Attachment B (Project Description and Scope of Work).docx

DOCX document 76 KB Posted

Attached to
Wolf Mtn. Communication Site Build
Solicitation number
S-73000-00008156
Issued by
Lane County, Oregon

About this file

This document is the Attachment B (Project Description and Scope of Work) for the Oregon Department of Transportation (ODOT) Wireless Communications Section's Wolf Mountain Communications Site Build project. The project involves the construction of a new radio communications facility, including a transmission tower and ancillary facilities, on Wolf Mountain in the Willamette National Forest. ODOT will provide the shelter, generator, tower, and propane tank, while the contractor is responsible for the remaining materials and installation. The mandatory construction period is during the summer of 2024, between June 1 and November 29. The contractor must comply with various federal, state, and local permitting requirements, as well as technical specifications outlined in the attachments. The project requires special inspections, testing, and commissioning, and the contractor is responsible for maintaining the access road and site condition during and after construction.

The contract opportunity does not provide details on pricing terms, set asides, incumbents, funding requirements and sources, or other financial information. The focus is on the technical requirements and project scope for the construction of the new communication site.

View the file

Other files

File Type Posted
35809_ITB_PW dojapprvd.docx DOCX document
Attachment C (Specifications).pdf PDF
Attachment E (GeoTechReport)(For Informational Purposes Only)08192016.pdf PDF
35809 Addendum 3 Revised.docx DOCX document
Attachment A-1 (Site Plans).pdf PDF
Attachment G (LMR Antenna System Standard).pdf PDF
35809 Addendum 1.docx DOCX document
Attachment D (Permits).pdf PDF
35809 Addendum 6_Final.docx DOCX document
Attachment A-2 (Tower Plans).pdf PDF
Attachment A-3 (Communication Shelter Plans).pdf PDF
Attachment F (Communication Site Antenna and Tower Mounted Equipment Installation Standards).pdf PDF
Attachment I (Structural Analysis Report)(For informational purposes only).pdf PDF
35809 Addendum 2.docx DOCX document
Mandatory_Pre-Bid_Sign_In_Roster(For Informational Purposes Only).pdf PDF
35809 Addendum 4_Final.docx DOCX document
35809 Addendum 5_Final.docx DOCX document
Attachment A-4 (Generator Shelter Plans).pdf PDF
Attachment D (Permits)~1.pdf PDF
Attachment J (Bid Pricing Form) Revised.xlsx XLSX spreadsheet
Preliminary Results~70.xlsx XLSX spreadsheet
WMCP RFP advertisement.pdf PDF
Attachment A (Site Plans) InfoOnly.pdf PDF
Attachment B (Tower Plans)~1.pdf PDF
Attachment C (Specifications Manual) Revised~1.doc DOC document
Attachment E (GeoTechReport)(For Informational Purposes Only)08192016~1.pdf PDF
Attachment H (Antenna Sweep Display Examples).pdf PDF
Intent To Award~4.xlsx XLSX spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Department of Transportation Wireless Communications Section Communications Site Construction Scope of Work – Wolf Mountain

ATTACHMENT B

PROJECT DESCRIPTION AND SCOPE OF WORK

Oregon Department of Transportation Wireless Communications Section

PROJECT NAME: Wolf Mountain Communications Site Build (the “Project”)

SCOPE OF WORK: The Project is construction of a new radio communications facility for public safety, including a transmissions tower and ancillary facilities, on Wolf Mountain in the Willamette National Forest. This is a raw land full communication site build including tower, ice bridge, radio room and generator shelter, propane tank, site grounding, and electrical.

Oregon Department of Transportation (“ODOT” or “Agency”) will provide shelters, generator, tower, and propane tank. The remaining materials are the responsibility of Contractor.

WORK LOCATION: The radio communications facility, including transmissions tower and ancillary facilities, is located on Wolf Mountain in the Willamette National Forest (the “Site”). Access is via Forest Road 526 which connects to Forest Road 23, which travels southeast from Oakridge and Kitson Springs.

