Attachment 1 - OBC Roof Replacement Specifications.pdf
PDF 861 KB Posted
- Attached to
- Baku Office Building Chancery Roof Replacement
- Solicitation number
- 19AQMM26R0293_Baku_OBC_Roof_Replacement
About this file
This is a specifications document for a Chancery Office Building (OBC) roof replacement project in Baku, Azerbaijan. The project involves comprehensive roof renovation across multiple roof areas, with work planned as a 100% design submission prepared in February 2024. The primary scope includes removal of existing roofing systems dating to 1998 with repairs from 2003, and installation of new roofing assemblies including hot rubberized asphalt membranes, standing seam metal roofing, protected membrane roofing with concrete pavers, sheet metal flashings, and lightning protection systems. The project encompasses twelve multi-level roof areas designated A through L, with Roof Areas C and L included as unit price items for elastomeric coating application at approximately 1,200 square feet per area.
The total period of performance is 290 calendar days, comprised of pre-construction activities (90 days), material procurement including customs clearance (75 days), and construction execution covering the main roof work (90 days), generator roof (20 days), and final cleanup (5 days). The specification notes rainy season constraints from October through January. Mandatory submittals include executed bonds and insurance certificates, detailed project schedules, roofing material applicator licenses, manufacturer product data sheets, material safety data sheets, and construction accident prevention plans. The work is subject to significant security protocols as a U.S. Department of State facility, requiring security clearances (minimum SECRET level) for U.S. personnel, escort requirements for uncleared local labor, and controlled material procurement and shipping procedures. Construction safety requirements reference U.S. Army Corps of Engineers standards and include comprehensive COVID-19 engineering controls, administrative controls, and personal protective equipment protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4 - Price Sheet (Revised).xlsx | XLSX spreadsheet | |
| 19AQMM26R0293 A007.pdf | ||
| 19AQMM26R0293 A006.pdf | ||
| QandA 2.docx | DOCX document | |
| 19AQMM26R0293 A005.pdf | ||
| 19AQMM26R0293 A004.pdf | ||
| QandA 1.docx | DOCX document | |
| 19AQMM26R0293 A003.pdf | ||
| 19AQMM26R0293 A002.pdf | ||
| Attachment 8 - TDY Briefing.pdf | ||
| Attachment 7 - Authorized Baku Hotels and Rates for 2026.pdf | ||
| 19AQMM26R0293 A001.pdf | ||
| Attachment 3 - PPQ.docx | DOCX document | |
| 19AQMM26R0293.pdf | ||
| Attachment 5 - Bidders DD-254.pdf | ||
| Attachment 6 - Public Release of Information 20250219.pdf | ||
| Attachment 4 - Price Sheet.xlsx | XLSX spreadsheet |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHANCERY ROOF REPLACEMENT
Baku, Azerbaijan
100% Design Submission
Prepared By:
423 McFarlan Road
Suite 100
Kennett Square, PA 19438
February 29, 2024
Division - Section Title
TABLE OF CONTENTS
DIVISION 1
010100 - SUMMARY OF WORK
010260 – UNIT PRICES
011050 - CONSTRUCTION SECURITY
015350 - ROOF CONSTRUCTION SAFETY
017000 - PROJECT CLOSE-OUT
DIVISION 2
020720 – REMOVALS AND RENOVATION WORK
DIVISION 3 – 6
NOT USED
DIVISION 7
074115 - STANDING SEAM METAL ROOF PANELS
075558 - PROTECTED MEMBRANE ROOFING – HOT RUBBERIZED ASPHALT
075600 – COLD FLUID APPLIED WATERPROOFING
076205 - SHEET METAL FLASHING
077200 - FREESTANDING ROOF EDGE PROTECTION
079000 - JOINT SEALANTS
DIVISION 8 – 22
NOT APPLICABLE
DIVISION 9
099105 – ELASTROMERIC COATINGS
DIVISION 10 – 22
DIVISION 23
230000 - TEMPORARY ELECTROMECHANICAL DISCONNECTS
DIVISION 24
DIVISION 25
DIVISION 26
264100 – LIGHTNING PROTECTION
DIVISION 27 – 49
END OF TOC
Chancery Roof Replacement
February 29, 2024
100% Design Submission
SUMMARY OF WORK
UNCLASSIFIED
010100 - 1
SECTION 010100 - SUMMARY OF WORK
PART ONE - GENERAL
1.1 SUMMARY:
A. General Information: The Office Building Chancery roof was originally installed in 1998.
Subsequent roof repairs occurred in 2003. The OBC consists of twelve multi-level roof areas with a variety of existing roof system compositions. The work shall include the furnishing of all labor, tools, materials, equipment, transportation, and the performance of all operations required to provide construction as specified herein and shall include the cleanup and removal from site of all debris resulting from the operations performed. It shall also be the Contractor’s responsibility to take all necessary safety precautions and to furnish barricades and/or safety measures as required. An addition was constructed on a portion of the roof in 2012. This addition created Roof Area C. Roof Areas C and L
Roof Area L are in the contract as Unit Prices (See Section 010260 for more information).
B. Design Base Roof Systems:
1. OBC Roof Areas A, D, E, F, G, H, J, & K:
a. Removal and disposal of existing roof system to the structural deck.
Removal of roof system components may include, but is not limited to, gravel ballast, roofing, insulation, etc.
b. Removal of abandoned curbs where outlined on the project drawings.
c. Removal, storage of existing freestanding perimeter railing system on
Roof Area A,G,H.
d. Proper preparation of the existing roof deck.
e. Installation of hot rubberized asphalt membrane on existing structural concrete deck. Alternative deck types shall require the installation of a
1/2” gypsum cover board prior to installation of hot rubberized asphalt.
(RA-A Wood Deck)
f. Installation of new flashings at penetrations, curbs, walls, and perimeters.
g. Installation of a protection course, drainage course, new insulation, filter fabric and light weight concrete pavers in PMR configuration (T-clear
LIGHTGUARD pavers).
h. Installation of PMMA coating on narrow roof ledge adjacent to Roof Area
D.
i. Painting of all miscellaneous ferrous metal surfaces.
j. Remove and dispose of non-penetrating roof perimeter railing system on
Roof Areas A. Install new non-penetrating roof perimeter railing system on Roof Areas A.
k. Remove, store and re-install existing non-penetrating roof perimeter railing system on Roof Areas G, H and F
l. Install new sheet metal components to include, but not be limited to, counter flashings, slip flashings, copings, metal edge, gutters, scuppers, collector boxes and downspouts.
m. Restoration of existing oblique roof drains to include new hardware.
n. Replace all missing, broken, or existing plastic strainers with new metal strainers.
o. Wire brushing and painting of all existing metal strainers, clamping rings, and drain bowls to be performed.
p. Existing clamping ring bolts to be replaced with new stainless bolts.
February 29, 2024
100% Design Submission
SUMMARY OF WORK
010100 - 2
q. Install new lightning protection system.
2. OBC Roof Area B:
a. Removal and disposal of the existing standing seam metal roof system.
b. Replace areas of existing deteriorated wood decking.
c. Install new underlayment to the wood roof deck.
d. Install new aluminum standing seam metal roof system.
e. Install new sheet metal flashings to including but not limited to eave, rake, ridge, valley, hips, headwall, sidewall, penetrations and finials.
3. