About this file

This solicitation requests comprehensive facilities support services for the Federal Law Enforcement Training Center located in Artesia, New Mexico. The contractor must provide project management, environmental support, logistics, janitorial services, facilities and grounds maintenance, and biowaste management. All labor, equipment, transportation, administrative support, training and supplies necessary to ensure competent performance of the facilities support services in accordance with the terms of the Performance Work Statement must be provided. Interested offerors should review the consolidated sections in the attachments for all sections of the solicitation. The closing date for receipt of proposals is not specified in the document provided.

View the file

Other files

File Type Posted
Questions and Answers 0004 for 70LART21RPFB00001.pdf PDF
70LART21RPFB00001 Amendment 0004.pdf PDF
Attachment 33-Non-Accountable Property P0003.pdf PDF
Attachment 44-GFP P0003.pdf PDF
70LART21RPFB00001 P0003.pdf PDF
Attachment 11-Equipment List P0003.pdf PDF
Attachment 34-Non-Disclosure Agreement P0003.pdf PDF
70LART21RPFB00001 P0002.pdf PDF
Amendment No. 2 SECTION L 70LART21RPFB00001.pdf PDF
Amendment No. 1 SECTION I 70LART21RPFB00001.pdf PDF
70LART21RPFB00001 Amendment No. 1.pdf PDF
Amendment No. 1 SECTION L 70LART21RPFB00001.pdf PDF
Amendment No. 1 SECTION K 70LART21RPFB00001.pdf PDF
Attachment 49 WD 2015-5455 Rev. 13.pdf PDF
Attachment 6-Customer Complaint.pdf PDF
Attachment 33-Non-Accountable Property.pdf PDF
Attachment 4d - Emp Elig Verif (I-9).pdf PDF
Attachment 27- Generators.pdf PDF
Attachment 5-CMMS Work Classifications.pdf PDF
Attachment 44-GFP.pdf PDF
Attachment 40-Target System Bench Stock List.pdf PDF
Attachment 4e-OF306.pdf PDF
Attachment 30-FLETC OAO Integrated PestManagement Plan Updated 2018 - Copy (2).pdf PDF
Attachment 22-FTC-ADM-61 Service Contract Work Request.pdf PDF
Attachment 4a-DHS Form 11000-25 Instructions.pdf PDF
Attachment 24-FTC-MRSD-10 Inventory Control Form.pdf PDF
Attachment 29-Hazardous Waste Management Plan 2014 - Copy (2).pdf PDF
Attachment 23- FTC-ADM-67 CDR.pdf PDF
Attachment 20-FTC-ADM-44-Survey Report.pdf PDF
Attachment 13-Facility List.pdf PDF
Attachment 39 -Spill Prevention (SPCC) Plan.pdf PDF
Attachment 18-FTC-ADM-1A-Purchase Req.pdf PDF
Attachment 16-Fire Extinguisher List.pdf PDF
Attachment 36-OFFICE SUPPLY CATALOG.pdf PDF
Attachment 17-Freight and Deliverables.pdf PDF
Attachment 34- Non Disclosure Agreement.pdf PDF
Attachment 41-70-09I Traffic Regs on FLETC Facilities.pdf PDF
Attachment 19-FTC-ADM-43-Prop Acct Chg.pdf PDF
Attachment 28-HISTORICAL DATA.pdf PDF
70LART21RPFB00001 Consolidated Sections.pdf PDF
Attachment 14-Facility Maps.pdf PDF
Attachment 32-Mail Reports.pdf PDF
Attachment 21-FTC-ADM-46-Move Order Req.pdf PDF
Attachment 48 2015-10-28 CBA.pdf PDF
Attachment 9-E.O. 13834 Implementing Instructions.pdf PDF
Attachment 1-Abbreviations and Definitions.pdf PDF
Attachment 12-Representative PM Task Sheets.pdf PDF
Attachment 26-FTC-SSD-40 Contractors Receiving Report.pdf PDF
Attachment 10-Energy Conservation Measures.pdf PDF
Attachment 35-OF-347 Order for Supplies or Services.pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Introduction The following covers the basic concept of monthly performance testing of electric motor driven fire pumps. Testing helps verify that the pumps will start automatically and operate without failure when needed.

The information provided is not intended to cover all aspects of the periodic maintenance needed by a fire pump system, its drivers, power supplies or back-up power supply mechanisms nor does the test cover the annual flow test that should be completed on all fire pumps to help verify that the pumps are operating at the manufacturer’s specifications. The procedures in this document are not intended to comply with any governmental regulations.

