This Statement of Work (SOW) details a construction services project for replacing mechanical and plumbing systems at the Jonathon M. Wainwright Memorial Medical Center in Walla Walla, Washington. The project involves comprehensive upgrades for 11 buildings, with work including controls system modifications, electrical and architectural adjustments, structural modifications, and fire/life safety updates. The aging VA facility, with buildings over 50 years old, requires replacement of major mechanical and plumbing components such as piping, valves, gauges, and supporting systems that have exceeded their useful life.
The project scope encompasses removing dead legs from existing systems, providing proper plumbing line routing, and installing new HVAC systems to meet building requirements. The contractor will have 360 days to complete the work, with performance monitored by the Contracting Officer's Representative (COR) from Engineering Service. Deliverables include inspection, testing documents, manuals, and warranty documents per specifications. The project will be located at 77 Wainwright Drive, Walla Walla, WA, and requires a final systems demonstration as part of the acceptance criteria.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
687-21-106 Replace Mechanical and Plumbing Systems
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Jonathon M. Wainwright Memorial Medical Center Walla Walla, Washington
May 21, 2025
1. General
Many of the buildings at the Walla Walla VA exceed 50 years old and many systems are beyond their useful lives. This project replaces major mechanical and plumbing components and secondary distribution systems on the Walla Walla campus, such as piping, valves, gauges, and supporting components that have exceeded their useful life. This project includes removing dead legs from the system and providing proper routing of plumbing lines through the buildings. In some buildings, new HVAC systems are required to meet the building usage requirements as well as address deficient systems.
2. Scope
The scope of work for this project includes the following for 11 buildings:
a. Controls system modifications to integrate the mechanical scope items and remove demolished equipment from controls systems.
b. Electrical work required to disconnect demolished mechanical equipment & connect new mechanical equipment.
c. Architectural work as required to remove & install mechanical systems.
d. Structural modifications as required to support new mechanical systems.
e. Fire/life safety modifications are required to support new mechanical systems.
3. Deliverables Inspection, testing documents, and manuals and warranty documents per Specifications.
4. Period of Performance
The contractor has 360 days to perform all described work.
5. Performance Monitoring
The COR assigned to the Engineering Service will evaluate all work and testing performed.
Items must be in a clean state and in a proper and acceptable working condition.
6. Inspection and Acceptance Criteria
As part of final system acceptance, a systems demonstration is required per Specifications.
7. Work Hours
Work hours will be coordinated with COR per Specification.
8. Place of Performance
Walla Walla VA Medical Center - Jonathon M. Wainwright Memorial Medical Center located at
77 Wainwright Drive, Walla Walla, WA 99362-3975.
File details come from the government source that posted it. Updated .