This is an Environmental Planning and Historic Preservation Decision Support System (DSS) document recording the approval of a Multi-facility Roof Repair/Replacement project at the Federal Law Enforcement Training Centers (FLETC) Charleston facility.

The project, identified as DSS-FLETC-2026-25078, seeks to repair and/or replace roofs on multiple buildings across the FLETC Charleston campus located at 2000 Bainbridge Ave, North Charleston, South Carolina, 29405. The project has a proposed timeline from April 13, 2026 to April 12, 2027, with FY 2026 funding. The project has completed all required environmental review stages: In Preparation (04/13/2026), Environmental Review (04/14/2026), and Project Approved (04/14/2026). The project is categorically excluded under DHS CATEX D3 (Repair and Maintenance Activities) as it involves repair and maintenance of Department-managed buildings that do not result in a change in functional use or impact on historically significant elements. No mitigation, Environmental Assessment (EA), Environmental Impact Statement (EIS), or tribal consultation is required. The Memorandum for Record documents that the action is not expected to result in significant adverse environmental impacts and qualifies for categorical exclusion in accordance with DHS Directive 023-01 and Instruction 023-01-001-01, Implementation of NEPA. Seven Statements of Objectives (SOOs) are attached addressing roof replacement requirements for Buildings B1, B16, B23, B26, B46, B53, and B61. Document preparer is Jeff Blankenship (jeff.blankenship@fletc.dhs.gov) and Environmental Reviewer is Stephen DeRohn (stephen.derohn@fletc.dhs.gov).

View the file

Other files

File Type Posted
Attachment 45 Amendment 70LCHS26QPFB00034 0004 SF30.pdf PDF
Attachment 2 Combined Synopsis Solicitation.pdf PDF
Attachment 41 B16 Infrared.mp4 MP4 file
Attachment 2 Combined Synopsis Solicitation.pdf PDF
Attachment 39 Building 286 Infrared.MP4 MP4 file
Attachment 42 B1 Part A Infrared.mp4 MP4 file
Attachment 43 B1 Part B Infrared.mp4 MP4 file
Attachment 40 Building 286 Part B Infrared.MP4 MP4 file
Attachment 44 Amendment 70LCHS26QPFB00034 0003 SF30.pdf PDF
Attachment 22 B61 Roof 1 Penetrations.pdf PDF
Attachment 25 B23 Roof Penetrations.pdf PDF
Attachment 30 B61 Core Pictures.pdf PDF
Attachment 33 B16 Basis of Design Job Sheet.pdf PDF
Attachment 18 Building 23 Infrared.MP4 MP4 file
Attachment 20 Building 46 Infrared.MP4 MP4 file
Attachment 24 B61 Roof 3 Penetrations.pdf PDF
Attachment 34 B46 Upper Roof Basis of Design Job Sheet.pdf PDF
Attachment 38 CLIN Structure Pricing Submission.pdf PDF
Attachment 2 Combined Synopsis Solicitation.pdf PDF
Attachment 17 Master RFI Log.xlsx XLSX spreadsheet
Attachment 19 Building 26 Infrared.MP4 MP4 file
Attachment 21 B26 Roof Penetrations.pdf PDF
Attachment 26 B46 Demo Penetrations.pdf PDF
Attachment 27 B16 Demo Penetrations.pdf PDF
Attachment 29 B286 Roof Drawings.pdf PDF
Attachment 31 B1 Basis of Design Job Sheet.pdf PDF
Attachment 35 B61 CLIN 0001 Base SOW REVISION.pdf PDF
Attachment 23 B61 Roof 2 Penetrations.pdf PDF
Attachment 28 B23 Roof Drawings.pdf PDF
Attachment 32 B286 Basis of Design Job Sheet.pdf PDF
Attachment 36 Amendment 70LCHS26QPFB00034 0001 SF30.pdf PDF
Attachment 37 Amendment 70LCHSQPFB00034 0002 SF30.pdf PDF
Attachment 17 RFI Log.xlsx XLSX spreadsheet
Attachment 16 Site Visit Attendance Sign-in Sheet.pdf PDF
Attachment 15 Bldg 1 - CLIN 0006 Opt 5.pdf PDF
70LCHS26QPFB00034_0001.pdf PDF
Attachment 6 Bldg 16 - CLIN 0002 Opt 1.pdf PDF
Attachment 8 Bldg 1792 - CLIN 0004 Opt 3.pdf PDF
Attachment 11 FLETC Form 121-00-02 Visitor Access Request.pdf PDF
Attachment 1 SF 1449 - 70LCHS26QPFB00034.pdf PDF
Attachment 2 Combined Synopsis Solicitation.pdf PDF
Attachment 4 Bldg 46 - CLIN 0001 Base.pdf PDF
Attachment 3 Bldg 61 - CLIN 0001 Base.pdf PDF
Attachment 5 Bldg 26 - CLIN 0001 Base.pdf PDF
Attachment 7 Bldg 286 - CLIN 0003 Opt 2.pdf PDF
Attachment 9 Bldg 23 - CLIN 0005 Opt 4.pdf PDF
Attachment 10 Construction Wage Determination.pdf PDF
Attachment 12 Division 01 General Requirements.pdf PDF
Attachment 13 Division 07 Specifications.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Environmental Planning and Historic Preservation Decision Support System

