Attachment_6_Submittal_Schedule.pdf
PDF 219 KB Posted
- Attached to
- GILA BOX GAOA CAMPGROUND IMPROVEMENTS Federal contract opportunity
- Solicitation number
- 140L0624R0032
About this file
This document is a Submittal Schedule for the Bureau of Land Management's Riverview Camp Host Improvements, Owl Creek Campground Improvements, and Riverview Campground Improvements projects under solicitation number 140L0624R0032.
The Submittal Schedule lists 56 required submittals for the Riverview Camp Host Improvements project, 33 for the Owl Creek Campground Improvements, and 28 for the Riverview Campground Improvements. Key submittals include safety plans, work schedules, concrete mix designs, material data, shop drawings, product data and samples, warranties, and operation and maintenance data. Most submittals are due 15 working days prior to needing approval or delivery to the site, with some exceptions. The document provides the specification references and due dates for each submittal. This is an administrative document that details the required submittals for these construction projects, but does not include any pricing, award, or other contractual terms.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management 1 of 3 SUBMITTALS SCHEDULE Riverview Camp Host Improvements Gila Box RNCA GLHN #20049.01
RIVERVIEW CAMP HOST SITE IMPROVEMENTS LIST OF SUBMITTALS
Sub.
No.
Submittals Required
Spec. Ref-erence
Date Due**
1 Completed Schedule of Items & Costs **
2 Safety Plan BLM Con-tract
Precon Meeting
3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor
Precon Meeting
4 Work Schedule Precon Meeting
5 Estimated Progress Payment Schedule 011500 **
6 Metal Fabrications: Shop Drawings 055000 **
7 Chain Link Fencing: Products and Shop Drawings
323100 **
8 Concrete Mix Design Data 033000 10 days before placing
9 Aggregate Base Material Data 312000 10 days before placing
10 Concrete Placement Schedule & Plan 033000 **
11 Concrete Batch Tickets 033000 At time of delivery
12 Concrete Break Test Results 033000 When completed
13 Subgrade and ABC compaction tests 312000 When completed
14 Concrete Reinforcement Shop Drawings 033000 **
15 Contractor Record Drawings 017000 Upon Closeout
16 Insulated Metal Building: Product Data and Samples for initial selection
129300
17 Insulated Metal Building: Submittals vary by manufacturer. May include the following:
Shop Drawings, Manufacturer’s Installation Instructions, Letter of Design Certification, Contractor’s Certificate, Installers Certificate, Mill Certificate, Roofing System Certificate, Accessory Samples, Color Samples, etc.
129300 Varies by manu-facturer
18 Insulated Metal Building: Operation and Maintenance Data, Production Warranties
129300 Upon Closeout
19 Shade Structure: Product Data and Samples for initial selection
129300 20 days prior to ordering
20 Shade Structure: Structural Calculations, Shop Drawings
129300 10 days before placing
21 Shade Structure: Color samples for verifica-tion
129300 10 days before placing
22 Shade Structure: Operation and Mainte-nance Data, Product Warranties
129300 Upon Closeout
23 Picnic Table: Product Data and Samples for initial selection
129300 20 days prior to ordering
24 Picnic Table: Material and color sample 129300 10 days before placing
25 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details and installation per manufac-turer.
