Attachment 2 Sample Service Order Form.xlsx
XLSX spreadsheet 98 KB Posted
- Solicitation number
- W912DY26RA002
About this file
The document is a detailed Service Order Form template for a federal maintenance contract, specifically designed for fuels infrastructure maintenance. The form provides comprehensive instructions for completing service order documentation, covering critical sections such as service order information, authorization, safety requirements, and quality of work evaluation. Key components include blocks for capturing service order type, contractor details, facility information, maintenance category, priority level, and specific work descriptions.
The form is structured to support preventive and corrective maintenance activities, with specific emphasis on safety documentation, work complexity assessment, and performance tracking. Notable features include dropdown menus for service order types, military service selection, mandatory safety document listings, and a complexity matrix to determine the level of supporting information required. The template appears closely linked to the related federal contract opportunity for Fuels South Atlantic Division maintenance services, which covers maintenance work in Virginia, North Carolina, South Carolina, Georgia, Florida, Alabama, Mississippi, Puerto Rico, and the U.S. Virgin Islands.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
SERVICE ORDER FORM INSTRUCTIONS
FMSR Form: SO Validation
| All service order information should be put into this sheet. All other sheets will be populated from this sheet |
| PART I |
| Block C3: Service Order number will be provided by the government. It is the three letter site code, contractor three letter abbreviation, and service order number. |
| Block E3: Insert the SO initiation Revision # if any |
| Block C4: Insert the full Prime Contractor's name. |
| Block C5: Insert Facility Number(s). Use Alt-Enter to add rows. |
| Block D5: Insert Facility Name(s). Use Alt-Enter to add rows. |
| Block C6: Insert the three letter site code. |
| Block D6: Insert the Site Name. |
| Block C7: Insert the date that the service order was initiated by the FMSR. |
| Block C8: Select Yes or no depending if the service order is required due to a Notice of Violation (NOV) or to prevent a NOV. |
| Block D8: Insert the description of the NOV. |
| Block C9: Select Yes or no depending if the service order is related to a Natural Disaster |
| Block D9: Insert Name of the disaster (e.g., Hurricane, Tsunami, Flood, etc.) |
| Block H3: Select the service order type from the drop down menu. Normally this is determined by the FMSR on the service order initiation form. |
| Block H4: Insert the contract number. |
| Block H5: Insert the task order number. |
| Block H6: Select the military service from the drop down menu. This will be the service that actually owns the real property fuel systems. |
| Block I6: Insert the abbreviated Army Corps Military District such as POD-H, POD-J, NAD-AF, SPD-N1, etc. |
| Block H7: Insert the funding CLIN for the particular service order. |
| Block H8: Insert the maintenance category (DLA Work Category) that most represents the majority of the work being performed under this service order. This can be found in the Facility Maintenance Plan. |
| Block H9: Select service order priority level as designated by the FMSR. |
| Block A11: Insert service order description and utilize SO description continuation sheet at bottom of form as necessary. As part of SO description, please list the required safety documents. Use Alt-Enter to add rows. |
| PART II |
| Block D13: Insert FMSR full Name |
| Block D14: FMSR digitally signs/dates initial validation of Service Order authorizing repair. |
| Block D15: FMSR digitally signs/dates initial validation of Service Order authorizing repair. |
| Block D17: FMSR digitally signs/dates final validation of Service Order authorizing repair. |
| Block D18: FMSR digitally signs/dates final validation of satisfactory completion of Service Order repair. |
| PART III |
| Rows 20-29: FMSR should use this section to report on Contractor's Quality of Work. Part III will be used for final evaluation of Contractor performance. |
| Block A30: Use the comment section for any box checked "NO" to explain Contractor deficiency in the quality of work. Other comments negative or positive are encouraged. |
| Additional Instructions for Contractor: |
| 1. Once sheet is filled out it must be converted to stand alone PDF document. |
| 2. The PDF FMSR sheet needs to have text boxes, check boxes, and Digital signature fields added to the appropriate area. |
| 3. The FMSR Form is the only form to be sent to the FMSR. |
KO Form: SO Submission
| PART I |
| Block C3: Populates from FMSR Form |
| Block E3: Insert the SO submission Revision # if any. Block A25 will be the log of all revisions for this SO. |
| Block C4: Populates from FMSR Form |
| Block C5: Insert the full Sub-Contractor's name |
| Block E5: Populates from FMSR Form |
| Block C6: Populates from FMSR Form |
| Block D6: Populates from FMSR Form |
| Block C7: Populates from FMSR Form |
| Block D7: Populates from FMSR Form |
| Block B8: Insert the date that the service order was submitted by the Contractor. |
| Block E8: Select Yes or No depending if the service order contains a long lead item as described in PWS Appendix A. |
| Block B9: Insert the estimated time of arrival of the long lead item |
| Block E9: Insert expected start work date for the service order |
| Block C10: Populates from FMSR Form |
| Block D10: Populates from FMSR Form |
| Block C11: Populates from FMSR Form |
| Block D11: Populates from FMSR Form |
| Block H3: Populates from FMSR Form |
| Block H4: Populates from FMSR Form |
| Block H5: Populates from FMSR Form |
| Block H6: Populates from FMSR Form |
| Block I6: Populates from FMSR Form |
| Block H7: Populates from FMSR Form |
| Block H8: Populates from FMSR Form |
| Block H9: Insert the UFC 3-460-03 Section Reference Number associated with the Maintenance Category as described in the Facility Maintenance Plan. |
| Block G10: Insert the Component Unique Identifier(s) (CUID) associated with the component as described in the Facility Maintenance Plan. Use Alt-Enter to add rows |
| Block J10: Insert the Contractor's Deficiency Unique Identifier (DUID) as identified on the deficiency report. Use Alt-Enter to add rows. |
| Blaock B12: Insert Yes or No if CMITM was used in SO. |
| Block G11: CEHNC will select Yes or No if a WP has been approved based on the Contractor's request. |
| Block J11: Populates from FMSR Form |
