This is a Pricing Schedule Template for Architect-Engineer (A-E) services that will be used for Task Order pricing under the Edwards AFB IDIQ contract (FA4610-11-R-0034). The template establishes a negotiation worksheet format for proposed rates across multiple labor categories and cost elements, with columns for Base Hourly Rate, Overhead and Fringe percentages, Subtotal, General & Administrative (G&A) percentage, Total Cost, Profit percentage, and Total Firm-Fixed-Price (FFP) Rate.

The template encompasses extensive labor categories organized by discipline and seniority level, including Project Management, Architects, Community Planners, Landscape Architects, Structural Engineers, Civil Engineers, Mechanical Engineers, Electrical Engineers, Environmental Engineers, Fire Protection Engineers, and Geotechnical Engineers, along with specialized roles such as Title II Construction Representatives, Surveyors, Survey Crews, Cost Estimators, Specification Writers, CAD Drafters, and Clerks. The template also includes cost elements for per diem travel expenses (meals, lodging, mileage, hotel, and airfare) based on Joint Travel Regulations (JTR) rates, and reproduction costs for various drawing sizes and formats. A companion Task Order Rate Worksheet is included for specific task order pricing, with columns for quantity estimates across different phases (IA, IB, II) and corresponding FFP rates. The template provides for escalation rates across multiple contract years and allowance for subconsultants and other services on a lump sum basis, supporting the flexible nature of the multi-year IDIQ structure with a $25,000,000 ceiling.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSED RATES

Negotiation Worksheet
ARCHITECT-ENGINEER

<<Ktr XYZ>>

(*) The same rates are used for Title I and Other Services Investigative
LABOR CATEGORY CLASSIFICATIONBASE HOURLY RATEOVERHEAD (+ FRINGE) %SUBTOTALG&A %TOTAL COSTPROFIT %TOTAL FFP RATE
Escalation Rate For Option Periods:
PROJECT MANAGEMENT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0Password
SENIOR LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0PZIOC
MID LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
TITLE II CONSTR REP$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEYOR$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEY CREW$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
COST ESTIMATING$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
SPEC WRITING$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
AUTOCAD DRAFTING$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
CLERK$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

PER DIEM - TRAVEL

MEALS AND LODGING >24 HOURSJTR rate(per day)
MEALS ONLY > 12 HOURS BUT < 24 HOURSJTR rate(per day)
MILEAGE (300 Miles/Car - 1 Car)JTR rate(per mile)
HOTEL (Includes 15.5% Lodging Tax)JTR rate(night)
AIRFAREJTR rate(round trip)

REPRODUCTION

FULL-SIZE DRAWING PHOTOCOPIES (24" x 36")$ - 0(per sheet)
HALF-SIZE DRAWING PHOTOCOPIES (11" x 17")$ - 0(per sheet)
LETTER-SIZE PHOTOCOPIES (8-1/2" x 11")$ - 0(per sheet)
CD/DVD$ - 0(per disk)
BINDERS$ - 0(per each)
COLOR RENDERING PRINT$ - 0(per sq ft)
DELIVERY$ - 0(per each)

FA4610-11-R-0034

Attachment 1

Page &P of &N

SUMMARY

Negotiation Worksheet
SummaryPassword
PZIOC
<<Ktr XYZ>>
EscalationOverheadProfit
0.00%0.00%0.00%
(*) The same rates are used for Title I and Other Services Investigative
LABOR CATEGORY CLASSIFICATIONBASIC CONTRACT YEARYEAR 1YEAR 2YEAR 3YEAR 4Comments
PROJECT MANAGEMENT$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL COMMUNITY PLANNER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL LANDSCAPE ARCHITECT$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL STRUCTURAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL CIVIL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL MECHANICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ELECTRICAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ENVIRONMENTAL ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL FIRE PROT ENGINEER$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL GEOTECHNICAL ENGR$ - 0$ - 0$ - 0$ - 0$ - 0
TITLE II CONSTR REP$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEYOR$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEY CREW$ - 0$ - 0$ - 0$ - 0$ - 0
COST ESTIMATING$ - 0$ - 0$ - 0$ - 0$ - 0
SPEC WRITING$ - 0$ - 0$ - 0$ - 0$ - 0
AUTOCAD DRAFTING$ - 0$ - 0$ - 0$ - 0$ - 0
CLERK$ - 0$ - 0$ - 0$ - 0$ - 0

PER DIEM - TRAVEL (All Years) **

MEALS AND LODGING >24 HOURSJTR rateJTR rateJTR rateJTR rateJTR rate(per day)
MEALS ONLY > 12 HOURS BUT < 24 HOURSJTR rateJTR rateJTR rateJTR rateJTR rate(per day)
MILEAGE (300 Miles/Car - 1 Car)JTR rateJTR rateJTR rateJTR rateJTR rate(per mile)
HOTEL (Includes 15.5% Lodging Tax)JTR rateJTR rateJTR rateJTR rateJTR rate(night)
AIRFAREJTR rateJTR rateJTR rateJTR rateJTR rate(round trip)
** In accordance with JTR

