This document contains the General Conditions for a state construction contract issued by the State of New Hampshire for Center Strafford Site MEP (Mechanical, Electrical, Plumbing) Upgrades. The contract establishes the foundational legal framework governing the relationship between the State of New Hampshire Department and the selected contractor, along with all subcontractors and suppliers involved in the project execution.
The General Conditions outline extensive requirements for contract administration, including the contractor's responsibility to provide site access for departmental and government inspections at all times. Work is limited to normal hours of 7:00 a.m. to 3:30 p.m. Monday through Friday unless otherwise approved in writing, with no work permitted on Saturdays, Sundays, or legal holidays except in emergencies. The contractor must employ a competent superintendent satisfactory to the Department at all times, with authority to supervise operations and ensure conformance to contract documents; failure to perform these duties results in a stipulated penalty of up to $500 per day. The Department retains authority to interpret contract documents, approve or order changes, and make final determinations on all work quality and acceptability. Liquidated damages are assessed for failure to meet completion deadlines according to a tiered schedule based on contract value, ranging from $200 to $500 per working day. The contract includes provisions for substantial completion certification, punch list completion, final inspection and acceptance, and comprehensive termination clauses covering both termination with fault and termination without fault, with the latter contingent upon available state and federal appropriations.
Payment is made monthly based on certified estimates of work performed, with a five percent retainage held until final completion. The contractor must submit detailed requisitions for payment at least ten days before the end of each billing period and is responsible for obtaining all required construction licenses, permits, and fees. Material payments are subject to submission of supporting documentation including paid invoices and freight bills, with restrictions on advance payments for materials not yet incorporated into the work. The contract requires the contractor to maintain good title to all materials and supplies and prohibits purchases under conditional sale agreements. Final payment is processed no less than 60 days after project acceptance and is contingent upon the contractor providing a complete release of all claims for itself, its subcontractors, and suppliers, along with a release of the contract bond. The contractor is responsible for all safety and health standards compliance in accordance with OSHA regulations, hazardous materials identification and reporting, and immediate suspension of work upon discovery of contaminated materials pending departmental approval to resume.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| attachment-9-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-7-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-6-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-5-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-1-rfb-dmavs-2026-06.docx | DOCX document | |
| addendum-2-rfb-dmavs-2026-06.pdf | ||
| addendum-4-rfb-dmavs-2026-06.pdf | ||
| addendum-3-rfb-dmavs-2026-06.pdf | ||
| attachment-2-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-10-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-3-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-8-rfb-dmavs-2026-06.docx | DOCX document | |
| attachment-11-rfb-dmavs-2026-06-upgrades.pdf | ||
| rfb-dmavs-2026-06.pdf | ||
| addendum-1-rfb-dmavs-2026-06.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL CONDITIONS
1. CONTRACT DOCUMENTS
A. The Contract Documents consist of the Contract Agreement, General Conditions, and Supplementary General Conditions, Drawings and Specifications, including all Addenda issued prior to execution of the Contract; Bonds where required; insurance certificates: and subsequently thereto, Change Orders issued in accordance with the General Conditions.
B. The Contract Documents shall be signed by the Department and the Contractor in as many original counterparts as may be mutually agreed. No Contract shall be considered as in effect until it has been fully executed by all of the parties thereto and the award concurred in by Governor and Council. If there is federal funding, it must also have the concurrence of the applicable Federal Agency having jurisdiction.
C. This Contract is executed in a number of counterparts, each of which is an original and constitutes the entire agreement between the parties. This Contract shall be construed according to the laws of the State of New Hampshire. No portion of this Contract shall be understood to waive the sovereign immunity of the State. This Contract shall not be amended, except as specified herein, except with the approval of the Governor and Council.
D. The Contract Documents are complementary and anything called for by one of the Contract Documents and not called for by the others shall be of like effect as if required by all.
E. Should the Contract Documents disagree in themselves or with each other, the Contractor shall provide the better quality or greater quantity of work and or materials, unless specifically otherwise directed by written Addendum to the Contract.
F. The Contractors and all subcontractors shall refer to all of the Contract Documents, including those not specifically showing the work of their specialized trades, and shall perform all work reasonably inferable from them as being necessary to produce the intended results.
