NHARNG - State Military Reservation - Building 1 Alterations
Solicitation number
RFB-DMAVS-2027-03
Issued by
Merrimack County, New Hampshire

About this file

This is a Scope of Services document (Exhibit B) for the New Hampshire Department of Military Affairs & Veterans Services (DMAVS) and the New Hampshire Army National Guard (NHARNG) for Building 1 Alterations at the State Military Reservation in Concord, NH, under RFB-DMAVS-2027-03. The project consists of modifying and upgrading the HVAC system and associated controls, including demolition of existing systems and work across the Mechanical, Plumbing, Electrical, and Architectural disciplines. The scope includes four alternates: replacement of three energy recovery ventilation units (ERV-1, ERV-2, and ERV-3) in their existing locations, and replacement of controls for existing terminal devices and associated equipment in Building 1 Room 167. The contractor must provide all labor, parts, materials, tools, equipment, supplies, transportation, and personal protective equipment necessary to perform the work. The contract term is effective upon Governor and Executive Council approval through May 31, 2027. Primary project contact is Ken Coombs, Architect/Project Manager, at (603) 227-1466, with secondary contact Ben Stevens, Design & Construction Branch Chief, at (603) 724-1086.

The contract establishes standard payment procedures with monthly partial estimates subject to a five percent retainage until final completion, with final payment due within thirty days of project acceptance. Normal working hours are 7:00 a.m. to 3:30 p.m., Monday through Friday, with the contractor subject to displacement without notice in the event of military missions taking priority. Liquidated damages range from $200 to $500 per day depending on contract amount, calculated based on failure to complete work on schedule. The contractor is responsible for obtaining all required permits and licenses, providing temporary facilities (electricity, lighting, heating, cooling, ventilation, water, and sanitary facilities), maintaining security and dust control, and submitting comprehensive documentation including record drawings in AutoCAD or Revit format, operation and maintenance manuals, product warranties, and construction progress schedules. The contractor must provide a competent superintendent on-site at all times and is fully responsible for all subcontractor performance. All work is guaranteed against defects for one year from substantial completion, with the contractor liable for correction of any defective work at its own expense.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF NEW HAMPSHIRE

