ATTACHMENT 1 - Specifications.pdf

PDF 10 MB Posted

Attached to
Y1AZ--EHRM Training and Administrative Support Space Construction - St. Cloud Federal contract opportunity
Solicitation number
36C77622B0026
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This solicitation is seeking a general contractor to renovate the EHRM Training Room and Administrative Support Space at the St. Cloud VA Medical Center. Work includes general construction, alterations, removal of existing structures, millwork, permanently mounted equipment, interior finishes, and other items. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center Austin as number 36C77622B0026. Responses are due based on the standard FAR solicitation timeline and award will be made to a responsible contractor whose offer conforms to the solicitation and is most advantageous to the government considering price and other factors.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Training and Administrative Support Space Construction - St. Cloud, newest first.
File Type Posted
36C77622B0026 0003.pdf PDF
Response 2 - 21 08 00 Commissioning of Fire Suppression Systems.pdf PDF
Response 29 - 21 13 13 Wet-Pipe Sprinkler Systems Revised.pdf PDF
Response 29 - FX-101 Revised.pdf PDF
Response 45 - GI000 Supplement.pdf PDF
Technical Questions - FINAL - St. Cloud 5-23-22.pdf PDF
Response 29 - EF101A.pdf PDF
Response 46 - ELPD 101.pdf PDF
Response 15 - 23 09 23 Direct-Digital Control System for HVAC.pdf PDF
Response 43 - B-04 EHRM-HA101.pdf PDF
Response 43 - DSCF2239.pdf PDF
Response 45 - GC100 Supplement.pdf PDF
Response 17 - 01 45 29 Testing Laboratory Services Revised.pdf PDF
36C77622B0026 0002.pdf PDF
Site Visit Sign-In Sheet 4-19-22.pdf PDF
ATTACHMENT 8 - Construction Wage Rates - Stearns 4-1-22.pdf PDF
36C77622B0026 0001.pdf PDF
36C77622B0026 - 4-7-22.pdf PDF
ATTACHMENT 2 - Drawings 1 of 2.pdf PDF
ATTACHMENT 4 - Brand Name Justification - St. Cloud.pdf PDF
ATTACHMENT 6 - COVID-19 Safety Protocols 12-14-21.pdf PDF
ATTACHMENT 9 - Contractor Safety - Environmental Form.docx DOCX document
ATTACHMENT 3 - Drawings 2 of 2.pdf PDF
ATTACHMENT 7 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 8 - Construction Wage Rates - Stearns 2-25-22.pdf PDF
ATTACHMENT 10 - Site Visit Instructions.pdf PDF
ATTACHMENT 5 - Contractor Core Work Hours.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications

St. Cloud VA Health Care System

4801 Veterans Drive

St. Cloud, MN 56303

EHRM Training and Admin Space Support

Building 4

VA Contract No. 36C263-19-D-0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft-AE Project No. 18-116

Construction BID Documents

September 17, 2021

DIVISION 00

SPECIAL SECTIONS

EHRM TRAINING AND ADMIN SPACE SUPPORT

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

01-01-21

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

00 01 10-1 02/02/2022

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 03-20

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 2-1-20

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 01-21

01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 42 00 Cutting, Removal, Demolition, Restoration and Patching 12-11

02 82 13.13 Glovebag Asbestos Abatement 9-1-15

02 83 33.13 Lead-Based Paint Removal and Disposal 8-1-16

DIVISION 03 – CONCRETE (NOT USED)

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 2-1-16

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 10-17

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

01-01-21

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

00 01 10-2 02/02/2022

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 31 13 Access Doors and Frames 01-21

08 71 00 Door Hardware 01-21

08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 22 26 Operable Partitions 05-20

10 26 00 Wall and Door Protection 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS

12 36 61.16 Solid Surface Countertops

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

01-01-21

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

00 01 10-3 02/02/2022

22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

23 07 11 HVAC Insulation 02-20

23 21 13 Hydronic Piping 02-20

23 22 13 Steam and Condensate Heating Piping 02-20

23 31 00 HVAC Ducts and Casings 02-20

23 34 00 HVAC Fans 02-20

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 73 00 Indoor Central-Station Air-Handling Units 03-20

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 09 23 Lighting Controls 01-18

26 24 16 Panelboards 01-18

26 27 26 Wiring Devices 01-18

26 43 13 Surge Protective Devices 01-17

26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 00 Communications Equipment Room Fittings 06-15

27 15 00 Communications Structured Cabling 01-16

27 51 16 Public Address and Mass Notification Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm 10-11

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

01-01-21

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

00 01 10-4 02/02/2022

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – Electrical Power Generation (NOT USED)