G. All indications or notations which apply to one of a number of similar situations, materials or processes shall be deemed to apply to all such situations, materials or processes wherever they appear in the work, except where a contrary result is clearly indicated by the Contract Documents.
H. Where codes, standards, requirements, and publications of public and private bodies are referred to in the Contract Documents, such references shall be understood to be to the latest revision prior to the date of receiving Bids, except where otherwise indicated.
I. Where no explicit quality or standards for materials or workmanship is established for work, such work is to be of good quality for the intended use and consistent with the quality of the surrounding work and of the construction of the Project in general.
J. All manufactured articles, materials, and equipment shall be applied, installed, connected, erected, tested, cleaned, and conditioned in accordance with the manufacturer's written or printed directions and instructions, unless specifically indicated otherwise in the Contract Documents.
K. The Drawings are generally made to scale, but all working dimensions shall be taken from the figured dimensions or by actual measurements at the job. In case by scaling. Study and compare all the Drawings and verify all figures before laying out or constructing work. The Contractor shall be responsible for errors in his work that might have been avoided thereby. Whether or not an error is believed to exist, deviation from the Drawings and the dimensions given thereon shall be made only after approval in writing from the Department.
L. The Mechanical, Fire Protection (sprinkler) and Electrical Drawings, when provided, are diagrammatic only, and are not intended to show the exact physical locations or configurations of work. Such work shall be installed to clear all obstructions, permit proper clearances by coordinating his work with other trades, and present an orderly appearance where exposed.
2. ACCESS TO THE WORK
A. The Contractor shall provide for access to the work for inspection by the Department and government officials having jurisdiction. The Consultant, Engineer, and officials of Local, State, and Federal Agencies in the case of such programs as they administer and their authorized representatives shall have access at all times to the work for inspection wherever it is in preparation or progress, and the Contractor shall provide proper facilities for such access and inspection.
3. CONTRACT ADMINISTRATION
A. The Department shall determine the amount, quality, and acceptability and fitness of all parts of the work, shall interpret the Contract Documents, and any Change Orders, and shall decide all other issues in connection with the work. The Department shall have the authority to approve or order changes in the work that alter the terms or conditions of the Contract. The Department shall confirm in writing any oral order, direction, requirements or determination.
B. When a Federal Agency participates in the cost of the work covered by this Contract, the work shall be under the observation and inspection of the Department, but subject to the inspection and approval of the proper officials of the Federal Agency.
4. ACCIDENT PROTECTION
A. It is a condition of this Contract, and shall be made a condition of each subcontract entered into pursuant to the Contract, that the Contractor and any Subcontractors shall not require any laborer or mechanic employed in the performance of the Contract to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous to his health of safety as determined by construction safety and health standards of the Occupational Safety and Health Administration, United States Department of Labor, which standards include, by reference, the established Federal Safety and Health Regulations for Construction. These standards and regulations comprise Part 1910 and Part 1926 respectively of Title 29 of the Code of Federal Regulations and are set forth in the Federal Register. In the event any revisions in the Code of Federal Regulations are published, such revisions will be deemed to supersede the appropriate Part 1910 and Part 1926, and be effective as of the date set forth in the revised regulation.
5. HAZARDOUS MATERIALS
A. The Contractor shall also be aware of laws and regulations relating to hazardous materials that may be encountered during construction operations, either within project limits or at material sites off the project. The health and safety of employees, the general public, and the potential of damage to the overall environment is possible if hazardous materials are not recognized, reported, and the appropriate action taken to dispose of, remove from the site, or otherwise contain the possible contaminants.
B. If any abnormal condition is encountered or exposed that indicates the presence of a hazardous material or toxic waste, construction operations shall be immediately suspended in the area and the Department notified. No further work shall be conducted in the area of the contaminated material until the site has been investigated and the Department has given approval to continue the work in the area. The Contractor shall fully cooperate with the Department and perform any remedial work as directed. Work shall continue in other areas of the Project unless otherwise directed.
C. Exposure to hazardous materials may result from contact with, but not necessarily limited to, such items as drums, barrels, and other containers, waste such as cars, batteries, and building construction debris. Containers leaking unknown chemicals or liquids, abandoned cars leaking petroleum products, batteries leaking acid, construction debris which may include asbestos, or any other source of suspected hazardous material found within excavation areas or stockpiled on land within construction limits shall be referred to the Department of Environmental Services and the Department so that a proper identification of the materials may be made and disposal procedures initiated as required.