| Block E11: Populates SO complexity |
| Block B12: Populates if any CMITM items were used in the SO |
| Block D12: Populates the CMITM item used |
| Block G12: Populates the quantity of CMITM items used |
| Block J12: Populates the total quantity of CMITM items within that category for the option year |
| PART II |
| Block C14: Insert the name of the Task Order Safety Manager. |
| Block H14: Insert the name of the expected person who will perform the duties of the on-site safety and health officer (SHO). If the actual person on-site changes redline this block with the actual person on-site. |
| Block C15: Select the level of the required on-site SHO from the drop down menu (Based on TOSM determination). The levels are defined in the contract PWS. If the actual the actual SHO on-site changes redline this block with the actual person (same level) on-site. |
| Block H15: Designate whether supporting documents for the jobsite SHO are included in the service order, already accepted in the APP, or not applicable. |
| Block C16: Provide a justification for the selected level of on-site SHO. The contractor is required to have an individual responsible for safety on all jobsites. The Task Order Safety Manager shall make this determination and provide justification to the Government Designated authority (GDA) for acceptance. |
| Block C17: Enter Qualified / Competent Person's name. |
| Block H17: Designate whether supporting documents for the Qualified / Competent Person are included in the service order, already accepted in the APP, or not applicable. |
| Block C18: Select yes if there are new, or updated plans added to the service order that were not included in the APP. Reference EM385-1-1 APPENDIX A for a list of plans requiring an individual safety plan. |
| Block A21-22: List all safety plans required for SO (See Appendix A). |
| Block H18: Select Yes if all AHAs on this service order have been pre-accepted. Select No if there are new AHAs (not previously accepted). |
| Block F21-22: List all AHAs required for this service order. Every Service order submitted must have AHA/s tailored to the service order. |
| Block D24-25: The Task Order Safety Manager needs to e-sign and date this form prior to submittal. Signature verifies SO safety documentation has been reviewed and approved. Approved means documentation meets all contract, OSHA, and regulatory requirements prior to submittal. |
| Block A26: Service Order Revision Log ADD or DELETE ROW. This allows the Contractor to click the button to add cells or remove cells from this section. |
| Block A27-A:29: Insert the Revision Number and small description of what was revised. |
| Block K27-K29: Insert Date of submission for each revision. |
| Block A31: Populates from FMSR Service Order Form |
| PART III |
| Instructions for Contractor |
| Block D33-34: The Contract Safety Manager needs to e-sign and date this form prior to submittal. Signature verifies SO safety documentation has been reviewed and approved. Approved means documentation meets all contract, OSHA, and regulatory requirements prior to submittal. |
| Block D35-36: Project Manager needs to e-sign and date this form prior to submittal. Signature verifies that SO Package has been reviewed and approved. Approved means package meets all contract requirements prior to submittal. |
| Block D37-40: For Government Use Only. |
| 1. The form allows the Contractor to add or delete cells by clicking the ADD or DELETE ROW buttons in each section. |
| 2. All labor rates shall be fully burdened labor rates in accordance with Contractor's accepted proposal documents. |
| 3. ALL prime contractor costs associated with the service order shall be included in the service order fee. The prime contractor service order fee shall be applied to the total subcontracted costs, prime contractor material costs, and on-site prime contractor labor cost. This means the contractor can self-perform the service order and still apply the SO fee to their own labor. The service order fee will not be applied to |
travel and tax. Labor shall be fully burdened.
| 4. Travel/Travel Labor/Per Diem for NTE/ESOs will be included on the Travel Expense Report and submitted in accordance with the PWS Appendix A. |
| 5. Taxes on the KO form are dependent upon work location and shall be input in the appropriate cell for the work location. |
| 6. Cells not applicable should be left blank. |
| 7. When ready to submit for approval the Contractor will convert this to a pdf document and the Contractor's authorized representatives (including the Safety Manager) will digitally sign the form |
COMPLEXITY MATRIX:
This is a guide to help the contractor determine the amount of supporting information that will be required as part of the SO
When form is complete it will be converted to a pdf document to be included with the service order
SUBMITTING THE SERVICE ORDER:
The contractor will make a PDF Portfolio and add the following PDF documents to the portfolio:
FMSR Form with initial validation signature
KO Form with all required Contractor's signatures
Complexity matrix
AHA Sheet
UFC Work Type Category - Government use only.
This Excel file will also be included in its raw filled out state
Work Plan-If approved by Government
FMSR Form
| SERVICE ORDER FORM | ||||||
| PART I - SERVICE ORDER INFORMATION | ||||||
| SERVICE ORDER NUM.: | XYZ-KTR-100 | REV # | SERVICE ORDER TYPE: | Routine | ||
| CONTRACTOR: | Contractor Name | CONTRACT NUMBER: | Contract # | |||
| FACILITY NUM./NAME: | ||||||
| (Use ALT-Enter to add rows) | 6AA |
XXXX
T2-468
TEXTRA47
9999 aaa
STOR JET FL
EXAMPLE NAME 2
JP-8 Fuel Tank Terminal 2 Terminal 3 Terminal 4 Terminal 5
| Pier 17 | TASK ORDER NUMBER: | Task Order # | |||||
| SITE CODE/SITE NAME: | XYZ | Site Name | SERVICE & PHASE: | Air Force | SAD-AF2 | ||
| SERVICE ORDER INITIATION DATE: | 26-Oct-20 | FUNDING CLIN: | 0004AA | ||||
| Notice of Violation (NOV) Related? | No | MAINTENANCE CATEGORY: | Air Compressors | ||||
| Is the SO related to Natural Disaster? | No | SO PRIORITY LEVEL: | P2 | ||||
| DETAILED SO DESCRIPTION: (Use ALT-Enter to add rows or new paragraphs) | |||||||
| Replace PRT Pump/Motor Assembly - CUIDs: ROB-4302-CENPT-0002 & ROB-4302-ELEMT-0002. |
Per the FMSR, the PRT pump/motor assembly for Tank #23 (FAC 4302) requires replacement. It has been noted that the motor is defective as well as the pump.
Ktr to replace the defective pump/motor assembly. A qualified electrician will be present for all efforts to make electrical disconnects and final terminations as required. Work will be IAW NFPA 780 article 500.
MORE INFO
MORE INFO More and Better Info.
