This document is a Revised Definition of Contract Line Items for a federal contract opportunity to conduct a Non-Time Critical Removal Action (NTCRA) under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) at the Caneel Bay Resort in the Virgin Islands National Park.

The key details are:

  • The work includes removing approximately 13,000 bank cubic yards (BCY) of contaminated soil and landfill refuse and 40 loose CY of contaminated sediment, transporting it to disposal facilities, and performing limited site restoration such as spreading clean fill, grading, and seeding.
  • The contract will use unit-priced items subject to the variation in quantity clause, with a ceiling and notification requirements. The intent is to remove sufficient material to reach the Site's removal action objectives.
  • The contract is a best value, negotiated procurement set-aside for Small Business concerns, with a magnitude estimated between $5-10 million. Proposals are due approximately 30 days after the RFP is posted.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VIIS - 5SER3346 01 27 00 - 1

REVISED DEFINITION OF CONTRACT LINE ITEMS

CANEEL BAY REMOVAL ACTION – SOIL AND SEDIMENT REMOVAL

VIRGIN ISLANDS NATIONAL PARK - 5SER3346

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS (Revised in Amendment 3.)

PART 1 -– GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item (CLIN), and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

C. The estimated quantities that are the basis to apply FAR clause 52.211-18, Variation in Estimated Quantity, are listed in the Contract Price Schedule (Form 1); quantities listed in this section are informational only.

D. In addition to the paragraphs from Section 01 11 00 listed below, each CLIN shall be performed in accordance with Attachment 1, NTCRA Work Plan, and all relevant specification sections in its Appendix 1.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

A. Contract Line Item Number 1: Construction Plan Document Preparation and SubmittalContract Support Tasks.

1. 1. This item consists of the includes tasks and documentation listed in all sections of

Attachment 1, including preparation and submittal of the Construction Plan documents defined in Section 01 31 00, Part 1.2., B; Attachment 2; and all activities not listed below, such as project management and oversight, subcontractor management, bonds, insurance, and progress meetings.

2. Costs associated with the on-site supervision of remaining CLINs and Options shall be included in their prices, not in CLIN 1.

32. Payment will be made at the contract lump sum price (L.S.).

B. Contract Line Item Number 2: Area 2 – Mobilization and Site Preparation of Soil Area

1. This item consists of the Work defined described in Parts 1.2, Subparts D.2.a, D.2.b, D.2.c, and D.2.d of Section 01 11 00 and includes installation, maintenance, and removal of erosion and sedimentation controls; establishment of support areas, establishment of excavation limits, and clearing.

2. Payment will be made at the contract lump sum price (L.S.).

VIIS - 5SER3346 01 27 00 - 2

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

C. Contract Line Item Number 3: Area 2 -– Soil Removal

1. This item consists of the Work defined described in Part 1.2, Subparts D.2.e and D.2.f of Section 01 11 00 and includes excavation, loading, transportation, and disposal of surface soil from Soil Removal Units A2-Soil1, A2-Soil2, A2-Soil3, and A2-Soil4, as depicted on Figure 2 (total estimated volume of 288 bank cubic yards (BCY)) at an approved disposal facility in continental United States (CONUS).

2. Payment will be made at the contract unit price for the actual quantity per ton.

Quantity will be measured and calculated by adding up all weight tickets from disposal site(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

D. Contract Line Item Number 4: Area 2 – Restoration of Soil Area

1. This item consists of the Work defined described in Part 1.2, Subparts D.2.g, D.2.h, and D.2.i of Section 01 11 00 includes a post-excavation survey, backfill with prepared topsoil, seeding, maintenance of erosion and sedimentation controls, and removal of non-biodegradable erosion and sedimentation controls.

2. Payment will be made at the contract lump sum price (L.S.).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

E. Contract Line Item Number 5: Area 2 –- Channel Sediment Removal Support

1. This item consists of the Work defined described in Part 1.2, Subparts D.3.a through D.3.e , b, c, d, and e of Section 01 11 00 and includes installation, maintenance, and removal of erosion and sedimentation controls; establishment of support areas, establishment of removal limits, and clearing, and installation of stormwater diversion features.

2. Payment will be made at the contract unit price for the actual quantity per ton, as evidenced on the manifest. Quantity will be measured and calculated by adding up all weight tickets from disposal site(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

F. Contract Line Item Number 6: Area 2 –- Sediment Removal

1. This item consists of the Work defined described in Part 1.2, Subpart D.3.f of Section 01 11 00 and includes removal, loading, transportation, and disposal of sediment from Sediment Removal Units A2-Sed1, A2-Sed2, and A2-Sed3, as depicted on Figure 3 (total estimated volume of 40 loose cubic yards (LCY)) at an approved disposal facility in

CONUS.