DEPARTMENT OF MILITARY AFFAIRS & VETERANS SERVICES NEW

HAMPSHIRE ARMY NATIONAL GUARD

NHARNG SMR - Building 1 Alterations

RFB-DMAVS-2027-03

EXHIBIT B

SCOPE OF SERVICES

Page 2 of 33 Initials: __________ Date: __________

Table of Contents

SECTION 1 – SCOPE OF SERVICES

1. GENERAL CONDITIONS

2. CONTRACT TERM

3. PRIMARY AND SECONDARY CONTACTS

SECTION 2 – PROJECT CONDITIONS

1. CONTRACT DOCUMENTS

2. ACCESS TO THE WORK

3. CONTRACT ADMINISTRATION

4. ACCIDENT PROTECTION

5. HAZARDOUS MATERIALS

6. SUBCONTRACTS

7. RESPONSIBILITY OF CONTRACTOR TO ACT IN EMERGENCY

8. SEPARATE CONTRACTS

9. MUTUAL RESPONSIBILITY OF CONTRACTORS

10. PAYMENTS TO CONTRACTOR

11. LIMITATION OF CONSTRUCTION OPERATIONS

12. CONTRACTOR'S TITLE TO MATERIALS

13. CHANGES IN WORK

14. PERMITS AND FEES

15. PATENTS

16. ASSIGNMENTS

17. SUPERINTENDENCE BY CONTRACTOR

18. FAILURE TO COMPLETE WORK ON TIME

19. SUBSTANTIAL COMPLETION AND FINAL INSPECTION

20. TERMINATION OF CONTRACT WITH FAULT

21. TERMINATION OF CONTRACT WITHOUT FAULT

22. ASSIGNMENT PROVISION

SECTION 3 – EXECUTION REQUIREMENTS

1. CLOSEOUT PROCEDURES

2. FINAL CLEANING

3. STARTING OF SYSTEMS

4. PROTECTING INSTALLED CONSTRUCTION

Page 3 of 33 Initials: __________

5. PROJECT RECORD DOCUMENTS

6. OPERATION AND MAINTENANCE DATA

7. MANUAL FOR MATERIALS AND FINISHES

8. MANUAL FOR EQUIPMENT AND SYSTEMS

9. SPARE PARTS AND MAINTENANCE PRODUCTS

10. PRODUCT WARRANTIES AND PRODUCT BONDS

11. MAINTENANCE SERVICE

12. GUARANTEE OF WORK

SECTION 4 – SUBMITTAL PROCEDURES

1. SUBMITTALS

2. CONSTRUCTION PROGRESS SCHEDULES

3. SAMPLES

4. TEST REPORTS

5. CERTIFICATES

6. MANUFACTURER'S INSTRUCTIONS

7. CONSTRUCTION PHOTOGRAPHS

SECTION 5 – TEMPORARY FACILITIES AND CONTROLS

1. TEMPORARY ELECTRICITY

2. TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

3. TEMPORARY HEATING

4. TEMPORARY COOLING

5. TEMPORARY VENTILATION

6. TELEPHONE SERVICE

7. WATER SERVICE

8. TEMPORARY SANITARY FACILITIES

9. FIELD OFFICES AND SHEDS

10. PARKING

11. PROGRESS CLEANING AND WASTE REMOVAL

12. BARRIERS

13. ENCLOSURES AND FENCING

14. SECURITY

15. DUST CONTROL

16. POLLUTION CONTROL

17. RODENT CONTROL

Page 4 of 33 Initials: __________

18. REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

SECTION 6 – TEMPORARY FACILITIES AND CONTROLS

1. REQUISITION FOR PAYMENT

2. SCHEDULE OF VALUES

3. UNIT PRICES

4. CHANGE PROCEDURES

5. DEFECT ASSESSMENT

6. ALTERNATES

7. ALLOWANCES

8. TESTING AND INSPECTION

Page 5 of 33 Initials: __________

SECTION 1 – SCOPE OF SERVICES

1. GENERAL CONDITIONS

A. This Agreement consists of the following documents: Form P-37 and Exhibits A, B, C, D, and

Attachments 6, 7, & 8 which are all incorporated herein by reference as if fully set forth herein.

B. The Exhibit B: Scope of Services shall include all the information and requirements about the project that are derived herein as well as the Project Manual (Attachment 6), the authorized construction drawings/documents and clarification sketches (Attachment 7) as well as any addendums.

C. The project consists of modifying and upgrading the HVAC system and associated controls. The project will include the Discipline(s) of: Demolition of existing systems, Mechanical, Plumbing, Electrical and some Architectural finishes.

a. Alternates 1, 2, 3, & 4:

i. Alternate 1: Add cost to replace erv-1 and its controls in the same location.

ii. Alternate 2: Add cost to replace erv-2 and its controls in the same location.

iii. Alternate 3: Add cost to replace erv-3 and its controls in the same location.

iv. Alternate 4: Add cost to replace the controls for the the existing terminal devices (cuh's, uh's, ftr's, hp-1 Through hp-4, heat exchangers and pumps located in building 1 room 167) not included in the primary scope and wire to the new network.

D. The Contractor will provide all labor, parts, materials, tools, equipment, supplies, transportation, vehicles, Personal Protective Equipment, and any other incidentals necessary to travel to the NHARNG State Military Reservation in Concord, NH, to perform the contract services specified herein.

E. For any unanticipated work required, a written proposal will be submitted to the agency primary contact for approval prior to work commencing.

2. CONTRACT TERM

This Agreement shall be effective upon Governor and Executive Council approval through May 31, 2027.

Page 6 of 33 Initials: __________

3. PRIMARY AND SECONDARY CONTACTS

The Contractor will report to and work in conjunction with a DMAVS/NHARNG Primary and Secondary Contact as designated by the Department. The initial Contacts will be:

Primary:

Ken Coombs Architect/Project Manager

(603) 227-1466 kenneth.e.coombs5.nfg@army.mil

Secondary:

Ben Stevens Design & Construction Branch Chief

(603) 724-1086 benjamin.m.stevens3.mil@army.mil

The Department reserves the right to appoint an alternate Primary and Secondary Contact to assist in managing this contract.

SECTION 2 – PROJECT CONDITIONS

1. CONTRACT DOCUMENTS

A. The Contract Documents consist of the Contract Agreement, General Conditions, and

Supplementary General Conditions, Drawings and Specifications, including all Addenda issued prior to execution of the Contract; Bonds where required; insurance certificates: and subsequently thereto, Change Orders issued in accordance with the General Conditions.

B. The Contract Documents shall be signed by the Department and the Contractor in as many original counterparts as may be mutually agreed. No Contract shall be considered as in effect until it has been fully executed by all of the parties thereto and the award concurred in by Governor and Council. If there is federal funding, it must also have the concurrence of the applicable Federal Agency having jurisdiction.

C. This Contract is executed in a number of counterparts, each of which is an original and constitutes the entire agreement between the parties. This Contract shall be construed according to the laws of the State of New Hampshire. No portion of this Contract shall be understood to waive the sovereign immunity of the State. This Contract shall not be amended, except as specified herein, except with the approval of the Governor and Council.

D. The Contract Documents are complementary and anything called for by one of the Contract Documents and not called for by the others shall be of like effect as if required by all.

E. Should the Contract Documents disagree in themselves or with each other, the Contractor shall provide the better quality or greater quantity of work and or materials, unless specifically otherwise directed by written Addendum to the Contract.

F. The Contractors and all subcontractors shall refer to all of the Contract Documents, including those not specifically showing the work of their specialized trades, and shall perform all work reasonably inferable from them as being necessary to produce the intended results.