| PART II - AUTHORIZATION | ||
| FMSRNAME (First and Last): | ||
| FMSRINITIAL VALIDATION: | ||
| E-SIGNED & DATED | ||
| By signing below, I certify that the services under the above Service Order have been satisfactorily completed. | ||
| FMSRFINAL VALIDATION: | ||
| E-SIGNED & DATED | ||
| PART III - QUALITY OF WORK | ||
| Was work performed in a quality manner? | YES | NO |
| Was work performed safely? | YES | NO |
| Was work performed in a timely manner? | YES | NO |
| Did the prime contractor successfully manage the subcontractor? | YES | NO |
| Did contractor communicate with you prior to and upon completion of work? | YES | NO |
| Was the work area kept clean during and upon completion of work? | YES | NO |
| Did contractor have all necessary certifications? | YES | NO |
| Were there any issues with the work performed? | YES | NO |
| Did contractor arrive with all parts, materials, and tools needed to complete the repair? | YES | NO |
| FMSR COMMENTS: Any box checked "NO" requires a comment, other comments encouraged. If contractor performed in a manner worth noting (positive or negative), please provide comments. | ||
| X |
KO Form
| PRIME CONTRACTOR | ||||
| PART I - SERVICE ORDER INFORMATION | ||||
| SERVICE ORDER NUM.: | XYZ-KTR-100 | REV # | SERVICE ORDER TYPE: | Routine |
| CONTRACTOR: | Contractor Name | CONTRACT NUMBER: | Contract # | |
| SUB-CONTRACTOR(S): | Sub-Contractor Name | DLA Wortk Type Category or UFC Section Ref Work Cat. | Air Compressors | |
| FACILITY NUM./NAME: | 6AA |
XXXX
T2-468
TEXTRA47
9999 aaa
STOR JET FL
EXAMPLE NAME 2
JP-8 Fuel Tank Terminal 2 Terminal 3 Terminal 4 Terminal 5
| Pier 17 | SERVICE & PHASE: | Air Force | SAD-AF2 | ||||||
| SITE CODE/SITE NAME: | XYZ | Site Name | FUNDING CLIN: | 0004AA | |||||
| SERVICE ORDER SUBMISSION DATE: | 29-Mar-21 | Does SO Include Long Lead Items? | No | MAINTENANCE CATEGORY: | Air Compressors | ||||
| Expected Deliver Date of LL item: | 9-Mar-21 | Expected Start Work Date: | 29-Apr-21 | UFC REFERENCE: | Sections 7-2 through 7-10 | ||||
| Notice of Violation Related? | No | CUID: | ROB-4302-CENPT-000 | ||||||
| ROB-4302-ELEMT-0002 | DUID: | DUID | |||||||
| Is the SO related to Natural Disaster? | No | COMPLEXITY: | Low | Work Plan Required (Yes/No): | No | SO Priority Level: | P2 | ||
| CMITM Used: (Yes/No): | Yes | ITEM(S) USED: | JOINT SEALANT/CRACK REPAIR | CONTRACT CMITM QUANTITY: | 800 LF | SO QUANTITY TOTAL: | 200/800 or 900/800 | ||
| PART II - SERVICE ORDER SAFETY INFORMATION | |||||||||
| TOSM NAME: | John Doe | JOBSITE SHO NAME: | John Doe | ||||||
| REQUIRED SHO LEVEL: | L2 - Dual Hatted Safety | SHO PROOF OF QUALIFICATION? | Included in SO | ||||||
| JUSTIFICATION FOR LEVEL OF SHO: | TEST | ||||||||
| QUALIFIED/COMPETENT PERSON'S NAME: | John Doe | QP/CP PROOF OF QUALIFICATION? | Included in SO | ||||||
| ANY NEW PLANS REQUIRE SAFETY REVIEW? | Yes | ALL AHAs ARE PREACCEPTED? | Yes | ||||||
| AHA Attached | No | ||||||||
| LIST INCLUDED PLANS (SEE EM385-1-1 APPENDIX A): | LIST INCLUDED AHAs: | ||||||||
| Test | test |
| By signing below, I certify that I have reviewed the safety documents for this service order and they meet all contract, OSHA, and regulatory requirements. |
| TASK ORDER SAFETY MANAGER SIGNATURE: (MUST BE E-SIGNED AND DATED) |
| Service Order Revision Log: Add Drop Down for Rev # | |
| Description: | Date: |
| Last Revision |
| SO DESCRIPTION: |
| Replace PRT Pump/Motor Assembly - CUIDs: ROB-4302-CENPT-0002 & ROB-4302-ELEMT-0002. |
Per the FMSR, the PRT pump/motor assembly for Tank #23 (FAC 4302) requires replacement. It has been noted that the motor is defective as well as the pump.
Ktr to replace the defective pump/motor assembly. A qualified electrician will be present for all efforts to make electrical disconnects and final terminations as required. Work will be IAW NFPA 780 article 500.
MORE INFO
MORE INFO More and Better Info.
| PART III - SERVICE ORDER PRICING | |
| Contractor Safety Manager | |
| E-SIGNED & DATED | |
| CONTRACTOR (Project Manager): | |
| E-SIGNED & DATED | |
| CONTRACTING OFFICER OR SOA: | |
| Fair and Reasonable - FAR 15.404-1 Technical Analysis | |
| Fair and Reasonable - FAR 15.404-1 Price Analysis | |
| E-SIGNED & DATED | |
| TOTAL COST OF SERVICE ORDER: | $108,955.00 |
| PRIME FULLY BURDENED LABOR | |||
| TOTAL MH | HOURLY RATE | TOTAL COST | |
| Labor Category / Description: Confirm All Rates are in Accordance with TO Proposed Rates. | |||
| Site Superintendant - 1-10 hr day | 10.00 | $100.00 | $1,000.00 |
| Doing Work | 5.00 | $17.75 | $88.75 |
| Labor Sub-Totals | $ 1,088.75 |
| PRIME MATERIAL/EQUIPMENT/OTHER | |||||||||
| QTY. | UNIT COST | TOTAL COST | |||||||
| Item Description | |||||||||
| Item Description | Manufacturer | Man. Part No. | Vendor Part No. | Catalog/Vendor | Catalog # | Vendor Price | |||
| Pump/Motor Assembly | R S Corcoran Co. | 3000 D (AA05) | R S Corcoran Co. | $5,000.00 | 1.00 | $5,000.00 | $5,000.00 | ||
| $600.00 | 10.00 | $600.00 | $6,000.00 | ||||||
| PRIME Material/Equipment/Other Sub-Totals | $11,000.00 |
| Subcontractor Total Cost | |
| Subcontractor(s) Name/Task: | |
| Subcontractor A - Remove Defective Pump/Motor Assembly | $100.00 |
| Something Cool but Not Cheap | $8,000.00 |
| 3rd Thing | $0.17 |
| Subcontractor Sub-Totals | $8,100.17 |
| Travel Total Cost | |||
| Travel (NTE’s/ESOs Only): | |||
| Travel A | $800.00 | ||
| Travel B | $11.30 | ||
| Travel C | $87,000.00 | ||
| Travel Sub-Totals | $87,811.30 | ||
| Prime Labor | $1,088.75 | ||
| Prime Materials/Equipment/Other | $11,000.00 | ||
| Tax (MSE) (example percentage) | 5% | $550.00 | |
| Subcontractor Cost | $8,100.17 | ||
| Travel Cost | $87,811.30 | ||
| SO Fee (Labor, MSE, Sub) (example percentage) | 2% | $403.78 |
| ESO Fee ($1) (example Fee) | $1.00 | ||
| TOTAL | $108,955.00 |
Add Row Add Row Add Row Delete Row Delete Row Delete Row Add Row Delete Row Add Row Delete Row
Complexity Matrix
| COMPLEXITY DETERMINATION SHEET |
| Instructions: Contractor should initially estimate the complexity of the service order. PLACE AN "X" IN THE BOX FOR LOW, MEDIUM, OR HIGH FOR EACH FACTOR. Depending on complexity, ensure the cooresponding required content is submitted with service order. |
This is meant to be a guide only. Final determination of complexity as well as what is required to be included with each service order will be determined by USACE.
