Attachment 9 - 668-16-110_Feasibility Study_Cost Estimate .pdf
PDF 291 KB Posted
- Solicitation number
- 36C26024R0038
About this file
This notice requests Standard Form 330 Architect-Engineer Qualifications packages for a design contract to modify the existing hot and cold potable water distribution systems in Buildings 1 and 12 at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The contract is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses and has an anticipated period of performance of 315 calendar days for design completion and a magnitude of construction between $1,000,000 and $2,000,000. Submissions are due by April 15, 2024 and will be evaluated based on professional qualifications, specialized experience and technical competence, capacity, past performance, knowledge of the locality, and experience in construction period services. The highest rated firm will receive a request for fee proposal to negotiate a fixed-price contract for architectural and engineering services.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Spokane Secondary Disinfection System 668-16-110ACC Cost Consultants, LLC Estimate Date: 27-Jul-21
Mann-Grandstaff VA Medical Center Seth J. Pszczolkowski Document Date: 14-Jul-21
Spokane, Washington 8060 SW Pfaffle Street, Suite 110 Print Date: 27-Jul-21
William Wilson Architects PC Tigard, Oregon 97223-8489 Print Time: 12:01 PM
Feasibility Study - v1.0 Phone: (503) 718-0075 Fax: (503) 718-0077 www.ArchCost.com Constr. Start: 01-Jul-22
DIRECT CONSTRUCTION COST SUMMARY
Component Total
Estimate $837,155
TOTAL DIRECT CONSTRUCTION COST $837,155
Budget 0 TBD
Indicated Surplus / (Deficit) (837,155)
The above estimates are for direct construction cost only. They do not include furnishings & equipment, architect and engineer design fees, consultant fees, inspection and testing fees, plan check fees, hazardous material testing and removal, financing costs, owners contingency, nor any other normally associated development costs.
The above estimates assume a competitively bid project, with at least three qualified bidders in each of the major sub-trades as well as the general contractors.
The above estimates assume a construction start date of: July 2022. If the start of construction is delayed beyond the date above, the estimates must be indexed at a rate of 5% to 7% per year compounded.
This is a probable cost estimate based on in-progress documentation provided by the Architect. The actual bid documents will vary from this estimate due to document completion, detailing, specification, addendum, etc. The estimator has no control over the cost or availability of labor, equipment, materials, over market conditions or contractor's method of pricing, and contractor's construction logistics and scheduling. This estimate is formulated on the estimator's professional judgment and experience. The estimate makes no warranty, expressed or implied, that the quantities, bids or the negotiated cost of the work will not vary from the estimator's opinion of probable construction cost.
Executive Summary - Page 1
VA Spokane Secondary Disinfection System 668-16-110ACC Cost Consultants, LLC Estimate Date: 27-Jul-21
Mann-Grandstaff VA Medical Center Stanley J. Pszczolkowski Document Date: 14-Jul-21
Spokane, Washington 8060 SW Pfaffle Street, Suite 110 Print Date: 27-Jul-21
William Wilson Architects PC Tigard, Oregon 97223-8489 Print Time: 12:01 PM
Feasibility Study - v1.0 Phone: (503) 718-0075 Fax: (503) 718-0077 www.ArchCost.com Constr. Start: 01-Jul-22
SUMMARY Base Building
