This document is a Section 017900 Demonstration and Training specification for the Utilities Infrastructure Project at Fermilab (Project No. PO 689280), dated October 13, 2023. The specification outlines comprehensive requirements for training Owner's personnel on system and equipment operation, maintenance, and documentation. Key requirements include developing detailed training modules for each system, creating instruction programs with specific learning objectives, and producing high-resolution digital video recordings of training sessions.
The specification mandates that training be conducted by qualified instructors and facilitators, with sessions occurring on-site using actual in-place equipment. Specific requirements include creating training modules covering system design, operational requirements, documentation review, emergency procedures, operations, adjustments, troubleshooting, maintenance, and repairs. Video recordings must be in MPEG format, produced by a digital camera with at least 12 megapixels, and organized according to the Project Manual's table of contents. Each training module must be recorded in segments not exceeding 15 minutes, with continuous running time displayed and audio narration describing the equipment and procedures.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Utilities Infrastructure Project TO1 CUB/CWP – Preliminary Advanced Procurement of Equipment-Rev 1 Fermilab Project No. PO 689280 October 13, 2023
DEMONSTRATION AND TRAINING 017900 - 1
SECTION 017900
DEMONSTRATION AND TRAINING
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following:
1. Instruction in operation and maintenance of systems, subsystems, and equipment.
2. Demonstration and training video recordings.
B. Demonstration and training shall be undertaken by the subcontractor, with exception of the Owner procured, Long Lead Equipment, which shall be undertaken by the vendor and subcontractor together.
1.2 INFORMATIONAL SUBMITTALS
A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module.
1. Indicate proposed training modules using manufacturer-produced demonstration and training video recordings for systems, equipment, and products in lieu of video recording of live instructional module.
B. Attendance Record: For each training module, submit list of participants and length of instruction time.
C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test.
1.3 CLOSEOUT SUBMITTALS
A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module.
1. Identification: On each copy, provide an applied label with the following information:
a. Name of Project.
b. Name and address of videographer.
c. Name of Architect.
d. Name of Construction Manager.
DEMONSTRATION AND TRAINING 017900 - 2
e. Name of Contractor / Vendor.
f. Date of video recording.
2. Transcript:
a. Prepared in PDF electronic format. Include a cover sheet with same label information as the corresponding video recording and a table of contents with links to corresponding training components. Include name of Project and date of video recording on each page.
3. At completion of training, submit complete training manual(s) for Owner's use prepared in same PDF file format required for operation and maintenance manuals specified in Section 017823 "Operation and Maintenance Data."
1.4 QUALITY ASSURANCE
A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance.
B. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Section 014000 "Quality Requirements," experienced in operation and maintenance procedures and training.
C. Videographer Qualifications: A professional videographer who is experienced photographing demonstration and training events similar to those required.
D. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to demonstration and training including, but not limited to, the following:
1. Inspect and discuss locations and other facilities required for instruction.
2. Review and finalize instruction schedule and verify availability of educational materials, instructors' personnel, audiovisual equipment, and facilities needed to avoid delays.
3. Review required content of instruction.
4. For instruction that must occur outside, review weather and forecasted weather conditions and procedures to follow if conditions are unfavorable.
1.5 COORDINATION
A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel.
B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content.
DEMONSTRATION AND TRAINING 017900 - 3
C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect.
1.6 INSTRUCTION PROGRAM
A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections.
B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component:
1. Basis of System Design, Operational Requirements, and Criteria: Include the following:
a. System, subsystem, and equipment descriptions.
b. Performance and design criteria if Contractor is delegated design responsibility.
c. Operating standards.
d. Regulatory requirements.
e. Equipment function.
f. Operating characteristics.
g. Limiting conditions.
h. Performance curves.
2. Documentation: Review the following items in detail:
a. Emergency manuals.
b. Systems and equipment operation manuals.
c. Systems and equipment maintenance manuals.
d. Product maintenance manuals.
e. Project Record Documents.
f. Identification systems.
g. Warranties and bonds.
h. Maintenance service agreements and similar continuing commitments.
3. Emergencies: Include the following, as applicable:
a. Instructions on meaning of warnings, trouble indications, and error messages.
b. Instructions on stopping.
c. Shutdown instructions for each type of emergency.
d. Operating instructions for conditions outside of normal operating limits.
e. Sequences for electric or electronic systems.
f. Special operating instructions and procedures.
4. Operations: Include the following, as applicable:
a. Startup procedures.
