About this file

This document outlines commissioning requirements for fire suppression systems in a federal construction project. The St. Cloud VA Medical Center is renovating training and administrative support spaces and seeking a general contractor to provide all labor, materials, equipment and supervision. The work includes construction, alterations, removal of existing structures, millwork, permanently mounted equipment and interior finishes. The contractor must coordinate inspections throughout construction and complete pre-functional checklists to verify installation and systems readiness for testing. The commissioning process includes contractor tests, systems functional performance testing to evaluate reactions to changes and emergency conditions, and training of VA operations and maintenance staff.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Training and Administrative Support Space Construction - St. Cloud, newest first.
File Type Posted
Response 17 - 01 45 29 Testing Laboratory Services Revised.pdf PDF
36C77622B0026 0003.pdf PDF
Response 29 - 21 13 13 Wet-Pipe Sprinkler Systems Revised.pdf PDF
Response 29 - FX-101 Revised.pdf PDF
Response 45 - GI000 Supplement.pdf PDF
Technical Questions - FINAL - St. Cloud 5-23-22.pdf PDF
Response 29 - EF101A.pdf PDF
Response 46 - ELPD 101.pdf PDF
Response 15 - 23 09 23 Direct-Digital Control System for HVAC.pdf PDF
Response 43 - B-04 EHRM-HA101.pdf PDF
Response 43 - DSCF2239.pdf PDF
Response 45 - GC100 Supplement.pdf PDF
36C77622B0026 0002.pdf PDF
Site Visit Sign-In Sheet 4-19-22.pdf PDF
ATTACHMENT 8 - Construction Wage Rates - Stearns 4-1-22.pdf PDF
36C77622B0026 0001.pdf PDF
ATTACHMENT 5 - Contractor Core Work Hours.pdf PDF
36C77622B0026 - 4-7-22.pdf PDF
ATTACHMENT 2 - Drawings 1 of 2.pdf PDF
ATTACHMENT 4 - Brand Name Justification - St. Cloud.pdf PDF
ATTACHMENT 6 - COVID-19 Safety Protocols 12-14-21.pdf PDF
ATTACHMENT 9 - Contractor Safety - Environmental Form.docx DOCX document
ATTACHMENT 3 - Drawings 2 of 2.pdf PDF
ATTACHMENT 1 - Specifications.pdf PDF
ATTACHMENT 7 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 8 - Construction Wage Rates - Stearns 2-25-22.pdf PDF
ATTACHMENT 10 - Site Visit Instructions.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EHRM TRAINING AND ADMIN SPACE SUPPORT

St. Cloud VA Health Care System

4801 Veteran’s Drive, St. Cloud, MN 56303

Building 4

05-01-15

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

Bancroft Project No. 18-116

21 08 00-1 05/10/2022

SECTION 21 08 00

COMMISSIONING OF FIRE SUPPRESSION SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 21.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissioning the Fire

Suppression systems, subsystems and equipment.

1.4 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Division 21, is required in cooperation with the VA.

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals. The

VA will provide a list of submittals that will be reviewed by the Fire

Protection Designer of Record. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01

33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 21 13 13.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The Contractor shall coordinate with the project construction manager to schedule inspections as required to support the Commissioning Process.

4801 Veteran’s Drive, St. Cloud, MN 56303

Building 4

05-01-15

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236

21 08 00-2 05/10/2022

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. Refer to Division

21 Sections for Pre-Functional testing requirements.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. A designated representative of the VA will witness selected Contractor tests. Contractor Pre-Functional tests shall be completed prior to scheduling Systems Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Functional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. Refer to Division 21 Sections for Functional Performance testing requirements. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. A designated representative of the VA will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance personnel is required in cooperation with the COR. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. The instruction shall be scheduled in coordination with the COR after submission and approval of formal training plans.

Refer to Division 21 Sections for additional Contractor training requirements.

----- END -----

4801 Veteran’s Drive, St. Cloud, MN 56303

Building 4

05-01-15

Contract No. 36C26319D0022

Task Order No. 36C77621N1993

Station Project No. 656-21-236