| TASK | Impacts | Complexity Rating | |||
| Likelihood | Minor | Moderate | Major | ||
| Coordination with other trades, other contractors, customer, owner/operators, or regulatory | Unlikely | 0 | 1 | 3 | 1 |
| Moderate | 1 | 2 | 3 | ||
| Likely | 2 | 3 | 3 | ||
| Technical complexity of equipment being serviced. | Unlikely | 0 | 1 | 3 | 1 |
| Moderate | 1 | 2 | 3 | ||
| Likely | 2 | 3 | 3 | ||
| Required fuel system outages or outages of supporting utilities | Unlikely | 0 | 1 | 3 | 1 |
| Moderate | 1 | 2 | 3 | ||
| Likely | 2 | 3 | 3 | ||
| Level of unknowns or undefined conditions | Unlikely | 0 | 1 | 3 | 1 |
| Moderate | 1 | 2 | 3 | ||
| Likely | 2 | 3 | 3 | ||
| Logistical difficulty accessing the site or obtaining materials | Unlikely | 0 | 1 | 3 | 1 |
| Moderate | 1 | 2 | 3 | ||
| Likely | 2 | 3 | 3 | ||
| OVERALL COMPLEXITY RATING | 5 | ||||
| Low = 1-5 | |||||
| Moderate = 6-10 | |||||
| High = 11-15 |
| Required Content | *Complexity | ||
| Low | Medium | High | |
| Scope of Work | Yes | Yes | Yes |
| Estimated Duration in Calendar Days | Yes | Yes | Yes |
| Pictures | Yes | Yes | Yes |
| Cost Proposals | Yes | Yes | Yes |
| SSAPP | Yes | Yes | Yes |
| AHA | Yes | Yes | Yes |
| Manufacturers Data | A/R | Yes | Yes |
| WORK PLAN REQUIRED FOR MEDIUM AND HIGH COMPLEXITY | |||
| Table of Contents | * | Yes | Yes |
| Work Plan Narrative | * | Yes | Yes |
| Sketches | * | Yes | Yes |
| Detailed Drawings | * | A/R | A/R |
| Project Specific Schedule | * | A/R | Yes |
| Specifications | * | A/R | Yes |
| Project Specific Quality Control Plan | * | A/R | A/R |
| Work Plan Review Meeting/Pre-Con | * | A/R | A/R |
| Site Investigation Report | * | A/R | A/R |
| As Required by the Government = * |
AHA
| Activity Hazard Analysis (AHA) | |||||||||||
| AHA Number | Overall Risk Assessment Code (RAC) - Use Highest RAC from Tasks Below | M | |||||||||
| SERVICE ORDER NUMBER | XYZ-KTR-100 | Rev # | Risk Assessment Code (RAC) Matrix | ||||||||
| TASK ORDER SAFETY MANAGER NAME: | |||||||||||
| CONTRACT NUMBER: | Contract # | Severity | Probability | ||||||||
| TASK ORDER/DELIVERY #: | Task Order # | ||||||||||
| PRIME CONTRACTOR: | Contractor Name | Frequent | Likely | Occasional | Seldom | Unlikely | |||||
| SUBCONTRACTOR: | |||||||||||
| JOBSITE SAFETY & HEALTH OFFICER: | Catastrophic | E | E | H | H | M | |||||
| CONTRACTOR QUALIFIED PERSON: | Critical | E | H | H | M | L | |||||
| CONTRACTOR COMPETENT PERSON: | Marginal | H | M | M | L | L | |||||
| Negligible | M | L | L | L | L | ||||||
| RAC CHART and ACCEPTANCE BY GOVERNMENT DESIGNATED AUTHORITY | Review each “Hazard” with identified safety “Controls” and determine (RAC) | ||||||||||
| E = EXTREMELY HIGH (PWO/OICC/ROICC) | Identify the RAC (Probability/Severity) as E, H, M, or L for each “Hazard”. Place the highest RAC at the top of AHA. This is the overall risk assessment code for this activity | ||||||||||
| H = HIGH RISK (FEAD DIRECTOR) | “Severity” is the outcome/degree if an incident, near miss, or accident did occur and identified as: Catastrophic, Critical, Marginal, or Negligible after controls are in place | ||||||||||
| M = MODERATE RISK (CM or ET or PAR) | “Probability” is the likelihood to cause an incident, near miss, or accident did occur and identified as: Frequent, Likely, Occasional, Seldom, or Unlikely after controls are put in place. | ||||||||||
| L = LOW RISK (ET or PAR) | |||||||||||
| Job Steps | Hazards | Controls | RAC | ||||||||
| E | |||||||||||
| H | |||||||||||
| M | |||||||||||
| L |
Work Type Category
| Component Unique Identifier: | Site Code-Facility #-Component Acronym-Sequential # | Air Compressors | Aboveground Field-Erected Tanks (Section 8-4) | |||||
| Example: | AAD-00063A-RCVL-0001 | Alarms | Aboveground Piping (Section 6-1.3) | |||||
| NOTE: If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This | ||||||||
| CUID shall be the standard for all DLA capitalized equipment | Bollard | Aboveground Piping and Equipment Coatings (Section 6- 10.1) | ||||||
| DLA Work Type Category | UFC Section Reference Work Category | |||||||
| (Revised per Change 1, 29 April 2021) | Component | |||||||
| Acronym | Building | Aboveground Shop Fabricated Tanks (Section 8-5.1) | ||||||
| Air Compressors | Air Compressors | AIRC | Containment/Joints | Air Compressors | ||||
| Alarms | Externally Mounted Level Alarms (Section 8-9.9.1) | EMLA | Corrosion Control/Coatings | Air Eliminator Tanks (Section 3-10.1) | ||||
| Internally Mounted Level Alarms (Section 8-9.9.3) | IMLA | Electrical/Lighting | Aircraft Fueling Hoses (Section 4-7.5) | |||||
| Bollard | Bollards | BLRD | Electrical/Power | Aluminum Honeycomb Floating Pans (Section 8-9.1.1) | ||||
| Building | Building HVAC | BHVAC | Electrical/Protection | API 510 Inspections | ||||
| Building Domestic Water System | BWTR | Eyewash/Shower | API 653 or STI Inspection | |||||
| Building Waste Water | BWSW | Fencing/ Gates | Automatic Air Vents (Section 3-10.2) | |||||
| Building - Lighting | BLTG | Filtration | Automatic Line Leak Detector (Section 7-19.1.2) | |||||
| Building - Architectural | BARCH | Fire Suppression Equipment | Back Pressure Control Valves (Section 4-4.2.6) | |||||
| Building - Fire Sprinkler System | BFIRE | Fuel Laboratories | Back-Up Power Generators | |||||
| Containment/Joints | Containment Systems (General) (Section 8-10.1) | CSGEN | Gauges | Ball Valves (Section 6-6.2.4) | ||||
| Concrete and Cement Brick Dike/Berm Walls (Section 8- | ||||||||
| 10.2.1) | DKBW | Generators | Basket Strainers (Section 3-6.4) | |||||
