Attachment A - Cost Details 22019.xlsx

XLSX spreadsheet 199 KB Posted

Attached to
472/22091. SMD; Parnall CF - New Heavy Diesel Program (CM)
Solicitation number
RFP - 171 - 230000000652
Issued by
Jackson County, Michigan

About this file

This document is an Attachment A - Cost Details for the state and local contract opportunity 472/22091. SMD; Parnall CF - New Heavy Diesel Program (CM) issued by the State of Michigan for Jackson County. The contract opportunity requests services for a New Heavy Diesel Program at the Parnall Correctional Facility. The contract term is not specified, and no renewal options are mentioned. No information is provided regarding the specific products or services required, item quantities, response dates, due dates, site visits, bidder's meetings and conferences, or award dates.

The document contains cost details, but does not provide any information on pricing terms, set asides, incumbents, funding requirements and sources, or other salient details. The document appears to be a supporting exhibit with financial information, but the context and purpose within the overall contract opportunity is not clear from the provided information.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Conditions

ERROR:#REF!

Field Office Costs & Reimbursables and General Conditions duration: 11 months

NUMQuantityUnitRateTotal
CostComments
Field Offices
31IT Equipment(Computers,printers,etc.)0devices$3,000Not Included
312.90%IT Support / Assistance0months$150Not Included
31Proj. Mgmt. Internet Based Software0months$500Not Included
31Proj. Mgmt. Internet Teamsite0lump sum$1,500Not Included
31Internet Connectivity - Setup / Activation/Deactivation1lump sum$500$500
31Internet Connectivity - Access11months$450$4,950
31Project Office Trailer11months$500$5,500
32East Side Superintendent Trailer0months$1,250Not Included
32Set-up/Teardown Site Office1allow$2,000$2,000
32Temporary Toilets11months$250$2,750
Drinking Water11months$150$1,650
Gas, Water, Electric Hook up for Trailers1lump sum$2,000$2,000
32Temporary Water Connection for Trailers11lump sum$30$330
33Wireless Communications11months$900$9,900
33Copy/FAX/Office Equipment11months$500$5,500
33Telephone (including monthly bills)11months$400$4,400
Travel11months$1,200$13,200
33Office Furnishings1lump sum$1,500$1,500
34Office Supplies11months$500$5,500
34Postage & Express11months$300$3,300
34Printing (Internal)1lump sum$7,500$7,500
34Office Electrical Power11allow$500$5,500

Total Field Offices & Reimbursables: $75,980

&F&A Page &P of &N &D

GC's

INSTRUCTIONS: ATTACHMENT A

The following tables are provided to assist you in determining the projected total cost for the Construction Manager to perform their Management Services as described in the proposed CM Agreement (Attachment B).

It is not a requirement for you to complete all of the line items in the table for your proposal to be considered. However, all of the items listed on the table must be included in your projected total costs and costs for each category must be completed. The CM shall be limited to reimbursement for only those items priced below, If the CM requires items not listed in order to perform the CM services for the project please identify those additional items where indicated "Other - list as applicable" below. If an item listed below does not apply please mark it N/A.

