This document appears to be a set of technical specifications for the Gila Box Owl Creek Campground project that is part of a federal contract opportunity. The key details are:
The project will demolish and remove existing camp site amenities at seven camp sites, including shade structures, picnic tables, site number posts, fire rings, and grills. It will also remove and replace the door and roof of an existing single-vault toilet building and an informational kiosk at the parking lot. Additionally, the project will install four new 12" HDPE storm water culverts with rip rap and grade outlet channels. The contractor will be responsible for re-grading the parking lot, access road, and campsites. New camp site amenities, including ramadas, picnic tables, site number posts, fire rings, and grills, will be installed at each of the seven camp sites.
The solicitation number for the overall federal contract opportunity is 140L0624R0032, named "GILA BOX GAOA CAMPGROUND IMPROVEMENTS", issued by the Department of the Interior Bureau of Land Management National Office.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OWL CREEK CAMPGROUND
TECHNICAL SPECIFICATIONS
GLHN PROJECT #20049.01
October 18, 2023
GLHN Architects & Engineers, Inc. |2939 E Broadway Blvd, Tucson, AZ 85716 T 520.881.4546 | F 520.795.1822 | GLHN.com
Gila Box Owl Creek Campground
Bureau of Land Management TOC - 1 Table of Gila Box Owl Creek Campground GLHN #20049.01 Contents
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
011010 Summary of Work 011500 Measurement and Payment 012000 Project Meetings 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Control/Quality Assurance 017000 Contract Closeout 017419 Construction Waste Management and Disposal 017839 Project Record Documents
DIVISION 02 – EXISTING CONDITIONS
024119 Selective Demolition
DIVISION 03 – CONCRETE
033000 Cast in Place Concrete
DIVISION 05 – METALS
055000 Metal Fabrications
DIVISION 12 - SPECIALTIES
129300 Site Furnishings
DIVISION 31 – EARTHWORK
311000 Site Clearing 312000 Earth Moving
DIVISION 33 – UTILITIES
334200 Stormwater Conveyance
Bureau of Land Management TOC - 2 Table of Gila Box Owl Creek Campground GLHN #20049.01 Contents
THIS PAGE INTENTIONALLY LEFT BLANK
Bureau of Land Management 011010 - 1 Summary of Work Owl Creek Campground GLHN #20049.01
SECTION 011010 – SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance
1.2 WORK INCLUDED
A. This project will:
1. Demolish and remove existing camp site amenities including ramada, concrete picnic table, site number post, fire ring and grill at each of seven camp sites.
2. Re-grade parking lot, access road and campsites. Install new ramada, picnic table, site number post, fire ring and grill at each of seven camp sites.
3. Remove and replace the door and roof of existing single-vault toilet building at the parking lot.
4. Remove and replace existing informational kiosk at the parking lot.
5. Install four new, 12” HDPE storm water culverts with rip rap at inlets and outlets, and grade outlet channels to daylight at an existing wash.
1.3 CONTRACTOR USE OF PREMISES
A. Confine operations to the site of the proposed Work or within the areas provided and shown on the drawings. Construction camps and staging areas outside the construction area must be approved by the Contracting Officer (CO). Obtain advance approval from the CO of all staging areas, excavated soil stockpile and waste areas and camp areas.
B. It shall be understood the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the GOVERNMENT by reason of any act of an employee or trespasser whether GOVERNMENT has paid CONTRACTOR for equipment or materials in storage or not. It shall be further understood should any occasion arise necessitating access by the GOVERNMENT to the sites occupied by these stored materials and equipment, the CONTRACTOR owning or responsible for the stored materials or equipment shall immediately provide same. No materials or equipment may be placed upon the property of the GOVERNMENT until the CO has agreed to the location proposed by the CONTRACTOR to be used for storage. CONTRACTOR is solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the Work.