| Dike/Berm Floors (Section 8-10.2.2) | DKBF | Heating Coils | Bollards | |||||
| Earthen Dike Walls (Section 8-10.3) | ETHDW | Hoses | Boom Reels (Section 5-9) | |||||
| Self-Diking or Vaulted Tank Containment (Section 8-10.4) | SDVTCS | Hydrazine | Breakaways (Section 7-4) | |||||
| Flexible Membrane Liners (Section 8-10.5) | FXML | Inspections | Building - Architectural | |||||
| Fuel Truck and Rail Car Containment Areas (Section 11-1.1) | FTKRCC | Issue/Receive - Ground | Building - Fire Sprinkler System | |||||
| Remote Spill Containment (Section 11-1.2) | RSCS | Issue/Receive - Marine | Building - Lighting | |||||
| Piers and Wharves Fuel Containment Systems (Section 5- 1.2) - Testing | FPWCT | Liquefied Petroleum | Building Domestic Water System | |||||
| Fuel Pier/Wharf Containment (PWS Section 3) | FPWC | Meter/ calibrations | Building HVAC | |||||
| Corrosion Control/Coatings | Aboveground Piping and Equipment Coatings (Section 6- 10.1) | AGPCT | Miscellaneous | Building Waste Water | ||||
| Miscellaneous | Miscellaneous Deactivated Components (Section 12-5) | MDEAC | Natural Disaster | Butterfly Valves (Section 6-6.2.6) | ||||
| Electrical/Lighting | Lighting (Section 9-1.8) | LIGHT | Natural Gas | Canopies (Section 11-2.2) | ||||
| Electrical/Power | Electrical Equipment (Section 9-1.2) | ELEQ | Nozzle | Card and Key Locks (Section 9-3) | ||||
| Power Cables (Section 9-1.3) | PWRCBL | Other | Cathodic Protection (Section 9-2.1) | |||||
| Motor Controls (Section 9-1.4) | MTRCT | Pantograph | Centrifugal Pumps (Section 3-8.1) | |||||
| Panelboards (Section 9-1.5) | PNLB | Piping | Check Valves (Section 6-6.2.8) | |||||
| Electric Motors (Section 9-1.7) | ELEMT | Pressure/Temperature Control | CNG Compressors (Section 10-2.2) | |||||
| Electronic Equipment (9-1.9) | ELTREQ | Pump | CNG Dispenser Hoses (Section 10-2.5) | |||||
| Card and Key Locks (Section 9-3) | CKLK | Signage/Markings | CNG Dispensers (Section 10-2.4) | |||||
| Electrical/Protection | Power Grounding Systems (Section 9-1.6.1) | PWRGS | Structures | CNG Piping (Section 10-2.1) | ||||
| Static Grounding Systems (Section 9-1.6.2) | STGS | Tank | CNG Storage (Section 10-2.3) | |||||
| Cathodic Protection (Section 9-2.1) | CP | Testing | Coatings Condition Survey | |||||
| Lightning Surge Arresters (Section 9-2.2.1) | LSAR | Underground Pits | Combination Dual Rate-of-Flow Control and Solenoid Valves (Section 4-3.3.1) | |||||
| Lightning Protection Systems (Section 9-4) | LPTS | Valves | Concrete and Cement Brick Dike/Berm Walls (Section 8- |
10.2.1)
| Ground Verification System (Section 9-5) | GRVS | Waste | Containment Systems (General) (Section 8-10.1) | |
| Electronic Overfill Protection Systems (Section 9-6) | EOPS | Cranes and Hoists (Section 11-6) | ||
| Eyewash/Shower | Emergency Eyewash/Showers (Section 11-3) | EMEWSH | Deactivated Petroleum Fuel Pipelines (Section 12-3) | |
| Fencing/ Gates | Fencing | FENC | Deactivated Petroleum Fuel Pumps (Section 12-4) | |
| Gates | GATE | Deactivated Petroleum Fuel Tanks (Section 12-2) | ||
| Filtration | Pre-Filters (Section 3-6.1) | PFVSL | Defuel Control Valve (Section 4-3.2.7) | |
| Filter Separators (Section 3-6.2) | FLSP | Defuel/Flush Valves (Section 4-4.2.3) | ||
| Haypack Filters (Section 3-6.3) | HPKF | Detachable Pantographs (Section 4-7.1.2) | ||
| Basket Strainers (Section 3-6.4) | BSTR | Dial Thermometer (Section 6-9.1) | ||
| Filter Separator Sump Heaters (Section 3-6.5) | FSSH | Diaphragm Pumps (Section 3-8.7) | ||
| Sidestream Filtration Systems (Section 8-9.11) | SSFTS | Differential Pressure Gauges (Section 6-7.2) | ||
| Fire Suppression Equipment | Flame Arrestors (Section 8-9.5) | FLMARR | Differential Pressure Transmitters (Section 6-7.4) | |
| Foam Fire Protection Systems (Section 8-9.15) | FFPS | Dike/Berm Floors (Section 8-10.2.2) | ||
| Fire Protection Systems - Wet Pipe | FPRS | Dispenser Cabinet (Section 7-7) | ||
| Fuel Laboratories | Ventilation Hoods (Section 11-4.1) | VENTHD | Dispenser Filters (Section 7-9) | |
| Gauges | Pressure and Pressure/Vacuum Gauges (Section 6-7.1) | PVGA | Dispenser Hoses (Section 7-3) | |
| Differential Pressure Gauges (Section 6-7.2) | DPGA | Dispenser Meters (Section 7-8) | ||
| Mechanical Tape Gauges (Section 8-9.7) | MTGA | Dispenser Nozzles (Section 7-2) | ||
| Mechanically Operated Tape Gauge (Section 8-9.8.1) | MOTGA | Dispenser Strainers (Section 7-10) | ||
| Magnetostrictive Probes (Section 8-9.8.2) | MRPRB | Dispenser Sumps (Section 7-13) | ||
| Servo Gauge (Section 8-9.8.3) | SRVGA | Double Block and Bleed Valves (Section 6-6.2.5) | ||
| Generators | Back-Up Power Generators | BGEN | Double-Wall Piping (Section 6-1.4) | |
| Heating Coils | Steam Type Heating Coils (Section 8-9.16.1) | STHC | Double-Walled Underground Shop-Fabricated Tanks (Section |
8-5.4.2) Thermal Fluid Type Heating Coils (Section 8-9.16.2) TFTHC Dual Pressure Relief, Solenoid Shutoff, and Check Valves (Section 4-3.3.2)
| Electric Rod Type Heating (Section 8-9.16.3) | ERTH | Dual Rate-of-Flow Control Valves (Section 4-3.2.8) | |||||
| Hoses | Loading Fuel Hoses (Section 3-9.1) | LDHS | Earthen Dike Walls (Section 8-10.3) | ||||
| Offloading Fuel Hoses (Section 3-9.2) | OLHS | EFSO Systems (Section 7-16) | |||||
| Aircraft Fueling Hoses (Section 4-7.5) | ACFHS | Electric Motors (Section 9-1.7) | |||||
| Hydrazine | Hydrazine Charging Units (Section 10-3) | HDZCU | Electric Rod Type Heating (Section 8-9.16.3) | ||||
| Inspections | Trouble Shoot | TRBST | Electrical Equipment (Section 9-1.2) | ||||