PRE CONSTRUCTION PHASE COSTS
NAMEITEMQUANTITYUNITRATETOTAL
Project Executive$0
Sr. Project Manager$0
Project Manager$0
Project Engineer$0
Project Superintendent$0
Assistant Superintendent$0
Field Engineer$0
Layout Engineer$0
Safety Officer$0
Lead Estimator$0
Estimator$0
Civil Estimator$0
Mechanical Estimator$0
Electrical Estimator$0
Secretarial & Clerical$0
Accounting$0
Other - list as applicable:$0
$0
$0
$0
CM Pre-Construction Phase Reimbursable Expenses$0
Travel/Mileage/Meals (INCLUDE IN STAFF RATES)
Electronic Plan Room$0
Document Reproductions$0
Postage & Expressage$0
Other - list as applicable:$0
$0
$0
$0
TOTAL PRE CONSTRUCTION PHASE COSTS$0
BIDDING PHASE STAFF COSTS
NAMEITEMQUANTITYUNITRATETOTAL
Project Executive$0
Sr. Project Manager$0
Project Manager$0
Project Engineer$0
Project Superintendent$0
Assistant Superintendent$0
Field Engineer$0
Layout Engineer$0
Safety Officer$0
Lead Estimator$0
Estimator$0
Civil Estimator$0
Mechanical Estimator$0
Electrical Estimator$0
Secretarial & Clerical$0
Accounting$0
Other - list as applicable:$0
$0
$0
$0
$0
Travel/Mileage/Meals (INCLUDE IN STAFF RATES)
$0
TOTAL BIDDING PHASE STAFF COSTS$0
CONSTRUCTION PHASE STAFF COSTS
NAMEITEMQUANTITYUNITRATETOTAL
Project Executive$0
Sr. Project Manager$0
Project Manager$0
Project Engineer$0
Project Superintendent$0
Assistant Superintendent$0
Field Engineer$0
Layout Engineer$0
Safety Officer$0
Lead Estimator$0
Estimator$0
Civil Estimator$0
Mechanical Estimator$0
Electrical Estimator$0
Secretarial & Clerical$0
Accounting$0
Other - list as applicable:$0
$0
$0
$0
$0
Travel/Mileage/Meals (INCLUDE IN STAFF RATES)
$0
TOTAL CONSTRUCTION PHASE STAFF COSTS$0
CLOSEOUT PHASE STAFF COSTS
NAMEITEMQUANTITYUNITRATETOTAL
Project Executive$0
Sr. Project Manager$0
Project Manager$0
Project Engineer$0
Project Superintendent$0
Assistant Superintendent$0
Field Engineer$0
Layout Engineer$0
Safety Officer$0
Lead Estimator$0
Estimator$0
Civil Estimator$0
Mechanical Estimator$0
Electrical Estimator$0
Secretarial & Clerical$0
Accounting$0
Other - list as applicable:$0
$0
$0
$0
$0
Travel/Mileage/Meals (INCLUDE IN STAFF RATES)
$0
CLOSEOUT PHASE STAFF COSTS$0
REIMBURSABLE CM GENERAL CONDITION EXPENSES
ITEMQUANTITYRATEUNITTOTAL
CONSTRUCTION MANAGER GENERAL CONDITIONS - only those costs required for the CM to perform its management services
Temp Office Trailer Rental$0
Temp Office Trailer Set Up$0
Temp Office Trailer Furnishings$0
Temp Office Trailer HVAC$0
Temp Office Trailer Electric$0
Temporary water to trailer(s)$0
Temp Office Trailer toilets$0
Site Office Supplies$0
Site Office Water Cooler$0
Postage$0
Express Mail$0
Digital Photography & Video$0
Copy/Scan Machine$0
Printers$0
Computers$0
Temp Office Equipment$0
Printing$0
Internet Set Up and Service Fee$0
Software & Support$0
Mobile Phone Expense$0
Field Office Phone service$0
Field Office Phone Equipment$0
Site Two Way Radio$0
On site Vehicle & Fuel Expenses$0
Site Office Debris Removal$0
Travel/Mileage/Meals (INCLUDE IN STAFF RATES)
$0
Other - list as applicable:$0
$0
$0
$0
$0
$0
Performance/Payment Bonds (COST PER PROPOSAL SUMMARY PAGE)
CM CGL Insurance (COST PER PROPOSAL SUMMARY PAGE)
Builder's Risk Insurance (COST PER PROPOSAL SUMMARY PAGE)
$0
TOTAL CM GENERAL CONDITIONS EXPENSES$0
Construction Support General Conditions shall be defined and estimated by the CM in conjunction with the Project Team as design develops. CM shall manage all construction support general conditions either as a reimbursable expense, at cost (no mark up), or assigned to a trade contract as recommended by the CM and mutually accepted by the Project Team.
Construction Support General Conditions may include, but not limited to, items such as the following with preliminary recommended assignment identified by CM:
Construction Support General Conditions
Trade ContCM Reimb
Quality Control & Testing
Construction Quality Control Testing Bldg/Site
Permits & Special Fees (if applicable)
Driveway/Roadway Improvement Permits, Bond & Fees
Building Permits
Specialty Permits
Water Connection Fees
Sanitary Connection Fees
Storm Connection Fees
Gas Service Charges
Electric Power Service Charges
Soil Erosion & Sedimentation Control (from DTMB)
Other permits/fees
Barricades, Enclosure & Control Signs
Project Sign
Safety Signage
Opening Protection
Weather Enclosure
Control Signs
Temporary Fencing
Covered Walkways
Site Barricades / Fences
On-Site Utilities
Temporary Electric
Temporary Water
Winter Heat
Temporary Building HVAC
Temporary Building HVAC Energy/Costs
Other On-Site Services
Layout Engineering/Surveying
Site Security
Site Webcam
Project Wide Hoisting (if applicable)
Safety and First Aid
Trade Contract & storage Trailers
Small Tools & Supplies
Temporary Toilets
Temporary Fire Protection
Weekly Clean-up
Final Clean-up
Dump Permits & Fees (RECYCLING preferred)
Debris Hauling/Removal (RECYCLING preferred)
Temporary Road Installation/Maint.
Temp Stair/lift
Roadway Maintenance
Storage Trailers
Dust Control
Snow Removal

Other (Specify)

DNR Parks Division - ARPA Improvements

751/22384.CDP

Page &P

File details come from the government source that posted it. Updated .