G. All indications or notations which apply to one of a number of similar situations, materials or processes shall be deemed to apply to all such situations, materials or processes wherever they appear in the work, except where a contrary result is clearly indicated by the Contract Documents.

mailto:kenneth.e.coombs5.nfg@army.mil mailto:benjamin.m.stevens3.mil@army.mil

Page 7 of 33 Initials_______ Date_______

H. Where codes, standards, requirements, and publications of public and private bodies are referred to in the Contract Documents, such references shall be understood to be to the latest revision prior to the date of receiving Bids, except where otherwise indicated.

I. Where no explicit quality or standards for materials or workmanship is established for work, such work is to be of good quality for the intended use and consistent with the quality of the surrounding work and of the construction of the Project in general.

J. All manufactured articles, materials, and equipment shall be applied, installed, connected, erected, tested, cleaned, and conditioned in accordance with the manufacturer's written or printed directions and instructions, unless specifically indicated otherwise in the Contract Documents.

K. The Drawings are generally made to scale, but all working dimensions shall be taken from the figured dimensions or by actual measurements at the job. In case by scaling. Study and compare all the Drawings and verify all figures before laying out or constructing work. The Contractor shall be responsible for errors in his work that might have been avoided thereby.

Whether or not an error is believed to exist, deviation from the Drawings and the dimensions given thereon shall be made only after approval in writing from the Department.

L. The Mechanical, Fire Protection (sprinkler) and Electrical Drawings, when provided, are diagrammatic only, and are not intended to show the exact physical locations or configurations of work. Such work shall be installed to clear all obstructions, permit proper clearances by coordinating his work with other trades, and present an orderly appearance where exposed.

2. ACCESS TO THE WORK

A. The Contractor shall provide for access to the work for inspection by the Department and government officials having jurisdiction. The Consultant, Engineer, and officials of Local, State, and Federal Agencies in the case of such programs as they administer and their authorized representatives shall have access at all times to the work for inspection wherever it is in preparation or progress, and the Contractor shall provide proper facilities for such access and inspection.

3. CONTRACT ADMINISTRATION

A. The Department shall determine the amount, quality, and acceptability and fitness of all parts of the work, shall interpret the Contract Documents, and any Change Orders, and shall decide all other issues in connection with the work. The Department shall have the authority to approve or order changes in the work that alter the terms or conditions of the Contract. The Department shall confirm in writing any oral order, direction, requirements or determination.

B. When a Federal Agency participates in the cost of the work covered by this Contract, the work shall be under the observation and inspection of the Department, but subject to the inspection and approval of the proper officials of the Federal Agency.

Page 8 of 33 Initials_______

4. ACCIDENT PROTECTION

A. It is a condition of this Contract, and shall be made a condition of each subcontract entered into pursuant to the Contract, that the Contractor and any Subcontractors shall not require any laborer or mechanic employed in the performance of the Contract to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous to his health of safety as determined by construction safety and health standards of the Occupational Safety and Health Administration, United States Department of Labor, which standards include, by reference, the established Federal Safety and Health Regulations for Construction. These standards and regulations comprise Part 1910 and Part 1926 respectively of Title 29 of the Code of Federal Regulations and are set forth in the Federal Register. In the event any revisions in the Code of Federal Regulations are published, such revisions will be deemed to supersede the appropriate Part 1910 and Part 1926, and be effective as of the date set forth in the revised regulation.

5. HAZARDOUS MATERIALS

A. The Contractor shall also be aware of laws and regulations relating to hazardous materials that may be encountered during construction operations, either within project limits or at material sites off the project. The health and safety of employees, the general public, and the potential of damage to the overall environment is possible if hazardous materials are not recognized, reported, and the appropriate action taken to dispose of, remove from the site, or otherwise contain the possible contaminants.

B. If any abnormal condition is encountered or exposed that indicates the presence of a hazardous material or toxic waste, construction operations shall be immediately suspended in the area and the Department notified. No further work shall be conducted in the area of the contaminated material until the site has been investigated and the Department has given approval to continue the work in the area. The Contractor shall fully cooperate with the Department and perform any remedial work as directed. Work shall continue in other areas of the Project unless otherwise directed.

C. Exposure to hazardous materials may result from contact with, but not necessarily limited to, such items as drums, barrels, and other containers, waste such as cars, batteries, and building construction debris. Containers leaking unknown chemicals or liquids, abandoned cars leaking petroleum products, batteries leaking acid, construction debris which may include asbestos, or any other source of suspected hazardous material found within excavation areas or stockpiled on land within construction limits shall be referred to the Department of Environmental Services and the Department so that a proper identification of the materials may be made and disposal procedures initiated as required.

D. Disposition of the hazardous material or toxic waste shall be made under the requirements and regulations of the Department of Environmental Services. Work required disposing of these materials and any remedial work shall be performed under

Page 9 of 33 Initials_______ a Supplemental Agreement or Contract item, if included in the Contract.

6. SUBCONTRACTS

A. Nothing contained in the Specifications or Drawings shall be construed as creating any contractual relationship between any Subcontractor and the Department. The Divisions or Sections of the Specifications are not intended to control the Contractor in dividing the work among Subcontractors or to limit the work performed by any trade.