| API 510 Inspections | API510 | Electronic Equipment (9-1.9) | |||||
| API 653 or STI Inspection | API653 | Electronic Overfill Protection Systems (Section 9-6) | |||||
| Coatings Condition Survey | CCS | Emergency Eyewash/Showers (Section 11-3) | |||||
| Dispenser Nozzles (Section 7-2) | DSNZ | Emergency Shut-off Valves (Section 4-4.2.9) | |||||
| Dispenser Hoses (Section 7-3) | DSHS | Emergency Shutoff Valves (Shear Valves) (Section 7-12) | |||||
| Breakaways (Section 7-4) | DSBW | Emergency Vents (Section 8-9.4) | |||||
| Swivels (Section 7-5) | DSSW | External High Level Shutoff Valves (HLSO) (Section 8-9.6.1) | |||||
| Hose Retriever (Section 7-6) | HSRTV | Externally Mounted Level Alarms (Section 8-9.9.1) | |||||
| Dispenser Cabinet (Section 7-7) | DSCB | Fencing | |||||
| Dispenser Meters (Section 7-8) | DSMTR | Fill Ports (Section 8-9.12) | |||||
| Dispenser Filters (Section 7-9) | DSFLR | Filter Separator Control Valves (Section 4-4.2.2) | |||||
| Dispenser Strainers (Section 7-10) | DSSTR | Filter Separator Sump Heaters (Section 3-6.5) | |||||
| Ground Vehicle Fuel Piping (Section 7-11) | GVFP | Filter Separators (Section 3-6.2) | |||||
| Component Unique Identifier: | Site Code-Facility #-Component Acronym-Sequential # | Fire Protection Systems - Wet Pipe | |||||
| Example: | AAD-00063A-RCVL-0001 | Fire Valves (Section 6-6.4.1) | |||||
| NOTE: If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This | |||||||
| CUID shall be the standard for all DLA capitalized equipment | Fixed Pantographs (Section 4-7.1.1) | ||||||
| DLA Work Type Category | UFC Section Reference Work Category | ||||||
| (Revised per Change 1, 29 April 2021) | Component | ||||||
| Acronym | Flame Arrestors (Section 8-9.5) | ||||||
| Issue/Receive - Ground | Emergency Shutoff Valves (Shear Valves) (Section 7-12) | ESHVL | Flexible Ball Joints (Section 6-8) | ||||
| Dispenser Sumps (Section 7-13) | DSSMP | Flexible Membrane Liners (Section 8-10.5) | |||||
| Transition Sumps (Section 7-14) | TRSMP | Floating Roof and Pan Legs (Section 8-9.1.6) | |||||
| Remote Dispenser Pumps (Section 7-15.1) | RDSP | Floating Roof and Pan Pressure/Vacuum Vents (Section 8- 9.1.5) | |||||
| Self-Contained Dispenser Pumps (Section 7-15.2) | SCDSP | Floating Roofs (Section 8-9.1.4) | |||||
| EFSO Systems (Section 7-16) | EFSO | Floating Suction Lines (Section 8-9.14) | |||||
| Stage I Vapor Recovery (Section 7-17.1) | SIVP | Foam Fire Protection Systems (Section 8-9.15) | |||||
| Stage II Vapor Recovery (Section 7-17.2) | SIIVP | Foundations (Section 8-4.3) | |||||
| Vapor Burners (Section 7-17.3) | VPBNR | Fuel Additive Injectors (Section 3-11) | |||||
| Point Sensor - Dry (Section 7-19.1.1) | PSDRY | Fuel Pier/Wharf Containment (PWS Section 3) | |||||
| Automatic Line Leak Detector (Section 7-19.1.2) | ALLD | Fuel Truck and Rail Car Containment Areas (Section 11-1.1) | |||||
| Visual Monitoring (Section 7-20.1) | VSLM | Fueling Nozzles (Section 4-7.3) | |||||
| Issue/Receive - Marine | Marine Receipt (Section 5-2) | MRNRCP | Fusible Link Butterfly Valves (Section 6-6.4.2) | ||||
| Marine Issue (Section 5-3) | MRNISU | Gate Valves (Section 6-6.2.3) | |||||
| Marine Loading Arms (Section 5-4) | MRNLA | Gates | |||||
| Marine Transfer Hoses (Section 5-5.1) | MBTHS | Gear Pumps (Section 3-8.6) | |||||
| Underwater Hoses (Section 5-5.2) | UWHS | Gearboxes (Section 3-8.9) | |||||
| Single Point Mooring Systems (Section 5-7.1) | SPMSS | General System Control Valves (Section 4-3.2.1) | |||||
| Multi Point Mooring Systems (Section 5-7.2) | MPMSS | Geodesic Dome Roofs (Section 8-4.2) | |||||
| Submerged Piping Systems (Section 5-8) | SMPS | Globe Valves (Section 6-6.2.7) | |||||
| Boom Reels (Section 5-9) | BMRL | Ground Vehicle Fuel Piping (Section 7-11) | |||||
| Liquefied Petroleum | Liquefied Petroleum Tanks (Section 10-1.1) | LPTANK | Ground Verification System (Section 9-5) | ||||
| Liquefied Petroleum Pipelines (Section 10-1.2) | LPPIPE | Haypack Filters (Section 3-6.3) | |||||
| Liquefied Petroleum Vapor Lines (Section 10-1.3) | LPVPL | High Point Vent Pits (Section 6-11.3) | |||||
| LPG Vaporizers (Section 10-1.4) | LPGVPZ | High Point Vents (Section 6-12.2) | |||||
| Petroleum Gas Regulators (Section 10-1.5) | PGREG | Hose Retriever (Section 7-6) | |||||
| Liquefied Petroleum Gas Hoses (Section 10-1.6) | LPGHS | Hydrant Adapters (Section 4-7.2) | |||||
| Meter/ calibrations | Positive Displacement Meters (Section 3-7.1) | PDMT | Hydrant Control Valves (Section 4-4.2.8) | ||||
| Turbine Flow Meters (Section 3-7.2) | TBFMT | Hydrant Fuel Pits (Section 6-11.2) | |||||
| Orifice Flow Meters (Section 3-7.3) | OFMT | Hydrazine Charging Units (Section 10-3) | |||||
| Natural Disaster | Natural Disaster | Internal Combustion Drives (Section 3-8.8) | |||||
| Natural Gas | CNG Piping (Section 10-2.1) | NGPIPE | Internal HLSO Valves (Section 8-9.6.2) | ||||
| CNG Compressors (Section 10-2.2) | NGCOMP | Internally Mounted Level Alarms (Section 8-9.9.3) | |||||
| CNG Storage (Section 10-2.3) | NGSTOR | Isolation Valve Pits (Section 6-11.1) | |||||
| CNG Dispensers (Section 10-2.4) | NGDS | Issue Venturi (Section 4-4.2.4) | |||||
| CNG Dispenser Hoses (Section 10-2.5) | NGDSHS | Lateral Control Pits (Section 6-11.5) | |||||
| Nozzle | Hydrant Adapters (Section 4-7.2) | HADP | Lighting (Section 9-1.8) | ||||
| Fueling Nozzles (Section 4-7.3) | FLNZ | Lightning Protection Systems (Section 9-4) | |||||
| Other | Fuel Additive Injectors (Section 3-11) | FAIJ | Lightning Surge Arresters (Section 9-2.2.1) | ||||