DIRECT CONSTRUCTION COSTS Cost
Area
02 | EXISTING CONDITIONS $19,000
09 | FINISHES 16,800
22 | PLUMBING 400,606
26 | ELECTRICAL 19,131
SUB-TOTAL $455,537
Premium for after hours work / coordination 68,331 Verify
Estimating / Design Contingency 5.00% 26,193 Market Interest / Procurement Procedures 5.00% 27,503 normally 5 to 8%, use 5%
Index To Construction Start 5.00% 27,503 escalation rate @ ± 5% per year
General Conditions / Insurance / Bond 15.50% 93,785 General Contractor OH & Profit 10.00% 69,885 Washington State Sales Tax 8.90% 68,418
TOTAL DIRECT CONSTRUCTION COST $837,155
Comments
Division Summary - Page 2
VA Spokane Secondary Disinfection System 668-16-110ACC Cost Consultants, LLC Estimate Date: 27-Jul-21
Spokane, Washington 8060 SW Pfaffle Street, Suite 110 Print Date: 27-Jul-21
William Wilson Architects PC Tigard, Oregon 97223-8489 Print Time: 12:01 PM
Feasibility Study - v1.0 Phone: (503) 718-0075 Fax: (503) 718-0077 www.ArchCost.com Constr. Start: 01-Jul-22
Estimate Quantity Unit Cost / Unit Cost Sub-totals Comments
02 | EXISTING CONDITIONS
Demolition o demo existing allowance 1 allw $15,000.00 $15,000 o temp barricades 1 sum 1,500.00 1,500 o cont. clean-up 1 sum 2,500.00 2,500
Sub-total $19,000
SUB-TOTAL 02 | EXISTING CONDITIONS $19,000
09 | FINISHES
Patch Flooring & Walls patch / repair flooring & walls 1 allow 15,000.00 15,000
Sub-total 15,000
Paint & Wallcoverings x paint walls - allowance 1 sum 1,500.00 1,500 o misc. specialty painting, touchup 1 sum 300.00 300
Sub-total 1,800
SUB-TOTAL 09 | FINISHES $16,800
22 | PLUMBING
Mechanical o mobilization 1 sum 15,000.00 15,000 sink / lav filter addition 40 ea 1,276.00 51,040 mixing valve replace / add 96 ea 700.73 67,270 cw pipe <2" 2,800 lf 62.74 175,685
7.5 ton chiller 1 ea 18,240.00 18,240 3 ton chiller 1 ea 14,390.00 14,390 chiller pipe 750 lf 37.78 28,335 recirculation pump 3 ea 1,110.00 3,330 balancing valve 8 ea 461.25 3,690 balancing calibration 24 hr 95.00 2,280 braized plate heat exchanger 3 ea 3,506.67 10,520 miscellaneous project costs 2% 1 allw 7,826.00 7,826 project closeout 1 sum 3,000.00 3,000 Sub-total 400,606
SUB-TOTAL 22 | PLUMBING $400,606
Estimate - Page 3
VA Spokane Secondary Disinfection System 668-16-110ACC Cost Consultants, LLC Estimate Date: 27-Jul-21
Spokane, Washington 8060 SW Pfaffle Street, Suite 110 Print Date: 27-Jul-21
William Wilson Architects PC Tigard, Oregon 97223-8489 Print Time: 12:01 PM
Feasibility Study - v1.0 Phone: (503) 718-0075 Fax: (503) 718-0077 www.ArchCost.com Constr. Start: 01-Jul-22
Estimate Quantity Unit Cost / Unit Cost Sub-totals Comments
26 | ELECTRICAL
Electrical ch-1 / 1" emt conduit 100 lf 8.74 874 ch-1 / 1" rigid conduit 10 lf 20.08 201 ch-1 / #6 awg thwn, 3+1g 5 clf 175.18 788 ch-1 / #12 awg thwn, 2+1g 4 clf 67.77 237 ch-1 / nema 3r fusible disconnect, 3p-60a 1 ea 719.41 719 ch-1 / 3p-50a breaker 1 ea 289.24 289 ch-1 / 1p-20a breaker 1 ea 96.71 97 ch-1 / weatherproof in-use rec cover 1 ea 41.42 41 ch-1 / gfci 20a hospital grade rec 1 ea 77.73 78 ch-1 / masonry mount single gang box, steel 1 ea 37.10 37 ch-1 / coupling sealtite to rigid 1" 1 ea 60.71 61 ch-1 / coupling sealtite to rigid 3/4" 1 ea 46.60 47 ch-1 / weatherproof flex conduit, 1" x 10' 1 ea 295.83 296 ch-1 / emt fittings, 1" 1 ea 138.70 139 ch-1 / rigid fittings, 1" 1 ea 326.22 326 ch-1 / emt fittings 3/4" 10 ea 9.38 94 ch-1 / rigid fittings 3/4" 10 ea 25.96 260 ch-1 / flex fittings, 1" 2 ea 34.90 70 ch-1 / miscellaneous parts 1 sum 454.55 455 ch-1 / field bends, 1" & 3/4" 1 sum 104.67 105 ch-1 / core