DEMONSTRATION AND TRAINING 017900 - 4
b. Equipment or system break-in procedures.
c. Routine and normal operating instructions.
d. Regulation and control procedures.
e. Control sequences.
f. Safety procedures.
g. Instructions on stopping.
h. Normal shutdown instructions.
i. Operating procedures for emergencies.
j. Operating procedures for system, subsystem, or equipment failure.
k. Seasonal and weekend operating instructions.
l. Required sequences for electric or electronic systems.
m. Special operating instructions and procedures.
5. Adjustments: Include the following:
a. Alignments.
b. Checking adjustments.
c. Noise and vibration adjustments.
d. Economy and efficiency adjustments.
6. Troubleshooting: Include the following:
a. Diagnostic instructions.
b. Test and inspection procedures.
7. Maintenance: Include the following:
a. Inspection procedures.
b. Types of cleaning agents to be used and methods of cleaning.
c. List of cleaning agents and methods of cleaning detrimental to product.
d. Procedures for routine cleaning.
e. Procedures for preventive maintenance.
f. Procedures for routine maintenance.
g. Instruction on use of special tools.
8. Repairs: Include the following:
a. Diagnosis instructions.
b. Repair instructions.
c. Disassembly; component removal, repair, and replacement; and reassembly instructions.
d. Instructions for identifying parts and components.
e. Review of spare parts needed for operation and maintenance.
1.7 PREPARATION
A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 017823 "Operation and Maintenance Data."
DEMONSTRATION AND TRAINING 017900 - 5
B. Set up instructional equipment at instruction location.
1.8 INSTRUCTION
A. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate between Contractor and Owner for number of participants, instruction times, and location.
B. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system.
1. Owner will furnish Contractor with names and positions of participants.
C. Scheduling: Provide instruction at mutually agreed-on times. For equipment that requires seasonal operation, provide similar instruction at start of each season.
1. Schedule training with Owner with at least seven days' advance notice.
D. Training Location and Reference Material: Conduct training on-site in the completed and fully operational facility using the actual equipment in-place. Conduct training using final operation and maintenance data submittals.
E. Evaluation: At conclusion of each training module, assess and document each participant's mastery of module by use of performance-based test.
F. Cleanup: Collect used and leftover educational materials and give to Owner. Remove instructional equipment. Restore systems and equipment to condition existing before initial training use.
1.9 DEMONSTRATION AND TRAINING VIDEO RECORDINGS
A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice.
1. At beginning of each training module, record each chart containing learning objective and lesson outline.
B. Digital Video Recordings: Provide high-resolution, digital video in MPEG format, produced by a digital camera with minimum sensor resolution of 12 megapixels and capable of recording in full HD mode.
1. Submit video recordings by uploading to web-based Project software site.
2. File Hierarchy: Organize folder structure and file locations in accordance with Project
Manual table of contents. Provide complete screen-based menu.
3. File Names: Utilize file names based on name of equipment generally described in video segment, as identified in Project specifications.
4. Contractor and Installer Contact File: Using appropriate software, create a file for inclusion on the equipment demonstration and training recording that describes the
DEMONSTRATION AND TRAINING 017900 - 6
following for each Contractor involved on the Project, arranged in accordance with Project Manual table of contents:
a. Name of Contractor/Installer.
b. Business address.
c. Business phone number.
d. Point of contact.
e. Email address.
C. Recording: Mount camera on tripod before starting recording, unless otherwise necessary to adequately cover area of demonstration and training. Display continuous running time.
1. Film training session(s) in segments not to exceed 15 minutes.
a. Produce segments to present a single significant piece of equipment per segment.
b. Organize segments with multiple pieces of equipment to follow order of Project
Manual table of contents.
c. Where a training session on a particular piece of equipment exceeds 15 minutes, stop filming and pause training session. Begin training session again upon commencement of new filming segment.
D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording.
1. Furnish additional portable lighting as required.
E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed.
F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment.
