This document is a Construction Cost Estimate Breakdown for the RPR Transformers Substations Multi project at Moron Air Base, Spain, prepared by Kellogg Brown & Root. The solicitation (FA557525B0002) covers three Contract Line Item Numbers (CLINs): CLIN #1 Basic Package for Building #1536, CLIN #2 Additive #1 for Building #1551 and Wells, and CLIN #3 Additive #2 for North and South BAK12 transformer locations.
The project involves electrical infrastructure upgrades, including transformer vault installations, demolition of existing transformers, civil works, and underground electrical line work. The estimated project value ranges between $500,000 and $1,000,000. Key dates include a pre-proposal conference on 5 June 2025, question submission deadline of 20 June 2025, and bid submission deadline of 30 June 2025. The solicitation is restricted to local Spanish sources authorized to execute government works, with a bid acceptance period valid through 31 December 2025. The project is being conducted by the Department of the Air Force, United States Air Forces in Europe - Air Forces Africa.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers - Transformers.pdf | ||
| Concept drawings Rev1.pdf | ||
| Attachment 1a Specifications (Eng)- Transformers Multi.PDF | ||
| Attachment 5 Schedule of Material Submittals.xlsx | XLSX spreadsheet | |
| Attachment 8 DataSheets compilation.pdf | ||
| Attachment 3 QUUG 23-1017 Concept drawings.pdf | ||
| Attachment 4 Record Drawings.pdf | ||
| Attachment 7 Underground dist switchgear Specs.pdf | ||
| Solicitation - FA557525B0002.pdf | ||
| Attachment 1b Specifications (Esp)- Transformers Multi.PDF | ||
| Attachment 2 Photos.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |
| CONTRACTOR | ADDRESS |
| CONTRACT FOR (Work to be performed) | |||
| RPR, Transformers Substations, MULTI | |||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | |
| QUUG 23-1017 | MORÓN AIR BASE, SPAIN | ||
| ITEM | TOTAL PROJECT COST (Eur) | ||
| (1) | |||
| SUMMARY |
RESUMEN
CLIN #1: BASIC PACKAGE CLIN #1 - Bldg #1536 CLIN #1: PAQUETE BÁSICO CLIN #1 - Edificio #1536
TOTAL PROJECT COST OF BASIC PACKAGE INCLUDING OVERHEAD AND PROFIT
COSTE TOTAL DEL PROYECTO DE PAQUETE BÁSICO INCLUYENDO GASTOS GENERALES Y BENEFICIO
| TOTAL CLIN #1: BASIC PACKAGE | ||
| TOTAL CLIN #1: PAQUETE BÁSICO | 0.00 |
CLIN #2 ADDITIVE #1- Bldg #1551 & Wells CLIN #2: Additivo #1- Edificio #1551 & Pozos
| TOTAL PROJECT COST OF BASIC PACKAGE INCLUDING OVERHEAD AND PROFIT | ||
| COSTE TOTAL DEL PROYECTO DE PAQUETE BÁSICO INCLUYENDO GASTOS GENERALES Y BENEFICIO | 0.00 | |
| TOTAL CLIN #2 ADDITIVE #1- Bldg #1551 & Wells |
TOTAL CLIN #2: Additivo #1- Edificio #1551 & Pozos
CLIN #3: ADDITIVE #2 North & South BAK12.
CLIN #3: ADITIVO #2 BAK 12 Norte y Sur.
| TOTAL PROJECT COST OF BASIC PACKAGE INCLUDING OVERHEAD AND PROFIT | ||
| COSTE TOTAL DEL PROYECTO DE PAQUETE BÁSICO INCLUYENDO GASTOS GENERALES Y BENEFICIO | 0.00 | |
| TOTAL CLIN #3: ADDITIVE #2 North & South BAK12. |
TOTAL CLIN #3: ADITIVO #2 BAK 12 Norte y Sur.
