This document is a Material Submittals Schedule for a construction project to repair dormitory gutters and windows at Keesler Air Force Base. The project, identified as MAHG 23-1017, is a Service-Disabled Veteran-Owned Small Business set-aside with an estimated value between $1,000,000 and $5,000,000. The solicitation (FA301025R0027) requires contractors to submit various materials and documentation, including hazardous material questionnaires, MSDS forms, warranty documentation, and technical submittals for aluminum gutters, downspouts, joint sealants, and windows. Key submission deadlines include 10 days after award for technical specifications and 5 days prior to start date for hazardous material documentation. The project is being issued by the Department of the Air Force Air Education and Training Command, with a site visit scheduled for 20 August 2025, and includes two contract line items (CLIN) - one for general work and another for potential window replacement subject to funding availability.

View the file

Other files

File Type Posted
Solicitation Amendment FA301025R00270003 SF 30.pdf PDF
Attachment 11 - MAHG231017 - Addendum 2.pdf PDF
Solicitation Amendment - FA301025R00270003.pdf PDF
Solicitation Amendment FA301025R00270002 SF 30.pdf PDF
Solicitation Amendment - FA301025R00270002.pdf PDF
MAHG23-1017 - Additional QandA - 4Sept2025.pdf PDF
Attachment 10 - MAHG231017 - Addendum 1.pdf PDF
Attachment 9 - MAHG231017 - Original Joint Sealant Spec Avery Manor (for reference).pdf PDF
Solicitation Amendment - FA301025R00270001.pdf PDF
Solicitation Amendment FA301025R00270001 SF 30.pdf PDF
MAHG231017 - Questions and Answers - 26Aug2025.pdf PDF
Attachment 8 - MAHG231017 - Original Window Spec Avery Manor (for reference).pdf PDF
Pre-Bid Site Visit 20Aug.pdf PDF
Past Performance Questionnaire.pdf PDF
Attachment 1 -MAHG231017 Repair NPS Dorms Gutters and Windows SOW.pdf PDF
Attachment 3 -MAHG231017 Repair NPS Dorms Gutters and Windows Drawings.pdf PDF
Attachment 4 -MAHG231017 Repair NPS Dorms Gutters and Windows As-Builts.pdf PDF
Past Performance Reference List.pdf PDF
Attachment 2 -MAHG231017 Repair NPS Dorms Gutters and Windows Specs.pdf PDF
Attachment 7 -Submittal Procedures.pdf PDF
Attachment 6 -Wage Determination 11April2025.pdf PDF
Solicitation - FA301025R0027.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
MAHG231017Project Title: Repair NPS Dorms Gutters and WindowsSolicitation / Contract Number:

Attachment 5 - FA301025R0027

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission Date

fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

Submittal Numbers fergusog: Enter the Submittal Number

Date Contractor
NotifiedContractor Resubmittal

fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date

(MM/DD/YY)

Approved fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

1HazMat Questionnaire335 Days Prior to Start Date
2HazMat MSDS335 Days Prior to Start Date
3HazMat Reporting Entry Form335 Days Prior to Start DateSubmit Final Quantities
4HazMat Reporting entry Form33End of Contract
5Recycling and Landfill Report33End of Contract
6Warranty (Manufacture's)33End of Contract
71-Year Warranty (Contractor's)33End of Contract
807 70 23 Aluminum Gutters and Downspouts33310 Days after Award
907 92 00 Joint Sealant3310 Days after Award
1008 51 13 Aluminum Windows33310 Days after Award
11
12
13
14
15
16
17
18
19
20
21
22
23
8
9
10
10
11
12
13
11
15
16
12
12
13
14
15
20
14
15
16
17
18
19
20
21
22
23
24
25

&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).

&P of &N

File details come from the government source that posted it. Updated .