| Pantograph | Fixed Pantographs (Section 4-7.1.1) | FXPNT | Line Blanks, Ring Spacers, and Spectacle Blinds (Section 6- 6.2.9) | ||||
| Detachable Pantographs (Section 4-7.1.2) | DTPNT | Liquefied Petroleum Gas Hoses (Section 10-1.6) | |||||
| Piping | On-Base Pipelines (Section 6-1.1) | OBPL | Liquefied Petroleum Pipelines (Section 10-1.2) | ||||
| Non-DOT Regulated (Section 6-1.2.1) | NDPL | Liquefied Petroleum Tanks (Section 10-1.1) | |||||
| Aboveground Piping (Section 6-1.3) | AGPL | Liquefied Petroleum Vapor Lines (Section 10-1.3) | |||||
| Double-Wall Piping (Section 6-1.4) | DWPL | Loading Fuel Hoses (Section 3-9.1) | |||||
| Low Point Drains (Section 6-12.1) | LPDN | Low Point Drain Pits (Section 6-11.4) | |||||
| High Point Vents (Section 6-12.2) | HPVT | Low Point Drains (Section 6-12.1) | |||||
| Sight Flow Indicators (Section 6-12.3) | SFND | LPG Vaporizers (Section 10-1.4) | |||||
| Rope Sensor Systems (Section 6-13.1.1) | RPSS | Magnetostrictive Probes (Section 8-9.8.2) | |||||
| Point Sensor - Dry (Section 6-13.1.2) | PSDRY | Manual Valve Gear Operators (Section 6-6.2.10) | |||||
| Visual Monitoring (Section 6-14.1) | VSLM | Marine Issue (Section 5-3) | |||||
| Pipe Penetrations (Section 8-10.6) | PPEN | Marine Loading Arms (Section 5-4) | |||||
| Deactivated Petroleum Fuel Pipelines (Section 12-3) | DEACPL | Marine Receipt (Section 5-2) | |||||
| Pressure/Temperature Control | Air Eliminator Tanks (Section 3-10.1) | AELT | Marine Transfer Hoses (Section 5-5.1) | ||||
| Automatic Air Vents (Section 3-10.2) | AAVT | Mechanical Tape Gauges (Section 8-9.7) | |||||
| Surge Suppressors (Section 4-7.4) | SRGSP | Mechanically Operated Tape Gauge (Section 8-9.8.1) | |||||
| Thermal and Pressure Relief Valves (Section 6-6.3) | TPRVL | Miscellaneous Deactivated Components (Section 12-5) | |||||
| Pressure Transmitters (Section 6-7.3) | PRTR | Motor Controls (Section 9-1.4) | |||||
| Differential Pressure Transmitters (Section 6-7.4) | DPTR | Motor Operators (Section 6-6.6) | |||||
| Flexible Ball Joints (Section 6-8) | FBLJT | Multi Point Mooring Systems (Section 5-7.2) | |||||
| Dial Thermometer (Section 6-9.1) | DTHMR | Natural Disaster | |||||
| Emergency Vents (Section 8-9.4) | EMGVT | Non-DOT Regulated (Section 6-1.2.1) | |||||
| Pump | Centrifugal Pumps (Section 3-8.1) | CENP | Non-Surge Check Valves (Section 4-4.2.1) | ||||
| Vertical Inline Pumps (Section 3-8.2) | VILP | Offloading Fuel Hoses (Section 3-9.2) | |||||
| Vertical Turbine/Submerged Turbine Pumps (Section 3-8.3) | VTSP | Oil/Water Separators (Section 11-5) | |||||
| Sliding Vane Pumps (Section 3-8.5) | SLVP | On-Base Pipelines (Section 6-1.1) | |||||
| Gear Pumps (Section 3-8.6) | GERP | Orifice Flow Meters (Section 3-7.3) | |||||
| Diaphragm Pumps (Section 3-8.7) | DIAP | Overfill Valve for Product Recovery Tanks (Section 4-8.1) | |||||
| Internal Combustion Drives (Section 3-8.8) | ICDR | Panelboards (Section 9-1.5) | |||||
| Gearboxes (Section 3-8.9) | GRBX | Pantograph Control Valves (Section 4-5.2.12) | |||||
| Deactivated Petroleum Fuel Pumps (Section 12-4) | DEACP | Pantograph Pressure Control Valves (Section 4-5.2.13) | |||||
| Signage/Markings | Signage and Markings (Section 2-7) | SIGN | Petroleum Gas Regulators (Section 10-1.5) | ||||
| Structures | Pumphouse/Filter Buildings (Section 11-2.1) | PFBLDG | Piers and Wharves Fuel Containment Systems (Section 5- 1.2) - Testing | ||||
| Canopies (Section 11-2.2) | CNPY | Pipe Penetrations (Section 8-10.6) | |||||
| Cranes and Hoists (Section 11-6) | CRNHST | Plug Valves - Lubricated (Section 6-6.2.1) | |||||
| Aboveground Field-Erected Tanks (Section 8-4) | AGFET | Plug Valves - Non-lubricated (Section 6-6.2.2) | |||||
| Geodesic Dome Roofs (Section 8-4.2) | GEODR | Point Sensor - Dry (Section 6-13.1.2) | |||||
| Foundations (Section 8-4.3) | FOUND | Point Sensor - Dry (Section 7-19.1.1) | |||||
| Component Unique Identifier: | Site Code-Facility #-Component Acronym-Sequential # | Point Sensor - Dry (Section 8-9.13.1) | |||||
| Example: | AAD-00063A-RCVL-0001 | Point Sensor - Pressure/Vacuum (Section 8-9.13.3) | |||||
| NOTE: If component acronym is not listed, the contractor shall request an acronym be established through the HNC Project Manager and Project Engineer via email. Contractors may utilize other means of tracking/labeling assets such as QR codes in addition to the required CUID however, tracking/labeling must correlate with the CUID. This | |||||||
| CUID shall be the standard for all DLA capitalized equipment | Point Sensor - Wet (Section 8-9.13.2) | ||||||
| DLA Work Type Category | UFC Section Reference Work Category | ||||||
| (Revised per Change 1, 29 April 2021) | Component | ||||||
| Acronym | Pontoon Floating Pans (Section 8-9.1.3) | ||||||
| Tank | Aboveground Shop Fabricated Tanks (Section 8-5.1) | AGSFP | Positive Displacement Meters (Section 3-7.1) | ||||
| Self-Diking or Vaulted Tanks (Section 8-5.2) | SDVT | Power Cables (Section 9-1.3) | |||||
| Rectangular Concrete-Encased Tanks (Section 8-5.3) | RCET | Power Grounding Systems (Section 9-1.6.1) | |||||
| Single-Walled Underground Shop-Fabricated Tanks (Section 8-5.4.1) | UGSSFT | Pre-Filters (Section 3-6.1) | |||||
| Double-Walled Underground Shop-Fabricated Tanks (Section | |||||||
| 8-5.4.2) | UGDSFT | Pressure and Pressure/Vacuum Gauges (Section 6-7.1) | |||||
| Underground Field-Constructed Tanks (Cut and Cover Tanks) (Section 8-6) | UGFET | Pressure Control Valves (Section 4-4.2.7) | |||||
| Tank Cleaning (Section 8-7) | TCLEAN | Pressure Relief Valves (Section 4-3.2.6) | |||||