| TOTAL AMOUNT (€) | ||
| IMPORTE TOTAL (€) | € - 0 |
| TOTAL AMOUNT ($) | ||
| IMPORTE TOTAL ($) | $ - 0 |
&"Times New Roman,Regular"Page &P of &N
CLIN #1 BASIC PACKAGE
| CONSTRUCTION COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| GOVERNMENT ESTIMATE | MORÓN AIR BASE, SPAIN | |||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| RPR, Transformers Substations, MULTI | CLIN #1 BASIC PACKAGE Bldg #1536 | 0.00 € | $0.00 | |||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 23-1017 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| INITIAL SUBMITTALS |
SUBMITTALS INICIALES
| 1 | Initial Submittals preparation and delivery | |
| Preparacion y entrega de submittals iniciales | 1 |
| DEMOLITION WORKS | ||
| TRABAJOS DE DEMOLICIÓN | ||
| 2 | Remove and dispose off fenced transformer of Bldg #1536 | |
| Eliminar y transportar a vertedero transformador vallado del edificio #1536 | JOB | |
| 3 | Electrical demolition and disposal to authorized dump site | |
| Demolición eléctrica y transporte a vertedero autorizado | JOB | |
| STANDARD DEMOLITION WORKS TOTAL | ||
| TOTAL TRABAJOS DE DEMOLICIÓN ESTÁNDAR |
| CIVIL WORKS | ||||||
| TRABAJOS DE CIVIL | ||||||
| 4 | Levelling of the area | |||||
| Nivelación de la zona | CM | |||||
| 5 | Excavation for new utility vault, inc. sand bed | |||||
| Excavaciónm para nuevo centro de transformación, con lecho de arena | CM | |||||
| 6 | Backfill and compaction | |||||
| Relleno y compactación | CM | |||||
| 7 | Install pre-manufactured building 3.22 x 2.50 m | |||||
| Instalación edificio prefabricado 3.22 x 2.50 m | Ea | |||||
| 8 | Turf seeding | |||||
| Siembra de césped | Sm | |||||
| CIVIL WORKS TOTAL | ||||||
| TOTAL TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 |
| ELECTRICAL WORKS | ||||||
| TRABAJOS DE ELECTRICIDAD | ||||||
| New Transformer Vault, Bldg #1536 | ||||||
| Nuevo Centro de Transformación, Edif #1536 | ||||||
| 9 | Re-install HV Cable & Install New High Voltage Cable Terminals Indoors. | |||||
| Reinstalar cables de media tensión e Instalación de Terminales para Cable Alta Tensión Uso Interior. | Ea | |||||
| 10 | Line Cabinet SM AirSet-IM | |||||
| Celda de Línea SM AirSet-IM | Ea | |||||
| 11 | Install transformer Protection Cabinet SM AirSet-QM | |||||
| Instalar celda de Proteccion Transformador SM AirSet-QM | Ea | |||||
| 12 | Install transformer 12470/208V, 75 KVA 60 Hz Dyn11 | |||||
| Instalar transformador 12470/208V, 75 KVA 60 Hz Dyn11 | Ea | |||||
| 13 | HV cable jumpers between HV cabinet and transformers. | |||||
| Puentes de media tension entre Celdas M.T y transformador. | Ea | |||||
| 14 | Life Saving Kit | |||||
| Kit de Seguridad | Ea | |||||
| 15 | Copper cable 1x95 mm2 RZ1-K (AS) 0.6/1 kV | |||||
| Cable de cobre 1x95 mm2 RZ1-K (AS) 0.6/1 kV | Lm | |||||
| 16 | Copper cable 1x4 mm2 H07V-K (AS) 450/750V | |||||
| Cable de cobre 1x4 mm2 H07V-K (AS) 450/750V | Lm | |||||
| 17 | 3/4" RMC including couplings & accessories | |||||
| Conducto rígido acero galv. 3/4", incluso manguitos y accesorios | Lm | |||||
| 18 | Main distribution panelboard MDP | |||||
| Cuadro de distribución principal MDP | Ea | |||||
| 19 | Weatherproof lighting fixture 32W (+10% spares) | |||||
| Luminaria estanca 32 W (+10% recambio) | Ls | |||||
| 20 | LED floodlighting fixture (+10% spares) | |||||
| Proyectores LED (+10% recambio) | Ea | |||||