This is a high elevation site that has limited access during winter months. Construction will need to be performed during the summer months when the Site is accessible. If Contractor schedules work to occur during winter months, Contractor shall be responsible for any snow clearing for Site access and any damage to the access road that occurs from snow access at no cost to Agency.

Contractor shall be responsible for monitoring the forecasted weather. If Contractor’s schedule places their equipment at risk of being trapped on site due to a snow event, Contractor is responsible for removing the equipment. Agency will not provide additional payment for equipment charges for equipment trapped on site due to weather.

MANDATORY CONSTRUCTION PERIOD: The Project has a mandatory construction period. Construction must be completed during the weather-permitting period commencing summer of 2024, anticipated to be between June 1, 2024 – November 29, 2024.

APPLICABLE SPECIFICATIONS: Contractor shall comply with this Project Description and Scope of Work, including all requirements contained herein.

The Specifications Manual (Attachment C) sets forth the technical requirements applicable to this Project and incorporates the 2021 Oregon Standard Specifications for Construction (“Standard Specifications”), which are by this reference incorporated herein. Some sections of the specifications may be identified and modified by Attachment A-1 – A-4 (Plans). If there is any conflict between this Project Description and Scope of Work and the specifications, this document shall prevail.

Additional installation and equipment standards applicable to this Project can be found in:

· Attachment F – Communication Site Antenna and Tower Mounted Equipment Installation Standards

· Attachment G – LMR Antenna System Standard

· Attachment H – Antenna Sweep Display Examples

Contractor shall comply with the additional project requirements found at:

· Attachment D – Permits

Contractor shall complete grounding per the current, at the time of construction, Motorola R56 Grounding Guidelines (“Grounding Guidelines”), which is incorporated herein by this reference.

LIMITATIONS OF OPERATIONS: Prior to and following construction, the Site requires an Agency escort or approval for access.

PROJECT SCHEDULES AND CONSTRUCTION REPORTING: Contractor shall maintain an up-to-date project schedule submitting revisions on a weekly basis if needed. At a minimum, the project schedule should include the following milestones when applicable to the project scope:

· Construction Start

· Each foundation concrete placement

· Below grade grounding inspection

· Tower stack

· Shelter set

· Propane tank installation

· Propane line test

· Generator commissioning

· Commercial power installation

· Fence installation

· Substantial Completion

· Final Completion At the end of each week, Contractor shall submit to Agency, their representatives, and the Engineer of Record a construction progress report that summarizes the work completed that week including photos documenting the progress.

PROJECT REQUIREMENTS

The following are Project Requirements applicable to this Project:

I. PERMITS AND FEDERAL REQUIREMENTS

a. The Site is located on federal land but subject to Lane County land use and permitting. Agency has acquired the land use approval for the Site, including variances from Lane County Building codes.

b. Agency has or will obtain the following and provide to Contractor if necessary for the Project:

· Lane County – Building Permit

· Lane County – Land Use Permit

· Special Use Permit 509-PA22-05636

· Special Use Permit 509-PA22-05637

· USFS Lease/Special Use Authorization (as amended) (WIL193 authorization for Private Mobile Radio Service 3-5-18)

· USDA Decision Memo – Wolf Mountain Tower Replacement Project – USDA Forest Service (10/20/17) and NTP (7-18-22)

· Operation & Maintenance Plan / Mitigation Measures

· Design Criteria & Implementation Guidance

c. Contractor shall obtain any required additional permits.

d. Federal Requirements.

i. All USFS construction regulations must be followed including equipment spill protection plans and means.

ii. All USFS Fire regulations must be followed during construction.

II. SITE PREP

a. Existing Conditions. Contractor shall be responsible for:

iii. Documenting the condition of the access road at the start of construction. Any claims made against Agency for damage to the road as a result of construction will be passed on to Contractor to resolve.

iv. Any repairs or maintenance to the Site access roads, during and immediately following construction, to ensure the roads remain in the same condition as before construction.

v. Maintaining existing gravel parking and drive areas leading up to and at the Site in the same or better condition at project completion, including adding new gravel as needed.

vi. Maintaining accessibility. The Site is being constructed near other existing communications facilities which will need to remain accessible during the duration of construction. This also includes not obstructing radio frequency paths with equipment.