REPRODUCTION (All Years)

FULL-SIZE DRAWING PHOTOCOPIES (24" x 36")$ - 0$ - 0$ - 0$ - 0$ - 0(per sheet)
HALF-SIZE DRAWING PHOTOCOPIES (11" x 17")$ - 0$ - 0$ - 0$ - 0$ - 0(per sheet)
LETTER-SIZE PHOTOCOPIES (8-1/2" x 11")$ - 0$ - 0$ - 0$ - 0$ - 0(per sheet)
CD/DVD$ - 0$ - 0$ - 0$ - 0$ - 0(per disk)
BINDERS$ - 0$ - 0$ - 0$ - 0$ - 0(per each)
COLOR RENDERING PRINT$ - 0$ - 0$ - 0$ - 0$ - 0(per sq ft)
DELIVERY$ - 0$ - 0$ - 0$ - 0$ - 0(per each)

FA4610-11-R0029

TASK ORDER

A-E TASK ORDER RATE WORKSHEET

<<KTR XYZ>>
DSN RENOVATE / CONVERT FEDERAL COURTHOUSE B2800 - FSPM25SL017
Project Manager:AF Project Manager TBD
Date of Proposal:
Period of Performance:180 Calendar Days
Year of Contract:0(0 - 4)
QUANTITY
LABOR CATEGORY CLASSIFICATIONUNIT OF MEASUREIAIBIINEGOTIATED FFP RATESUB TOTAL
PROJECT MANAGEMENTHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ARCHITECTHOUR$ - 0$ - 0Password$ - 0$ - 0$ - 0
MID LEVEL ARCHITECTHOUR$ - 0$ - 0PZIOC$ - 0$ - 0$ - 0
JUNIOR LEVEL ARCHITECTHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL COMMUNITY PLANNERHOUR$ - 0$ - 0
MID LEVEL COMMUNITY PLANNERHOUR$ - 0$ - 0
JUNIOR LEVEL COMMUNITY PLANNERHOUR$ - 0$ - 0
SENIOR LEVEL LANDSCAPE ARCHITECTHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL LANDSCAPE ARCHITECTHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL LANDSCAPE ARCHITECTHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL STRUCTURAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL STRUCTURAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL STRUCTURAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL CIVIL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL CIVIL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL CIVIL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL MECHANICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL MECHANICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL MECHANICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ELECTRICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ELECTRICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ELECTRICAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL ENVIRONMENTAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL ENVIRONMENTAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL ENVIRONMENTAL ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL FIRE PROT ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL FIRE PROT ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL FIRE PROT ENGINEERHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SENIOR LEVEL GEOTECHNICAL ENGRHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
MID LEVEL GEOTECHNICAL ENGRHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
JUNIOR LEVEL GEOTECHNICAL ENGRHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
TITLE II CONSTR REPHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEYORHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SURVEY CREWHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
COST ESTIMATINGHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
SPEC WRITINGHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
AUTOCAD DRAFTINGHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
CLERKHOUR$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0
SUBCONSULTANTS / OTHER SERVICES
LUMP SUM$ - 0
LUMP SUM$ - 0
LUMP SUM$ - 0
LUMP SUM$ - 0
LUMP SUM$ - 0
LUMP SUM$ - 0
$ - 0
PER DIEM - TRAVEL
MEALS AND LODGING >24 HOURSPER DAY(JTR RATE)ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!
MEALS ONLY > 12 HOURS BUT < 24 HOURSPER DAY(JTR RATE)ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!
MILEAGE (300 Miles/Car - 1 Car)PER MILE(JTR RATE)ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!
HOTEL (Includes 15.5% Lodging Tax)PER NIGHT(JTR RATE)ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!
AIRFAREROUND TRIP(JTR RATE)ERROR:#VALUE!
ERROR:#VALUE!
REPRODUCTION
FULL-SIZE DRAWING PHOTOCOPIES (24" x 36")COPY$ - 0$ - 0$ - 0$ - 0
HALF-SIZE DRAWING PHOTOCOPIES (11" x 17")COPY$ - 0$ - 0$ - 0$ - 0
LETTER-SIZE PHOTOCOPIES (8-1/2" x 11")COPY$ - 0
CD/DVDDISK$ - 0$ - 0$ - 0$ - 0
BINDERSEACH$ - 0$ - 0$ - 0$ - 0
COLOR RENDERING PRINTSQ FT$ - 0$ - 0$ - 0$ - 0
DELIVERYEACH$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
REPRODUCTION SUBTOTAL$ - 0
PER DIEM - TRAVEL SUBTOTALERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!ERROR:#VALUE!
SUBCONSULTANTS / OTHER SERVICES SUBTOTAL$ - 0
TITLE I & II SUBTOTAL$ - 0
TOTAL:ERROR:#VALUE!