Multi-facility Roof Repair/Replacement - Project Approved

Status

In Preparation (04/13/2026)

Environmental Review (04/14/2026)

Project Approved (04/14/2026)

Project Information

General Name: Multi-facility Roof Repair/Replacement

DSS ID: DSS-FLETC-2026-25078

Security: Unclassified Description: This project seeks to repair and/or replace the roofs on multiple buildings across the campus.

Funded through IRA?: No Funded through the IIJA?: No Critical Infrastructure?: No Adopting Another Agency CATEX, or CATEX Determination?: No Project Type: Repair & Maintenance Activities - Repair and maintenance of Department-managed buildings, roads, airfields, grounds, equipment, and other facilities which do not result in a change in functional use or an impact on a historically significant element or setting. (CATEX D3) Mitigation Required?: No Tiering - PEA/PEIS?: No Adopting EA/EIS?: No Requires EA/EIS?: No Project Priority: Normal Federal Assistance: No Estimated Project Cost: (not entered)

Component Component: FLETC - Federal Law Enforcement Training Centers Region/Area/Unit: FLETC Charleston - Charleston, Charleston County, SC

Dates FY Funding: 2026 Proposed Project Start: 04/13/2026 Proposed Project End: 04/12/2027 Review Start: 04/13/2026

Multi-facility Roof Repair/Replacement (Unclassified)

Page 1 of 6 Printed On 4/14/2026 7:01:04 AM

Project Location

Site Specific: 2000 Bainbridge Ave, North Charleston, South Carolina, 29405

Team

Document Preparer, Jeff Blankenship, jeff.blankenship@fletc.dhs.gov

Environmental Reviewer, Stephen DeRohn, stephen.derohn@fletc.dhs.gov

Categorical Exclusions

D3 - Repair and maintenance of Department-managed buildings, roads, airfields, grounds, equipment, and other facilities which do not result in a change in functional use or an impact on a historically significant element or setting (e.g. replacing a roof, painting a building, resurfacing a road or runway, pest control activities, restoration of trails and firebreaks, culvert maintenance, grounds maintenance, existing security systems, and maintenance of waterfront facilities that does not require individual regulatory permits).

Decision Documents

Memorandum For Record (MFR), 4.98kB

Attachments

SOO - B1 Roof Replacement.docx, 39.35kB

SOO - B16 Roof Replacement.docx, 38.63kB

SOO - B23 Roof Replacement.docx, 40.04kB

SOO - B26 Roof Replacement.docx, 39.83kB

SOO - B46 Roof Replacement.docx, 40.00kB

SOO - B53 Roof Replacement.docx, 39.31kB

SOO - B61 Roof Replacement.docx, 39.62kB

Comments

There are no comments.

Tribal Consultations

Tribal Consultation Initiated: No Tribal Consultation not initiated explanation: Not required.