1.4 PROTECTION OF EXISTING STRUCTURES
A. Where excavation will be required adjacent to existing structures, the CONTRACTOR is solely responsible to maintain the structural integrity of the existing structures. Take whatever means necessary to ensure the existing structures are not damaged. Repair all damage to the existing structures at CONTRACTOR's expense.
Bureau of Land Management 011010 - 2 Summary of Work Owl Creek Campground GLHN #20049.01
1.5 FIELD CHECK OF EXISTING STRUCTURES
A. Check all dimensions and elevations of existing structures or other existing items, both above and below ground, affected by or affecting the Work under this contract, prior to the start of construction or ordering materials and equipment affected thereby.
1.6 FIELD SURVEY AND SITE LAYOUT
A. Contractor shall locate, identify and protect in place all project control points (refer to plans).
B. Contractor shall layout the locations of all new improvements for BLM Recreation staff approval prior to construction. Notify Field Office staff a minimum of 5 working days prior to requiring approval.
1.7 SITE ACCESS
A. Determine the adequacy of all roads, culverts, cattle guards, and bridges used in moving or gaining access for equipment and materials to the construction site. Provide alternative methods of access, such as a temporary crossing for any equipment that exceeds the structural limits of existing facilities. Improvements for road access including fill, culverts, and fencing to remain after project completion as approved by CO.
1.8 LIVESTOCK
A. The CONTRACTOR shall provide temporary fencing for excluding livestock from construction areas, excavations, trenches, etc.
B. CONTRACTOR shall be solely responsible for any livestock injuries or losses as a result of CONTRACTOR’s activities.
1.9 FIELD OFFICES AND SHEDS
A. Provide field offices and storage areas or sheds required for completion of the work. Locate these temporary structures in areas approved by the CO. All expenses for telephone, utilities, security and waste disposal are the responsibility of the CONTRACTOR. Provide the name and phone number of a representative who may be contacted after hours in case of emergency.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011010
Bureau of Land Management 011500 - 1 Measurement Gila Box Owl Creek Campground GLHN #20049.01 and Payment
SECTION 011500 – MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance
1.2 SCOPE
A. The method of measurement and basis of payment is described in this section.
1.3 GENERAL
A. Bid price for each item of the Contract covers all Work shown on the Drawings and required by the specifications and other Contract Documents.
B. All costs are included in the unit and lump-sum prices bid including all materials, equipment, supplies and appurtenances; all construction plant, equipment, and tools; and all labor and supervision necessary to fully complete the Work.
C. No item that is required by the Contract Documents, for the proper and successful completion of the Work, will be paid for outside of or in addition to the prices submitted in the Bid.
D. All work not specifically set forth as a pay item in the Bid Form is considered an incidental obligation of the CONTRACTOR, and all costs in connection therewith shall be included in the unit prices bid.
1.4 ESTIMATED QUANTITIES
A. All quantities in the Price Schedule of the Bid Form or other Contract Documents, which are to be paid per field measurement, are approximate only, and are to be used only as:
1. A basis for estimating the probable cost of the Work, and
2. For the purpose of comparing Bids submitted for the Work.
B. Actual work performed, and materials furnished under the unit-price items for those items to be field measured may differ from the estimated quantities.
C. Basis of payment for work and materials will be the actual amount of work done and materials furnished to the pay lines defined in this section.
D. Payment will be paid at the unit price bid for listed items successfully completed according to Contract requirement.
Bureau of Land Management 011500 - 2 Measurement Gila Box Owl Creek Campground GLHN #20049.01 and Payment
E. Lump-sum items and those based on neat-line plan dimensions are not field-measured. They will be paid at neat-line or the lump-sum price bid for the items listed.
1.5 AUTHORITY
A. Contracting Officer (CO) will perform all measurements and compute quantities for payment.
CO will verify measurements and quantities provided by CONTRACTOR.
