This document is an Addendum to a Request for Construction Management Proposal issued by the Michigan Department of Technology, Management and Budget for the Parnall Correctional Facility Vocational Village Expansion - New Diesel Mechanic Program project. The Addendum provides clarifications and modifications to the original RFP, including the provision of 50% Design Development drawings, the requirement to submit a "certification of Michigan Based Business and Responsibility Certification" form, and directions on how to complete the Cost Proposal forms. The proposal due date is 1/26/2023.

The RFP has a Not-to-Exceed cost of $7,500,000, which proposers are instructed to use in completing the Cost Proposal forms. Proposers are also required to provide a simple projected cost estimate based on estimated square foot costs to verify the reasonableness of the $7,500,000 basis number. The RFP combines the RFQ and RFP submission into a single process to expedite the selection.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 6/16)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR CONSTRUCTION

MANAGEMENT PROPOSAL

ADDENDUM NO. 2

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

1/20/2023

PROJECT NAME

Parnall Correctional Facility Vocational Village Expansion – New Diesel Mechanic Program

FILE NUMBER

472/22019.SMD

PROJECT DIRECTOR

Scott DeKorte

PROPOSAL DUE DATE:

1/26/2023

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

1. Attachment “C” is the 50% Design Development drawings issued with the RFP.

2. Section I-4 of the RFP: Provide “certification of Michigan Based Business and Responsibility

Certification” form. These are the same as Part 3-Proposal Certification.

3. Attachment E-Scope of Work Outline: This form shows the basis of the scope of work to be included in the RFP. This form is for informational purposes only. No additional action is requested with this form.

4. Part 2-Cost Proposal: $7,500,000” is to be inserted where “$AMOUNT” is indicated. $7,500,000 is to be used for the NTE cost listed at the bottom of the form (Line C).

5. Part 3-Proposal Cost: The cost listed on this sheet is to equal “total CM cost proposal subtotal” (Line A) on Part 2-Cost Proposal.

6. The complete RFP is a joint RFQ and RFP submission. Although this varies slightly from previous SOM CM processes, we have elected to combine them within this RFP to expedite the process.

7. A simple projected cost estimate based on estimated square foot costs should be part of this RFP.

The review committee is simply looking to verify that the $7,500,000.00 CM basis number is reasonable or unreasonable for the scope of work dictated. A simple verbal description (single paragraph) will suffice.