D. Disposition of the hazardous material or toxic waste shall be made under the requirements and regulations of the Department of Environmental Services. Work required disposing of these materials and any remedial work shall be performed under a Supplemental Agreement or Contract item, if included in the Contract.
6. SUBCONTRACTS
A. Nothing contained in the Specifications or Drawings shall be construed as creating any contractual relationship between any Subcontractor and the Department. The Divisions or Sections of the Specifications are not intended to control the Contractor in dividing the work among Subcontractors or to limit the work performed by any trade.
B. The Contractor shall be as fully responsible to the Department for the acts and omissions of Subcontractors and of persons employed by them, as he is for the acts and omissions of persons directly employed by him.
C. The Contractor shall, without additional expense to the State, utilize the services of specialty Subcontractors, as required.
D. The Department will not normally undertake to settle any differences between the Contractor and his Subcontractors or between Subcontractors.
E. The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to bind Subcontractors to the Contractor by the terms of the General Conditions and other Contract Documents insofar as applicable to the work of Subcontractors and to give the Contractor the same power as regards terminating any subcontract that the Department may exercise over the Contractor under any provisions of the Contract Documents.
F. Within fifteen (15) days after the award of the Contract, the Contractor shall submit a complete list of all of the Subcontractors setting forth in detail the work they will be responsible for. If a subcontractor is added during the construction process the Contractor will revise the list and resubmit to the Department.
7. RESPONSIBILITY OF CONTRACTOR TO ACT IN EMERGENCY
A. In case of any emergency that threatens loss or injury of property, and/or safety of life, the Contractor shall act, without previous instructions from the Department, as the situation may warrant. He shall notify the Department thereof immediately thereafter. Any compensation claimed by the Contractor together with substantiating documents in regard to expense, shall be submitted to the Department and the amount of compensation shall be determined by agreement.
8. SEPARATE CONTRACTS
A. The Department may award other Contracts in connection with the Project, the work under which will proceed simultaneously with the execution of this Contract. The Contractor shall coordinate operations with those of other Contractors.
9. MUTUAL RESPONSIBILITY OF CONTRACTORS
A. If the Contractor or any of his/her Subcontractors or employee’s causes loss or damage to any separate Contractor or Subcontractor on the work, the Contractor or Subcontractor agrees to settle with such separate Contractor or Subcontractor by agreement, if he/she will so settle. If such separate Contractor or Subcontractor sues the State because of any loss so sustained, the Department shall notify the Contractor and/or their subcontractors, who shall indemnify and hold harmless the Department against any expenses or judgment arising there from.
10. PAYMENTS TO CONTRACTOR
A. The Department will manifest payments to the Contractor each calendar month on the basis of duly certified and approved estimate of the work performed during the preceding period. In preparing estimates, the material delivered on the site and any preparatory work done may be taken into consideration.
B. At least ten (10) days before the end of the billing period, the Contractor shall submit to the Department an itemized Requisition for Payment, supported by such data substantiating the Contractor's right to payment as the Department may require. If payment is to be made on account of materials or equipment not incorporated in the work, but delivered and suitably stored at the site, such payment shall be conditional upon submission by the Contractor of bills of sale or such other procedure satisfactory to the Department to establish the State's title to such materials or equipment or otherwise protect the State's interest including applicable insurance.
C. Immediately upon receipt of the Department Approved Monthly Requisition for Payment, Contractor shall post same at the Contractor's Field Office or project site in a location where Subcontractors and Suppliers have clear access.
D. A five (5) percent retainage of the value of the work performed on each partial estimate will be deducted and retained by the Department until after completion of the entire Contract in an acceptable manner. The balance remaining after the specified percentage has been retained, less all previous payments, will be certified for payment on each partial estimate.
E. Within thirty (30) days after acceptance, the Department shall pay to the Contractor the amount of the Contract less all prior payments. All prior payments and estimates, including those relative to extra work, shall be subject to correction by this payment, which is throughout this Contract called the Final Payment.
F. Retainage will be released at Final Payment.
i. After the Certificate of Substantial Completion has been issued, upon written application by the Contractor and with the approval of the Surety, the Department may release a portion of the retained amount.