B. CONTRACTOR provides access to work areas for survey measurements, as required.
1.6 MEASURED QUANTITIES
A. Measurement by Volume: Measured by cubic dimension using mean length, width, and height or thickness.
1. Measurement for payment of excavations upon or against which concrete or cementitious backfill is not to be placed will be limited to the lines and grades shown on the Drawings or to the most practical lines, grades, and dimensions established by the CO, in writing. No measurement will be made of over excavations beyond design lines and grades.
2. Fill quantities will be computed using the average-end-area method or other computation method approved of by the CO.
B. Measurement by Area: Measured by square dimension using mean length and width. Items that are measured by area will be measured parallel to the ground surface.
C. Linear Measurement: Measured by linear dimension at the item centerline or mean chord. Items that are measured by the lineal foot will be measured parallel to the ground surface, unless otherwise specified.
D. Stipulated Sum/Price Items: Measured by weight, volume, area, or linear means, or combination, as appropriate, as completed items or units of the work.
E. Lump-Sum Items: Will not be measured for payment. Interim measurements may be made to monitor work progress.
1.7 SCHEDULE OF VALUES
A. A schedule of values or “allocation of contract price” is required for all lump sum items.
B. The schedule of values is used only to help assess the intermediate value of work completed for the purpose of making progress payments. The schedule of values is not considered as a commitment to prices in the event of later negotiations.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 011060
Bureau of Land Management 012000 - 1 Project Gila Box Owl Creek Campground GLHN #20049.01 Meetings
SECTION 012000 – PROJECT MEETINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. BLM Manual 9100 – Facility Planning, Design, Construction and Maintenance
1.2 PRE-CONSTRUCTION MEETING
A. A virtual (online) pre-construction conference will be held prior to the start of work. CONTRACTOR will be notified in advance of meeting time, date and platform. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
B. The CONTRACTOR, subcontractors and the persons responsible for coordination of the work are required to be present at the meeting.
C. The CONTRACTOR is required to be prepared to summarize and explain procedures planned for the project and to present the pre-construction submittals required.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012000
Bureau of Land Management 012000 - 2 Project Gila Box Owl Creek Campground GLHN #20049.01 Meetings
Bureau of Land Management 013200 - 1 Construction Progress Gila Box Owl Creek Campground GLHN #20049.01 Documentation
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's Construction Schedule.
3. Construction schedule updating reports.
4. Daily construction reports.
5. Material location reports.
6. Site condition reports.
7. Unusual event reports.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Event: The starting or ending point of an activity.
Bureau of Land Management 013200 - 2 Construction Progress Gila Box Owl Creek Campground GLHN #20049.01 Documentation
F. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either Government or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file, where indicated.
2. PDF file.
3. 3 paper copies, of sufficient size to display entire period or schedule, as required.
B. Startup construction schedule.
1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities.
C. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.
D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.
E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
4. Earnings Report: Compilation of Contractor's total earnings from commencement of the
Work until most recent Application for Payment.
F. Construction Schedule Updating Reports: Submit with Applications for Payment.
G. Daily Construction Reports: Submit at weekly intervals.
Bureau of Land Management 013200 - 3 Construction Progress Gila Box Owl Creek Campground GLHN #20049.01 Documentation
H. Material Location Reports: Submit at weekly intervals.
I. Site Condition Reports: Submit at time of discovery of differing conditions.
J. Unusual Event Reports: Submit at time of unusual event.
K. Qualification Data: For scheduling consultant.
1.5 QUALITY ASSURANCE
A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Government's request.
1.6 COORDINATION
A. Coordinate Contractor's Construction Schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.
1. Use Microsoft Project, Scheduling component of Project website software for current Windows operating system.
B. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using CPM scheduling.
1. In-House Option: Government may waive requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and reporting techniques.
Submit qualifications.
2. Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged delays, and time impact.
C. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
Bureau of Land Management 013200 - 4 Construction Progress Gila Box Owl Creek Campground GLHN #20049.01 Documentation
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013200
Bureau of Land Management 013300 - 1 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Submittal schedule requirements.