drill, 1" 2 ea 83.14 166 ch-1 / core drill, 3/4" 2 ea 67.15 134 ch-1 / throughwall seal, 1" 1 ea 456.42 456 ch-1 / throughwall seal, 3/4" 1 ea 441.19 441 ch-1 / emt, 3/4" 100 lf 7.11 711 ch-2 / 1" emt conduit 100 lf 8.74 874 ch-2 / 1" rigid conduit 10 lf 20.08 201 ch-2 / #6 awg thwn, 3+1g 5 clf 175.18 788 ch-2 / #12 awg thwn, 2+1g 4 clf 67.77 237 ch-2 / nema 3r fusible disconnect, 3p-60a 1 ea 719.41 719 ch-2 / 1p-20a breaker 1 ea 289.24 289 ch-2 / 3p-50a breaker 1 ea 96.71 97 ch-2 / weatherproof in-use rec cover 1 ea 41.42 41 ch-2 / gfci 20a hospital grade rec 1 ea 77.73 78 ch-2 / masonry mount single gang box, steel 1 ea 37.10 37 ch-2 / coupling sealtite to rigid 1" 1 ea 60.71 61 ch-2 / coupling sealtite to rigid 3/4" 1 ea 46.60 47 ch-2 / weatherproof flex conduit, 1"x10' 1 ea 295.83 296 ch-2 / emt fittings, 1" 1 ea 138.70 139 ch-2 / rigid fittings, 1" 1 ea 326.22 326 ch-2 / emt fittings 3/4" 10 ea 9.38 94 ch-2 / rigid fittings 3/4" 10 ea 25.96 260 ch-2 / flex fittings, 1" 2 ea 34.90 70 ch-2 / miscellaneous parts 1 sum 454.55 455 ch-2 / field bends, 1" & 3/4" 1 sum 104.67 105 ch-2 / core drill, 1" 2 ea 83.14 166 ch-2 / core drill, 3/4" 2 ea 67.15 134 ch-2 / throughwall seal, 1" 1 ea 456.42 456 ch-2 / throughwall seal, 3/4" 1 ea 441.19 441 ch-2 / emt, 3/4" 100 lf 7.11 711 chwp-1 / emt, 3/4" 100 sum 7.11 711 chwp-1 / emt fittings, 3/4" 10 sum 9.38 94 chwp-1 / 1p-20a breaker 1 sum 96.71 97 chwp-1 / 1 / #12 awg 2+1G 4 sum 67.77 237 chwp-1 / hospital grade 20a rec xtra heavy duty 1 sum 77.10 77
Estimate - Page 4
VA Spokane Secondary Disinfection System 668-16-110ACC Cost Consultants, LLC Estimate Date: 27-Jul-21
Spokane, Washington 8060 SW Pfaffle Street, Suite 110 Print Date: 27-Jul-21
William Wilson Architects PC Tigard, Oregon 97223-8489 Print Time: 12:01 PM
Feasibility Study - v1.0 Phone: (503) 718-0075 Fax: (503) 718-0077 www.ArchCost.com Constr. Start: 01-Jul-22
Estimate Quantity Unit Cost / Unit Cost Sub-totals Comments
26 | ELECTRICAL - Continued
Electrical - continued chwp-1 / 4" ss box 1 sum 38.80 39 chwp-1 / field bends 1 sum 104.67 105 chwp-1 / core drill, 3/4" 2 sum 67.15 134 chwp-1 / misc parts 1 sum 134.50 135 chwp-2 / emt, 3/4" 100 sum 7.11 711 chwp-2 / emt fittings, 3/4" 10 sum 9.38 94 chwp-2 / 1p-20a breaker 1 sum 96.71 97 chwp-2 / 1 / #12 awg 2+1G 4 sum 67.77 237 chwp-2 / hospital grade 20a rec xtra heavy duty 1 sum 77.10 77 chwp-2 / 4" ss box 1 sum 38.80 39 chwp-2 / field bends 1 sum 104.67 105 chwp-2 / core drill, 3/4" 2 sum 67.15 134 chwp-2 / misc parts 1 sum 134.50 135 chwp-3 / emt, 3/4" 100 sum 7.11 711 chwp-3 / emt fittings, 3/4" 10 sum 9.38 94 chwp-3 / 1p-20a breaker 1 sum 96.71 97 chwp-3 / 1 / #12 awg 2+1G 4 sum 67.77 237 chwp-3 / hospital grade 20a rec xtra heavy duty 1 sum 77.10 77 chwp-3 / 4" ss box 1 sum 38.80 39 chwp-3 / field bends 1 sum 104.67 105 chwp-3 / core drill, 3/4" 2 sum 67.15 134 chwp-3 / misc parts 1 sum 134.50 135
Sub-total 19,131
SUB-TOTAL 26 | ELECTRICAL $19,131
SUB-TOTAL 455,537 $455,537
Premium for after hours work / coordination 15.00% 68,331 Verify
Estimating / Design Contingency 5.00% 26,193 Market Interest / Procurement Procedures 5.00% 27,503 normally 5 to 8%, use 5%
Index To Construction Start 01-Jul-22 5.00% 27,503 escalation rate @ ± 5% per year
General Conditions / Insurance / Bond 15.50% 93,785 General Contractor OH & Profit 10.00% 69,885 Washington State Sales Tax 8.90% 68,418 381,618 83.77%
TOTAL DIRECT CONSTRUCTION COST
Estimate $837,155
Estimate - Page 5
File details come from the government source that posted it. Updated .