B. The Contractor shall be as fully responsible to the Department for the acts and omissions of Subcontractors and of persons employed by them, as he is for the acts and omissions of persons directly employed by him.

C. The Contractor shall, without additional expense to the State, utilize the services of specialty Subcontractors, as required.

D. The Department will not normally undertake to settle any differences between the Contractor and his Subcontractors or between Subcontractors.

E. The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to bind Subcontractors to the Contractor by the terms of the General Conditions and other Contract Documents insofar as applicable to the work of Subcontractors and to give the Contractor the same power as regards terminating any subcontract that the Department may exercise over the Contractor under any provisions of the Contract Documents.

F. Within fifteen (15) days after the award of the Contract, the Contractor shall submit a complete list of all of the Subcontractors setting forth in detail the work they will be responsible for. If a subcontractor is added during the construction process the Contractor will revise the list and resubmit to the Department.

7. RESPONSIBILITY OF CONTRACTOR TO ACT IN EMERGENCY

A. In case of any emergency that threatens loss or injury of property, and/or safety of life, the Contractor shall act, without previous instructions from the Department, as the situation may warrant. He shall notify the Department thereof immediately thereafter.

Any compensation claimed by the Contractor together with substantiating documents in regard to expense, shall be submitted to the Department and the amount of compensation shall be determined by agreement.

8. SEPARATE CONTRACTS

A. The Department may award other Contracts in connection with the Project, the work under which will proceed simultaneously with the execution of this Contract. The Contractor shall coordinate operations with those of other Contractors.

9. MUTUAL RESPONSIBILITY OF CONTRACTORS

A. If the Contractor or any of his/her Subcontractors or employee’s causes loss or damage to any separate Contractor or Subcontractor on the work, the Contractor or

Page 10 of 33 Initials_______

Subcontractor agrees to settle with such separate Contractor or Subcontractor by agreement, if he/she will so settle. If such separate Contractor or Subcontractor sues the State because of any loss so sustained, the Department shall notify the Contractor and/or their subcontractors, who shall indemnify and hold harmless the Department against any expenses or judgment arising there from.

10. PAYMENTS TO CONTRACTOR

A. The Department will manifest payments to the Contractor each calendar month on the basis of duly certified and approved estimate of the work performed during the preceding period. In preparing estimates, the material delivered on the site and any preparatory work done may be taken into consideration.

B. At least ten (10) days before the end of the billing period, the Contractor shall submit to the Department an itemized Requisition for Payment, supported by such data substantiating the Contractor's right to payment as the Department may require. If payment is to be made on account of materials or equipment not incorporated in the work, but delivered and suitably stored at the site, such payment shall be conditional upon submission by the Contractor of bills of sale or such other procedure satisfactory to the Department to establish the State's title to such materials or equipment or otherwise protect the State's interest including applicable insurance.

C. Immediately upon receipt of the Department Approved Monthly Requisition for Payment, Contractor shall post same at the Contractor's Field Office or project site in a location where Subcontractors and Suppliers have clear access.

D. A five (5) percent retainage of the value of the work performed on each partial estimate will be deducted and retained by the Department until after completion of the entire Contract in an acceptable manner. The balance remaining after the specified percentage has been retained, less all previous payments, will be certified for payment on each partial estimate.

E. Within thirty (30) days after acceptance, the Department shall pay to the Contractor the amount of the Contract less all prior payments. All prior payments and estimates, including those relative to extra work, shall be subject to correction by this payment, which is throughout this Contract called the Final Payment.

F. Retainage will be released at Final Payment.

a. After the Certificate of Substantial Completion has been issued, upon written application by the Contractor and with the approval of the Surety, the Department may release a portion of the retained amount.

G. Payment for Material On Hand:

a. Partial payments are made for materials to be incorporated in the Work, provided the materials meet the requirements of the Contract and are delivered on, or in the vicinity of, the Project site and stored in acceptable places. Partial payments will not exceed 90 percent of the Contract unit price for the item or the amount supported by copies of paid invoices, freight bills, or other

Page 11 of 33 Initials_______ supporting documents required by the Department. The quantity paid will not exceed the corresponding quantity estimate in the Contract. No partial payment will be made on living or perishable materials until incorporated in the Work.

b. When material payments exceed $100,000 or 10 percent (10%) of the total contract amount, whichever is less, notarized copies of paid invoices or copies of canceled checks for all such materials must be submitted to the Department within 45 days of the end date of the estimate on which the material allowance was paid. Failure to provide such documentation will result in the deduction of such material allowance from future estimates until documentation is provided.

c. All material and work covered by partial payments made shall thereupon become the sole property of the Department, but this provision shall not be construed as relieving the Contractor of the sole responsibility of all materials and work upon which payments have been made or the restoration of any damaged work or as a waiver of the right of the State to require the fulfillment of all the terms of the Contract.