| 21 | Ligthing emergency kit | |||||
| Kit de alumbrado de emergencia. | Ea | |||||
| 22 | Grounding system | |||||
| Sistema de puesta a tierra | Ls | |||||
| 23 | Receptacle & toggle switch with conduit and wiring | |||||
| Enchufe e interruptor con cableado y conducto | Ea | |||||
| New Transformer Vault, Bldg #1536. | ||||||
| Total Nuevo Centro de Transformación, Edif #1536. | 0.00 | 0.00 | 0.00 | 0.00 |
| New UG lines | ||||||
| Nuevas líneas enterradas | ||||||
| 24 | High voltage A1 type prefabricated manhole with cover D-400. | |||||
| Arqueta prefabricada tipo A1 alta tension con tapa D-400. | Ea | |||||
| 25 | Copper cable 1x95 mm2 RZ1-K (AS) 0.6/1 kV | |||||
| Cable de cobre 1x95 mm2 RZ1-K (AS) 0.6/1 kV | Lm | |||||
| New UG lines Total | ||||||
| Total Nuevas líneas enterradas | 0.00 | 0.00 | 0.00 | 0.00 | ||
| ELECTRICAL WORKS TOTAL | ||||||
| TOTAL TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 |
FINAL SUBMITTALS
SUBMITTALS FINALES
26 Final Submittals preparation and delivery Preparacion y entrega de submittals finales
| WORK SUMMARY | ||||||
| RESUMEN TRABAJOS | ||||||
| INITIAL SUBMITTALS | ||||||
| SUBMITTALS INICIALES | 0.00 | 0.00 | ||||
| DEMOLITION WORKS | ||||||
| TRABAJOS DE DEMOLICIÓN | 0.00 | 0.00 | 0.00 | 0.00 | ||
| CIVIL WORKS | ||||||
| TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 | ||
| ELECTRICAL WORKS | ||||||
| TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 | ||
| FINAL SUBMITTALS | ||||||
| SUBMITTALS FINALES | 0.00 | 0.00 | ||||
| GRAND TOTAL | ||||||
| GRAN TOTAL | 0.00 | 0.00 | 0.00 | 0.00 |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD 15.00% 0.00
SUBTOTAL 0.00
PROFIT 10.00% 0.00
| TOTAL PROJECT EUROS | 0.00 | ||
| $1 | 0.9249 | euros | |
| TOTAL PROJECT US$ | 0.00 |
DATE: 7 February 2025 FIRM NAME: KELLOG BROWN & ROOT.
TITLE: ELECTRICAL ENGINEER BY: LUIS RODRíGUEZ LóPEZ
These costs and overhead and profit percentages will be applied in any possible future modifications
&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N
CLIN #2 Additive #1
| CONSTRUCTION COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| GOVERNMENT ESTIMATE | MORÓN AIR BASE, SPAIN | |||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| RPR, Transformers Substations, MULTI | CLIN #2 ADDITIVE #1- Bldg #1551 & Wells | 0.00 € | $0.00 | |||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 23-1017 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| DEMOLITION WORKS | ||||||||||
| TRABAJOS DE DEMOLICIÓN | ||||||||||
| 1 | Remove and dispose off fenced transformer of Bldg #1551 & Wells | |||||||||
| Eliminar y transportar a vertedero transformador vallado del edificio #1551 y de los pozos. | JOB | |||||||||
| 2 | Electrical demolition and disposal to authorized dump site | |||||||||
| Demolición eléctrica y transporte a vertedero autorizado | JOB | |||||||||
| 3 | Recovery of wells & Bldg #1551 HV cables. | |||||||||
| Recuperacion de cables de alta tension de los pozos y edificio #1551 | JOB | |||||||||
| STANDARD DEMOLITION WORKS TOTAL | ||||||||||
| TOTAL TRABAJOS DE DEMOLICIÓN ESTÁNDAR | 0.00 | 0.00 | 0.00 | 0.00 |
| CIVIL WORKS | ||||||
| TRABAJOS DE CIVIL | ||||||
| 3 | Levelling of the area | |||||
| Nivelación de la zona | CM | |||||
| 4 | Excavation for new utility vault, inc. sand bed | |||||
| Excavaciónm para nuevo centro de transformación, con lecho de arena | CM | |||||