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

05-01-20

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

09/17/2021

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI001 COVER SHEET

GI002 DRAWING INDEX

GI003 GENERAL PROJECT AND CODE DATA

GI004 GENERAL PROJECT NOTES

GI101 GENERAL LIFE SAFETY PLAN

GC100 GENERAL SITE STAGING PLAN

GC101 GENERAL PHASING PLANS

GC102 GENERAL INFECTION CONTROL RISK ASSESSMENT

GC103 GENERAL INFECTION CONTROL RISK ASSESMENT CLASS IV

HAZARDOUS MATERIALS

HA101 HAZARDOUS MATERIALS PLAN - ASBESTOS LEAD - FIRST LEVEL

STRUCTURAL

SF101 STRUCTURAL - OPERABLE PARTITION DETAILS

ARCHITECTURAL

A001 ARCHITECTURALABBREVIATIONS, SYMBOLS AND MOUNTING HEIGHTS

AD101 ARCHITECTURAL DEMOLITION FLOOR PLANS

ACD101 ARCHITECTURAL DEMOLITION REFLECTED CEILING PLAN

A101 ARCHITECTURAL FLOOR PLAN

A101.1 ARCHITECTURAL FLOOR PLAN - AREA 1

A101.2 ARCHITECTURAL FLOOR PLAN - AREA 2

AC101.1 ARCHITECTURAL REFLECTED CEILING PLAN - AREA 1

AC101.2 ARCHITECTURAL REFLECTED CEILING PLAN - AREA 2

A301 ARCHITECTURAL PARTITION TYPES + DETAILS

A401 ARCHITECTURAL INTERIOR ELEVATIONS

A402 ARCHITECTURAL INTERIOR ELEVATIONS

A501 ARCHITECTURAL DETAILS

A502 ARCHITECTURAL DETAILS

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

05-01-20

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

09/17/2021

00 01 15 - 2

A601 ARCHITECTURAL DOOR SCHEDULE

AF101 ARCHITECTURAL FINISH PLAN

AF601 ARCHITECTURAL FINISH SCHEDULES

AW101 ARCHITECTURAL WAYFINDING (SIGNAGE) PLAN

AW601 WAYFINDING DETAILS

FIRE

SUPPRESSION

FX101 FIRE SUPPRESSION PLAN

PLUMBING

P001 PLUMBING - GENERAL NOTES, SYMBOLS, AND ABBREVIATIONS

PD101 PLUMBING - DEMOLITION PLAN - FIRST FLOOR

P101 PLUMBING - DOMESTIC, SANITARY & VENT PLAN

P501 PLUMBING - DETAILS

P601 PLUMBING - SCHEDULES

MECHANICAL

M001 MECHANICAL - GENERAL NOTES, SYMBOLS, AND ABBREVIATIONS

MD101 MECHANICAL DEMOLITION PLAN - FIRST FLOOR

M101 MECHANICAL PLAN - FIRST FLOOR

M102 MECHANICAL - LOWER PENTHOUSE & ENLARGED MECH ROOM PLANS

M501 MECHANICAL - DETAILS

M502 MECHANICAL - DETAILS

M601 MECHANICAL - SCHEDULES

M701 MECHANICAL - CONTROLS

M702 MECHANICAL - CONTROLS

ELECTRICAL

E001 ELECTRICAL- GENERAL NOTES

E002 ELECTRICAL- SYMBOLS AND ABBREVIATIONS

ELPD101 ELECTRICAL - LIGHTING AND POWER DEMO. PLAN-FIRST FLOOR

ETD101 ELECTRICAL - TECHNOLOGY DEMOLITION PLAN - FIRST FLOOR

EFD101 ELECTRICAL - FIRE ALARM AND FIRE PROTECTION DEMOLITION PLAN

ELP101 ELECTRICAL - LIGHTING AND POWER PLAN - FIRST FLOOR

ET101 ELECTRICAL - TECHNOLOGY PLAN - FIRST FLOOR

EF101 ELECTRICAL - FIRE ALARM AND FIRE PROTECTION PLAN

ED600 ELECTRICAL - PANEL DEMOLITION SCHEDULES

E600 ELECTRICAL - PANEL SCHEDULES

4801 Veterans Drive, St. Cloud, MN 56303

Building 4

05-01-20

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

09/17/2021

00 01 15 - 3

E601 ELECTRICAL - ELECTRICAL CLOSET ROOM 100A

E700 ELECTRICAL-ROOM LIGHTING SCHEMES

- - - END - - -

DIVISION 01

GENERAL REQUIREMENTS

4801 Veterans Drive, St. Cloud, MN 56303

01-01-21

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 1 02/02/2022

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, furnish labor and materials and perform work to include demolition and removal of existing structures, and for the construction per the bid documents for EHRM TRAINING + ADMINISTRATOVE SPACE SUPPORT Building 4 at the St. Cloud VA Health Care System as required by all drawings, codes and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

C. Offices of Bancroft Architects + Engineers, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the

Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA Security

Management Program, obtain all appropriate badging, obtain permission of the VA police, be identified by project and employer, and be restricted from unauthorized access.