H. Payment for Material Not on Hand:

a. The Department will not pay for products and or materials that have not been delivered and stored properly on the construction site.

I. Release of Claims:

a. Neither the final payment nor any part of the retained percentage shall become due until the Contractor shall deliver a complete release of all claims arising under and by virtue of this Contract, including claims for all Subcontractors and suppliers of either materials or labor, plus a release of the Contract Bond and a statement that all Subcontractors and suppliers have been paid. The Department, may pay any and all such claims, in whole or in part, and deduct the amount or amounts so paid from any partial or final payment.

J. Final Payment:

a. Application for Final Payment received from the Contractor will be processed for payment not less than 60 days after project acceptance and final completion unless accompanied by a release of the Contract Bond. This payment shall be the amount of the Contract, amended by approved change orders, less previous payments minus liquidated damages, additional penalties or holdbacks. All prior partial estimates and payments shall be subject to correction in the final estimate and payment.

K. Acceptance of Final Payment Constitutes Release:

a. The acceptance of the Final Payment by the Contractor shall be and shall operate as a release to the Contractor of all claims and of all liability to the Department for all things done or furnished in connection with this work. No payment, however, final or otherwise, shall operate to release the Contractor and its Sureties from any obligations under this Contract or the Contract Bond.

Page 12 of 33 Initials_______

Acceptance of Final Payment shall not impact any warrantees provided by the Contractor with respect to this project.

11. LIMITATION OF CONSTRUCTION OPERATIONS

A. The normal working hours will be from 7:00 am until 3:30 pm M-F unless otherwise agreed in writing by the department.

B. The contractor may be displaced at any time with no notice in the event of a military mission that takes priority over construction.

C. In the State of New Hampshire, legal holidays occur on:

a. New Year's Day

b. Washington's Birthday

c. Memorial Day Fourth of July

d. Labor Day

e. Veterans' Day

f. Thanksgiving Day and Day After

g. Christmas Day

D. Whenever a holiday is observed on a Friday or a Monday. The Contractor shall be required to suspend work for three (3) calendar days.

E. No work shall be performed on Saturday, Sundays or legal holidays except in cases of emergency and upon permission of the Department.

12. CONTRACTOR'S TITLE TO MATERIALS

A. No materials or supplies for the work shall be purchased by the Contractor or any

Subcontractor subject to any chattel mortgage or under a conditional sale or other agreement by which an interest is retained by the seller. The Contractor warrants that he has good title to all materials and supplies for which he accepts partial payment. If any claim is made with respect to materials provided by the contactor, subcontractors, or Independent Contractors, the Contractor shall defend any such claim and shall pay any judgment or settlement thereon.

13. CHANGES IN WORK

A. The Department may at any time, by a written order, and without notice to the Sureties, make changes in the Drawings and Specifications and Completion Date of this Contract and within the general scope thereof.

B. The order shall stipulate the mutual agreed upon lump sum price, which shall be added to or deducted from the Contract Price. The Contractor shall furnish an itemized breakdown of the prices used in computing the value of any change that might be ordered.

C. The compensation herein provided shall be accepted by the Contractor as payment in full, including superintendence, bond, overhead, and profit, for extra work performed

Page 13 of 33 Initials_______ on a force account basis. For all such work, the Contractor shall furnish certified copies of the payrolls on forms provided for that purpose, invoices of all materials, and such other information as may be required by the Department.

14. PERMITS AND FEES

A. The selected Contractor is to obtain and pay for all construction licenses, permits, and fees as may be required by law for construction of State’s facility, and pay for all fees and charges, and use of the property other than the site of the work for storage of materials or other purposes.

B. The Contractor shall pay all applicable Federal, State and Local sales and other taxes, except taxes and assessments on the real property comprising the site of the Project.

15. PATENTS

A. The Contractor shall hold and save the Department and its officers, agents, servants, and employees harmless from liability of any nature including cost and expenses, for or on account of any patented or unpatented invention, process, article or applicable manufactured or used in the performance of the Contract, including its use, unless otherwise specifically stipulated in the Contract Documents.

16. ASSIGNMENTS

A. The Contractor shall not assign the whole or any part of this Contract or any monies due or to become due hereunder, without the written consent of the Department and of all Sureties executing any Bonds on behalf of the Contractor if in connection with said Contract.

17. SUPERINTENDENCE BY CONTRACTOR

A. The Contractor shall employ a competent Foreman or Superintendent, satisfactory to the Department, on the work site at all times to supervise the work in progress, with authority to act for him. The Contractor shall not change superintendents without permission from the Department and shall submit a request in writing with justification for such a change.

a. The superintendent shall be responsible for verifying that all materials, installation, coordination, and workmanship are in conformance with the contract documents.

b. Unless the Department has granted prior written approval, the superintendent shall not, himself, engage in “hands on” construction work.

c. In the event the superintendent fails or refuses to perform functions mentioned above as determined by the Department, the Contractor agrees to a stipulated penalty of up to $500.00 per day, in addition to any liquidated damages provided hereunder.