VIIS - 5SER3346 01 27 00 - 3

2. Payment will be made at the contract unit price for the actual quantity per ton, as evidenced on the manifest. Quantity will be measured and calculated by adding up all weight tickets from disposal site(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

G. Contract Line Item Number 7: Area 3 – Mobilization and Site Preparation

1. This item consists of the Work defined described in Parts 1.2, Subparts D.4.a through D.4.e , 4a, b, c, d, and e of Section 01 11 00 and includes abandonment of MW-301;

installation, maintenance, and removal of erosion and sedimentation controls;

establishment of support areas, establishment of excavation limits, and clearing, chipping, and stockpiling cleared vegetative debris.

2. Payment will be made at the contract lump sum price (L.S.).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

H. Contract Line Item Number 8: Area 3 – Excavation and Stockpiling

1. This item consists of the Work defined described in Part 1.2, Subpart D.4.f of Section 01 11 00 and includes excavation and stockpiling of soils and landfill materials prior to disposal (estimated volume of 12,535 BCY), as shown on Figures 4a, 4b, and 4c, and as indicated by the Project Engineer.

2. This item includes loading, transport and disposal of incidental segregated solid waste but excludes loading, transport, and disposal of soils.

23. Payment will be made on a unit price basis for the actual quantity per ton, using the quantity determined in CLIN 97.

34. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

I. Contract Line Item Number 9: Area 3 – Soil Loading, Transport, and Disposal of RCRA non-hazardous landfill materials in CONUS.

1. This item consists of the Work defined described in Part 1.2, Subparts D.4.f, D.4.g, and D.4.h of Section 01 11 00 and includes loading, transporting, and disposal of contaminated soils, contaminated vegetative material, and contaminated landfill materials, as indicated by the Project Engineer, all of which are determined to be RCRA non-hazardous, at an approved facility in CONUS (estimated maximum volume of 12,535 BCY) and surveying of final excavation extents.

2. Payment will be made on a unit price basis for the actual quantity per ton of excavated soil materials loaded, transported, and disposed. Quantity will be measured and calculated by adding up all weight tickets from disposal site(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

VIIS - 5SER3346 01 27 00 - 4

J. Contract Line Item Number 10: Area 3 – Soil Spreading, Grading, Revegetation, and Site Restoration

1. This item consists of the Work defined described in Parts 1.2, Subparts D.4.i, D.4.j, D.4.k, and D.4.l H, i, j, and k of Section 01 11 00 and includes surveys of final excavation extents and final grade, grading, preparation and spreading of topsoil, seeding, maintenance of erosion and sedimentation controls, and removal of non-biodegradable erosion and sedimentation controls, spreading chipped (cleared) vegetative debris as mulch in locations indicated by the Project Engineer, and stockpiling excess.

2. Payment will be made at the contract lump sum price (L.S.).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

K. Contract Line Item Number 11: Area 3 – Loading, Transport, and Disposal of RCRA hazardous landfill materials in CONUS

1. This item consists of the Work described in Part 1.2, Subparts D.4.f, D.4.g, and D.4.h of Section 01 11 00 and includes loading, transporting, and disposal of contaminated soils, buried vegetative material, and/or contaminated landfill materials, as indicated by the Project Engineer, all of which are determined to be RCRA hazardous, at an approved facility in CONUS (estimated maximum volume of 125 BCY).

2. Payment will be made on a unit price basis for the actual quantity per ton of excavated materials loaded, transported, and disposed. Quantity will be measured and calculated by adding up all weight tickets from disposal site(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

K.L. Option A: Additional topsoil (per cubic yard).

1. This item consists of purchasing, transporting, preparing, and placing topsoil as described in Parts 1.2, D., 2. h and 4. j and will be exercised only if excavations are larger in areal extent than shown in the Figures. Note that purchasing, transporting, preparing, and placing established quantities of topsoil for Area 2 (soil area) and Area 3 is included in CLINs 4 and 10.

2. Payment will be made on a unit price basis for the actual quantity per cubic yard.

Quantity will be measured and calculated by adding up purchase tickets from source(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

L.M. Option B: Common fill (per cubic yard).

1. This item consists of purchasing, transporting, placing, and compacting common fill as described in Part 1.2, D., 2. h. and will be exercised if, to meet the Site’s RAOs, the Area 2 (soil) excavation is deeper than 0.5 feet below existing grade, or if fill is needed in any section of Area 3.

VIIS - 5SER3346 01 27 00 - 5

2. Payment will be made on a unit price basis for the actual quantity per cubic yard.

Quantity will be measured and calculated by adding up purchase tickets from source(s).

3. No separate measurement for payment will be made for labor, equipment, or materials required for this item.

END OF REVISED SECTION 01 27 00