Attachment 5-648-20-116 Drawings 67-97.pdf

PDF 5 MB Posted

Attached to
Z2DA--CON 648-20-116 Correct Electrical FCA Deficiencies Bldgs. /Site (Vancouver)
Solicitation number
36C26026R0040
Issued by

About this file

This document is a comprehensive set of electrical construction drawings for a multi-building VA facility renovation project in Vancouver, Washington. The plans depict detailed electrical layouts, demolition requirements, and equipment specifications across multiple buildings (BLDG 013-027, Rooms M & A-117, RM 6 & A-117, and others) for a fully sprinklered construction project in the design-build phase.

The electrical work encompasses demolition and new installation of power distribution systems, including pad-mount transformers, switchboards, panelboards, and associated raceways and conductors. Key components specified include multiple 307/303 panels, XFMRs (transformers) at various kilovolt ratings (kVA), disconnect switches, surge protective devices, lighting fixtures, fire safety systems, emergency generator connections, and telecommunications infrastructure. The work is phased to minimize operational disruption, with specific shutdown coordination required on weekends only. Contractors must provide temporary mobile generators and power distribution during equipment transitions, handle all refueling and coordination logistics, perform circuit tracing to identify unknown circuits, and conduct comprehensive electrical testing and inspections per specifications before full commissioning and energization of new equipment. Site-specific electrical rooms, mechanical spaces, and utility coordination are detailed throughout the plans with corresponding key notes and general specifications addressing conductor sizing, conduit installation, grounding, and bonding requirements.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ON FLOOR BELOW.

i. DEMOLISH EXISTING PAD MOUNT SWITCH "PMS-10" AND PAD MOUNT TRANSFORMER "PMT-10" SERVING BUILDING 1.

ii. DEMOLISH EXISTING SWITCHBOARD. ALL EXISTING FEEDER RACEWAYS AND CONDUCTORS SHALL BE PRESERVED FOR RE-TERMINATION.

iii. INSTALL REPLACEMENT PADMOUNT TRANSFORMER "PMT-10" AND ASSOCIATED VAULT "MH-10". EXTEND EXISTING MV RACEWAY AND CONDUCTORS AS REQUIRED FOR TRANSFORMER INSTALLATION.

v. PROVIDE RACEWAY INSTALLATION FROM MV TRANSFORMER TO SWITCHBOARD VIA VAULT "MH-10"; EXTEND EXISTING RACEWAYS AS REQUIRED.

iv. INSTALL REPLACEMENT SWITCHBOARD. PROVIDE AND TERMINATE CONDUCTORS TO SWITCHBOARD

E. PERFORM ALL ELECTRICAL TESTING AND INSPECTIONS PER SPECIFICATIONS. FULLY COMMISION AND ENERGIZE NEW EQUIPMENT.

EP504

J

J01-EELA-2

01-EELA-6

TYP.

J J

01-EELA-8

01-EELA-10

J

01-EELA-4

HEAT TRACE JUNCTION BOX. LOCATE PER MECHANICAL

DRAWINGS.

REPLACE BUILDING 1 CLC GENERATOR; INSTALLATION OF REPLACEMENT GENERATOR WILL REQUIRE A SHUTDOWN. SHUTDOWN WORK SHALL BE PERFORMED. WORK SHALL BE PERFORMED ONLY ON WEEKENDS; COORDINATE WITH VA FOR EXACT OUTAGE AND WORK PLANS. THE FOLLOWING PHASING STEPS MAY BE USED TO PERFORM THE WORK AS FOLLOWS:

CONTRACTOR SHALL PERFORM CIRCUIT TRACING TO

IDENTIFY UNKNOWN CIRCUIT BREAKER LOADS.

CONTRACTOR SHALL UPDATE CIRCUIT DIRECTORY WITH

IDENTIFIED LOAD. CIRCUIT DIRECTORY SHALL BE

TYPE-WRITTEN AND PRINTED, NOT HANDWRITTEN.

REFERENCE ASSOCIATED PANEL SCHEDULE FOR

ADDITIONAL INFORMATION.

File details come from the government source that posted it. Updated .