| 5 | Backfill and compaction | |||||
| Relleno y compactación | CM | |||||
| 6 | Install pre-manufactured building 3.22 x 2.50 m | |||||
| Instalación edificio prefabricado 3.22 x 2.50 m | Ea | |||||
| 7 | Turf seeding | |||||
| Siembra de césped | Sm | |||||
| CIVIL WORKS TOTAL | ||||||
| TOTAL TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 | ||
| ELECTRICAL WORKS | ||||||
| TRABAJOS DE ELECTRICIDAD | ||||||
| New Transformer Vault, Bldg #1551 | ||||||
| Nuevo Centro de Transformación, Edif #1551 | ||||||
| 8 | Re-install HV Cable & Install New High Voltage Cable Terminals Indoors. | |||||
| Reinstalar cables de media tension e Instalacion de Terminales para Cable Alta Tensión Uso Interior. | Ea | |||||
| 9 | Line Cabinet SM AirSet-IM | |||||
| Celda de Línea SM AirSet-IM | Ea | |||||
| 10 | Install transformer Protection Cabinet SM AirSet-QM | |||||
| Instalar celda de Proteccion Transformador SM AirSet-QM | Ea | |||||
| 11 | Install transformer 12470/208V, 50 KVA 60 Hz Dyn11 | |||||
| Instalar transformador 12470/208V, 50 KVA 60 Hz Dyn11 | Ea | |||||
| 12 | HV cable jumpers between HV cabinet and transformers. | |||||
| Puentes de media tension entre Celdas M.T y transformador. | Ea | |||||
| 13 | Life Saving Kit | |||||
| Kit de Seguridad | Ea | |||||
| 14 | Copper cable 1x95 mm2 RZ1-K (AS) 0.6/1 kV | |||||
| Cable de cobre 1x95 mm2 RZ1-K (AS) 0.6/1 kV | Lm | |||||
| 15 | Copper cable 1x4 mm2 H07V-K (AS) 450/750V | |||||
| Cable de cobre 1x4 mm2 H07V-K (AS) 450/750V | Lm | |||||
| 16 | 3/4" RMC including couplings & accessories | |||||
| Conducto rígido acero galv. 3/4", incluso manguitos y accesorios | Lm | |||||
| 17 | Main distribution panelboard MDP | |||||
| Cuadro de distribución principal MDP | Ea | |||||
| 18 | Weatherproof lighting fixture 32W (+10% spares) | |||||
| Luminaria estanca 32 W (+10% recambio) | Ls | |||||
| 19 | LED floodlighting fixture (+10% spares) | |||||
| Proyectores LED (+10% recambio) | Ea | |||||
| 20 | Ligthing emergency kit | |||||
| Kit de alumbrado de emergencia. | Ea | |||||
| 21 | Grounding system | |||||
| Sistema de puesta a tierra | Ls | |||||
| 22 | Receptacle & toggle switch with conduit and wiring | |||||
| Enchufe e interruptor con cableado y conducto | Ea |
| New Transformer Vault, Bldg #1551. | ||||
| Total Nuevo Centro de Transformación, Edif #1551. | 0.00 | 0.00 | 0.00 | 0.00 |
| New UG lines | ||
| Nuevas líneas enterradas | ||
| 23 | Copper cable 5 x 10 mm2 RZ1-K (AS) 0.6/1 kV | |
| Cable de cobre 5 x 10 mm2 RZ1-K (AS) 0.6/1 kV | Lm |
| New UG lines Total | ||||
| Total Nuevas líneas enterradas | 0.00 | 0.00 | 0.00 | 0.00 |
| ELECTRICAL WORKS TOTAL | ||||
| TOTAL TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 |
| WORK SUMMARY | ||||
| RESUMEN TRABAJOS | ||||
| DEMOLITION WORKS | ||||
| TRABAJOS DE DEMOLICIÓN | 0.00 | 0.00 | 0.00 | 0.00 |
| CIVIL WORKS | ||||
| TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 |
| ELECTRICAL WORKS | ||||
| TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 |
| GRAND TOTAL | ||||
| GRAN TOTAL | 0.00 | 0.00 | 0.00 | 0.00 |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD 15.00% 0.00
SUBTOTAL 0.00
PROFIT 10.00% 0.00
| TOTAL PROJECT EUROS | 0.00 | ||
| $1 | 0.9249 | euros | |
| TOTAL PROJECT US$ | 0.00 |
DATE: 7 February 2025 FIRM NAME: KELLOG BROWN & ROOT.
