Attachment 1 - Specifications Vol 1.pdf

PDF 5 MB Posted

Attached to
Expand Primary Care Minor Construction - Lake Nona (West) Project 675-102
Solicitation number
36C77623B0044
Issued by

About this file

This document outlines specifications for a construction project to expand primary care at the Orlando VA Medical Center in Orlando, Florida. The solicitation number is 36C77623B0044 and involves expanding primary care space by constructing a new 7,900 square foot addition. Key project details include demolishing an existing roof area and sections of precast wall panels and metal wall panels. The construction work also includes installing a new roof system, exterior wall cladding, doors, finishes, fixtures and extending mechanical, electrical and plumbing systems to the new space. The estimated period of performance is indicated as 120 calendar days.

View the file

Other files

File Type Posted
Public - Lake Nona Bid Opening Abstract.pdf PDF
36C77623B0044 0006.pdf PDF
36C77623B0044 0005.pdf PDF
Technical Questions and Answers.pdf PDF
2017 Orlando VA Medical Center ACM Report Compressed.pdf PDF
Hazardous Material Survey for Womens Helath Clinic Reception Area- Existing.pdf PDF
00 01 10_REV 230801.pdf PDF
36C77623B0044 0004.pdf PDF
08 71 00_REV 2023-08-01.pdf PDF
36C77623B0044 0003.pdf PDF
Remove Note from 2.3.pdf PDF
Site Visit Sign-In Sheet.pdf PDF
Construction Wage Rates - Orange County - 7-7-23.pdf PDF
36C77623B0044 0002.pdf PDF
675-102 Supplement to General Requirements Spec - 7-5-23.pdf PDF
675102-21109_AQ602.pdf PDF
675102-21109_AQ601.pdf PDF
36C77623B0044 0001.pdf PDF
675102-21109_AQ603.pdf PDF
08 71 00_REV 2023-06-05.pdf PDF
Attachment 2 - Specifications Vol 2.pdf PDF
Attachment 8 - ACM Report Compressed - 2017 - Orlando VA Medical Center.pdf PDF
Attachment 3 - Specifications Vol 3.pdf PDF
IFB - 36C77623B0044.pdf PDF
Attachment 5 - Drawings - 675-102 - 43-86.pdf PDF
Attachment 7 - Drawings - 675-102 - 131-173.pdf PDF
Attachment 13 - Brand Name Justification - Lake Nona Primary Care_Redacted.pdf PDF
Attachment 4 - Drawings - 675-102 - 1-42.pdf PDF
Attachment 6 - Drawings - 675-102 - 87-130.pdf PDF
Attachment 12 - Site Visit Instruction.pdf PDF
Attachment 11 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 9 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 10 - Construction Wage Rates - Orange County - 6-2-23.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

Orlando VA Medical Center 13800 Veterans Way | Orlando, Florida 32827

Expand Primary Care at Lake Nona (West)

Building 01 & 02

VA Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109

Issue for Bid Submittal

Volume 1 of 3 Divisions 00-09

October 19th, 2022

Revised March 13th, 2023

DIVISION 00

ORLANDO VA MEDICAL CENTER

ORLANDO, FLORIDA 32827

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 10 Table of Contents 01-21 00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01-21 01 32 16.01 Architectural and Engineering CPM Schedules 03-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 03-19 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 01-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21 03 45 00 Precast Architectural Concrete 01-21

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 31 00 Steel Decking 01-21 05 36 00 Composite Metal Decking 01-21 05 40 00 Cold-Formed Metal Framing 01-21 05 50 00 Metal Fabrications 08-18 05 51 00 Metal Stairs 01-21 05 58 13 Column Covers

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 08 00 Facility Exterior Closure Commissioning 01-21 07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 42 13 Metal Wall Panels 07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 71 00 Roof Specialties 01-21 07 72 00 Roof Accessories 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 01-21

DIVISION 08 - OPENINGS

08 00 01 Blast Performance Requirements 01-22 08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 14 73 Interior Sliding Wood Door Assemblies 08 31 13 Access Doors and Frames 01-21 08 44 13 Glazed Aluminum Curtain Walls 04-20 08 71 00 Door Hardware 01-21 08 71 13 Automatic Door Operators 01-21 08 71 13.11 Low Energy Power Assist Door Operators 01-21 08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 30 13 Ceramic/Porcelain Tiling 01-21 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 05-18 09 65 19 Resilient Tile Flooring 05-18 09 67 23.50 Resinous Terrazzo Flooring (RES-5) 01-21 09 68 00 Carpeting 01-21 09 72 16 Vinyl-Coated Fabric Wall Covering 01-21 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 10-3

SECTION NO. DIVISION AND SECTION TITLES DATE

10 11 13 Chalkboards and Markerboards 01-21 10 11 23 Tackboards 01-21 10 14 00 Signage 01-21 10 21 23 Cubicle Curtain Tracks 01-21 10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT

11 73 00 Ceiling Mounted Patient Lift System 08-20

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17 12 32 00 Manufactured Wood Casework 09-15 12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14– CONVEYING EQUIPEMENT

14 92 00 Pneumatic Tube System

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-20 22 14 00 Facility Storm Drainage 09-15 22 40 00 Plumbing Fixtures 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment

02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 73 00 Indoor Central-Station Air-Handling Units 03-20 23 82 00 Convection Heating and Cooling Units 03-20 23 82 16 Air Coils 03-20 23 84 00 Humidity Control Equipment 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 22 00 Low-Voltage Transformers 01-18 26 24 16 Panelboards 01-18 26 26 00 Power Distribution Units for Static Uninterruptible

Power Systems 01-18

26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 41 00 Facility Lightning Protection 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Control, Communication and Signal Wiring 06-15

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

01-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 10-5

SECTION NO. DIVISION AND SECTION TITLES DATE

27 11 00 Communications Equipment Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16 27 51 16 Public Address and Mass Notification Systems 10-18 27 51 23 Intercommunications and Program Systems 06-15 27 52 23 Nurse Call and Code Blue Systems 10-18 27 53 19 Distributed Radio Antenna (Within Building) Equipment and System 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 08 00.01 DVA/USACE Projects Commissioning of Electronic Safety and Security Systems 08-19

28 13 00 Physical Access Control System 10-11 28 13 16 Physical Access Control System and Database Management 09-11 28 13 53 Security Access Detection 09-11 28 16 00 Intrusion Detection System 10-11 28 23 00 Video Surveillance 09-11 28 26 00 Electronic Personal Protection System 09-11 28 31 00 Fire Detection and Alarm 10-11 28 52 31 Emergency Call System 06-15