· If a disturbance to one of the other sites is required as part of this construction, it is the responsibility of the Contractor to coordinate with the appropriate site operators.

b. Infrastructure. For infrastructure above and below grade, Contractor shall connect the new buildings and electrical. Contractor shall:

i. For future use, pull strings in all conduits installed.

ii. Install appropriate termination at each end of all conduits.

c. Dewatering. High water levels may be encountered. Based on pre-bid observation of the Site, Contractor shall include sufficient time in the proposed construction schedule to accommodate dewatering that may be required. Should high water levels be encountered during construction, Contractor shall consult with Agency and Engineer to agree on construction plan for dewatering the site. The dewatering plan and compensation, if applicable, must be implemented by a Contract Change Order (“CCO”).

d. Earthwork.

i. Contractor shall comply with all grading requirements set forth in Attachment C.

ii. Contractor shall provide, install, and maintain all necessary sedimentation control and erosion prevention per Attachment A-1.

iii. Contractor shall comply with structural fill requirements per Attachment E, the geotechnical investigation report, and Attachment A-1, engineer design requirements, including importing and exporting construction spoils.

iv. If Contractor finds excavated materials do not match the design documents, Contractor shall seek written approval from Agency for clarification on the use of the material.

v. If Contractor fails to appropriately schedule and execute the work and to protect, preserve, and properly handle earth materials suitable for fill such that suitable soil materials become unusable, Contractor shall be responsible to provide suitable imported fill material at no cost to Agency.

Signage and Hardware. Contractor shall provide all new signage and install with tamper proof hardware.

ii. Signage to be installed on the building on or near the radio room door.

III. SHELTER WITH SNOW VESTIBULES

Agency purchased a 12'x20' prefabricated equipment shelter and a mated 12'x10' prefabricated generator shelter, approx. 50,000 pounds.

a. Transport. Contractor shall transport shelters to the Site from the storage location located at the ODOT Maintenance Yard in Oakridge, Oregon.

i. Contractor shall provide the equipment for shelter pick up, off load, and installation on site.

ii. Contractor shall perform all field assembly of shelters installed as part of this contract.

b. Foundations. Contractor shall install and cure foundations to the requirements in Attachment A-1.

c. Installation.

i. Shelter anchoring requires inspection to verify anchor installation to the foundation.

ii. Contractor shall be responsible for field electrical connections for all newly installed shelters.

iii. Contractor shall provide and install two vestibules with snow hatches and snow hatch ladders.

iv. At Substantial Completion, the shelter shall be clean, fully operational, and ready for use by Agency.

IV. GENERATOR

Agency will provide the generator, seismic isolators, and controller.

a. Transport. Contractor shall transport generator and generator equipment from Agency’s Salem Yard to the Site.

b. Installation. Contractor shall install the generator.

i. Installation includes:

· Cummins 40kW (C40N6)

· Seismic Isolators

· PC500 Controller

ii. Contractor shall not use galvanized gas piping on all fuel supply lines.

iii. Contractor shall provide and install snorkels on the generator shelter.

· Snorkels shall maintain the same air volume flow for the generator as the building openings.

· Snorkels shall be constructed of corrosion resistant material.

· Snorkels shall have ice shielding.

· Contractor shall provide and install ice shields for the two HVAC units.

V. TOWER

Agency will provide a 120-ft lattice tower. The upper 60-ft of the tower are new unused sections from another project. The lower 60-ft is being manufactured to the original tower design to match the upper tower sections.

a. Transport. Contractor shall provide pickup, transport, and offload tower sections from the following locations to the Site:

i. Lower sections – from Hwy 58 site

ii. Upper sections – from Agency’s Salem Yard

b. Foundations. Contractor shall install and cure foundations to the requirements in Attachment A-1.

c. Tower Installation.

i. Contractor shall provide stainless steel or galvanized exterior hardware. Contractor shall hot-dip galvanize all Contractor-supplied steel parts.

