Attachment 8 - Sample Work Plan.pdf

PDF 680 KB Posted

Attached to
AMENDMENT NO. 1 to SOLICITATION - Building Climate Resilience (BCR) Activity Federal contract opportunity
Solicitation number
72052221R00002
Issued by
US Agency for International Development Honduras

View the file

Other files for this federal contract opportunity

Other files attached to AMENDMENT NO. 1 to SOLICITATION - Building Climate Resilience (BCR) Activity, newest first.
File Type Posted
Amendment No. 1_Attachment 1.g. Results Framework.pdf PDF
Amendment No. 1_72052221R00002 final.pdf PDF
Amendment No. 1_Attachment 2 - Budget Template.xlsx XLSX spreadsheet
Amendment No. 1_Attachment 4 - Key Indvidual Certification.pdf PDF
Amendment No. 1_Attachment 11 - Q&As Document.pdf PDF
Amendment No.1_Attachment 1.h. Estrategia de Monitoreo_Calidad de Agua.pdf PDF
Amendment No. 1_Attachment 3 - Branding Strategy.pdf PDF
Amendment No. 1_Attachment 1.f. Migration Indicators Guidance.pdf PDF
Amendment No. 1_Attachment 1.e. USAIDs Geotargeting Approach.pdf PDF
Amendment No. 1_Attachment 1.i. Analisis Rápido de los Ecosistemas Críticos.pdf PDF
Amendment No. 1_72052221R00002 Revised RFPfinal.pdf PDF
Amendment No. 1_RFP Cover letter final.pdf PDF
RFP 7205221R00002Cover letter.pdf PDF
Attachment 9 - LCP 10OCT2021.pdf PDF
Attachment 5 - EBD Form No. AID 1420-17.doc DOC document
Attachment 4 - Key Indvidual Certification.pdf PDF
Attachment 1. b Western Honduras VA_ENGLISH_FINAL.pdf PDF
Attachment 7 - Past Performance Matrix.xlsx XLSX spreadsheet
RFP 72052221R00002.pdf PDF
Attachment 10 - Subcontrating Plan.pdf PDF
Attachment 2 - Budget Template.xlsx XLSX spreadsheet
Attachment 1. d USAID_FY_2021_Honduras_Country_Roadmap_en_US.pdf PDF
Attachment 1. c USAID_FY_2020_Honduras_Country_Roadmap_en_US.pdf PDF
Attachment 1. a USAID_Honduras CDCS Public Version_CLEAN.pdf PDF
Attachment 6 - LACIEE2105 ETD HO - Amend LACIEE1634 Extreme Poverty Sustainably Reduced.pdf PDF
Attachment 3 - Branding Strategy.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. 72052221R00007

ATTACHMENT 8

SAMPLE WORK PLAN

2001 2002

RESULTS, TASKS AND SUB-TASKS

LABOR

(WITH LOE IN

DAYS, BY

ACTIVITY)

RESOURCES INVOLVED

PROCESS &

OUTCOME

MEASURES SE

P

O C

T

N O

V

D

EC

JA

N

FE

B

M A

R

PR

M

Y

JU

N

JU

L

A U

G

YEAR 2 /

NOTES

1.1 I.R. or SUB-I.R.:

1.1.1. TASK: CCN-ST: (220)

TCN-ST TBD (30)

USN-ST TBD (30) Ongoing

Activity

1.1.1.1. Sub-Task:

Also supports another I.R. Cross-reference with 2.1.14.3.

1.1.2. TASK:

Continued until completion

Three 30 person hotel venue workshops @ $2500 per workshop.

25 regional 3 day trips @ $750 airfare and $112 per diem.

Three 30 person hotel venue workshops @ $2500 per workshop.

Workplan with LOE and Key Direct Costs rmetzger Callout This is the detailed workplan.

rmetzger Callout Figures found in the first table (Component Summary Budget) are also included under the “Labor” and “Resources” column.

rmetzger Line rmetzger Callout Amounts are indicated at the Task level; i.e., the amounts indicated are the sum of costs or LOE anticipated for all sub-tasks specified under the Task in question. In other words, the amounts indicated next to Tasks are aggregations of any amounts indicated for the sub-tasks found under each task.

rmetzger Callout Tasks are distinguished by 3 digits numbers (e.g. 1.2.1) and are in bold type.

rmetzger Callout Sub-Tasks have identification numbers with 4 or more digits.

rmetzger Callout This column provides examples of expected resulting work-products or the processes to be followed when activities are being implemented according to plan. The items identified should be a natural byproduct of appropriate progress in the completion of each activity or sub-activity.

Attachments 2-7
Attachment 2 - Branding Strategy
Attachment 3 - Key Ind Certification
Attachment 4 - IEE
LAC-IEE-15-65
IEE prepared by: Sofia Mendez, EG
Peter Hearne, MEO
INITIAL ENVIRONMENTAL EXAMINATION
Activity Location: Honduras
IEE Prepared by: Sofia Mendez, EG
Peter Hearne, MEO
Associated IEEs: LAC-IEE-10-82, LAC-IEE-14-13
1.0 BACKGROUND AND PROJECT DESCRIPTION
1.1 Purpose and Scope of IEE
1.2 Background
1.3 Sub-IR Descriptions with Illustrative Interventions
Current and Planned Activities
1.4 Geographic Coverage and Existing Conditions
1.5 National Environmental Policies, Procedures and Regulations
2. EVALUATION OF ENVIRONMENTAL IMPACT POTENTIAL
3. RECOMMENDED THRESHOLD DECISION AND MITIGATION ACTIONS
Environmental Compliance Language for Awards
Guidelines for Implementing Partners
USAID/Latin American and Caribbean Bureau (LAC) ENVIRONMENTAL MITIGATION and MONITORING PLAN (EMMP) 0F
USAID/LAC ENVIRONMENTAL MITIGATION and MONITORING PLAN (EMMP)