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 GENERAL - COVER SHEET

G002 GENERAL - DRAWING INDEX

GI001 GENERAL - GENERAL PROJECT NOTES

GI002 GENERAL - GENERAL DEMOLITION NOTES

GI101 GENERAL - CODE AND BUILDING INFORMATION

GI201 GENERAL – SITE STAGING PLAN

GI204 GENERAL - LIFE SAFETY PLAN - 4TH FLOOR

GI304 GENERAL - INFECTION CONTROL PLAN - 4TH FLOOR

GI304IS GENERAL – INFECTION CONTROL PLAN – 4TH FLOOR INTERSTITIAL SPACE

GI305 GENERAL – INFECTION CONTROL PLAN – 5TH FLOOR

GI400 GENERAL - INFECTION CONTROL GENERAL NOTES

GI404 GENERAL - INFECTION CONTROL TYPICAL CLASS IV

STRUCTURAL

S001 STRUCTURAL - GENERAL NOTES

S002 STRUCTURAL - SYMBOLS AND NOTATIONS

S011 STRUCTURAL - COMPONENTS AND CLADDING DIAGRAM

S012 STRUCTURAL - COMPONENTS AND CLADDING DIAGRAM

S104 STRUCTURAL - LEVEL 4 - FRAMING PLAN

S104IS STRUCTURAL - LEVEL 4 - INTERSTITIAL FRAMING PLAN

S105 STRUCTURAL - LEVEL 5 - FRAMING PLAN

S701 STRUCTURAL - TYPICAL DECK REINFORCEMENT DETAILS

S702 STRUCTURAL - TYPICAL DECK REINFORCEMENT DETAILS

S711 STRUCTURAL - TYPICAL STEEL DETAILS

S811 STRUCTURAL - STEEL SECTIONS AND DETAILS

ARCHITECTURAL

A001 ARCHITECTURAL - SYMBOLS, ABBREVIATIONS AND MATERIAL INDICATIONS

A002 ARCHITECTURAL - STANDARD MOUNTING HEIGHTS AND DIMENSIONS

A003 ARCHITECTURAL - GENERAL NOTES AND LEGENDS

AD104 ARCHITECTURAL - DEMOLITION PLAN - 4TH FLOOR

AD104IS ARCHITECTURAL – DEMOLITION PLAN – 4TH FLOOR INTERSTITIAL SPACE

AD105 ARCHITECTURAL - DEMOLITION PLAN - 5TH FLOOR

ACD104 ARCHITECTURAL - DEMOLITION REFLECTED CEILING PLAN - 4TH FLOOR

AD201 ARCHITECTURAL - DEMOLITION ELEVATIONS

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 15 - 2

A104 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR

A104.1 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR - AREA A

A104.2 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR - AREA B

A104.3 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR - AREA C

A104IS ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR INTERSTITIAL

A104IS.1 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR INTERSTITIAL - AREA A