| Aluminum Honeycomb Floating Pans (Section 8-9.1.1) | AHFP | Pressure Testing | |||||
| Steel Floating Pans (Section 8-9.1.2) | STLFP | Pressure Transmitters (Section 6-7.3) | |||||
| Pontoon Floating Pans (Section 8-9.1.3) | PTNFP | Product Saver Tanks (Section 8-9.10) | |||||
| Floating Roofs (Section 8-9.1.4) | FLTRF | Pumphouse/Filter Buildings (Section 11-2.1) | |||||
| Floating Roof and Pan Pressure/Vacuum Vents (Section 8- 9.1.5) | FPPVV | Rectangular Concrete-Encased Tanks (Section 8-5.3) | |||||
| Floating Roof and Pan Legs (Section 8-9.1.6) | FRPLG | Refuel Control Valves (Section 4-3.2.5) | |||||
| Secondary Tank Bottoms (Section 8-9.2) | SNDTB | Remote Dispenser Pumps (Section 7-15.1) | |||||
| Tank Pressure/Vacuum Vents (Section 8-9.3) | TPVVT | Remote Spill Containment (Section 11-1.2) | |||||
| Product Saver Tanks (Section 8-9.10) | PRDST | Return Venturi (Section 4-4.2.5) | |||||
| Fill Ports (Section 8-9.12) | FPRT | Rope Sensor Systems (Section 6-13.1.1) | |||||
| Point Sensor - Dry (Section 8-9.13.1) | PSDRY | Secondary Tank Bottoms (Section 8-9.2) | |||||
| Point Sensor - Wet (Section 8-9.13.2) | PSWET | Self-Contained Dispenser Pumps (Section 7-15.2) | |||||
| Point Sensor - Pressure/Vacuum (Section 8-9.13.3) | PSPV | Self-Diking or Vaulted Tank Containment (Section 8-10.4) | |||||
| Visual Leak Detection (Section 8-9.13.4) | VSLLD | Self-Diking or Vaulted Tanks (Section 8-5.2) | |||||
| Floating Suction Lines (Section 8-9.14) | FLTSL | Servo Gauge (Section 8-9.8.3) | |||||
| Stilling Wells (Section 8-9.17) | STGW | Sidestream Filtration Systems (Section 8-9.11) | |||||
| Deactivated Petroleum Fuel Tanks (Section 12-2) | DEACT | Sight Flow Indicators (Section 6-12.3) | |||||
| Testing | Pressure Testing | Signage and Markings (Section 2-7) | |||||
| Underground Pits | Isolation Valve Pits (Section 6-11.1) | ISVLP | Single Point Mooring Systems (Section 5-7.1) | ||||
| Hydrant Fuel Pits (Section 6-11.2) | HDFP | Single-Walled Underground Shop-Fabricated Tanks (Section 8-5.4.1) | |||||
| High Point Vent Pits (Section 6-11.3) | HPVP | Sliding Vane Pumps (Section 3-8.5) | |||||
| Low Point Drain Pits (Section 6-11.4) | LPDP | Stage I Vapor Recovery (Section 7-17.1) | |||||
| Lateral Control Pits (Section 6-11.5) | LTCP | Stage II Vapor Recovery (Section 7-17.2) | |||||
| Valves | General System Control Valves (Section 4-3.2.1) | GSCVL | Static Grounding Systems (Section 9-1.6.2) | ||||
| Refuel Control Valves (Section 4-3.2.5) | RCVL | Steam Type Heating Coils (Section 8-9.16.1) | |||||
| Pressure Relief Valves (Section 4-3.2.6) | PRCVL | Steel Floating Pans (Section 8-9.1.2) | |||||
| Defuel Control Valve (Section 4-3.2.7) | DFCVL | Stilling Wells (Section 8-9.17) | |||||
| Dual Rate-of-Flow Control Valves (Section 4-3.2.8) | DRFCVL | Submerged Piping Systems (Section 5-8) | |||||
| Combination Dual Rate-of-Flow Control and Solenoid Valves (Section 4-3.3.1) | CFSCVL | Surge Suppressors (Section 4-7.4) | |||||
| Dual Pressure Relief, Solenoid Shutoff, and Check Valves | |||||||
| (Section 4-3.3.2) | DPSCVL | Swivels (Section 7-5) | |||||
| Non-Surge Check Valves (Section 4-4.2.1) | NSCKVL | Tank Cleaning (Section 8-7) | |||||
| Filter Separator Control Valves (Section 4-4.2.2) | FSCVL | Tank Pressure/Vacuum Vents (Section 8-9.3) | |||||
| Defuel/Flush Valves (Section 4-4.2.3) | DFFCVL | Thermal and Pressure Relief Valves (Section 6-6.3) | |||||
| Issue Venturi (Section 4-4.2.4) | ISVTR | Thermal Fluid Type Heating Coils (Section 8-9.16.2) | |||||
| Return Venturi (Section 4-4.2.5) | RTVTR | Transition Sumps (Section 7-14) | |||||
| Back Pressure Control Valves (Section 4-4.2.6) | BPCVL | Trouble Shoot | |||||
| Pressure Control Valves (Section 4-4.2.7) | PCVL | Truck Fill Valves (Section 6-6.5.1) | |||||
| Hydrant Control Valves (Section 4-4.2.8) | HCVL | Turbine Flow Meters (Section 3-7.2) | |||||
| Emergency Shut-off Valves (Section 4-4.2.9) | ESOVL | Underground Field-Constructed Tanks (Cut and Cover Tanks) (Section 8-6) | |||||
| Pantograph Control Valves (Section 4-5.2.12) | PTCVL | Underwater Hoses (Section 5-5.2) | |||||
| Pantograph Pressure Control Valves (Section 4-5.2.13) | PTPCVL | Vapor Burners (Section 7-17.3) | |||||
| Overfill Valve for Product Recovery Tanks (Section 4-8.1) | OVLPRT | Ventilation Hoods (Section 11-4.1) | |||||
| Plug Valves - Lubricated (Section 6-6.2.1) | PLVL | Vertical Inline Pumps (Section 3-8.2) | |||||
| Plug Valves - Non-lubricated (Section 6-6.2.2) | NPLVL | Vertical Turbine/Submerged Turbine Pumps (Section 3-8.3) | |||||
| Gate Valves (Section 6-6.2.3) | GTVL | Visual Leak Detection (Section 8-9.13.4) | |||||
| Ball Valves (Section 6-6.2.4) | BLVL | Visual Monitoring (Section 6-14.1) | |||||
| Double Block and Bleed Valves (Section 6-6.2.5) | DBBVL | Visual Monitoring (Section 7-20.1) | |||||
| Butterfly Valves (Section 6-6.2.6) | BFVL | ||||||
| Globe Valves (Section 6-6.2.7) | GLVL | ||||||
| Check Valves (Section 6-6.2.8) | CKVL | ||||||
| Line Blanks, Ring Spacers, and Spectacle Blinds (Section 6- 6.2.9) | BLIND | ||||||
| Manual Valve Gear Operators (Section 6-6.2.10) | MVLGO | ||||||
| Fire Valves (Section 6-6.4.1) | FRVL | ||||||
| Fusible Link Butterfly Valves (Section 6-6.4.2) | FLBFVL | ||||||
| Truck Fill Valves (Section 6-6.5.1) | TFVL | ||||||
| Motor Operators (Section 6-6.6) | MTROP | ||||||
| External High Level Shutoff Valves (HLSO) (Section 8-9.6.1) | EHLSVL | ||||||
| Internal HLSO Valves (Section 8-9.6.2) | IHLSVL | ||||||
| Waste | Oil/Water Separators (Section 11-5) | OWS |