G. Payment for Material On Hand:
i. Partial payments are made for materials to be incorporated in the Work, provided the materials meet the requirements of the Contract and are delivered on, or in the vicinity of, the Project site and stored in acceptable places. Partial payments will not exceed 90 percent of the Contract unit price for the item or the amount supported by copies of paid invoices, freight bills, or other supporting documents required by the Department. The quantity paid will not exceed the corresponding quantity estimate in the Contract. No partial payment will be made on living or perishable materials until incorporated in the Work.
ii. When material payments exceed $100,000 or 10 percent (10%) of the total contract amount, whichever is less, notarized copies of paid invoices or copies of canceled checks for all such materials must be submitted to the Department within 45 days of the end date of the estimate on which the material allowance was paid. Failure to provide such documentation will result in the deduction of such material allowance from future estimates until documentation is provided.
iii. All material and work covered by partial payments made shall thereupon become the sole property of the Department, but this provision shall not be construed as relieving the Contractor of the sole responsibility of all materials and work upon which payments have been made or the restoration of any damaged work or as a waiver of the right of the State to require the fulfillment of all the terms of the Contract.
H. Payment for Material Not on Hand:
i. The Department will not pay for products and or materials that have not been delivered and stored properly on the construction site.
I. Release of Claims:
i. Neither the final payment nor any part of the retained percentage shall become due until the Contractor shall deliver a complete release of all claims arising under and by virtue of this Contract, including claims for all Subcontractors and suppliers of either materials or labor, plus a release of the Contract Bond and a statement that all Subcontractors and suppliers have been paid. The Department, may pay any and all such claims, in whole or in part, and deduct the amount or amounts so paid from any partial or final payment.
J. Final Payment:
i. Application for Final Payment received from the Contractor will be processed for payment not less than 60 days after project acceptance and final completion unless accompanied by a release of the Contract Bond. This payment shall be the amount of the Contract, amended by approved change orders, less previous payments minus liquidated damages, additional penalties or holdbacks. All prior partial estimates and payments shall be subject to correction in the final estimate and payment.
K. Acceptance of Final Payment Constitutes Release:
i. The acceptance of the Final Payment by the Contractor shall be and shall operate as a release to the Contractor of all claims and of all liability to the Department for all things done or furnished in connection with this work. No payment, however, final or otherwise, shall operate to release the Contractor and its Sureties from any obligations under this Contract or the Contract Bond. Acceptance of Final Payment shall not impact any warrantees provided by the Contractor with respect to this project.
11. LIMITATION OF CONSTRUCTION OPERATIONS
A. The normal working hours will be from 7:00 am until 3:30 pm M-F unless otherwise agreed in writing by the department.
B. The contractor may be displaced at any time with no notice in the event of a military mission that takes priority over construction.
C. In the State of New Hampshire, legal holidays occur on:
a. New Year's Day
b. Washington's Birthday
c. Memorial Day Fourth of July
d. Labor Day
e. Veterans' Day
f. Thanksgiving Day and Day After
g. Christmas Day
h. Whenever a holiday is observed on a Friday or a Monday. The Contractor shall be required to suspend work for three (3) calendar days.
i. No work shall be performed on Saturday, Sundays or legal holidays except in cases of emergency and upon permission of the Department.
12. CONTRACTOR'S TITLE TO MATERIALS
A. No materials or supplies for the work shall be purchased by the Contractor or any Subcontractor subject to any chattel mortgage or under a conditional sale or other agreement by which an interest is retained by the seller. The Contractor warrants that he has good title to all materials and supplies for which he accepts partial payment. If any claim is made with respect to materials provided by the contactor, subcontractors, or Independent Contractors, the Contractor shall defend any such claim and shall pay any judgment or settlement thereon.
13. CHANGES IN WORK
A. The Department may at any time, by a written order, and without notice to the Sureties, make changes in the Drawings and Specifications and Completion Date of this Contract and within the general scope thereof.
B. The order shall stipulate the mutual agreed upon lump sum price, which shall be added to or deducted from the Contract Price. The Contractor shall furnish an itemized breakdown of the prices used in computing the value of any change that might be ordered.