ii. All required field modifications to steel must be properly treated with cold galvanizing compound.

iii. All exterior zip ties must be stainless steel. Protruding ends of all interior nylon zip ties must be flush cut. All interior zip ties must be black UV resistant nylon.

iv. All exposed Unistrut and all-thread ends must be covered with appropriately sized rubber caps.

v. Contractor shall notify the Agency 48 hours in advance of beginning construction of the tower and 24 hours in advance of completing construction of the tower to full height.

vi. Contractor shall install tower climb and waveguide ladder per the plans.

d. RF Antenna Installation. Agency will provide antennas and ancillary equipment to be installed on tower. ODOT is providing the following materials to complete the installations of the antennas: antennas, clamps, RF jumper cables, mounting brackets, mounting hardware, hoist grips, cushion standoff kits, adaptors, Heliax cable, DIN connectors and weather hoods, ground kits, polyphasers, electrical tape, cable ties, entry panel (where needed) and weatherproofing kit. Contractor shall supply all other materials, tooling, and transportation equipment necessary to complete this work.

i. Transport. Contractor shall pickup all provided materials from the ODOT Salem Yard and transport to the Site.

· Contractor shall return any unused provided materials from the Site to the ODOT Salem Yard or to the ODOT Wireless Area Radio Specialist.

ii. Installation. Contractor shall:

· Install the following 7 RF antennas on the tower per Attachment A-1, pages S-1 and S-2, and according to the Communication Site Antenna and Tower Mounted Equipment Installation Standards document (Attachment F): Antennas 1, 2, 3, 4, 5, 8, and 9.

· Provide pictures of the installed antennas and weatherproofed connectors upon completion of work.

· Route all new transmission lines into the shelter through entry ports leaving several feet to allow for equipment rack positioning.

· Sweep test the antennas according to the LMR Antenna System Standard Method and Antenna Sweep Display Examples (Attachments G and H).

· Reports shall be submitted to ODOT and will be reviewed and verified by ODOT personnel at completion of installation.

· Notify the Project Manager(s) at least 48 hours prior to performing sweep tests.

· Document all ODOT asset tag information on the installed antennas.

· Providing photos of the tags with the Part/Serial Number manufacturer tag is the simplest method we suggest.

VI. ICE BRIDGE

Contractor shall purchase the ice bridge.

a. Installation. Contractor shall install the ice bridge and posts from shelter to tower.

i. The ice bridge requires heavy duty angle iron construction method for high elevation sites.

VII. PROPANE TANK

Agency will provide the 1000-gallon propane tank.

a. Transport. Contractor shall transport propane tank from Agency’s Salem Yard to the Site.

b. Installation.

i. Contractor shall provide and install:

· Concrete pad

· Propane tank (Agency-provided)

· 60-ft buried gas line to shelter

· Protective bollards

· Ice shield and posts

ii. Contractor shall not use galvanized gas piping on all fuel supply lines.

· Contractor shall review and supply construction drawings to propane subcontractor to confirm accuracy for propane line build and installation.

VIII. POWER

a. Installation. Contractor shall install electrical work per Attachment A-1.

i. Electrical installation shall occur under or immediately adjacent to the existing access road from the existing pole mounted transformer adjacent to the existing AT&T access road to the main service disconnect to be located on the shelter.

ii. Contractor shall coordinate underground power installation with local utility provider, Lane Electric Cooperative.

iii. Contractor shall perform all electrical Work in compliance with the National Electric Code and the local jurisdiction requirements.

iv. Contractor shall obtain any electrical permits required by the local jurisdiction.

v. Contractor shall notify the Agency and the Agency 72 hours prior to installation of a new power meter.

b. Grounding. Contractor shall perform all grounding work in accordance with this Attachment, Attachment A-1, and the current version of the Grounding Guidelines in addition to all applicable local, State, and national codes.

i. Contractor shall provide three-point fall of potential test of the installed ground ring upon site completion. This test shall be performed in accordance with Motorola’s procedures and recommendations. This test can be performed after the site is operational.

ii. If there is a conflict between this Attachment, Attachment A-1 and the Grounding Guidelines, Contractor shall request clarification through the Agency.

iii. New buildings, tower, ice bridge installations, and grounding upgrades require new ground bar installations as shown in Attachment A-1. Ground bar locations are at the tower (“TGB”) and interior (“MGB”) and exterior (“EGB”) of the entry port.

iv. Attachment A-1 may not give a full representation of all required grounding bonds. Contractor shall bond all exterior metal components and structures per Grounding Guidelines.

v. While Grounding Guidelines allow for irreversible below grade ground connections, Agency will only accept exothermic welds.