129300 10 days before placing
Bureau of Land Management 2 of 3 SUBMITTALS SCHEDULE
Gila Box RNCA GLHN #20049.01
26 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
27 Charcoal Grill: Product Data and Samples for initial selection.
129300 20 days prior to ordering
28 Charcoal Grill: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
29 Fire Ring: Product Data and Samples for ini-tial selection
129300 20 days prior to ordering
30 Fire Ring: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
31 Residential Appliances: Washer. Product Da-ta and Samples for initial selection
113100 20 days prior to ordering
32 Residential Appliances: Dryer. Product Data and Samples for initial selection
113100 20 days prior to ordering
33 Propane Tank Cutsheet; Site Gas Utility Pip-ing, Gas Regulator, Valves & Fittings
221119
34 Site Water Service Piping, Plumbing Valves and Fittings
221119
10 days before
35 Low-Voltage Electrical Power Conductors and Cables
260519 15 working days prior to needing approval
36 Control-Voltage Electrical Power Cables 260523 15 working days prior to needing approval
37 Grounding and Bonding for Electrical Sys-tems
260526 15 working days prior to needing approval
Hangers and Supports for Electrical Systems 260529 15 working days prior to needing
39 Conduits for Electrical Systems
260533.13
15 working days approval
40 Boxes and Covers for Electrical Systems 260533.16 15 working days prior to needing
41 Identification for Electrical Systems
260553 15 working days approval
42 Short-Circuit Studies 260573.13 15 working days prior to needing
43 Coordination Studies
260573.16 15 working days approval
44 Arc-Flash Hazard Analysis 260573.19 15 working days prior to needing approval
45 Panelboards 262416 15 working days prior to needing approval
46 Wiring Devices 262726 15 working days prior to needing approval
47 General-Grade Single Straight-Blade Recep-tacles
262726.31 15 working days
Bureau of Land Management 3 of 3 SUBMITTALS SCHEDULE
Gila Box RNCA GLHN #20049.01 approval
48 Receptacles with Arc-Fault and Ground- Fault Protective Devices
262726.37 15 working days prior to needing
49 Enclosed Switches
262816 15 working days
50 Photovoltaic Collectors
263100 15 working days approval
51 Battery Storage Bank 263100 15 working days prior to needing approval
52 Gas Engine Driven Generator Sets 262313.16 15 working days prior to needing approval
53 Transfer Switches 263600 15 working days prior to needing approval
54 LED Exterior Lighting 265619 15 working days prior to needing approval
55 Metal Building Heating/Cooling Unit 113100 15 working days prior to needing approval
56 Electrical: Operation and Maintenance Da-ta, Product Warranties
Div. 26 Upon Closeout
NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.
* Due date for samples shall be coordinated with the BLM at the Pre-Construction meeting, and may be 20 days prior to approval or more.
** Due date for all submittals is 15 working days prior to needing approval or delivery to the site, unless noted otherwise.
Bureau of Land Management 1 of 2 SUBMITTALS SCHEDULE Owl Creek Campground Improvements Gila Box RNCA GLHN #20049.01
OWL CREEK CAMPGROUND IMPROVEMENTS LIST OF SUBMITTALS
Date Due**
1 Completed Schedule of Items & Costs **
2 Safety Plan BLM Con-tract
Precon Meeting
3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor
Precon Meeting
4 Work Schedule Precon Meeting
5 Estimated Progress Payment Schedule 011500 **
6 Metal Fabrications: Shop Drawings 055000 **
7 Concrete Mix Design Data 321313 10 days before placing
8 Aggregate Base Material Data 312000 10 days before placing
9 Concrete Placement Schedule & Plan 321313 **
10 Storm pipe Materials submittal Plan 10 days before placing
11 Concrete Batch Tickets 321313 At time of delivery
12 Subgrade and ABC compaction tests 312000 When completed
13 Contractor Record Drawings 017000 Upon Closeout
14 Shade Structure: Product Data and Samples for initial selection
129300 20 days prior to ordering
15 Shade Structure: Structural Calculations, Shop Drawings
129300 10 days before placing
16 Shade Structure: Color samples for verifica-tion
129300 10 days before placing
17 Shade Structure: Operation and Mainte-nance Data, Product Warranties
129300 Upon Closeout
18 Picnic Table: Product Data and Samples for initial selection
129300 20 days prior to ordering
19 Picnic Table: Material and color sample 129300 10 days before placing
20 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details, and installation per manu-facturer.