2. Administrative and procedural requirements for submittals.
B. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.
2. Section 013233 "Photographic Documentation" for submitting preconstruction photographs, periodic construction photographs, and final completion construction photographs.
3. Section 014000 "Quality Assurance" for submitting test and inspection reports, and schedule of tests and inspections.
4. Section 017000 "Contract Closeout" for submitting closeout submittals and maintenance material submittals.
5. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Government’s responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Government’s responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."
1.4 SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Government and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.
Bureau of Land Management 013300 - 2 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 30 calendar days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.
a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal Category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Government’s final release or approval.
g. Scheduled dates for purchasing.
h. Scheduled date of fabrication.
i. Scheduled dates for installation.
j. Activity or event number.
1.5 SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Government.
4. Name of Contractor.
5. Name of firm or entity that prepared submittal.
6. Names of subcontractor, manufacturer, and supplier.
7. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier, and alphanumeric suffix for resubmittals.
8. Category and type of submittal.
9. Submittal purpose and description.
10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
11. Drawing number and detail references, as appropriate.
12. Indication of full or partial submittal.
13. Location(s) where product is to be installed, as appropriate.
14. Other necessary identification.
15. Remarks.
16. Signature of transmitter.
B. Options: Identify options requiring selection by Government.
C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Government on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
Bureau of Land Management 013300 - 3 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
E. Submittals for Web-Based Project Software: Prepare submittals as PDF files, or other format indicated by Project software website.
1.6 SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Email: Prepare submittals as PDF package and transmit to Government. By sending via email. Include PDF transmittal form. Include information in email subject line as requested by Government.
a. Government will return annotated file. Annotate and retain one copy of file as a digital Project Record Document file.
2. Web-Based Project Software: Prepare submittals in PDF form, and upload to web- based Project software website. Enter required data in web-based software site to fully identify submittal.
3. Paper: Prepare submittals in paper form and deliver to Government.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
4. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 14 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Government will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 14 calendar days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Government’s consultants, Government, or other parties is indicated, allow 21 calendar days for initial review of each submittal
D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
Bureau of Land Management 013300 - 4 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Government’s action stamp.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Government’s action stamp.
1.7 SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
2. Paper Sheet Size: Except for templates, patterns, and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 11 by 17 inches.
a. Two opaque (bond) copies of each submittal. Government will return one copy.
Bureau of Land Management 013300 - 5 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
e. Number and title of applicable Specification Section.
f. Specification paragraph number and generic name of each item.
3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.
4. Web-Based Project Software: Prepare submittals in PDF form, and upload to web- based Project software website. Enter required data in web-based software site to fully identify submittal.
5. Paper Transmittal: Include paper transmittal including complete submittal information indicated.
6. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.
7. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Government will return submittal with options selected.
8. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.
2. Manufacturer and product name, and model number if applicable.
Bureau of Land Management 013300 - 6 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
3. Number and name of room or space.
4. Location within room or space.
E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of governments, and other information specified.
F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.
G. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
Provide a notarized signature where indicated.
2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.
H. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
Bureau of Land Management 013300 - 7 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
1.8 DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Government.
B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and three paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
1.9 CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents.
Note corrections and field dimensions. Mark with approval stamp before submitting to Government.
B. Contractor's Approval: Indicate Contractor's approval for each submittal. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
1. Government will not review submittals received from Contractor that do not have Contractor's review and approval.
1.10 GOVERNMENT’S REVIEW
A. Action Submittals: Government will review each submittal, indicate corrections or revisions required, and return it.
1. PDF Submittals: Government will indicate, via markup on each submittal, the appropriate action.
Bureau of Land Management 013300 - 8 Submittal Gila Box Owl Creek Campground GLHN #20049.01 Procedures
2. Paper Submittals: Government will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.
B. Informational Submittals: Government will review each submittal and will not return it or will return it if it does not comply with requirements. Government will forward each submittal to appropriate party.