C. The compensation herein provided shall be accepted by the Contractor as payment in full, including superintendence, bond, overhead, and profit, for extra work performed on a force account basis. For all such work, the Contractor shall furnish certified copies of the payrolls on forms provided for that purpose, invoices of all materials, and such other information as may be required by the Department.
14. PERMITS AND FEES
A. The selected Contractor is to obtain and pay for all construction licenses, permits, and fees as may be required by law for construction of State’s facility, and pay for all fees and charges, and use of the property other than the site of the work for storage of materials or other purposes.
B. The Contractor shall pay all applicable Federal, State and Local sales and other taxes, except taxes and assessments on the real property comprising the site of the Project.
15. PATENTS
A. The Contractor shall hold and save the Department and its officers, agents, servants, and employees harmless from liability of any nature including cost and expenses, for or on account of any patented or unpatented invention, process, article or applicable manufactured or used in the performance of the Contract, including its use, unless otherwise specifically stipulated in the Contract Documents.
16. ASSIGNMENTS
A. The Contractor shall not assign the whole or any part of this Contract or any monies due or to become due hereunder, without the written consent of the Department and of all Sureties executing any Bonds on behalf of the Contractor if in connection with said Contract.
17. SUPERINTENDENCE BY CONTRACTOR
A. The Contractor shall employ a competent Foreman or Superintendent, satisfactory to the Department, on the work site at all times to supervise the work in progress, with authority to act for him. The Contractor shall not change superintendents without permission from the Department and shall submit a request in writing with justification for such a change.
i. The superintendent shall be responsible for verifying that all materials, installation, coordination, and workmanship are in conformance with the contract documents.
ii. Unless the Department has granted prior written approval, the superintendent shall not, himself, engage in “hands on” construction work.
iii. In the event the superintendent fails or refuses to perform functions mentioned above as determined by the Department, the Contractor agrees to a stipulated penalty of up to $500.00 per day, in addition to any liquidated damages provided hereunder.
18. FAILURE TO COMPLETE WORK ON TIME
A. If the Contractor fails to complete all of the work or sections of the Project, if sections are indicated, within the time specified in the Contract or within any additional time allowed, for each working day the Liquidated Damages identified in Section C below will be deducted from any money due the Contractor. This deduction will be made. not as a penalty, but as fixed, agreed liquidated damages for inconvenience to the Department and for reimbursing the Department the cost of the Administration of the Contract, including personnel, time, engineering and inspection. Should the amount of money otherwise due the Contractor be less than the amount of such liquidated damages, the Contractor and its Surety shall be liable to the Department for such deficiency.
B. If the Department permits the Contractor to continue and finish the work after the time fixed for its completion, it shall in no way operate as a waiver on the part of the Department of any of its rights under the Contract. When the final acceptance has been duly made by the Department, any liquidated damage charges shall end.
C. The fixed, agreed, liquidated damages shall be assessed in accordance with the following schedule.
Original Contract Amount Amount of Liquidated damages per day From more than: to and including:
0 25,000 $200.00 25,000 50,000 $300.00 50,000 100,000 $400.00 100,000 500,000 $500.00
19. SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When the Contractor believes the project is substantially complete they shall submit an application for substantial completion to the Department. The Contractor shall submit to the Department a list of items of work to be completed or corrected, accompanied by a cost value of these items. The Department will also provide a “punch List” of items to be completed based on their interpretation of the required finished product. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all work in accordance with the Contract Documents. On the basis of an inspection by the Department which determines that the work is substantially complete, a certificate of Substantial Completion shall be issued which will establish the Date of Substantial Completion and state the responsibilities of the Department and the Contractor for such as security, maintenance, heat, utilities, damage to the work and insurance, any other pertinent issues and fix the time limit within which the Contractor shall complete the items listed herein. Warranties required by the Contract Documents shall commence on the Date of Substantial Completion unless otherwise provided in the Certificate of Substantial Completion.
B. If the Contractor fails to proceed to complete the items on the "punch list," then in addition to the corrective measures listed in the Certificate of Substantial Completion, the Department may use the monies still due the Contractor to have such items completed and the Contractor shall lose any claim to the monies so used.