F. The Key Personnel assigned by the contractor for the performance of work on this contract shall be acceptable to VA in terms of personal and professional conduct and technical knowledge.~

Should the assignment to this contract of any person by the contractor be deemed to conflict with the interests of VA, or in the event performance is deemed to be unsatisfactory at any time

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 2 02/02/2022 during the life of the contract, the Contracting Officer may notify the contractor and request the person be removed from the assignment.~ The reason for removal will be documented and a request to receive key personnel replacement within three (3) business days of the notification will be made. Replacement of key personnel qualifications shall be equal to or greater than those of the key personnel being replaced.~ Employment and staffing difficulties will not be justification for failure to meet established schedules. The contractor is required to submit a resume with qualifications for the proposed replacement which shall be approved by the COR and CO prior to the replacement starting work.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID includes all work per drawings and specifications included but not limited to general construction, alterations, necessary removal of existing structures and construction and certain other items.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge.

They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting

Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 3 02/02/2022

3. No photography of VA premises is allowed without written permission of the Contracting

Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency. The General

Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law

Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 4 02/02/2022

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. 5 permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

F. Prior to commencing work, the general contractor shall provide proof that the project supervisor assigned to the project is an OSHA 30 certified “competent person” (CP) (29 CFR

1926.20 (b) (2)). The CP will maintain a presence at the work site whenever the employees of the general contractor or subcontractors are present.

G. Training:

1. The Contractor’s project supervisor is required to attend GEMS and safety training provided by VA St. Cloud. Training must be attended prior to being designated as a job supervisor on any VA St. Cloud construction project.

2. All employees of general contractor and subcontractors shall have, at a minimum, the 10-hour OSHA certified Construction Safety course and other relevant competency training, as determined by VA CP with input from the Infection Control Risk Assessment (ICRA) team.

3. Submit training records of all such employees for approval before the start of work.

4. Notice to proceed will be issued not less than 2 weeks after receipt of bonds; time extensions will not be granted because of the need for training.

H. Identification Badge:

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 5 02/02/2022

1. All contractor employees working on this project will be required to obtain and wear while on VA property, a VA picture identification badge. The badge will only be issued to those employees having the appropriate OSHA Construction Safety Cards. A completed badge request form, proof of OSHA training and any other required certificates shall be submitted electronically 15 business days in advance of working on site. Contractors will then be issued a badge free of charge by the VA. A separate site visit prior to performing work by the contractor employee shall be expected to obtain a badge. All ID badges must be returned upon completion. There will be a $200 charge for each PIV/Flash ID badge not returned at the end of the contract. There will be a $25 charge for “facility” badges and “contractor” or consultant badges. Reference security procedures for additional information.

2. Contractor and subcontractor employees that will work on VA property shall submit the following information to the Contracting Officer’s Representative (COR) when requesting a badge:

a. First, middle, and last name (Legal Name, as shown on picture ID)

b. Date of Birth (DOB)

c. Social Security Number (SSN)

d. Height

e. Eye Color

f. Hair Color

g. Name of Firm or Company

h. VA Contract Number

i. VA Project Name

j. Name of COR

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 6 02/02/2022

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the

Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by theCOR .

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 7 02/02/2022

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor.

I. Parts of Building(s) No.(s) 4 will be occupied during performance of work.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 8 02/02/2022 or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR [Chief

Engineer] [Chief of Facilities Management]. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.

Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON

WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.

Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of

COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 9 02/02/2022 be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by COR.

This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

O. Coordination of Construction with Cemetery Director: The burial activities at a National

Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workers shall not pass through the service area during this period:

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings areas of buildings in which alterations

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 10 02/02/2022 occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR , to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and

"CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 11 02/02/2022

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse.

Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with

Contractor's operation.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.

Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.

Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 12 02/02/2022 shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)

disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 13 02/02/2022

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract.

The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 14 02/02/2022

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the

Contractor shall respond in a timely manner. Written verification will follow oral

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 15 02/02/2022 instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the

Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the

Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty

Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 16 02/02/2022

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

Power failure (entire area or any building operational after 1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

Exterior lights not operational.

h) Code 1-Gas

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 17 02/02/2022

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

2) Leaking water supply pipes

k) Code 2-Plumbing

Flush valves not operating properly

Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Damage to property is occurring.

o) Code 2-Water (Exterior)

No water to facility.

p) Code 2-Water (Hot)

No hot water in portion of building listed.

q) Code 3

All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 18 02/02/2022 until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.13 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the

Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 19 02/02/2022

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National

Electrical Code, (2020 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government. Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

01 00 00 - 20 02/02/2022

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.15 TEMPORARY USE OF EXISTING ELEVATORS

A. Contractor will not be allowed the use of existing elevators.

1.16 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1. *Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center . Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the

Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the

Government, the Contractor shall remove all the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .