Attachment_6_Submittal_Schedule.pdf

PDF 219 KB Posted

Attached to
GILA BOX GAOA CAMPGROUND IMPROVEMENTS Federal contract opportunity
Solicitation number
140L0624R0032
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document is a Submittal Schedule for the Bureau of Land Management's Riverview Camp Host Improvements, Owl Creek Campground Improvements, and Riverview Campground Improvements projects under solicitation number 140L0624R0032.

The Submittal Schedule lists 56 required submittals for the Riverview Camp Host Improvements project, 33 for the Owl Creek Campground Improvements, and 28 for the Riverview Campground Improvements. Key submittals include safety plans, work schedules, concrete mix designs, material data, shop drawings, product data and samples, warranties, and operation and maintenance data. Most submittals are due 15 working days prior to needing approval or delivery to the site, with some exceptions. The document provides the specification references and due dates for each submittal. This is an administrative document that details the required submittals for these construction projects, but does not include any pricing, award, or other contractual terms.

View the file

Other files for this federal contract opportunity

Other files attached to GILA BOX GAOA CAMPGROUND IMPROVEMENTS, newest first.
File Type Posted
Attachment11B_QuestionsAnswers_3_0005.pdf PDF
Sol_140L0624R0032_Amd_0005.pdf PDF
Attachment11A_QuestionsAnswers_2_0004.pdf PDF
Sol_140L0624R0032_Amd_0004.pdf PDF
Sol_140L0624R0032_Amd_0003.pdf PDF
Attachment_11_QuestionsAnswers_1_0003.pdf PDF
Attachment_12_Gila_Box_Potential_Laydown_Area_0003.pdf PDF
Attachment_10_24R0032_Site_Visit_Sign_In_Sheet_0003.pdf PDF
Attachment_3E_Specifications_Compaction_Test_Schedule_0003.pdf PDF
140L0624R0032_SF30_Continuation_Pages_Amend_3_0003.pdf PDF
Attachment_2D_Drawings_Kearney_Camp_Rd_Profile_May_2024_0003.pdf PDF
Sol_140L0624R0032_Amd_0002.pdf PDF
Attachment_3D_Site_Furnishings_Specifications_0001.pdf PDF
SF30_Continuation_Pages_Amend_1_0001.pdf PDF
Sol_140L0624R0032_Amd_0001.pdf PDF
Attachment_7_Gila_Box_Geotechnical_Evaluation.pdf PDF
Attachment_1_SOW_20240213.pdf PDF
Attachment_5_Price_Breakout.pdf PDF
Attachment_4B_Wage_Determination_AZ20240025.pdf PDF
Attachment_2A_Drawings_Camp_Host_Site.pdf PDF
Attachment_8_Lim_on_SubK_Breakout.xlsx XLSX spreadsheet
Attachment_4C_Wage_Determination_AZ20240029.pdf PDF
Attachment_9_SF1442_Completion_Instructions.pdf PDF
Attachment_2B_Drawings_Owl_Creek_Campground.pdf PDF
Sol_140L0624R0032.pdf PDF
Attachment_3A_Specifications_Camp_Host_Site.pdf PDF
Attachment_2C_Drawings_Riverview_Campground.pdf PDF
Attachment_3B_Specifications_Owl_Creek_Campground.pdf PDF
Attachment_3C_Specifications_Riverview_Campground.pdf PDF
Attachment_4A_Wage_Determination_AZ20230009.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bureau of Land Management 1 of 3 SUBMITTALS SCHEDULE Riverview Camp Host Improvements Gila Box RNCA GLHN #20049.01

RIVERVIEW CAMP HOST SITE IMPROVEMENTS LIST OF SUBMITTALS

Sub.

No.

Submittals Required

Spec. Ref-erence

Date Due**

1 Completed Schedule of Items & Costs **

2 Safety Plan BLM Con-tract

Precon Meeting

3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor

Precon Meeting

4 Work Schedule Precon Meeting

5 Estimated Progress Payment Schedule 011500 **

6 Metal Fabrications: Shop Drawings 055000 **

7 Chain Link Fencing: Products and Shop Drawings

323100 **

8 Concrete Mix Design Data 033000 10 days before placing

9 Aggregate Base Material Data 312000 10 days before placing

10 Concrete Placement Schedule & Plan 033000 **

11 Concrete Batch Tickets 033000 At time of delivery

12 Concrete Break Test Results 033000 When completed

13 Subgrade and ABC compaction tests 312000 When completed

14 Concrete Reinforcement Shop Drawings 033000 **

15 Contractor Record Drawings 017000 Upon Closeout

16 Insulated Metal Building: Product Data and Samples for initial selection

129300

17 Insulated Metal Building: Submittals vary by manufacturer. May include the following:

Shop Drawings, Manufacturer’s Installation Instructions, Letter of Design Certification, Contractor’s Certificate, Installers Certificate, Mill Certificate, Roofing System Certificate, Accessory Samples, Color Samples, etc.

