Special systems work –Special systems supervisor
f) IT Work – IT Supervisor
g) Miscellaneous work – COR/AE
9) Written Deliverables – It is the contractor’s responsibility to provide all written requirements on time. It is the contractor’s responsibility to request all written requirements from the COR on time.
10) Oversight – The Contractor shall always have a site superintendent present when there is work in progress and/or contractors onsite, including subcontractors.
a. COR shall be notified work will take place prior to any work commencing. This includes work of the contractor and all subcontractors.
11) Critical Path – The following areas will have limited access and are considered critical path of this project. Administration space shall be the alternate area to perform work when the contractor cannot work in the below space:
a. ICU
b. Inpatient Wards to include 2C, 4C, 4D, 3B, 2A
c. Mental Health Wards 5C and 5D
d. Inpatient Radiology
e. Surgery
f. Jade Opal Clinic
12) Work to be performed – This project includes communications infrastructure upgrades within one primary facility and eleven other minor buildings across the Phoenix Veterans Administration Medical Center Campus. This includes either the relocation/replacement or remodel of approximately 47 existing telecommunications rooms (TRs) and one data center, to bring them up to VA Electronic Health Records Modernization (EHRM) IT standards while IT services remain operational. The contractor shall provide a turn-key project for these rooms in accordance with VA Office of Information and Technology (OIT) and EHRM infrastructure standards, as follows:
a. Construct two new towers along the exterior of the existing primary facility.
Towers are constructed using structural steel HSS sections, with light steel framing wall infill, and potential to support off-site fabrication in modules. The towers will contain in total, ten TR’s, ten small electrical rooms and ten small mechanical rooms. New TR’s in towers will replace approximately fifteen existing TR’s.
b. Expand three existing TR’s in the primary facility and one TR in a minor building on campus.
c. Renovate approximately twenty-eight TR’s by upgrading HVAC, electrical and telecom infrastructure.
d. Installation of upgraded communication infrastructure (new data outlets, patch panels, upgrade to Cat 6A cable as needed to achieve 1GB connectivity to end user devices. Upgrade and provide redundant fiber-optic cabling.
e. Installation of all low voltage raceway systems and room fittings to support network equipment, including all required bracing/backing/mounting materials and back boxes to support installation of IT equipment.
f. Installation of required power, grounding, uninterruptible power supplies, building management system, fire protection/alarm and security system interfaces.
Address HVAC requirements, and other system requirements, for TRs/data centers in the area or associated with the area of work.
g. Removal of all legacy IT equipment and room fittings (e.g., racks, cable trays) from any TR that is being abandoned due to TR relocations under the scope of this effort. Removal of abandoned or replaced cabling.
Attachments:
644-20-201_DrawingsSet1of2 644-20-201_DrawingsSet1of2 644-20-201_Specifications
PVAHCS - Carl T Hayden Medical Center
Project No. 644-20-201 June 25, 2021
23 05 41 - 1
SECTION 23 05 41
NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the application of noise control measures, and vibration control techniques to boiler plant rotating equipment and parts including chillers, cooling towers, boilers, pumps, fans, compressors, motors and steam turbines.
B. A complete listing of all common acronyms and abbreviations are included in Section
23 05 11, COMMON WORK RESULTS FOR HVAC.
Noise criteria, , vibration tolerance and vibration isolation for HVAC and plumbing work.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA and SAMPLES.
B. Section 23 05 10, COMMON WORK RESULTS FOR HVAC.
C. Section 23 31 00, HVAC DUCTS and CASINGS.
1.3 QUALITY ASSURANCE
A. Refer to article, QUALITY ASSURANCE in specification Section 23 05 11, COMMON
WORK RESULTS FOR HVAC and STEAM GENERATION.
B. Noise Criteria:
1. Noise levels in all 8 octave bands due to equipment and duct systems shall not exceed following NC levels:
TYPE OF ROOM NC LEVEL
Audio Speech Pathology 25
Audio Suites 25
Auditoriums, Theaters 35-40
Bathrooms and Toilet Rooms 40
Chapels 35
Conference Rooms 35
Corridors (Nurse Stations) 40
Corridors(Public) 40
Dining Rooms, Food Services/ Serving 40
Examination Rooms 35
Gymnasiums 50
Project No. 644-20-201 June 25, 2021
230541 - 2
Kitchens 50
Laboratories (With Fume Hoods) 45 to 55
Laundries 50
Lobbies, Waiting…
This is the start of the file's text. The full file is on GovTribe.