Page 14 of 33 Initials_______

18. FAILURE TO COMPLETE WORK ON TIME

A. If the Contractor fails to complete all of the work or sections of the Project, if sections are indicated, within the time specified in the Contract or within any additional time allowed, for each working day the Liquidated Damages identified in Section C below will be deducted from any money due the Contractor. This deduction will be made. not as a penalty, but as fixed, agreed liquidated damages for inconvenience to the Department and for reimbursing the Department the cost of the Administration of the Contract, including personnel, time, engineering and inspection. Should the amount of money otherwise due the Contractor be less than the amount of such liquidated damages, the Contractor and its Surety shall be liable to the Department for such deficiency.

B. If the Department permits the Contractor to continue and finish the work after the time fixed for its completion, it shall in no way operate as a waiver on the part of the Department of any of its rights under the Contract. When the final acceptance has been duly made by the Department, any liquidated damage charges shall end.

C. The fixed, agreed, liquidated damages shall be assessed in accordance with the following schedule.

Original Contract Amount Amount of Liquidated damages per day From more than: to and including:

0 25,000 $200.00 25,000 50,000 $300.00 50,000 100,000 $400.00 100,000 500,000 $500.00

19. SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. When the Contractor believes the project is substantially complete, they shall submit an application for substantial completion to the Department. The Contractor shall submit to the Department a list of items of work to be completed or corrected, accompanied by a cost value of these items. The Department will also provide a “punch List” of items to be completed based on their interpretation of the required finished product. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all work in accordance with the Contract Documents. On the basis of an inspection by the Department which determines that the work is substantially complete, a certificate of Substantial Completion shall be issued which will establish the Date of Substantial Completion and state the responsibilities of the Department and the Contractor for such as security, maintenance, heat, utilities, damage to the work and insurance, any other pertinent issues and fix the time limit within which the Contractor shall complete the items listed herein. Warranties required by the Contract Documents shall commence on the Date of Substantial Completion unless otherwise provided in the Certificate of Substantial Completion.

Page 15 of 33 Initials_______

B. If the Contractor fails to proceed to complete the items on the "punch list," then in addition to the corrective measures listed in the Certificate of Substantial Completion, the Department may use the monies still due the Contractor to have such items completed and the Contractor shall lose any claim to the monies so used.

C. Upon written notice that the work is ready for final inspection and acceptance, the Department shall promptly make such inspection, and when they find the work acceptable under the Contract Documents and the Contract fully performed, the Contractor will be provided written notice to that effect. The Contractor shall provide all certificates and reports, as required, throughout the contract and shall coordinate their preparation and submission. Failure to submit such certificates and reports shall be considered default of contract.

20. TERMINATION OF CONTRACT WITH FAULT

A. If the Contractor:

a. Fails to begin work under Contract within the time specified in the notice to proceed, or

b. Fails to perform the work with sufficient workmen and equipment, or with sufficient materials to assume prompt completion of said work, or

c. Performs the work unsuitably or neglects or refuses to remove materials or to perform anew such work as may be rejected as unacceptable and unsuitable, or

d. Discontinues the prosecution of the work, or

e. Fails to resume work, which has been discontinued, within a reasonable time after notice to do so, or

f. Becomes insolvent or has declared bankruptcy, or commits any act of bankruptcy or insolvency, or

g. Fails to pay subcontractors and material/product suppliers, or

h. Makes an assignment for the benefit of creditors, or

i. For any other causes whatsoever, fails to carry on the work in an acceptable manner.

B. The Department will give notice, in writing, to the Contractor and his Surety for such delay, neglect, and default for any item identified above.

a. If the Contractor or Surety does not proceed in accordance with the Notice, then the Department will, upon the Contractor's failure to comply with such Notice, have full power and authority without violating the Contract, to take the prosecution of the work out of the hands of the Contractor. The Department may enter into an agreement for the completion of said Contract according to the terms and conditions thereof or use such other methods as in his opinion will be required for the completion of said Contract in an acceptable manner.

b. All extra costs and charges incurred by the Department as a result of such delay, neglect or default, together with the cost of completing the work under the Contract will be deducted from any monies due or which may become due said

Page 16 of 33 Initials_______

Contractor. If such expenses exceed the sum that would have been payable under the Contract, then the Contractor and the Surety shall be liable and shall pay to the Department, the amount of such excess.

21. TERMINATION OF CONTRACT WITHOUT FAULT

A. Except in cases controlled by the preceding section, the Department, for any cause, including, but not limited to an order of any Federal authority or petition of the Contractor due to circumstances beyond his control may by written notice to the Contractor and the Surety terminate the Contract or any portion thereof subject to the Condition(s) i, ii, iii and iv provided below.