TITLE: ELECTRICAL ENGINEER BY: LUIS RODRíGUEZ LóPEZ
These costs and overhead and profit percentages will be applied in any possible future modifications
&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N
CLIN #3 Additive #2
| CONSTRUCTION COST ESTIMATE BREAKDOWN | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| GOVERNMENT ESTIMATE | MORÓN AIR BASE, SPAIN | |||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| RPR, Transformers Substations, MULTI | CLIN #3 ADDITIVE #2- North & South BAK 12 | 0.00 € | $0.00 | |||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| QUUG 23-1017 | MORÓN AIR BASE, SPAIN | |||||||||
| UNIT | MATERIAL COST | LABOR COSTS | OTHER | |||||||
| LIN | ITEM | OF | DIRECT | LINE | ||||||
| NO. | MEAS. | QUANTI. | UNIT | TOTAL | MH/MD | AV.RAT | TOTAL | COSTS | TOTAL | |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| DEMOLITION WORKS | ||||||||||
| TRABAJOS DE DEMOLICIÓN | ||||||||||
| 1 | Remove and dispose off fenced transformer of N&S BAK12 | |||||||||
| Eliminar y transportar a vertedero transformador de BAK12 Norte y Sur. | JOB | |||||||||
| 2 | Electrical demolition and disposal to authorized dump site | |||||||||
| Demolición eléctrica y transporte a vertedero autorizado | JOB | |||||||||
| STANDARD DEMOLITION WORKS TOTAL | ||||||||||
| TOTAL TRABAJOS DE DEMOLICIÓN ESTÁNDAR | 0.00 | 0.00 | 0.00 | 0.00 |
| CIVIL WORKS | ||||||
| TRABAJOS DE CIVIL | ||||||
| 3 | Levelling of the area | |||||
| Nivelación de la zona | CM | |||||
| 4 | Excavation for news utility vaults, inc. sand bed | |||||
| Excavaciónm para nuevos centros de transformación, con lecho de arena | CM | |||||
| 5 | Backfill and compaction | |||||
| Relleno y compactación | CM | |||||
| 6 | Install pre-manufactured building 3.22 x 2.50 m | |||||
| Instalación edificio prefabricado 3.22 x 2.50 m | Ea | |||||
| 7 | Turf seeding | |||||
| Siembra de césped | Sm | |||||
| CIVIL WORKS TOTAL | ||||||
| TOTAL TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 | ||
| ELECTRICAL WORKS | ||||||
| TRABAJOS DE ELECTRICIDAD | ||||||
| News Transformer Vaults, N&S BAK 12 | ||||||
| Nuevos Centros de Transformación, BAK 12 Nortre y Sur | ||||||
| 8 | Re-install HV Cable & Install New High Voltage Cable Terminals Indoors. | |||||
| Reinstalar cables de media tension e Instalacion de Terminales para Cable Alta Tensión Uso Interior. | Ea | |||||
| 9 | Line Cabinet SM AirSet-IM | |||||
| Celda de Línea SM AirSet-IM | Ea | |||||
| 10 | Install transformer Protection Cabinet SM AirSet-QM | |||||
| Instalar celda de Proteccion Transformador SM AirSet-QM | Ea | |||||
| 11 | Instal transformer 12470/208V, 50 KVA 60 Hz Dyn11 | |||||
| Instalar transformador 12470/208V, 50 KVA 60 Hz Dyn11 | Ea | |||||