Page 2 of 6 Printed On 4/14/2026 7:01:04 AM

Page 3 of 6 Printed On 4/14/2026 7:01:04 AM

DHS National Environmental Policy Act Memorandum For Record for Categorically Excluded Actions that do not require a REC

INTRODUCTION

The purpose of this Memorandum for Record is to provide a record that the potential for impacts to the quality of the human environment has been considered in the decision to implement the Proposed Action described below, in compliance with the National Environmental Policy Act of 1969 (NEPA) and DHS Directive 023-01 and Instruction 023-01-001-01, Implementation of NEPA. DHS has previously analyzed actions of this type and concluded that there is no potential for significant impact on the human environment, that a DHS Categorical Exclusion applies, and that a more detailed review and documentation in a Record of Environmental Consideration is not necessary.

SECTION I - Description of Proposed Action

1. Title of Proposed Action: Multi-facility Roof Repair/Replacement

2. Identifying Number of Proposed Action (if available): DSS-FLETC-2026-25078

3. Project Security Type: Unclassified

4. Estimated Start Date: 04/13/2026

5. Location of Proposed Action (e.g., Nationwide, Regional, Site-Specific. If site-specific, provide street address, city, county and state):

Site Specific: 2000 Bainbridge Ave, North Charleston, South Carolina, 29405

6. Project Type:

Repair & Maintenance Activities - Repair and maintenance of Department-managed buildings, roads, airfields, grounds, equipment, and other facilities which do not result in a change in functional use or an impact on a historically significant element or setting. (CATEX D3)

7. Description of Proposed Action.

This project seeks to repair and/or replace the roofs on multiple buildings across the campus.

8. Document Preparer: Jeff Blankenship

9. Environmental Reviewer: Stephen DeRohn

SECTION II - Finding

Page 4 of 6 Printed On 4/14/2026 7:01:04 AM

This action is not expected to result in any significant adverse environmental impacts as described in the National Environmental Policy Act of 1969 (NEPA). The proposed action has been thoroughly reviewed by the Federal Law Enforcement Training Centers and it has been determined, by the undersigned, that this action is categorically excluded under current DHS by the undersigned, that this action is categorically excluded under current DHS CATEX (D3; ) from further environmental documentation, in accordance with DHS Directive 023- 01 and Instruction 023-01-001-01, Implementation of NEPA, since implementation of this action:

Clearly fits within one or more of the categories of excludable actions listed in Appendix A of DHS Instruction 023-01-001-01;

1.

Has not been segmented into smaller parts in order to avoid a more extensive evaluation of the potential for significant environmental impacts; and

2.

Does not involve any extraordinary circumstances, as defined in DHS Instruction 023-01-001-01, Section V(B)(2), that would create the potential for a normally excluded action to have a significant environmental effect.

3.

DHS is aware of the November 12, 2024 decision in Marin Audubon Society v. Federal Aviation Administration, No. 23-1067 (D.C. Cir. Nov. 12, 2024). To the extent that a court may conclude that the Council on Environmental Quality (CEQ) regulations implementing NEPA are not judicially enforceable or binding on this agency action, DHS has nonetheless elected to follow those regulations at 40 C.F.R. Parts 1500–1508, in addition to the Department’s procedures/regulations implementing NEPA in Instruction 023-01-001, rev. 01, “Implementation of NEPA” to meet the agency’s obligations under NEPA, 42 U.S.C. §§ 4321 et seq.

04/13/2026 Jeff Blankenship Date Document Preparer

04/14/2026 Stephen DeRohn Date Environmental Reviewer

Page 5 of 6 Printed On 4/14/2026 7:01:04 AM

Preview of Attachments The following pages will display this project's attachments that are of these file types:

.jpg /.jpeg

.png

.gif

.txt

.pdf

The attachments of compatible file types from this project are:

Note:

All project attachments can be downloaded at the 'File Upload/Manage Attachments' page.

Page 6 of 6 Printed On 4/14/2026 7:01:04 AM

Multi-facility Roof Repair/Replacement

Page 6 of 6 Printed On 4/14/2026 7:01:04 AM