129300 Varies by manu-facturer

18 Insulated Metal Building: Operation and Maintenance Data, Production Warranties

129300 Upon Closeout

19 Shade Structure: Product Data and Samples for initial selection

129300 20 days prior to ordering

20 Shade Structure: Structural Calculations, Shop Drawings

129300 10 days before placing

21 Shade Structure: Color samples for verifica-tion

129300 10 days before placing

22 Shade Structure: Operation and Mainte-nance Data, Product Warranties

129300 Upon Closeout

23 Picnic Table: Product Data and Samples for initial selection

129300 20 days prior to ordering

24 Picnic Table: Material and color sample 129300 10 days before placing

25 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details and installation per manufac-turer.

129300 10 days before placing

Bureau of Land Management 2 of 3 SUBMITTALS SCHEDULE

Gila Box RNCA GLHN #20049.01

26 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

27 Charcoal Grill: Product Data and Samples for initial selection.

129300 20 days prior to ordering

28 Charcoal Grill: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

29 Fire Ring: Product Data and Samples for ini-tial selection

129300 20 days prior to ordering

30 Fire Ring: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

31 Residential Appliances: Washer. Product Da-ta and Samples for initial selection

113100 20 days prior to ordering

32 Residential Appliances: Dryer. Product Data and Samples for initial selection

113100 20 days prior to ordering

33 Propane Tank Cutsheet; Site Gas Utility Pip-ing, Gas Regulator, Valves & Fittings

221119

34 Site Water Service Piping, Plumbing Valves and Fittings

221119

10 days before

35 Low-Voltage Electrical Power Conductors and Cables

260519 15 working days prior to needing approval

36 Control-Voltage Electrical Power Cables 260523 15 working days prior to needing approval

37 Grounding and Bonding for Electrical Sys-tems

260526 15 working days prior to needing approval

Hangers and Supports for Electrical Systems 260529 15 working days prior to needing

39 Conduits for Electrical Systems

260533.13

15 working days approval

40 Boxes and Covers for Electrical Systems 260533.16 15 working days prior to needing

41 Identification for Electrical Systems

260553 15 working days approval

42 Short-Circuit Studies 260573.13 15 working days prior to needing

43 Coordination Studies

260573.16 15 working days approval

44 Arc-Flash Hazard Analysis 260573.19 15 working days prior to needing approval

45 Panelboards 262416 15 working days prior to needing approval

46 Wiring Devices 262726 15 working days prior to needing approval

47 General-Grade Single Straight-Blade Recep-tacles

262726.31 15 working days

Bureau of Land Management 3 of 3 SUBMITTALS SCHEDULE

Gila Box RNCA GLHN #20049.01 approval

48 Receptacles with Arc-Fault and Ground- Fault Protective Devices

262726.37 15 working days prior to needing

49 Enclosed Switches

262816 15 working days

50 Photovoltaic Collectors

263100 15 working days approval

51 Battery Storage Bank 263100 15 working days prior to needing approval

52 Gas Engine Driven Generator Sets 262313.16 15 working days prior to needing approval

53 Transfer Switches 263600 15 working days prior to needing approval

54 LED Exterior Lighting 265619 15 working days prior to needing approval

55 Metal Building Heating/Cooling Unit 113100 15 working days prior to needing approval

56 Electrical: Operation and Maintenance Da-ta, Product Warranties

Div. 26 Upon Closeout

NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.

* Due date for samples shall be coordinated with the BLM at the Pre-Construction meeting, and may be 20 days prior to approval or more.

** Due date for all submittals is 15 working days prior to needing approval or delivery to the site, unless noted otherwise.

Bureau of Land Management 1 of 2 SUBMITTALS SCHEDULE Owl Creek Campground Improvements Gila Box RNCA GLHN #20049.01