| 12 | HV cable jumpers between HV cabinet and transformers. | |||||
| Puentes de media tension entre Celdas M.T y transformador. | Ea | |||||
| 13 | Life Saving Kit | |||||
| Kit de Seguridad | Ea | |||||
| 14 | Copper cable 1x95 mm2 RZ1-K (AS) 0.6/1 kV | |||||
| Cable de cobre 1x95 mm2 RZ1-K (AS) 0.6/1 kV | Lm | |||||
| 15 | Copper cable 1x4 mm2 H07V-K (AS) 450/750V | |||||
| Cable de cobre 1x4 mm2 H07V-K (AS) 450/750V | Lm | |||||
| 16 | 3/4" RMC including couplings & accessories | |||||
| Conducto rígido acero galv. 3/4", incluso manguitos y accesorios | Lm | |||||
| 17 | Main distribution panelboard MDP | |||||
| Cuadro de distribución principal MDP | Ea | |||||
| 18 | Weatherproof lighting fixture 32W (+10% spares) | |||||
| Luminaria estanca 32 W (+10% recambio) | Ls | |||||
| 19 | LED floodlighting fixture (+10% spares) | |||||
| Proyectores LED (+10% recambio) | Ea | |||||
| 20 | Ligthing emergency kit | |||||
| Kit de alumbrado de emergencia. | Ea | |||||
| 21 | Grounding system | |||||
| Sistema de puesta a tierra | Ls | |||||
| 22 | Receptacle & toggle switch with conduit and wiring | |||||
| Enchufe e interruptor con cableado y conducto | Ea |
| Total News Transformer Vaults, N&S Bak 12 | ||||
| Total Nuevos Centros de Transformación, Nortre y Sur Bak 12 | 0.00 | 0.00 | 0.00 | 0.00 |
| New UG lines | ||||||
| Nuevas líneas enterradas | ||||||
| 23 | High voltage A1 type prefabricated manhole with cover D-400. | |||||
| Arqueta prefabricada tipo A1 alta tension con tapa D-400. | Ea | |||||
| New UG lines Total | ||||||
| Total Nuevas líneas enterradas | 0.00 | 0.00 | 0.00 | 0.00 | ||
| ELECTRICAL WORKS TOTAL | ||||||
| TOTAL TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 |
| WORK SUMMARY | ||||
| RESUMEN TRABAJOS | ||||
| DEMOLITION WORKS | ||||
| TRABAJOS DE DEMOLICIÓN | 0.00 | 0.00 | 0.00 | 0.00 |
| CIVIL WORKS | ||||
| TRABAJOS DE CIVIL | 0.00 | 0.00 | 0.00 | 0.00 |
| ELECTRICAL WORKS | ||||
| TRABAJOS DE ELECTRICIDAD | 0.00 | 0.00 | 0.00 | 0.00 |
| GRAND TOTAL | ||||
| GRAN TOTAL | 0.00 | 0.00 | 0.00 | 0.00 |
TOTAL MATERIAL COSTS 0.00
TOTAL LABOR COSTS 0.00
TOTAL OTHER DIRECT COSTS 0.00
TOTAL DIRECT COSTS 0.00
OVERHEAD 15.00% 0.00
SUBTOTAL 0.00
PROFIT 10.00% 0.00
| TOTAL PROJECT EUROS | 0.00 | ||
| $1 | 0.9249 | euros | |
| TOTAL PROJECT US$ | 0.00 |
DATE: 7 February 2025 FIRM NAME: KELLOG BROWN & ROOT.
TITLE: ELECTRICAL ENGINEER BY: LUIS RODRíGUEZ LóPEZ
These costs and overhead and profit percentages will be applied in any possible future modifications
&"Times New Roman,Regular"INDEPENDENT GOVERNMENT ESTIMATE &"Times New Roman,Bold"FOR OFFICIAL USE ONLY &"Times New Roman,Regular"Page &P of &N
File details come from the government source that posted it. Updated .