Procedures A monthly operational test of all fire pumps should be conducted by running the pump in a “no- flow” or “churn” situation with all valves open as per normal. Qualified operating personnel should monitor the pump while the pump is running. Each pump should run for the proper time interval and be observed for problems. This document contains checklists for an electric motor driven pump. The proper checklist should be used to record vital data about the pump and to help identify abnormalities in the operation of the pump. Any abnormalities should be corrected immediately or noted for future correction. If any major malfunctions, such as smoke, excessive vibration, or excessive noise are witnessed, discontinue the test immediately and repair equipment as soon as possible.

A. Test Procedure: The monthly pump operational test is part of the overall preventative maintenance procedures for a fire pump. The run test helps ensure that the pump will operate without mechanical difficulty and protect the facility if a fire should occur.

1. Notify the alarm company that the fire pump is going to be tested.

2. Start the pump with a drop in system pressure. To do this, open the drain cock located near the pump controller with the jockey pump turned off. Record the pump starting pressure.

3. Check the pump packing glands to verify that a slight discharge of water is visible. If no water is dripping, adjust the packing gland nuts appropriately.

4. Check for excessive vibration, unusual noise, or other signs of malfunction. Make corrections as needed. Discontinue the test if destructive failure appears imminent.

Make repairs as soon as possible. If all appears normal continue with the test.

5. Record the system suction and discharge pressures. Record other system data as listed on the appropriate checklist.

6. Verify that the pump operates for the appropriate time period; a minimum of 10 minutes for electric motor driven pumps and 30 minutes for diesel engine driven pumps.

7. Periodically verify that the pump and driver are not overheating during the test.

8. Shut down the pump manually.

9. Turn the jockey pump back on. Restore the fire pump controller to the automatic start

Attachment 21 position.

10. Notify the alarm company that the test is complete and that the alarm system should be put back to normal service.

B. Interpretation of test results: Once test data is recorded, compare it to previous tests to determine if the pump is operating satisfactorily. Significant differences in operation should be analyzed as to the cause. Corrective actions should be completed as soon as possible and the pump retested.

Maintenance Fire pump components should receive preventative maintenance. As with any mechanical device the fire pump needs inspection, lubrication, fluid checks and changes, cleaning and testing. The following systems are typically part of a fire pump and require scheduled preventative maintenance: pump systems; mechanical transmission components; electrical systems; diesel engine systems; exhaust systems; lubrication systems; cooling systems; and battery systems.

The best resource for a preventative maintenance program for a fire pump is from the fire pump manufacturer. Fire pumps should be maintained in accordance with manufacturer’s specifications; the procedures in this paper are suggested guidelines. NFPA 25 also suggests schedules for weekly, monthly, quarterly and annual inspection, testing and maintenance of these systems.

Fire pumps should also receive annual full-flow testing to measure the pump’s flow and pressure performance against the manufacturer’s rating of the pump. Any significant reduction in pump performance should be investigated and/or repaired immediately.

Conclusion Fire pumps are required at many facilities to provide the needed pressure for the sprinkler and fire hose standpipe systems. Without a fire pump these systems would not operate adequately.

Proper testing and maintenance of fire pump systems is critical to maintaining fire protection for such facilities. The testing procedures and checklists in this guide can help increase the reliability of a fire pump. The checklists included at the end of this document can be used as they are or they can be adapted for a particular facility and fire pump installation.

FIRE PUMP

MONTHLY TESTING AND INSPECTION CHECKLIST

(Electric - Motor Driven) By:

Date:

Before testing the fire pump, contact the alarm receiving station at telephone #: 575-748-8136

MONTHLY TESTING AND INSPECTION

ITEM STATUS

Yes No Pump room heat maintained at 40o F.?

Piping valves (suction, discharge and bypass) open? (Test header valve is closed?)

Suction reservoir full?

Wet pit suction screens unobstructed and in place?

Pump started automatically by dropping pressure? Start pressure psi

Pump running suction pressure normal? psi

Pump running discharge pressure normal? psi

Pump packing glands have slight water drip? (The water drip cools the packing)

Circulating relief valve has adequate flow while pump is running? (Cools pump)

Pump casing temperature within proper range (not hot to the touch)?

Water piping in good condition (no leaks from joints, cracks, etc.)?

Oil level in sight glass normal? (vertical pumps only)

Relief valve operational? (if provided)

Pump run at churn (no flow) for 10 minutes?

Pump controller pilot light (power on) illuminated?

Pump controller pilot light (transfer switch) illuminated?

Reverse phase pilot light off or normal phase pilot light on?

A "no" response above indicates the need for investigation and corrective action to restore the system to normal operation. These monthly inspection and test items are considered minimum requirements. The manufacturers' inspection and test requirements for the pump and motor may be more comprehensive and should be followed at all times.

Additional Comments:

After testing the fire pump, contact the alarm receiving station to verify alarms were received and restore alarm system to normal status.

Introduction
Procedures
Maintenance
Conclusion

File details come from the government source that posted it. Updated .