A104IS.2 ARCHITECTURAL - FLOOR PLAN - 4TH FLOOR INTERSTITIAL - AREA B

A105 ARCHITECTURAL - FLOOR PLAN - 5TH FLOOR

A105.1 ARCHITECTURAL - FLOOR PLAN - 5TH FLOOR - AREA A

A105.2 ARCHITECTURAL - FLOOR PLAN - 5TH FLOOR - AREA B

AC104 ARCHITECTURAL - REFFLECTED CEILING PLAN - 4TH FLOOR

AC104.1 ARCHITECTURAL - REFLECTED CEILING PLAN - 4TH FLOOR - AREA A

AC104.2 ARCHITECTURAL - REFLECTED CEILING PLAN - 4TH FLOOR - AREA B

AC104.3 ARCHITECTURAL - REFLECTED CEILING PLAN - 4TH FLOOR - AREA C

AC104IS ARCHITECTURAL – REFLECTED CEILING PLAN – 4TH FLOOR INTERSTITIAL

AC105 ARCHITECTURAL - REFLECTED CEILING PLAN - 5TH FLOOR

A201 ARCHITECTURAL - EXTERIOR ELEVATIONS

A202 ARCHITECTURAL - EXTERIOR ELEVATIONS

A301 ARCHITECTURAL - BUILDING SECTIONS

A311 ARCHITECTURAL - WALL SECTIONS

A312 ARCHITECTURAL - WALL SECTIONS

A321 ARCHITECTURAL - PARTITION TYPES

A401 ARCHITECTURAL - ENLARGED ROOMS AND INTERIOR ELEVATIONS

A402 ARCHITECTURAL - ENLARGED ROOMS AND INTERIOR ELEVATIONS

A403 ARCHITECTURAL - ENLARGED ROOMS AND INTERIOR ELEVATIONS

A404 ARCHITECTURAL - ENLARGED ROOMS AND INTERIOR ELEVATIONS

A405 ARCHITECTURAL - ENLARGED ROOMS AND INTERIOR ELEVATIONS

A411 ARCHITECTURAL - INTERIOR ELEVATIONS - CORRIDORS

A412 ARCHITECTURAL - INTERIOR ELEVATIONS - CORRIDORS

A413 ARCHITECTURAL - INTERIOR ELEVATIONS - CORRIDORS

A414 ARCHITECTURAL - INTERIOR ELEVATIONS

A415 ARCHITECTURAL - INTERIOR ELEVATIONS

A416 ARCHITECTURAL - INTERIOR ELEVATIONS

A421 ARCHITECTURAL – STAIR PLANS AND RAILING ELEVATIONS

A511 ARCHITECTURAL - EXTERIOR DETAILS

A512 ARCHITECTURAL – PRECAST REVEAL AND JOINT TYPES

A521 ARCHITECTURAL - INTERIOR DETAILS

A531 ARCHITECTURAL - ROOF DETAILS

A532 ARCHITECTURAL - TYPICAL ROOF DETAILS

A541 ARCHITECTURAL - CEILING DETAILS

A551 ARCHITECTURAL - CASEWORK SCHEDULE AND DETAILS

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 15 - 3

A552 ARCHITECTURAL - CASEWORK DETAILS - RECEPTION DESK

A561 ARCHITECTURAL - FINISH DETAILS

A571 ARCHITECTURAL - MOUNTING DETAILS

A581 ARCHITECTURAL - PENETRATION DETAILS

A601 ARCHITECTURAL - DOOR SCHEDULE AND DETAILS

A611 ARCHITECTURAL - WINDOW SCHEDULE AND DETAILS

INTERIORS

AF104 ARCHITECTURAL - FINISH PLAN - 4TH FLOOR

AF104.1 ARCHITECTURAL - FINISH PLAN - 4TH FLOOR - AREA A

AF104.2 ARCHITECTURAL - FINISH PLAN - 4TH FLOOR - AREA B

AF104.3 ARCHITECTURAL - FINISH PLAN - 4TH FLOOR - AREA C

AF601 ARCHITECTURAL - FINISH LEGEND

AF611 ARCHITECTURAL - FINISH SCHEDULE

WAYFINDING

AW104 ARCHITECTURAL – WAYFINDING – SCHEDULE AND LOCATION PLAN – 4TH FLOOR

AW104IS ARCHITECTURAL – WAYFINDING – 4TH FLOOR INTERSTITIAL

AW601 ARCHITECTURAL – WAYFINDING TYPES

EQUIPMENT

AJ104 ARCHITECTURAL - PNEUMATIC TUBE PLAN

AQ104 ARCHITECTURAL - EQUIPMENT PLAN - 4TH FLOOR

AQ104.1 ARCHITECTURAL - EQUIPMENT PLAN - 4TH FLOOR - AREA A

AQ104.2 ARCHITECTURAL - EQUIPMENT PLAN - 4TH FLOOR - AREA B

AQ104.3 ARCHITECTURAL - EQUIPMENT PLAN - 4TH FLOOR - AREA C

AQ601 ARCHITECTURAL - EQUIPMENT SCHEDULE

AQ602 ARCHITECTURAL - EQUIPMENT SCHEDULE

AQ603 ARCHITECTURAL - EQUIPMENT SCHEDULE

FIRE PROTECTION

FX001 FIRE PROTECTION - GENERAL NOTES, SYMBOLS AND ABBREVIATIONS

FXD104 FIRE PROTECTION - FOURTH FLOOR - DEMOLITION PLAN

FX104 FIRE PROTECTION - FOURTH FLOOR PLAN

FX501 FIRE PROTECTION - DETAILS

MECHANICAL

M001 MECHANICAL - GENERAL NOTES, SYMBOLS, AND ABBREVIATIONS

MHD104 MECHANICAL VENTILATION - LEVEL 4 DEMOLITION PLAN

MHD104-I MECHANICAL VENTILATION - LEVEL 4 INTERSTITIAL DEMOLITION PLAN

MH104 MECHANICAL VENTILATION - LEVEL 4 PLAN

MH104.1 MECHANICAL VENTILATION - LEVEL 4 - AREA A PLAN

MH104.2 MECHANICAL VENTILATION - LEVEL 4 - AREA B PLAN

MH104.3 MECHANICAL VENTILATION - LEVEL 4 - AREA C PLAN

MH104-I MECHANICAL VENTILATION - LEVEL 4 INTERSTITIAL PLAN

MH105 MECHANICAL VENTILATION - LEVEL 5 PLAN

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 15 - 4

