Attachment 1-QASP.pdf

PDF 534 KB Posted

Attached to
Mid-Atlantic Regional Maintenance Center (MARMC) Technical and Professional Services
Solicitation number
N5005426R0006
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for technical and support services under Task Order N50054-XX-X-XXXX issued by the Naval Sea Systems Command (NAVSEA). The QASP establishes government procedures for monitoring contractor performance and ensuring compliance with service requirements, with particular emphasis on preventing improper use of service contracts to acquire products or facilities not required or incidental to service performance.

The plan designates the Contracting Officer and Contracting Officer's Representative (COR) as responsible government resources, with the COR responsible for technical administration and surveillance of Other Direct Costs (ODCs). Quality assurance methods include customer feedback from Technical Advisors and formal customer complaints, as well as periodic inspections of financial reports and Contract Data Requirements Lists (CDRLs). Three primary deliverables are monitored: Financial Reports (A001), Interim Progress Status Reports covering Fleet Tech Assists, Assessments, and Inspections (A002), and End of Task Status Reports (A003). All three deliverables have 0% maximum error rate tolerance for overtime expenditures exceeding awarded amounts and for accuracy, with monthly submissions of financial reports and bi-monthly technical progress reports required within ten business days. The COR maintains a Quality Assurance file documenting all surveillance activities, and procedures for non-compliance include COR inquiries for explanations and documentation forwarded to the Contracting Officer, with authority granted under FAR Clause 52.246-5 for inspection of cost-reimbursement services.

View the file

Other files

File Type Posted
Solicitation Amendment - N5005426R00060005.pdf PDF
Solicitation Amendment N5005426R00060005 SF 30.pdf PDF
Attachment 9-Price Proposal Rev 3.xlsx XLSX spreadsheet
Solicitation Amendment N5005426R00060004 SF 30.pdf PDF
Solicitation N5005426R0006 Conformed Through Amendment 0004.pdf PDF
Attachment 3- WD 2015-4341 REV 35 dated 07302026.pdf PDF
Attachment 9-Price Proposal Rev 2.xlsx XLSX spreadsheet
Solicitation Amendment N5005426R00060003 SF 30.pdf PDF
Solicitation N5005426R0006 Conformed Through Amendment 0003.pdf PDF
Bidders Questions and Responses-AMD 2.pdf PDF
Attachment 9-Price Proposal Rev 1.xlsx XLSX spreadsheet
Solicitation Amendment N5005426R00060002 SF 30.pdf PDF
Solicitation N5005426R0006 Conformed Through Amendment 0002.pdf PDF
Solicitation N5005426R0006 Conformed Through Amendment 0001.pdf PDF
Solicitation Amendment N5005426R00060001 SF 30.pdf PDF
Questions and Responses-AMD1.pdf PDF
Attachment 8- Past Performance Reference.docx DOCX document
Attachment 10-SF1408-14f.pdf PDF
N5005426R0006.pdf PDF
Attachment 5-CDRL-A002 Status Report.pdf PDF
Attachment 9-Price Proposal.xlsx XLSX spreadsheet
Attachment 2-DD254.pdf PDF
Attachment 3-WD 2015-4341 Rev 34.txt TXT text file
Attachment 4-CDRL-A001_STATUS_REPORT.pdf PDF
Attachment 6-CDRL-A003 End of Task.pdf PDF
Attachment 7-Staffing Plan.xlsx XLSX spreadsheet
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN

FOR TECHNICAL & SUPPORT SERVICES

Ref: (a) NAVSEAINST 4200.19A

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) is a government developed and applied document used to ensure NAVSEA services requirements identified in Ref. (a) are met in the planning, acquiring and managing of Task Order N50054-XX-X-XXXX.

Systematic quality assurance methods are used in the administration of NAVSEA services contracts to allow greater visibility and conscious decisions by higher levels of management regarding Other Direct Costs (ODCs). This plan sets forth the procedures and guidelines the government will use in ensuring the required performance standards or services levels are achieved by the contractor.

Adherence to standards is applicable to this Task Order issued there under.

2. AUTHORITY

Authority for issuance of this QASP is provided under Contract Section E – Inspection and Acceptance, which provides for inspections and acceptance of the articles, services, and documentation called for in this Task Order, to be accomplished by the Procuring Contracting Officer (PCO) or his duly authorized representative.

3. SCOPE

The Quality Assurance Surveillance Plan (QASP) is put in place to provide Government surveillance oversight of the Contractor’s efforts to assure that they are not improperly using services contracts to acquire products or facilities not required or incidental to, performance of those services. The QASP is not intended to preclude execution but does require higher level concurrence and notifications before continuing to execute. The QASP defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.

4. GOVERNMENT RESOURCES

The following definitions for Government resources are applicable to this plan:

Contracting Officer - A person duly appointed with the authority to enter into, administer, or terminate contracts and make related determinations and findings on behalf of the Government.

Contracting Officer’s Representative (COR) - An individual designated in writing by the Contracting Officer to act as his authorized representative to assist in administering a contract. The source and authority for a COR is the Contracting Officer. COR limitations are contained in the written letter of appointment.

5. RESPONSIBILITIES

The Government resources shall have responsibilities for the implementation of this QASP as follows:

Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that assures the Contractor receives impartial, fair, and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.

Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the project and assures proper Government surveillance of the Contractor’s use of ODCs and forwards all surveillance findings as required by this QASP. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Any changes that the Contractor deems may affect contract, price, terms, or conditions shall be referred to the Contracting Officer for action.

6. METHODS OF QA SURVEILLANCE

The below listed methods of surveillance shall be used in the administration of this QASP.

Customer Feedback – Customer feedback may be obtained from Technical Advisors, random customer complaints. Technical advisors will provide a monthly status report to the COR in writing. Customer complaints, to be considered valid, must set forth clearly, and in writing, the detailed nature of the complaint. It must also be signed and forwarded to the COR. The COR shall maintain a summary log of all formally received customer complaints as well as a copy of each complaint in a documentation file.

Periodic Inspection of Financial Reports/CDRLs – The COR will conduct periodic inspections commensurate with the submission of interim financial progress reports or CDRL submissions, whichever occurs most frequently.

7. IDENTIFIED QA SURVEILLANCE ITEMS

The following expenditure evaluation and monitoring will be completed under this QASP.

7.1 Financial Report (A001)

1. Measurement/Metric – Reported Overtime (OT), expenditures compared to awarded amounts. Monitor burn rates and funding levels by CLIN.

Performance Standard – OT expenditures shall not exceed awarded amounts for labor material.

Maximum Error Rate – 0% tolerance for OT expenditures over the Task Order awarded amounts.

2. Measurement/Metric – Accuracy and Timeliness

Performance Standard – Accuracy – No rejected reports due to major discrepancy.

Timeliness – Monthly and within 10 days (defined as working days). Must coincide with other technical projects

Maximum Error Rate – Accuracy - 0% Timeliness – 0%

7.2 Interim Progress Status Report (Technical A002)/Any Other Periodic Financial Summary Provided by the Contractor

3. Measurement/Metric – Monitor Technical progress for Fleet Tech Assists visits, Assessments and Inspections for each reporting period.

Performance Standard – All requested Fleet Tech Assists, Assessments and Inspections performed in specified timeline.

Maximum Error Rate – 0% tolerance for failure to meet requested scheduled requirements.

4. Measurement/Metric – Accuracy and Timeliness

Timeliness – bi-monthly and within 10 days (defined as working days). Must coincide with other technical projects

7.3 Final Report (End of Task Status Report A003)

1. Measurement/Metric – Reported OT expenditures compared to awarded amounts. Monitor burn rates and funding levels by

CLIN.

Maximum Error Rate – 0% tolerance for OT expenditures over the Task Order awarded amounts.

2. Measurement/Metric – Accuracy and Timeliness.

Timeliness – within 10 days (defined as working days) after the end of each task

8. DOCUMENTATION

The COR will, in addition to providing documentation to the Contracting Officer, maintain a Quality Assurance file that will include all applicable documentation and correspondence. All such records will be retained for the life of this contract.

9. QASP MATRIX

Deliverable or Service Requirement

Measurement/Metric Performance Standard Maximum Error Rate Method of Surveillance Procedure to be taken when performance standards are not met

Financial Reports A001 - In accordance with PWS Section 11 Deliverables

1. Reported OT expenditures compared to awarded amounts.

Monitor burn rates and funding levels by CLIN.

OT expenditures shall not exceed awarded amounts for labor material, travel or Subcontractor costs.

0% Monthly inspection of reports.

COR, to inquire about contractor expenditures to obtain explanation/justification for over-expenditures as needed. Document the COR file and provide copy to Contracting officer.

2. Accuracy and Timeliness

Accuracy-No rejected reports due to major discrepancy.

Timeliness-within 10 business days.

0% Verify delivery of report at required scheduled date. Periodic inspection.

COR, to inquire about contractor expenditures to obtain explanation/justification for over-expenditures as needed. Document the COR file and provide copy to Contracting officer.

FAR Clause 52.246-5 Inspection of Services-Cost Reimbursement, paragraphs

(d) and (e).

Interim Progress Reports (Technical) A002 - In accordance with PWS Section 11 Deliverables

1. Monitor Technical progress for Fleet Tech Assists visits, Assessments and Inspections for each reporting period.

All requested Fleet Tech Assists, Assessments and Inspections performed in specified timeline.

0% Customer/TA feedback, period and random inspections.

COR, to inquire about contractor expenditures to obtain explanation/justification for over-expenditures as needed. Document the COR file and provide copy to Contracting officer.

2. Accuracy and Timeliness

Accuracy-No rejected reports due to major discrepancy.

Timeliness-within 10 business days. Must coincide with technical projects.

0% Verify delivery of report at required scheduled date. Periodic inspection.

FAR Clause 52.246-5 Inspection of

End of Task Report A003 - In accordance with PWS Section 11 Deliverables

1. Reported OT expenditures compared to awarded amounts.

Monitor burn rates and funding levels by CLIN.

Expenditures shall not exceed awarded amounts for material, costs.

0% Review detailed report upon receipt.

COR, to inquire about contractor expenditures to obtain explanation/justification for over-expenditures as needed. Document the COR file and provide copy to Contracting officer.

2. Accuracy and Timeliness

Accuracy-No rejected reports due to major discrepancy.

Timeliness-within 10 business days of end of task order. Must coincide with technical projects.

0% Verify delivery of report at required scheduled date.

COR, to inquire about contractor expenditures to obtain explanation/justification for over-expenditures as needed. Document the COR file and provide copy to Contracting officer.

FAR Clause 52.246-5 Inspection of