B. Notwithstanding anything to the contrary contained in these condition, it is understood and agreed by the parties hereto that all obligations of the Department hereunder, including the continuance of payments, are contingent upon the availability and continued appropriation of State and/or Federal Funds, and in no event shall the Department be liable for any payments hereunder in excess of such available or appropriated funds. In the event of a reduction, termination or failure to appropriate any or all such available funds or appropriations or a reduction of expenditures of State funds the Department may, by written notice to the Contractor and Surety, immediately terminate this Contract in whole or in part in accordance with the following conditions:

a. When a Contract, or portion thereof, is terminated before completion of all items of work in the Contract, payment will be made for the actual items of work completed. Payment of items of work not completed at time of termination shall be the greater of the following amounts: (1) a percentage of the Contract unit price, which percentage shall be the percentage of completion of the particular item at time of termination or (2) such amount as shall be mutually agreed upon by the parties. No claim for loss of anticipated profits on items or units of work not completed will be allowed.

b. Reimbursement for organization of the work and mobilization, when not otherwise included in the Contract, shall be made where the volume of work completed is too small to compensate the Contractor for these expenses under the Contract; the intent being that an equitable settlement be made with the Contractor.

c. Acceptable materials, obtained or ordered by the Contractor for the work, and that are not incorporated in the work shall, at the option of the Contractor, be purchased from the Contractor based upon the delivered cost of the materials at such points of delivery as may be designated by the Department. The Contractor shall do everything possible to cancel unfilled orders.

d. Termination of a Contract, or a portion thereof, shall not relieve the Contractor of his responsibilities for the work completed nor shall it relieve his Surety of its obligations for and concerning any claims arising out of the work performed.

Page 17 of 33 Initials_______

22. ASSIGNMENT PROVISION

A. The Contractor hereby agrees that it will assign to the Department all causes of action that it may acquire under the anti-trust laws of New Hampshire and the United States as a result of conspiracies, combinations or contracts in restraint of trade which affect the price of goods or services obtained by the Department under this Contract, if so requested by the Department.

SECTION 3 – EXECUTION REQUIREMENTS

1. CLOSEOUT PROCEDURES

A. Submit a signed Substantial Completion Application attesting that the Contract

Documents have been reviewed, Work has been inspected, and that all Work is complete in accordance with Contract Documents and ready for the Department review.

B. Only after completion of all Punch List items and submission of all items the Contractor shall submit a Final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

2. FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

C. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to surface and material being cleaned. Clean new light fixtures free from dust, dirt and fingerprints.

D. Replace filters of operating equipment.

E. Clean debris from roofs, roof drains, downspouts, and drainage systems.

F. Clean site, sweep paved areas, rake landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from site.

3. STARTING OF SYSTEMS

A. Coordinate schedule for start-up of various equipment and systems.

B. Notify the Department seven days prior to start-up of each item.

C. Verify each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify tests, meter readings, and specified electrical characteristics agree with those required by equipment or system manufacturer.

E. Verify wiring and support components for equipment are complete and tested.

F. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment

Page 18 of 33 Initials_______ or system installation prior to start-up, and to supervise placing equipment or system in operation.

G. Execute start-up under supervision of applicable manufacturer's representative and Contractors' personnel in accordance with manufacturer’s instructions.

H. Submit a written report stating that the equipment or system has been properly installed and is functioning correctly.

4. PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturers.

F. Prohibit traffic from landscaped areas.

5. PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the Work:

a. Drawings.

b. Specifications.

c. Addenda.

d. Change Orders and other modifications to the Contract.

e. Reviewed Shop Drawings, Product Data, approved submittals and Samples.

f. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure data is complete and accurate, enabling future reference by the Department.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following:

a. Manufacturer's name and product model and number.

b. Product substitutions or alternates utilized.

c. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

Page 19 of 33 Initials_______

a. Measured depths of' foundations in relation to finish floor datum.

b. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

c. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

d. Field changes of dimension and detail.

e. Details not on original Contract drawings.

f. Contractor to provide record drawings in AutoCad or Revit format compatible with current Department software as well as in PDF format.

g. Contractor to supply two (2) full size paper sets of record drawings to

Department.

G. Submit documents to the Department prior to final payment and release of retainage.

6. OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8·1/2 x 11 inch text pages, three D side ring binders with durable plastic covers. (2 complete copies of all materials required.)

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.

C. Internally subdivide binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Contents: Prepare Table of Contents for each volume, with each product or system description identified, typed on white paper, in three parts as follows:

a. Part I: Directory, listing names, addresses, and telephone numbers of Architect/Engineers), Contractor, Subcontractors, and major equipment suppliers.

b. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:

i. Significant design criteria.

ii. List of equipment.

iii. Parts list for each component.

iv. Operating instructions.

v. Maintenance instructions equipment and systems.

vi. Maintenance instructions for special finishes, including recommended cleaning methods, materials and schedules, and special precautions identifying detrimental agents.

c. Part 3: Project documents and certificates, including the following as required:

Page 20 of 33 Initials_______

i. Shop drawings and product data.

ii. Air and water balance reports.

iii. Certificates.

iv. Originals and Photocopies of warranties and bonds.

7. MANUAL FOR MATERIALS AND FINISHES

A. Submit one copy of preliminary draft or proposed formats and outlines of contents before start of Work. The Department will review draft and return one copy with comments.