129300 10 days before placing
21 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
22 Charcoal Grill: Product Data and Samples for initial selection.
129300 20 days prior to ordering
23 Charcoal Grill: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
24 Fire Ring: Product Data and Samples for ini-tial selection
129300 20 days prior to ordering
25 Fire Ring: Operation and Maintenance Da-ta, Product Warranties
129300 Upon Closeout
26 Campsite Markers: Product Data and Sam-ples for initial selection
129300 20 days prior to ordering
27 Campsite Markers: Operation and Mainte-nance Data, Product Warranties if available.
129300 Upon Closeout
28 Kiosk: Product Data and Samples for initial selection
129300 20 days prior toor-
Bureau of Land Management 2 of 2 SUBMITTALS SCHEDULE Owl Creek Campground Improvements Gila Box RNCA GLHN #20049.01 dering
29 Kiosk: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
30 Vault Toilet Repairs: Product Data and Sam-ples for initial selection
129300 20 days prior to ordering
31 Vault Toilet Repairs: Color samples for verifi-cation
129300 10 days before placing
32 Vault Toilet Repairs: Operation and Mainte-nance Data, Product Warranties
129300 Upon Closeout
33 HDPE Culverts 334200 10 days before placing
NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.
* Due date for samples shall be coordinated with the BLM at the Pre Construction meeting, and may be 20 days prior to approval or more.
Bureau of Land Management 1 of 2 SUBMITTALS SCHEDULE Riverview Campground Improvements Gila Box RNCA GLHN #20049.01
RIVERVIEW CAMPGROUND IMPROVEMENTS LIST OF SUBMITTALS
Date Due**
1 Completed Schedule of Items & Costs **
2 Safety Plan BLM Con-tract
Precon Meeting
3 List of Subcontractors & Suppliers with com-pleted Form SF1413 for each subcontractor
Precon Meeting
4 Work Schedule Precon Meeting
5 Estimated Progress Payment Schedule 011500 **
6 Metal Fabrications: Shop Drawings 055000 **
7 Concrete Mix Design Data 321313 10 days before placing
8 Aggregate Base Material Data 312000 10 days before placing
9 Concrete Placement Schedule & Plan 321313 **
10 Concrete Batch Tickets 321313 At time of delivery
11 Subgrade and ABC compaction tests 312000 When completed
12 Contractor Record Drawings 017000 Upon Closeout
13 Shade Structure: Product Data and Samples for initial selection
129300 20 days prior to ordering
14 Shade Structure: Structural Calculations, Shop Drawings
129300 10 days before placing
15 Shade Structure: Color samples for verifica-tion
129300 10 days before placing
16 Shade Structure: Operation and Mainte-nance Data, Product Warranties
129300 Upon Closeout
17 Picnic Table: Product Data and Samples for initial selection
129300 20 days prior to ordering
18 Picnic Table: Shop drawings with dimensions, general contraction component parts, an-choring details and installation per manu-facturer.
129300 10 days before placing
19 Picnic Table: Complete dates on manufac-turers and technical information. Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
20 Charcoal Grill: Product Data and Samples for initial selection.
129300 20 days prior to ordering
21 Charcoal Grill: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
22 Fire Ring: Product Data and Samples for ini-tial selection
129300 20 days prior to ordering
23 Fire Ring: Operation and Maintenance Da-ta, Product Warranties
129300 Upon Closeout
24 Campsite Markers: Product Data and Sam-ples for initial selection
129300 20 days prior to ordering
25 Campsite Markers: Operation and Mainte-nance Data, Product Warranties if available.
129300 Upon Closeout
26 Kiosk: Product Data and Samples for initial selection
129300 20 days prior to ordering
27 Kiosk: Operation and Maintenance Data, Product Warranties
129300 Upon Closeout
28 CMP Culverts 334200 10 days before
Bureau of Land Management 2 of 2 SUBMITTALS SCHEDULE Riverview Campground Improvements Gila Box RNCA GLHN #20049.01
NOTES: This list is not intended to be comprehensive or in chronologic order; consult individual sections. Refer to Section 013300, Submittal Procedures.
* Due date for samples shall be coordinated with the BLM at the Pre-Construction meeting, and may be 20 days prior to approval or more.
File details come from the government source that posted it. Updated .