C. Upon written notice that the work is ready for final inspection and acceptance, the Department shall promptly make such inspection, and when they find the work acceptable under the Contract Documents and the Contract fully performed, the Contractor will be provided written notice to that effect. The Contractor shall provide all certificates and reports, as required, throughout the contract and shall coordinate their preparation and submission. Failure to submit such certificates and reports shall be considered default of contract.
20. TERMINATION OF CONTRACT WITH FAULT
A. If the Contractor:
i. Fails to begin work under Contract within the time specified in the notice to proceed, or
ii. Fails to perform the work with sufficient workmen and equipment, or with sufficient materials to assume prompt completion of said work, or
iii. Performs the work unsuitably or neglects or refuses to remove materials or to perform anew such work as may be rejected as unacceptable and unsuitable, or
iv. Discontinues the prosecution of the work, or
v. Fails to resume work, which has been discontinued, within a reasonable time after notice to do so, or
vi. Becomes insolvent or has declared bankruptcy, or commits any act of bankruptcy or insolvency, or
vii. Fails to pay subcontractors and material/product suppliers, or
viii. Makes an assignment for the benefit of creditors, or
ix. For any other causes whatsoever, fails to carry on the work in an acceptable manner.
B. The Department will give notice, in writing, to the Contractor and his Surety for such delay, neglect, and default for any item identified above.
i. If the Contractor or Surety does not proceed in accordance with the Notice, then the Department will, upon the Contractor's failure to comply with such Notice, have full power and authority without violating the Contract, to take the prosecution of the work out of the hands of the Contractor. The Department may enter into an agreement for the completion of said Contract according to the terms and conditions thereof, or use such other methods as in his opinion will be required for the completion of said Contract in an acceptable manner.
ii. All extra costs and charges incurred by the Department as a result of such delay, neglect or default, together with the cost of completing the work under the Contract will be deducted from any monies due or which may become due said Contractor. If such expenses exceed the sum that would have been payable under the Contract, then the Contractor and the Surety shall be liable and shall pay to the Department, the amount of such excess.
21. TERMINATION OF CONTRACT WITHOUT FAULT
A. Except in cases controlled by the preceding section, the Department, for any cause, including, but not limited to an order of any Federal authority or petition of the Contractor due to circumstances beyond his control may by written notice to the Contractor and the Surety terminate the Contract or any portion thereof subject to the Condition(s) i, ii, iii and iv provided below.
B. Notwithstanding anything to the contrary contained in these condition, it is understood and agreed by the parties hereto that all obligations of the Department hereunder, including the continuance of payments, are contingent upon the availability and continued appropriation of State and/or Federal Funds, and in no event shall the Department be liable for any payments hereunder in excess of such available or appropriated funds. In the event of a reduction, termination or failure to appropriate any or all such available funds or appropriations or a reduction of expenditures of State funds the Department may, by written notice to the Contractor and Surety, immediately terminate this Contract in whole or in part in accordance with the following conditions:
i. When a Contract, or portion thereof, is terminated before completion of all items of work in the Contract, payment will be made for the actual items of work completed. Payment of items of work not completed at time of termination shall be the greater of the following amounts: (1) a percentage of the Contract unit price, which percentage shall be the percentage of completion of the particular item at time of termination or (2) such amount as shall be mutually agreed upon by the parties. No claim for loss of anticipated profits on items or units of work not completed will be allowed.
ii. Reimbursement for organization of the work and mobilization, when not otherwise included in the Contract, shall be made where the volume of work completed is too small to compensate the Contractor for these expenses under the Contract; the intent being that an equitable settlement be made with the Contractor.
iii. Acceptable materials, obtained or ordered by the Contractor for the work, and that are not incorporated in the work shall, at the option of the Contractor, be purchased from the Contractor based upon the delivered cost of the materials at such points of delivery as may be designated by the Department. The Contractor shall do everything possible to cancel unfilled orders.
iv. Termination of a Contract, or a portion thereof, shall not relieve the Contractor of his responsibilities for the work completed nor shall it relieve his Surety of its obligations for and concerning any claims arising out of the work performed.
22. ASSIGNMENT PROVISION
A. The Contractor hereby agrees that it will assign to the Department all causes of action that it may acquire under the anti-trust laws of New Hampshire and the United States as a result of conspiracies, combinations or contracts in restraint of trade which affect the price of goods or services obtained by the Department under this Contract, if so requested by the Department.