Attachment 21 - Seed Project Liquidated Damages.pdf
PDF 669 KB Posted
- Attached to
- JBER Exterior Paint IDIQ***Amendment 0003***
- Solicitation number
- FA500021R0022
About this file
This document contains liquidated damages terms for a federal contract opportunity for exterior painting projects on Joint Base Elmendorf-Richardson in Alaska. The contract is an Indefinite Delivery, Indefinite Quantity contract held by the 673rd Civil Engineering Office to supplement its in-house capabilities. Liquidated damages for delays are specified as $591.78 per day for the first and last days of delay, and $210.84 per day for all other delay days. The damages were calculated based on estimated daily costs for an inspector, project engineer, and chief of engineering to oversee delayed projects.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LIQUIDATED DAMAGES
DETERMINATION OF LIQUIDATED DAMAGES:
The estimated damages for the 673rd Civil Engineering Office for first and last days of delay beyond the project completion date are:
1. Inspector 2 hours/day @ $47.92/hour = $ 95.84
2. Project Engineer 2 hours/day @ $57.50/hour = $ 115.00
3. Chief of Engineering 1 hour/day @ $85.05/hour = $ 85.05
Total Civil Engineering Cost = $295.89X2 days= $591.78
The estimated damages for the 673rd Civil Engineering Office for all other days other than the first and last days of delay beyond the project completion date are:
1. Inspector 2 hours/day @ $47.92/hour = $95.84
2. Project Engineer 2 hours/day @ $57.50/hour = $115.00
Total Civil Engineering Cost = $210.84/day
FA500021R0022 JBER Paint IDIQ Attachment 22 - Seed Project Liquidated Damages
| 2021-07-29T11:47:25-0800 | |
| REINHART.SUSAN.RENEE.1259452526 |
File details come from the government source that posted it. Updated .