C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Government.
D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.
E. Government will return without review submittals received from sources other than Contractor.
F. Submittals not required by the Contract Documents will be returned by Government without action.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013300
Bureau of Land Management 014000 - 1 Quality Control Gila Box Owl Creek Campground GLHN #20049.01 Quality Assurance
SECTION 014000 – QUALITY CONTROL/QUALITY ASSURANCE
PART 1 - GENERAL
1.1 DEFINITIONS
A. Quality Control - planned and specific actions or operations necessary to produce a product that complies with the contract documents. Quality control consists of actions, inspections, sampling and testing necessary to ensure the work is in compliance with the contract documents and to control production and construction processes. Quality control is keyed to the construction sequence to quickly determine when the work is out of compliance with the contract documents and to respond to correct the situation and bring the work into compliance.
Quality control is the responsibility of the CONTRACTOR.
B. Quality Assurance – planned and systematic observations, testing and actions to verify the work complies with the contract documents. Quality assurance includes oversight of the CONTRACTOR’s quality control, verifying the results of the CONTRACTOR’s testing and additional assurance sampling and testing. The GOVERMENT will provide quality assurance at a level determined necessary by the Contracting Officer.
C. Verification/Compliance Testing – sampling and testing which is carried out independent of the CONTRACTOR’s quality control testing to confirm/verify the work complies with the contract documents. The frequency of verification/compliance testing will be determined by the Contracting Officer. Verification/compliance testing will not be used to determine construction procedures or operations (i.e. rolling patterns, lift thickness, etc.). Verification/compliance testing will be provided by the Contracting Officer, at the CONTRACTOR’S expense.
1.2 SUBMITTALS
A. Submit records of all CONTRACTOR tests to the Contracting Officer within 24 hours of the testing.
The Quality Control laboratory is to notify the CONTRACTOR and Contracting Officer promptly of irregularities or deficiencies observed in the Work during performance of the Quality Control Testing.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
A. Assure the GOVERNMENT and Contracting Officer have access to all work areas at all times work is in progress. Provide any special facilities or equipment to access work areas at CONTRACTOR expense.
B. the Contracting Officer when the work is ready for quality assurance/quality control testing.
Establish and update the construction schedule to provide the Contracting Officer estimated sampling/testing dates and times. Contracting Officer may choose to obtain a split and comparison test of any samples collected for quality control testing. Provide adequate notice of testing plans to coordinate collection of samples.
END OF SECTION 014000
Bureau of Land Management 014000 - 2 Quality Control Gila Box Owl Creek Campground GLHN #20049.01 Quality Assurance
Bureau of Land Management 017000 - 1 Contract Gila Box Owl Creek Campground GLHN #20049.01 Closeout
SECTION 017000 – CONTRACT CLOSEOUT
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work covered under this section includes items required in final closeout of this Project.
Included are items such as post-construction inspection, acceptance of the work, closeout records and Project record drawings.
1.2 SUBMITTALS
A. Provide closeout submittals for approval prior to final payment. Items to be submitted are:
1. Project Record Documents - See Item 3.02 for requirements.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
A. Cleaning:
1. Remove all tools, equipment, surplus materials, and rubbish. Repair all marred surfaces, and remove grease, dirt, stains and foreign materials from finished surfaces.
B. Project Record Drawings:
1. Using red colored ink, CONTRACTOR shall mark changes on a set of clean prints. Indicate all changes and revisions to the original design that affect the permanent structures and that exist in the completed work. Reference all underground facilities to permanent physical objects. Reference elevation of all existing lines on profile sheets or call out elevations in plan if no profile exists. Keep record drawings current during construction activities. Certification of accuracy and completeness is required on monthly payment requisitions.