B. For equipment, or component parts of equipment put into service during construction and operated by the Department, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes prior to Substantial Completion. Draft copy be reviewed and returned with Architect/Engineer comments. Revise content of document sets as required prior to final submission.

D. Submit two sets of revised final volumes in final form prior to final inspection.

E. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom manufactured products.

F. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

G. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation.

Include recommendations for inspections, maintenance, and repair.

H. Additional Requirements: As specified in individual product specification sections.

I. Include listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.

8. MANUAL FOR EQUIPMENT AND SYSTEMS

A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Contract Administrator will review draft and return one copy with comments.

B. For equipment, or component parts of equipment put into service during construction and operated by the Department, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes 15 days prior to Substantial Completion. Draft copy shall be reviewed and returned after Substantial Completion, with Architect/Engineer comments. Revise content of document sets as required prior to final submission.

D. Submit two sets of revised final volumes in final form prior to final inspection.

E. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting

Page 21 of 33 Initials_______ conditions. Include performance curves, with engineering data and tests, and complete nomenclature and model number of replaceable parts.

F. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and communications; typed and/or by label machine.

G. Include color coded wiring diagrams as installed.

H. Operating Procedures: Include stall-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and special operating instructions.

I. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and troubleshooting; disassembly, repair, and reassembly instructions;

and alignment, adjusting, balancing, and checking instructions.

J. Include servicing and lubrication schedule, and list of lubricants required.

K. Include manufacturer's printed operation and maintenance instructions.

L. Include sequence of operation by controls manufacturer.

M. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.

N. Include control diagrams by controls manufacturer as installed.

O. Include Contractor's coordination drawings, with color coded piping diagrams as installed.

P. Include charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.

Q. Include list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.

R. Include test and balancing reports as specified in Section 01400.

S. Additional Requirements: As specified in individual product specification sections.

T. Include listing in Table of Contents for design data, with tabbed dividers and space for insertion of data.

9. SPARE PARTS AND MAINTENANCE PRODUCTS

A. Furnish spare parts, maintenance, and extra products in quantities specified in individual specification sections.

B. Deliver to Project site and place in location as directed by State; obtain receipt prior to final payment.

10. PRODUCT WARRANTIES AND PRODUCT BONDS

A. Obtain warranties and bonds executed in duplicate by responsible subcontractors, suppliers, and manufacturers, within ten days after Substantial Completion. All warranties start dates shall be the Substantial Completion Date, if project is phased all warranties to start at the date of Substantial Completion of each phase.

B. Execute and assemble transferable warranty documents and bonds from subcontractors, suppliers, and manufacturers.

Page 22 of 33 Initials_______

C. Verify documents are in proper form, contain full information, and are notarized.

D. Co-execute submittals when required.

E. Include Table of Contents and assemble in three D side ring binder with durable plastic cover.

F. Submit prior to final Application for Payment.

G. Time Of Submittals:

a. For equipment or component parts of equipment put into service during construction with State's permission, submit documents within ten days after acceptance.

b. Make other submittals within ten days after Date of Substantial Completion, prior to final Application for Payment.

c. For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within ten days after acceptance, listing date or acceptance as beginning or warranty or bond period.

11. MAINTENANCE SERVICE

A. Furnish service and maintenance of components indicated in specification sections during warranty period.

B. Examine system components at frequency consistent with reliable operation. Clean, adjust, and lubricate as required.

C. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by manufacturer of original component.

D. Do not assign or transfer maintenance service to agent or Subcontractor without prior written consent of the Department.

12. GUARANTEE OF WORK

A. Except as otherwise specified, all work shall be guaranteed by the Contractor against defects resulting from the use of inferior materials, equipment or workmanship for one

(1) year from the Date of Substantial Completion of the work.

B. If, within any guarantee period, repairs or changes are required in connection with guaranteed work, which in the opinion of the Department, is rendered necessary as a result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract shall, promptly upon receipt of notice from the Department and at his own expense:

a. Place in satisfactory condition in every particular, all such guaranteed work, correct all defects therein.

b. Make good all damage to the building or site, or equipment or contents thereof;

which in the opinion of the Department is the result of the use of materials, equipment or workmanship which are inferior, defective, or not in accordance with the terms of the Contract.

Page 23 of 33 Initials_______

c. Make good any work or material, or the equipment and contents of said building or site disturbed in fulfilling any such guarantee.

C. In any case, wherein fulfilling the requirements of the Contract or of any guarantee, embraced in or required thereby, the Contractor disturbs any work guaranteed under another contract, he shall restore such disturbed work to a condition satisfactory to the Department and guarantee such restored work to the same extent as it was guaranteed under such other contracts.

D. If the Contractor, after notice, fails to proceed promptly to comply with the terms of the guarantee, the Department may have the defects corrected and the Contractor and his/her Surety shall be liable for all expense incurred.

E. All special guarantees applicable to definite parts of the work that may be stipulated in the Specifications or other papers…