OWL CREEK CAMPGROUND IMPROVEMENTS LIST OF SUBMITTALS

Date Due**

1 Completed Schedule of Items & Costs **

2 Safety Plan BLM Con-tract

Precon Meeting

3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor

Precon Meeting

4 Work Schedule Precon Meeting

5 Estimated Progress Payment Schedule 011500 **

6 Metal Fabrications: Shop Drawings 055000 **

7 Concrete Mix Design Data 321313 10 days before placing

8 Aggregate Base Material Data 312000 10 days before placing

9 Concrete Placement Schedule & Plan 321313 **

10 Storm pipe Materials submittal Plan 10 days before placing

11 Concrete Batch Tickets 321313 At time of delivery

12 Subgrade and ABC compaction tests 312000 When completed

13 Contractor Record Drawings 017000 Upon Closeout

14 Shade Structure: Product Data and Samples for initial selection

129300 20 days prior to ordering

15 Shade Structure: Structural Calculations, Shop Drawings

129300 10 days before placing

16 Shade Structure: Color samples for verifica-tion

129300 10 days before placing

17 Shade Structure: Operation and Mainte-nance Data, Product Warranties

129300 Upon Closeout

18 Picnic Table: Product Data and Samples for initial selection

129300 20 days prior to ordering

19 Picnic Table: Material and color sample 129300 10 days before placing

20 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details, and installation per manu-facturer.

129300 10 days before placing

21 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

22 Charcoal Grill: Product Data and Samples for initial selection.

129300 20 days prior to ordering

23 Charcoal Grill: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

24 Fire Ring: Product Data and Samples for ini-tial selection

129300 20 days prior to ordering

25 Fire Ring: Operation and Maintenance Da-ta, Product Warranties

129300 Upon Closeout

26 Campsite Markers: Product Data and Sam-ples for initial selection

129300 20 days prior to ordering

27 Campsite Markers: Operation and Mainte-nance Data, Product Warranties if available.

129300 Upon Closeout

28 Kiosk: Product Data and Samples for initial selection

129300 20 days prior toor-

Bureau of Land Management 2 of 2 SUBMITTALS SCHEDULE Owl Creek Campground Improvements Gila Box RNCA GLHN #20049.01 dering

29 Kiosk: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

30 Vault Toilet Repairs: Product Data and Sam-ples for initial selection

129300 20 days prior to ordering

31 Vault Toilet Repairs: Color samples for verifi-cation

129300 10 days before placing

32 Vault Toilet Repairs: Operation and Mainte-nance Data, Product Warranties

129300 Upon Closeout

33 HDPE Culverts 334200 10 days before placing

NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.

* Due date for samples shall be coordinated with the BLM at the Pre Construction meeting, and may be 20 days prior to approval or more.

Bureau of Land Management 1 of 2 SUBMITTALS SCHEDULE Riverview Campground Improvements Gila Box RNCA GLHN #20049.01

RIVERVIEW CAMPGROUND IMPROVEMENTS LIST OF SUBMITTALS

Date Due**

1 Completed Schedule of Items & Costs **

2 Safety Plan BLM Con-tract

Precon Meeting

3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor

Precon Meeting

4 Work Schedule Precon Meeting

5 Estimated Progress Payment Schedule 011500 **

6 Metal Fabrications: Shop Drawings 055000 **

7 Concrete Mix Design Data 321313 10 days before placing

8 Aggregate Base Material Data 312000 10 days before placing

9 Concrete Placement Schedule & Plan 321313 **

10 Concrete Batch Tickets 321313 At time of delivery

11 Subgrade and ABC compaction tests 312000 When completed

12 Contractor Record Drawings 017000 Upon Closeout

13 Shade Structure: Product Data and Samples for initial selection

129300 20 days prior to ordering

14 Shade Structure: Structural Calculations, Shop Drawings

129300 10 days before placing

15 Shade Structure: Color samples for verifica-tion

129300 10 days before placing

16 Shade Structure: Operation and Mainte-nance Data, Product Warranties

129300 Upon Closeout

17 Picnic Table: Product Data and Samples for initial selection

129300 20 days prior to ordering

18 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details and installation per manu-facturer.

129300 10 days before placing

19 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

20 Charcoal Grill: Product Data and Samples for initial selection.

129300 20 days prior to ordering

21 Charcoal Grill: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

22 Fire Ring: Product Data and Samples for ini-tial selection

129300 20 days prior to ordering

23 Fire Ring: Operation and Maintenance Da-ta, Product Warranties

129300 Upon Closeout

24 Campsite Markers: Product Data and Sam-ples for initial selection

129300 20 days prior to ordering

25 Campsite Markers: Operation and Mainte-nance Data, Product Warranties if available.

129300 Upon Closeout

26 Kiosk: Product Data and Samples for initial selection

129300 20 days prior to ordering

27 Kiosk: Operation and Maintenance Data, Product Warranties

129300 Upon Closeout

28 CMP Culverts 334200 10 days before

Bureau of Land Management 2 of 2 SUBMITTALS SCHEDULE Riverview Campground Improvements Gila Box RNCA GLHN #20049.01

NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.

* Due date for samples shall be coordinated with the BLM at the Pre-Construction meeting, and may be 20 days prior to approval or more.