C. Post-Construction Inspection:
1. Prior to expiration of the one-year correction period, the GOVERNMENT will inspect the Project to determine whether corrective work is required. The CONTRACTOR will be advised 14 days prior to inspection and notified in writing of all deficiencies. CONTRACTOR shall attend the post- construction inspection.
END OF SECTION 017000
Bureau of Land Management 017000 - 2 Contract Gila Box Owl Creek Campground GLHN #20049.01 Closeout
Bureau of Land Management 017419 - 1 Construction Waste Management Gila Box Owl Creek Campground GLHN #20049.01 and Disposal
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Disposing of nonhazardous demolition and construction waste.
1.2 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Government’s property.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 DISPOSAL OF WASTE
A. General: All demolition and construction was becomes the property of the Contractor. Remove waste materials from Project site and legally dispose of them at a recycling facility, in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of to accumulate on-site.
Bureau of Land Management 017419 - 2 Construction Waste Management Gila Box Owl Creek Campground GLHN #20049.01 and Disposal
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
END OF SECTION 017419
Bureau of Land Management 017839 - 1 Project Record Gila Box Owl Creek Campground GLHN #20049.01 Documents
SECTION 017839 - PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for project record documents, including the following:
1. Record Drawings.
2. Record Specifications.
3. Record Product Data.
4. Miscellaneous record submittals.
B. Related Requirements
1. Section 017700 "Closeout Procedures" for general closeout procedures.
1.3 CLOSEOUT SUBMITTALS
A. Record Drawings: Comply with the following:
1. Number of Copies: Submit one set of marked-up record prints.
2. Number of Copies: Submit copies of record Drawings as follows:
a. Initial Submittal:
1) Submit one paper-copy set of marked-up record prints.
2) Submit PDF electronic files of scanned record prints and one of file prints.
3) Submit record digital data files and one set of plots.
4) Government will indicate whether general scope of changes, additional information recorded, and quality of drafting are acceptable.
b. Final Submittal:
1) Submit one paper-copy set of marked-up record prints.
2) Submit record digital data files and three sets of record digital data file plots.
3) Plot each drawing file, whether or not changes and additional information were recorded.
B. Record Specifications: Submit one paper copy and annotated PDF electronic files of Project's Specifications, including addenda and contract modifications.
Bureau of Land Management 017839 - 2 Project Record Gila Box Owl Creek Campground GLHN #20049.01 Documents
C. Record Product Data: Submit one paper copy and annotated PDF electronic files and directories of each submittal.
1. Where record Product Data are required as part of operation and maintenance manuals, submit duplicate marked-up Product Data as a component of manual.
D. Miscellaneous Record Submittals: See other Specification Sections for miscellaneous record-keeping requirements and submittals in connection with various construction activities. Submit one paper copy and annotated PDF electronic files and directories of each submittal.
E. Reports: Submit written report weekly indicating items incorporated into project record documents concurrent with progress of the Work, including revisions, concealed conditions, field changes, product selections, and other notations incorporated.
1.4 RECORD DRAWINGS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract Drawings and Shop Drawings, incorporating new and revised drawings as modifications are issued.
1. Preparation: Mark record prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to provide information for preparation of corresponding marked-up record prints.
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an acceptable drawing technique.
c. Record data as soon as possible after obtaining it.
d. Record and check the markup before enclosing concealed installations.
e. Cross-reference record prints to corresponding photographic documentation.
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of foundations.
d. Locations and depths of underground utilities.
e. Changes made by Change Order or Construction Change Directive.
f. Changes made following Government’s written orders.
g. Details not on the original Contract Drawings.
h. Field records for variable and concealed conditions.
i. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings and Shop Drawings completely and accurately. Use personnel proficient at recording graphic information in production of marked-up record prints.
4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.
Bureau of Land Management 017839 - 3 Project Record Gila Box Owl Creek Campground GLHN #20049.01 Documents
B. Record Digital Data Files: Immediately before inspection for Certificate of Substantial…