Attachment_2_Addendum_to_Caneel_Bay_Resort_NTCRA_Work_Plan.pdf
PDF 345 KB Posted
- Attached to
- NTCRA under CERCLA at Virgin Islands Nat'l Park
- Solicitation number
- 140P2124R0023
About this file
This document is an Addendum to the Caneel Bay Resort NTCRA Work Plan for a soil and sediment removal action under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) at the Caneel Bay Resort within the Virgin Islands National Park.
The key details include: the contractor must notify the Contracting Officer (CO) in writing if undisturbed soils are not reached or solid waste is still present after excavating to the anticipated removal depths, and allow 14 days for the National Park Service (NPS) to review the notification and execute any contract modifications. The Project Engineer, hired under a separate NPS contract, is responsible for collecting confirmation samples and sending them for analysis. The Removal Action Contractor must complete on-site removal activities, including delivery to marine shipper, marine shipping, and mainland transportation and disposal, within 390 days after the Notice to Proceed. The Contractor must also provide a Transport and Disposal Plan that addresses coordination to ensure safe passage for the guest shuttle and equipment on the single lane road accessing the landfill.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Conduct soil NTCRA under CERCLA at Caneel Bay Resort Virgin Islands NP
Attachment 2: Addendum to Attachment 1, Caneel Bay Resort NTCRA Work Plan: Soil and Sediment Removal
Section 5.6: the Project Engineer is hired under a separate NPS contract for support services. The Project Engineer is responsible for collecting confirmation samples and sending them for analysis.
Sections 5.3, 5.6.3, and 5.6.4: In addition to the requirements in contract paragraph G.1 and FAR clause 52.236-2, if after excavating to the Anticipated Removal Depths (Figure 4b), refusal (bedrock) or undisturbed soils are not reached and/or solid waste is still present/visible, the contractor must notify the CO in writing. The notice shall include an estimate of the volume of material that would need to be removed to reach refusal or undisturbed soils, an updated schedule to remove the estimated volume, and any other helpful information. The CO will calculate the estimated cost using the unit prices in the contract and considering potential impacts to lump sum CLINs 4 and/or 10. Allow 14 days for NPS to review the notification and execute any modifications establishing new NTE quantities. The Project Engineer will collect confirmation samples when the full extent of authorized soil removal is complete (or bedrock is encountered). The Removal Action Contractor will stand by until confirmation sample results are received and shared by NPS. The Project Engineer will provide a plan for confirmation resampling, if necessary, for NPS to consider in conjunction with the Contractor’s notice.
Section 5.6.5: Removal Action Contractor shall provide the Project Engineer with the necessary and applicable documents within the timeframes listed in Appendix 1, 013100, Section 1.2. The Project Engineer will prepare the Completion Report.
Appendix 1, 013100, Section 1.2(D) (added): On-site removal activities, including delivery to marine shipper from on-island transporter, marine shipping, and mainland transportation and disposal must be completed within 390 days after issuance of the Notice to Proceed. Transmit waste manifests to NPS as soon as they are available from the disposal facility.
Appendix 1, 015719-3, Sections 1.3 and 2.4: The Project Engineer will provide dust monitor and gas monitor units that they will use to conduct monitoring.
Appendix 1, 026129, Section 1.2, Submittals, describes the Transport and Disposal (T&D) Plan that is included in the Construction Plan. The T&D plan must include specific site logistics for equipment routes, staging, and coordination at the Landfill area. The Landfill is accessed by a single lane road adjacent to the Bay. The single lane road is also used by a shuttle/taxi that brings day guests to/from Honeymoon Beach from the Resort entrance. Transport and Disposal Plan must adequately address on site coordination to ensure safe passage for guest shuttle and equipment, without disruptions of service. See diagram below from Google Maps identifying single lane road, landfill, and Honeymoon Beach.
Conduct soil NTCRA under CERCLA at Caneel Bay Resort Virgin Islands NP
Landfill
Honeymoon Beach
Single lane road
Attachment 2: Addendum to Attachment 1, Caneel Bay Resort NTCRA Work Plan: Soil and Sediment Removal