IX. INSPECTIONS

a. Special Inspector Inspections.

i. Contractor shall coordinate with Agency’s Special Inspector for all concrete, soils density, proctor, and steel inspections. Contractor shall collect all proctor samples for all proposed fill material (native and imported).

ii. Contractor shall coordinate with the Agency at least 48 hours prior to need for inspection. The minimum required inspections include concrete, steel, soils density, grounding, erosion control, and periodic inspections. All required inspections are listed in Attachment A-1.

iii. Additional aspects of the project may require inspection by Agency’s Special Inspector as required by the building permit. Refer to the permit package for the specifics.

iv. Concrete. Special Inspections (provided by Agency) and Agency inspections are required for all reinforced concrete with specified strength greater than 2500 psi.

· Concrete inspection required includes both reinforcing steel prior to pour and concrete during pour.

· Agency’s Special Inspector will provide up to 8 compression cylinders, tested (broken) on the following schedule: 3, 5, 7, 14, two at 28 days, and hold/56 days. The remaining cylinders are at the Contractor’s discretion for the test (break) days.

v. Earthwork. Fill placed below foundations and structural areas require inspection and testing.

· If tests are not performed as required, Contractor shall excavate and refill the area with the tester on site at Contractor’s expense.

b. Agency Representative Inspections.

i. An Agency Representative shall inspect the following key aspects of the site:

· Installation of fill including compaction of any non-structural fill

· Below grade conduit installation

· Below grade grounding

· Ufer grounds

· Grounding installation above grade conformance to standards

· Conformance to the site design

· Ground System fall of Potential Test (required witness during test)

· Fence post footings

· Substantial Completion

· Final Completion

ii. Inspection requests must be submitted at least one week prior to the desired inspection date.

iii. Power. Electrical Work may be reviewed by the Agency in addition to jurisdiction inspections.

· The Contractor shall provide access to all closed electrical boxes in which Contractor has performed Work.

iv. Grounding. All below-grade grounding constructed as part of this Contract requires Agency inspection before backfilling.

· In some jurisdictions, the jurisdiction may require inspecting aspects of the grounding in addition to the Agency inspection.

X. TESTING AND COMMISSIONING

a. Generator Commissioning. Contractor shall coordinate generator commissioning with generator supplier.

i. Commissioning shall include generator preparation, installation of battery, start-up and a 1-hour load-bank test.

ii. Contractor shall also coordinate scheduling of the commissioning with the Agency at least one week in advance of the commissioning.

iii. Commissioning by supplier is at no charge to Contractor.

b. HVAC. New heating, ventilation, and air conditioning units require commissioning by a licensed HVAC professional to be hired and provided by Contractor.

XI. CLOSE OUT

a. Road Repair. See II.a.iii above.

b. “Free of Vegetation.” Contractor shall ensure site compound is free of vegetation upon Site completion.

i. All tree stumps, debris and slash resulting from clearing of the Site, and all excess excavation materials become property of Contractor.

ii. Contractor shall remove all tree stumps, debris, slash, and all excess excavation materials from the Site and properly dispose of them. Contractor shall make all arrangements for suitable disposal.

iii. Contractor shall not burn debris and slash on Site.

c. Quality Control. Contractor shall inspect all installed equipment and structures for damages and quality and shall document the installation with photos immediately upon final construction, installation or assembly.

i. Contractor shall include sufficient photos in the Weekly Progress Report to document the installation and sufficient photos in the Closeout Package to document the quality of the installation.

image1.png