Attachment 7 Price Breakout.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Y1DZ--Renovate Pre-Engineered Metal Building 115 Project 671A4-22-109
Solicitation number
36C25725R0051
Issued by

About this file

The file is an Excel-based Price Schedule Breakdown attachment for a Department of Veterans Affairs project (Solicitation Number: 36C25725R0051) involving boiler replacement. The price breakdown document provides a detailed template for contractors to itemize costs across multiple construction divisions, including General Requirements, Facility Services, Site & Infrastructure, and Process Equipment subgroups. Although the current document shows $0.00 for all line items, it is structured to capture comprehensive pricing details such as insurance/bonds, taxes, overhead, subcontract markup, profit, and other potential project-related expenses. The document emphasizes that pricing is fixed-price and that the line item breakdown is for informational purposes only, not representing separate billable deliverables. The specific project appears to be a boiler and boiler plant replacement (Project Number 674-19-101) for the Veterans Health Administration's Veterans Integrated Service Network 17.

View the file

Other files

File Type Posted
36C25725R0051 0008.docx DOCX document
S06 36C25725R0051 0007.docx DOCX document
S05 Request For Information 07-24-25.pdf PDF
S04 Site Visit Sign-In Sheet - 671A4-22-109 Renovate Bldg 115 - 7-17-2025.pdf PDF
S06 36C25725R0051 0006.docx DOCX document
Request For Information 06-24-25.pdf PDF
Appendix to SOW-CandD Waste Recycling Form.doc DOC document
S06 36C25725R0051 0005.docx DOCX document
Request For Information 06-20-25.pdf PDF
Attachment 5 IFC Specifications 671A4-22-109 Reconstruct PEMB 115 SEALED-Annotated Reduced Scope.pdf PDF
Attachment 1 SOW - Bldg 115 Fire Repairs 7-08-2025.pdf PDF
Kerrville VA Site Map_PRE-BID MEETING LOCATION.pdf PDF
S06 36C25725R0051 0004.docx DOCX document
S04 Site Visit Sign-In Sheet - 671A4-22-109 Renovate Bldg 115.pdf PDF
S06 36C25725R0051 0003.docx DOCX document
Attachment 1 SOW - Bldg 115 Fire Repairs 6-05-2025.pdf PDF
S06 36C25725R0051 0001.docx DOCX document
Attachment 1 SOW - Bldg 115 Fire Repairs 6-06-2025.pdf PDF
S06 36C25725R0051 0002.docx DOCX document
Attachment 5 IFC Specifications 671A4-22-109 Reconstruct PEMB 115 SEALED.pdf PDF
Attachment 6 Self-Performed Work Calculations.docx DOCX document
Attachment 1 SOW - Bldg 115 Fire Repairs.pdf PDF
Attachment 8 Kerrville VA Site Map.pdf PDF
Attachment 4 IFC Plans 671A4-22-109 Reconstruct PEMB 115 SEALED.pdf PDF
Attachment 3 PCRA KD VA BULDING 115 RENOVATION PROJECT 04.15.25.pdf PDF
Attachment 2 Kerr County Wage Determination.pdf PDF
36C25725R0051_1.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

PRICE SCHEDULE BREAKDOWN INSTRUCTIONS
INSTRUCTIONS
1Awardee is Responsible for determining accuracy of formulas to calcualte SubTotals and Contract Totals as well as accurately transposing totals to the Price Summary
2The term “Division” used with each line item in the Price Schedule refers to the general construction industry term and association with the Construction Specification Institute or common CSI specification breakdown of work actions. These Divisions roughly match those presented to the Contractors when they review the contract document specification binders for this project as created by the architect of record.
3The contract line item price breakdown is for information purposes only and does not constitute separate billable deliverables.
4Field office overhead and general conditions are considered to represent the same category of costs and the terms are used interchangeably. As such, this category of costs will be applied only once to the contract and to any changes, if applicable.
5All pricing is fixed price.

Proposal Price Schedule

PRICE SCHEDULE BREAKDOWN
674-19-101

Replace Boilers and Boiler Plant

CLIN 0001
RatesBase Item
General Requirements & Facility ConstructionPrice
Division Item 1 General RequirementsN/A$0.00
Division Item 2 Existing ConditionsN/A$0.00
Division Item 3 ConcreteN/A$0.00
Division Item 4 MasonryN/A$0.00
Division Item 5 MetalsN/A$0.00
Division Item 6 Woods, Plastic and CompositesN/A$0.00
Division Item 7 Thermal and Moisture ProtectionN/A$0.00
Division Item 8 OpeningsN/A$0.00
Division Item 9 FinishesN/A$0.00
Division Item 10 SpecialtiesN/A$0.00
Division Item 11 EquipmentN/A$0.00
Division Item 12 FurnishesN/A$0.00
Division Item 13 Special ConstructionN/A$0.00
Division Item 14 Conveying EquipmentN/A$0.00
Facility Services SubgroupN/A$0.00
Division Item 21 Fire SuppressionN/A$0.00
Division Item 22 PlumbingN/A$0.00
Division Item 23 Heating, Ventilating and A/CN/A$0.00
Division Item 25 Integrated AutomationN/A$0.00
Division Item 26 ElectricalN/A$0.00
Division Item 27 CommunicationsN/A$0.00
Division Item 28 Electronic Safety & SecurityN/A$0.00
Site & Infrastructure Subgroup
Division Item 31 EarthworkN/A$0.00
Division Item 32 Exterior ImprovmentsN/A$0.00
Division Item 33 UtilitiesN/A$0.00
Division Item 34 TransportationN/A$0.00
Division Item 35 Waterway & Marine ConstructionN/A$0.00
Process Equipment Subgroup$0.00
Division Item 40 Process InterconnectionsN/A$0.00
Division Item 41 Material Processing & Handling EquipmentN/A$0.00
Division Item 42 Process Heating, Cooling, & Drying EquipmentN/A$0.00
Division Item 43 Process Gas & Liquid HandlingN/A$0.00
Division Item 44 Pollution & Waste Control EquipmentN/A$0.00
Division Item 45 Industry Specific Mfg. EquipmentN/A$0.00
Division Item 46 Water & Wastewater EquipmentN/A$0.00
Division Item 48 Electrical Power GenerationN/A$0.00

TOTAL DIVISIONS $0.00

Insurance / Bonds$0.00
Taxes / Other Fees (provide itemized list)$0.00
O&M Manuals and Red Line Drawings$0.00
Overhead$0.00
SubContract Mark-Up$0.00
Profit$0.00
SubTotals$0.00

Other Items not Requested Above (provide itemized list) $0.00

CONTRACT TOTALS$0.00
TOAL$0.00