attachment-7-rfb-dmavs-2026-06.docx

DOCX document 26 KB Posted

Attached to
Center Strafford Site MEP Upgrades
Solicitation number
RFB DMAVS 2026-06
Issued by
Strafford County, New Hampshire

About this file

This is a Temporary Facilities and Controls specification document for the Center Strafford Site MEP (Mechanical, Electrical, Plumbing) Upgrades project in New Hampshire. The document establishes requirements for temporary construction infrastructure including electricity, lighting, heating, cooling, ventilation, water service, sanitary facilities, and field offices. The contractor must provide flexible power cords, main service disconnects, temporary lighting for interior work areas and security purposes, branch wiring from power sources to distribution boxes, and temporary heating and cooling systems while utilizing existing building systems where available. Temporary ventilation must be provided to achieve material curing, dissipate humidity, and prevent accumulation of dust and fumes. The contractor must establish temporary water service, portable sanitary facilities, and coordinate any field office locations with the Department prior to placement, with storage areas sized according to Section specifications and maintained throughout the project duration.

The Department will pay for temporary electricity and water usage, with contractors required to exercise energy conservation measures. Contractors and subcontractors must park only in Department-designated spaces and are responsible for maintaining parking areas, approach walks, and general site cleanliness through weekly debris removal. The specification requires interior enclosures using temporary partitions with reinforced polyethylene and plywood to separate work areas from Department-occupied spaces, prevent dust and moisture penetration, and protect existing materials and equipment. Additionally, the contractor must implement a comprehensive security program restricting site access to authorized personnel with proper identification and maintaining worker logs available to the Department, maintain dust and pollution control measures in accordance with environmental regulations, implement rodent control measures, and remove all temporary utilities, equipment, and facilities prior to Final Application for Payment while restoring existing facilities to original condition.

View the file

Other files

File Type Posted
attachment-6-rfb-dmavs-2026-06.docx DOCX document
attachment-5-rfb-dmavs-2026-06.docx DOCX document
attachment-1-rfb-dmavs-2026-06.docx DOCX document
attachment-4-rfb-dmavs-2026-06.docx DOCX document
addendum-2-rfb-dmavs-2026-06.pdf PDF
addendum-4-rfb-dmavs-2026-06.pdf PDF
addendum-3-rfb-dmavs-2026-06.pdf PDF
attachment-2-rfb-dmavs-2026-06.docx DOCX document
attachment-10-rfb-dmavs-2026-06.docx DOCX document
attachment-3-rfb-dmavs-2026-06.docx DOCX document
attachment-8-rfb-dmavs-2026-06.docx DOCX document
attachment-11-rfb-dmavs-2026-06-upgrades.pdf PDF
rfb-dmavs-2026-06.pdf PDF
addendum-1-rfb-dmavs-2026-06.pdf PDF
attachment-9-rfb-dmavs-2026-06.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEMPORARY FACILITIES AND CONTROLS

1. TEMPORARY ELECTRICITY

A. The Department will pay cost of energy used. Exercise measures to conserve energy.

B. Provide flexible power cords as required for portable construction tools and equipment.

C. Provide main service disconnect and over-current protection at convenient location.

D. Permanent convenience receptacles may be utilized during construction.

2. TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations.

B. Provide and maintain lighting to interior work areas after dark for security purposes.

C. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps for specified lighting levels.

D. Maintain lighting and provide routine repairs, E. Permanent building lighting may be utilized during construction.

3. TEMPORARY HEATING

A. Existing building heating system may be used during construction. Exercise measures to conserve energy.

4. TEMPORARY COOLING

A. Existing building cooling system may be used during construction. Exercise measures to conserve energy.

5. TEMPORARY VENTILATION

A. Ventilate enclosed areas to achieve curing of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

B. Provide temporary fan units as required to maintain clean air for construction operations.

6. TELEPHONE SERVICE

A. Contractor may not use internal state/federal phone system.

7. WATER SERVICE

A. The Department will pay cost of temporary water used. Exercise measures to conserve energy. Utilize Department’s existing water system, extend and supplement with temporary devices as needed to maintain specified conditions for construction operations.

8. TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of project mobilization.

9. FIELD OFFICES AND SHEDS

A. If the contractor decides to have a field office the location shall be coordinated with the department prior to placement. There is limited space available in the construction area for storage or a field office.

B. Provide Portable or mobile buildings, or buildings constructed with floors raised above ground, securely fixed to foundations with steps and landings at entrance doors. Maintain during progress of Work; remove at completion of Work.

C. Storage Areas And Sheds: Size to storage requirements fill products of individual Sections, allowing for access and orderly provision for maintenance and for inspection of products.

D. Maintenance and Cleaning: Maintain approach walks free of mud, water, and snow.

E. Removal: At completion of Work remove buildings, foundations, utility services, and debris. Restore areas.

10. PARKING

A. Contractor and subcontractors to park in department directed spaces only.

11. PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing spaces.

C. Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and rubbish from site weekly and dispose off-site.

E. Elevator may be used for removal of construction waste. Contractor is responsible for maintaining cleanliness of said elevator as it is the only one in the building.

12. BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas to allow for the Department‘s use of the site and facility, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Protect non-owned vehicular traffic, stored materials, site and structures from damage.

13. ENCLOSURES AND FENCING

A. Interior Enclosures:

i. Provide temporary partitions and ceilings as indicated on Drawings to separate work areas from Department occupied areas, to prevent penetration of dust and moisture into Department occupied areas, and to prevent damage to existing materials and equipment.

ii. Construction: Framing with reinforced polyethylene and plywood sheet materials with closed joints and scaled edges at intersections with existing surfaces.

14. SECURITY

A. Security Program:

i. Protect new Work and existing premises from theft, vandalism, and unauthorized entry.

B. Entry Control.

i. Restrict entrance of persons and vehicles into Project site and existing facilities,

ii. Allow entrance only to authorized persons with proper identification.

iii. Maintain log of workers and visitors, make available to Department on request.

iv. Coordinate access of Department personnel to site in coordination with Department security forces.

C. Personnel Identification

i. Maintain list of accredited persons, submit copy to Department on request.

ii. A driver's license or other acceptable positive identification will be required.

15. DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means to prevent air-borne dust from dispersing into atmosphere.

C. After completion of work, clean all interior work surfaces.

16. POLLUTION CONTROL

A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations.

B. Comply with pollution and environmental control requirements of authorities having jurisdiction.

17. RODENT CONTROL

A. Provide methods, means, and facilities to prevent rodents from accessing or invading premises.

18. REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Final Application for Payment.

B. Clean and repair damage caused by installation or use of temporary work.

C. Restore existing facilities used during construction to original condition.

END OF SECTION

File details come from the government source that posted it. Updated .