G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 017900
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section includes administrative and procedural requirements for instructing Owner's personnel, including the following: |
| 1. Instruction in operation and maintenance of systems, subsystems, and equipment. |
| 2. Demonstration and training video recordings. |
B. Demonstration and training shall be undertaken by the subcontractor, with exception of the Owner procured, Long Lead Equipment, which shall be undertaken by the vendor and subcontractor together.
| 1.2 INFORMATIONAL SUBMITTALS |
| A. Instruction Program: Submit outline of instructional program for demonstration and training, including a list of training modules and a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module. Include learning objective and outline for each training module. |
| 1. Indicate proposed training modules using manufacturer-produced demonstration and training video recordings for systems, equipment, and products in lieu of video recording of live instructional module. |
| B. Attendance Record: For each training module, submit list of participants and length of instruction time. |
| C. Evaluations: For each participant and for each training module, submit results and documentation of performance-based test. |
| 1.3 CLOSEOUT SUBMITTALS |
| A. Demonstration and Training Video Recordings: Submit two copies within seven days of end of each training module. |
| 1. Identification: On each copy, provide an applied label with the following information: |
| a. Name of Project. |
| b. Name and address of videographer. |
| c. Name of Architect. |
| d. Name of Construction Manager. |
| e. Name of Contractor / Vendor. |
| f. Date of video recording. |
| 2. Transcript: |
| a. Prepared in PDF electronic format. Include a cover sheet with same label information as the corresponding video recording and a table of contents with links to corresponding training components. Include name of Project and date of video recording on each page. |
3. At completion of training, submit complete training manual(s) for Owner's use prepared in same PDF file format required for operation and maintenance manuals specified in Section 017823 "Operation and Maintenance Data."
| 1.4 QUALITY ASSURANCE |
| A. Facilitator Qualifications: A firm or individual experienced in training or educating maintenance personnel in a training program similar in content and extent to that indicated for this Project, and whose work has resulted in training or education with a record of successful learning performance. |
| B. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Section 014000 "Quality Requirements," experienced in operation and maintenance procedures and training. |
| C. Videographer Qualifications: A professional videographer who is experienced photographing demonstration and training events similar to those required. |
| D. Preinstruction Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to demonstration and training including, but not limited to, the following: |
| 1. Inspect and discuss locations and other facilities required for instruction. |
| 2. Review and finalize instruction schedule and verify availability of educational materials, instructors' personnel, audiovisual equipment, and facilities needed to avoid delays. |
| 3. Review required content of instruction. |
| 4. For instruction that must occur outside, review weather and forecasted weather conditions and procedures to follow if conditions are unfavorable. |
| 1.5 COORDINATION |
| A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations and to ensure availability of Owner's personnel. |
| B. Coordinate instructors, including providing notification of dates, times, length of instruction time, and course content. |
| C. Coordinate content of training modules with content of approved emergency, operation, and maintenance manuals. Do not submit instruction program until operation and maintenance data have been reviewed and approved by Architect. |
| 1.6 INSTRUCTION PROGRAM |
| A. Program Structure: Develop an instruction program that includes individual training modules for each system and for equipment not part of a system, as required by individual Specification Sections. |
| B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following as applicable to the system, equipment, or component: |
| 1. Basis of System Design, Operational Requirements, and Criteria: Include the following: |
| a. System, subsystem, and equipment descriptions. |
| b. Performance and design criteria if Contractor is delegated design responsibility. |
| c. Operating standards. |
| d. Regulatory requirements. |
| e. Equipment function. |
| f. Operating characteristics. |
| g. Limiting conditions. |
| h. Performance curves. |
| 2. Documentation: Review the following items in detail: |
| a. Emergency manuals. |
| b. Systems and equipment operation manuals. |
| c. Systems and equipment maintenance manuals. |
| d. Product maintenance manuals. |
| e. Project Record Documents. |
| f. Identification systems. |
| g. Warranties and bonds. |
| h. Maintenance service agreements and similar continuing commitments. |
| 3. Emergencies: Include the following, as applicable: |
| a. Instructions on meaning of warnings, trouble indications, and error messages. |
| b. Instructions on stopping. |
| c. Shutdown instructions for each type of emergency. |
| d. Operating instructions for conditions outside of normal operating limits. |
| e. Sequences for electric or electronic systems. |
| f. Special operating instructions and procedures. |
| 4. Operations: Include the following, as applicable: |
| a. Startup procedures. |
| b. Equipment or system break-in procedures. |
| c. Routine and normal operating instructions. |
| d. Regulation and control procedures. |