MH105.1 MECHANICAL VENTILATION - LEVEL 5 - AREA A PLAN

MH105.2 MECHANICAL VENTILATION - LEVEL 5 - AREA B & C PLAN

MP104 MECHANICAL PIPING - LEVEL 4 PLAN

MP104-I MECHANICAL PIPING - LEVEL 4 INTERSTITIAL PLAN

MP105 MECHANICAL PIPING - LEVEL 5 PLAN

M401 MECHANICAL SECTIONS

M501 MECHANICAL DETAILS

M502 MECHANICAL DETAILS

M503 MECHANICAL DETAILS

M601 MECHANICAL SCHEDULES

M602 MECHANICAL SCHEDULES

M701 MECHANICAL CONTROLS

M702 MECHANICAL CONTROLS

M703 MECHANICAL CONTROLS

PLUMBING

P001 PLUMBING - GENERAL NOTES, SYMBOLS AND ABBREVIATIONS

P002 PLUMBING - CALCULATIONS

PD103-I.1 PLUMBING - DEMOLITION PLAN, THIRD FLOOR INTERSTITIAL

PD104 PLUMBING - DEMOLITION PLAN, FOURTH FLOOR

P103-I.1 PLUMBING - FLOOR PLAN, THIRD FLOOR INTERSTITIAL

P104 PLUMBING - FLOOR PLAN, FOURTH FLOOR

P104-I.1 PLUMBING - FLOOR PLAN, FOURTH FLOOR INTERSTIITAL - ZONE 1

P104-I.2 PLUMBING - FLOOR PLAN, FOURTH FLOOR INTERSTIITAL - ZONE 2

P105 PLUMBING - FLOOR PLAN, FIFTH FLOOR

P501 PLUMBING - DETAILS

P502 PLUMBING - DETAILS

P601 PLUMBING - DOMESTIC WATER RISER DIAGRAM

P602 PLUMBING - SANITARY AND VENT RISER DIAGRAM

P603 PLUMBING – STORM RISER DIAGRAM

P701 PLUMBING - SCHEDULE

P702 PLUMBING - SCHEDULE

MEDICAL GAS

MG001 MEDICAL GAS - GENERAL NOTES, SYMBOLS AND ABBREVIATIONS

MG104 MEDICAL GAS - FLOOR PLAN, FOURTH FLOOR

MG104-I.1 MEDICAL GAS - FLOOR PLAN, FOURTH FLOOR INTERSTITIAL - ZONE 1

MG104-I.2 MEDICAL GAS - FLOOR PLAN, FOURTH FLOOR INTERSTITIAL - ZONE 2

ELECTRICAL

E001 ELECTRICAL GENERAL NOTES

E002 ELECTRICAL SYMBOLS AND ABBREVIATIONS

ELD104 ELECTRICAL – LIGHTING DEMO PLAN – LEVEL 4

EPD104 ELECTRICAL – POWER DEMO PLAN – LEVEL 4

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

05-01-20

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-2023

00 01 15 - 5

EPD105 ELECTRICAL – POWER DEMO PLAN – LEVEL 5

EL104 ELECTRICAL LIGHTING PLAN - 4TH FLOOR

EL104IS ELECTRICAL – LEVEL 4 INTERSTITIAL LIGHTING PLAN

EP104.1 ELECTRICAL POWER PLAN - LEVEL 4

EP104.2 ELECTRICAL OVERALL POWER PLAN - LEVEL 4

EP104IS ELECTRICAL – LEVEL 4 INTERSTITIAL POWER PLAN

EP105 ELECTRICAL / MECHANICAL POWER PLAN - 5TH FLOOR

ELP104 ELECTRICAL LIGHTNING PROTECTION

FA104 ELECTRICAL FIRE ALARM & SECURITY PLAN - 4TH FLOOR

E501 ELECTRICAL TYPICAL DETAILS

E502 ELECTRICAL DETAILS

E503 ELECTRICAL DETAILS

E504 ELECTRICAL LIGHTING AND CONTROLS SCHEDULES

E601 ELECTRICAL SINGLE LINE DIAGRAM

E701 PANEL SCHEDULES

E702 PANEL SCHEDULES

TELECOMMUNICATION

TT104IS TELECOMMUNICATION – LEVEL 4 INTERSTITIAL

TT104 TELECOMMUNICATION – LEVEL 4

TN104 NURSE CALL PLAN – LEVEL 4

TS104 SECURITY PLAN – LEVEL 4

TT404 TELECOMMUNICATION ENLARGED PLAN - LEVEL 4

TT501 TELECOMMUNICATIONS – DETAILS

TT502 TELECOMMUNICATIONS - DETAILS

TT503 TELECOMMUNICATIONS – DETAILS

TT504 TELECOMMUNICATIONS - DETAILS

TT600 TELECOMMUNICATIONS – SCHEMATICS, SCHEDULES, AND DIAGRAMS

TT601 TELECOMMUNICATIONS – SCHEMATICS, SCHEDULES, AND DIAGRAMS

- - - E N D - - -

DIVISION 01

EXPAND PRIMARY CARE AT LAKE NONA (WEST)

Bancroft Architects + Engineers

11-01-21

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of portions of existing structures, and furnish labor and materials and perform work for the Expand Primary Care at Lake Nona (West) project for the

Orlando VA Medical Center as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the

Contracting Officer. .

C. Offices of Bancroft Architects + Engineers, as

Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the General Contractor, the

Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -2

Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Core Working Hours:

1. Normal working hours for this contract will be from 7:30AM to

5:00PM (local time) Monday through Friday except for weekends and established Federal Holidays.

2. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR.

Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the

Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID : Work includes general construction as indicated on the drawings, including but not limited to:

1. Removal of an existing roof area, including roof drains and associated roof mounted accessories.

2. Removal of a section of existing precast wall panels.

3. Removal of a section of existing metal wall panels.

4. Construction of a new 7,900 SF Addition, including new roof system, exterior wall cladding, doors, hardware, finishes, fixtures and extension of existing Mechanical, Electrical and

Plumbing services to the new space.

5. Extension of the existing pneumatic tube system.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -3

B. ALTERNATE NO.1: BASE BID except deduct installation of WP-1.

Walls where WP-1 were to be installed are to be painted.

C. ALTERNATE NO.2: ALTERNATE 1 except deduct installation of WP-2 and WP-3. Walls where WP-2 & WP-3 were to be installed are to be painted.

D. ALTERNATE NO. 3: Alternate 2 except remove all terrazzo flooring.

In areas where terrazzo flooring was to be installed, LVT-2 to be installed instead.

E. ALTERNATE NO. 4: Alternate 3 except remove PT-2 and in areas where PT-2 were to be installed, provide WSF-1 instead.

F. ALTERNATE NO. 5: Alternate 4 except remove PT-4 and in areas where PT-4 were to be installed, provide EC-1.

G. ALTERNATE NO.6: Alternate 5 except remove Metal Column covers. In areas where Metal Column Covers were to be installed, provide 2-

1/2” metal stud framing around columns with 5/8” Gyp. Bd. Prime and Paint.

H. ALTERNATE NO. 7: Alternate 6 except remove Light Fixture L9. In areas where L9 were to be installed, provide L7 instead.

I. ALTERNATE NO. 8: Alternate 7 except remove SS-1 at windowsill locations and replace with Plastic Laminate. Color to be chosen from manufacturers standard colors.

J. ALTERNATE NO. 9: Alternate 8 except remove CW-1 from West

Elevation. Four (4) Windows total.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -4

K. ALTERNATE NO. 10: Alternate 9 except remove SS-1 from Reception, Staff Offices and Break Room and replace with Plastic Laminate.

Color to be chosen from manufacturers standard colors.

L. ALTERNATE NO. 11: Alternate 10 except remove 3-drawer base cabinet from Staff / Team area. Change from “CFCI” to “VFVI”.

M. ALTERNATE NO.12: Alternate 11 except remove all new interior scope of work from rooms 4A319, 4A318, 4A317, 4A316, 4A315, 4A313, 4A412, 4A311, 4A310, 4A309, 4A308, 4A306 and 4A305. These areas are to be left as shell space for future use.

N. ALTERNATE NO. 13: Alternate 12 except remove keynotes 5 & 6 from sheet AD104. On sheet AD104, also remove keynote 24 from the wall between Room 4A301 and the existing reception desk. That existing wall is to remain. Existing Carpet flooring to remain. Patch carpet flooring where walls have been removed. Existing walls remaining to be patched and painted P-1. Remove all new work associated with rooms 4A102, 4AC03, 4A103 AND 4A104.

O. ALTERNATE NO. 14: Base Bid except remove medical wireless access points (Medical WAP) including cabling and terminations. All cabling, terminations and wireless access points associated with the Guest Wi-Fi are to remain as part of the scope of work.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at

Contractor's expense.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -5

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. N/A

D. Key Control:

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -6

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See

Section 08 71 00, DOOR HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting

Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of

Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the

VA.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -7

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted

24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General

Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility

Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -8

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the

Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR .

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -9 utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to

Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -10 intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to

Medical Center Director, COR and Contractor, as follows:

I. Building(s) will be occupied during performance of work, but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical

Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m

(seven feet) minimum height, around the construction area

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -11 indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum

375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.

K. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C

(40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

L. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -12

Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the

Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11

REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical

Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -13

M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

N. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

P. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas.

Construction noise during the interment services shall not

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -14 disturb the service. Trucks and workers shall not pass through the service area during this period:

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply

Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -15

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -16

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by

COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -17

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -18

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant

Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;

and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -19 extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"

(FAR 52.236-2).

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

Contract No. 36C77621C0079 Station Project No. 675-102 Bancroft-AE Project No. 21-109 03-13-23

01 00 00 -20

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .