Attachment 12 DRAFT Appendix C Performance Requirement Summary.pdf
PDF 369 KB Posted
- Attached to
- RFP Fort Cavazos Roofing
- Solicitation number
- W912DY25R0008
About this file
This document is a Performance Requirements Summary (PRS) Appendix C for a roofing services contract at Fort Cavazos, Texas, detailing critical performance standards and quality assurance methods for the contractor. The document outlines specific performance objectives across multiple domains, including key personnel requirements, monthly reporting, maintenance completion rates, safety training, documentation preparation, and specialized training requirements such as Anti-Terrorism (AT) Level I, Operations Security (OPSEC), and Cyber Awareness training.
The performance standards are stringent, with most requirements demanding 95-100% compliance and zero deviation, with remedies including invoice payment reductions, potential negative Contractor Performance Assessment Reporting System (CPARS) ratings, and restrictions on performing work. The contract focuses on preventive and corrective maintenance for roofing services, with the contractor responsible for completing maintenance work requests, maintaining personnel certifications, submitting accurate documentation, and ensuring comprehensive safety and training compliance. Key performance metrics include maintaining licenses and certificates, completing preventative and corrective maintenance within specified timeframes, and submitting accurate service order documentation.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PWS Appendix C FY25 B1 Fort Cavazos Roofing Services Performance Requirements Summary
C. Performance Requirements Summary
C.1. General The rights of the Government and remedies described in this section are in addition to all other rights and remedies set forth in this contract. Specifically, the Government reserves its right under the Inspection of Services and Termination for Default clauses. Any deductions pursuant to the Performance Requirements Summary (PRS) shall reflect the reduced value of service performed under the contract. The Contractor shall not be relieved of full performance of the services hereunder and may be terminated for default based upon inadequate performance of service even if a deduction was previously taken for inadequate performance. The Government may modify the type and frequency of inspection of items.
C.1.1. Purpose The Performance Requirements Summary is designed to:
C.1.1.1.
List the contract requirements considered most critical to acceptable contract performance.
(Column 1).
C.1.1.2.
List the contract paragraph number(s) which describe the requirements (Column 2).
C.1.1.3.
Define the standard of performance for each required service specified (Column 3).
C.1.1.4.
Show the maximum allowable degree of deviation or Acceptable Quality Levels (AQLs) from perfect performance that will be allowed by the Government before contract performance is considered unsatisfactory (Column 4).’
C.1.1.5.
Explain the quality assurance methods the Government will use to evaluate the Contractor’s performance in meeting the contract requirements (Column 5).
C.1.1.6.
Show the remedy available to the Contractor or Government to bring performance within the standard defined in Column 4 (Column 6).
C.1.2. Nonconformance the government will document all Contractor non-conformances.
C.1.3. Performance Requirements Summary The Performance Requirements Summary lists those services/tasks for which the Government will make deductions from payment due the Contractor when services/tasks are found to be unsatisfactory during inspections made using the checklists. These deductions are in addition to reduced invoicing described in Section 7 of the PWS and the pricing workbook.
Performance Objective
PWS
Paragraph
Performance Standard
Performance Threshold (maximum error rate)
Method of Surveillance
Remedy if Performance
Threshold is not met
Provide Key Personnel
3.4
The Contractor shall provide a dedicated
CMM, a Lead Maintenance
Mechanic/M&S Supervisor, and a (part time) L1 SHO meeting all PWS requirements for positions
100% (zero deviation)
100% inspection
Deduction in invoice payment equal to contract cost of position(s) not filled until contractor provides qualified personnel
BaseOps Monthly Report &
Monthly Safety Report
Appendix D
Contractor shall submit a BaseOps
Monthly Report and a monthly Safety
Report (may be a combined report) showing performance data for the previous month
No more than one (1) late BaseOps report or one
(1) late Safety report during a performance period
100% Inspection
Deduction of 5% of all CLINS ordered in Task Order and potentially a negative CPARS narrative
Maintain Licenses and Certificates
3.8
The Contractor will ensure that the licenses or certificates of
Contractor personnel are kept current.
Copies of these licenses or certifications will be provided to the COR
100% (zero deviation)
Random Inspection
Contractor shall not perform work until qualified personnel are present;
deduction in invoice equal to the value of work not performed and potentially a negative CPARS narrative
Preventative / Recurring
Maintenance Completion
Rate
4.4
The Contractor shall complete PM in the month they are scheduled and IAW required standards
95% No more than
5% of the scheduled PM work requests are not complete in the month scheduled or IAW required standards.
100% Inspection
Potentially a negative CPARS rating; The Contractor shall not invoice for PM not performed (per the PM Cost tab of the awarded pricing workbook). The
Contractor may be held liable for equipment failures if PM is not completed. If failing to complete 100% of PM becomes a recurring issue, more severe remedies will be taken.
Corrective Maintenance Completion
Rate
4.5 and Appendix H
The Contractor shall complete all non-long lead CM work requests within the times listed in Table H.2.1 (Appendix H);
The Contractor shall annotate expected
95% No more than
5% of the scheduled CM work requests are not complete within the
100% Inspection
Reduced invoice equal to 1/2% for each business day SO not complete within the times listed in Table H.2.1 or time extension granted
Commented [HCACUC(1]: Only use if the customer wants a dedicated full time CMM.
PWS
Paragraph
Performance Standard
Performance Threshold (maximum error rate)
Method of Surveillance
Remedy if Performance
Threshold is not met completion time for long lead SO on the
SOF for KO approval;
See Appendix H for additional information on long lead SO times listed in Table H.2.1;
100% complete within time extension granted by the KO by the KO (e.g., 3 days late equals a 1.5% reduction) and potentially a negative CPARS narrative
Preparation of Service Order Documentation for Government
Approval
4.5 and Appendix H
95% of service order documentation prepared within times listed in Table H.2.1;
100% of service order documentation prepared within time extensions approved by the KO
95% No more than 5% of service order packages are not submitted or not submitted correctly for funding approval within the times listed in Table H.2.1;
100% complete within time extension granted by the KO
100% Inspection
Reduced invoice equal to 1/2% for each business day an acceptable SO not submitted within the times listed in Table
H.2.1 (e.g., submitted 3 days late equals a 1.5% reduction) and potentially a negative CPARS narrative
Perform Safety Requirements
Section 5
The Contractor shall perform checks for compliance with task order safety requirements and perform safety meetings prior to all maintenance tasks
(signed AHA to document meeting)
99% for the work completed
Random Sampling
3% of all CLINs ordered and potentially a negative CPARS narrative
Safety Training 5.5
Contractor shall complete all necessary safety training for all workers before they report on-site to perform work and document this training in the
BaseOps monthly report
100% (zero deviation)
Random Sampling
Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed/positions not filled and potentially a negative CPARS narrative
Contractor QC 6.1.1 The Contractor shall perform QC as required in the PWS
100% (zero deviation)
100% Inspection Contractor reported QC statistics in
Monthly Report
Reduced invoice equal to 1/2% for each % under the minimum required of the affected
CLIN
Rework Effectiveness
NA
100% of completed rework accepted by
100% (zero deviation)
100% Inspection
Reduced invoice equal to 25% of the
PWS
Paragraph
Performance Standard
Performance Threshold (maximum error rate)
Method of Surveillance
Remedy if Performance
Threshold is not met the Government without further rework work rejected by the Government and potentially a negative CPARS rating
AT Level I Training
8.7.1
All Contractor employees shall complete AT Level I training annually
100% (zero deviation)
100% inspection
Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative
OPSEC
Training
8.7.2
All Contractor employees shall complete OPSEC training annually
100% (zero deviation)
100% inspection
Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a negative CPARS narrative
Suspicious Activity
Reporting Training
8.7.3
All Contractor employees shall complete iWATCH training annually
100% (zero deviation)
100% inspection
Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a
Cyber Awareness
Training 8.7.4
All Contractor employees shall complete Cyber
Awareness training annually
100% (zero deviation)
100% inspection
Employee(s) not current in training shall not perform duties; reduction in invoice equal to work not performed and potentially a
Commented [HCACUC(2]: This and below are only applicable if on ATOPSEC (Probably will be)