| e. Control sequences. |
| f. Safety procedures. |
| g. Instructions on stopping. |
| h. Normal shutdown instructions. |
| i. Operating procedures for emergencies. |
| j. Operating procedures for system, subsystem, or equipment failure. |
| k. Seasonal and weekend operating instructions. |
| l. Required sequences for electric or electronic systems. |
| m. Special operating instructions and procedures. |
| 5. Adjustments: Include the following: |
| a. Alignments. |
| b. Checking adjustments. |
| c. Noise and vibration adjustments. |
| d. Economy and efficiency adjustments. |
| 6. Troubleshooting: Include the following: |
| a. Diagnostic instructions. |
| b. Test and inspection procedures. |
| 7. Maintenance: Include the following: |
| a. Inspection procedures. |
| b. Types of cleaning agents to be used and methods of cleaning. |
| c. List of cleaning agents and methods of cleaning detrimental to product. |
| d. Procedures for routine cleaning. |
| e. Procedures for preventive maintenance. |
| f. Procedures for routine maintenance. |
| g. Instruction on use of special tools. |
| 8. Repairs: Include the following: |
| a. Diagnosis instructions. |
| b. Repair instructions. |
| c. Disassembly; component removal, repair, and replacement; and reassembly instructions. |
| d. Instructions for identifying parts and components. |
| e. Review of spare parts needed for operation and maintenance. |
| 1.7 PREPARATION |
| A. Assemble educational materials necessary for instruction, including documentation and training module. Assemble training modules into a training manual organized in coordination with requirements in Section 017823 "Operation and Maintenance Data." |
| B. Set up instructional equipment at instruction location. |
| 1.8 INSTRUCTION |
| A. Facilitator: Engage a qualified facilitator to prepare instruction program and training modules, to coordinate instructors, and to coordinate between Contractor and Owner for number of participants, instruction times, and location. |
| B. Engage qualified instructors to instruct Owner's personnel to adjust, operate, and maintain systems, subsystems, and equipment not part of a system. |
| 1. Owner will furnish Contractor with names and positions of participants. |
| C. Scheduling: Provide instruction at mutually agreed-on times. For equipment that requires seasonal operation, provide similar instruction at start of each season. |
| 1. Schedule training with Owner with at least seven days' advance notice. |
| D. Training Location and Reference Material: Conduct training on-site in the completed and fully operational facility using the actual equipment in-place. Conduct training using final operation and maintenance data submittals. |
| E. Evaluation: At conclusion of each training module, assess and document each participant's mastery of module by use of performance-based test. |
| F. Cleanup: Collect used and leftover educational materials and give to Owner. Remove instructional equipment. Restore systems and equipment to condition existing before initial training use. |
| 1.9 DEMONSTRATION AND TRAINING VIDEO RECORDINGS |
| A. General: Engage a qualified commercial videographer to record demonstration and training video recordings. Record each training module separately. Include classroom instructions and demonstrations, board diagrams, and other visual aids, but not student practice. |
| 1. At beginning of each training module, record each chart containing learning objective and lesson outline. |
| B. Digital Video Recordings: Provide high-resolution, digital video in MPEG format, produced by a digital camera with minimum sensor resolution of 12 megapixels and capable of recording in full HD mode. |
| 1. Submit video recordings by uploading to web-based Project software site. |
| 2. File Hierarchy: Organize folder structure and file locations in accordance with Project Manual table of contents. Provide complete screen-based menu. |
| 3. File Names: Utilize file names based on name of equipment generally described in video segment, as identified in Project specifications. |
| 4. Contractor and Installer Contact File: Using appropriate software, create a file for inclusion on the equipment demonstration and training recording that describes the following for each Contractor involved on the Project, arranged in accordance with Project Manual table of contents: |
| a. Name of Contractor/Installer. |
| b. Business address. |
| c. Business phone number. |
| d. Point of contact. |
| e. Email address. |
| C. Recording: Mount camera on tripod before starting recording, unless otherwise necessary to adequately cover area of demonstration and training. Display continuous running time. |
| 1. Film training session(s) in segments not to exceed 15 minutes. |
| a. Produce segments to present a single significant piece of equipment per segment. |
| b. Organize segments with multiple pieces of equipment to follow order of Project Manual table of contents. |
| c. Where a training session on a particular piece of equipment exceeds 15 minutes, stop filming and pause training session. Begin training session again upon commencement of new filming segment. |
| D. Light Levels: Verify light levels are adequate to properly light equipment. Verify equipment markings are clearly visible prior to recording. |
| 1. Furnish additional portable lighting as required. |
| E. Narration: Describe scenes on video recording by audio narration by microphone while video recording is recorded. Include description of items being viewed. |
| F. Transcript: Provide a transcript of the narration. Display images and running time captured from videotape opposite the corresponding narration segment. |
| G. Preproduced Video Recordings: Provide video recordings used as a component of training modules in same format as recordings of live training. |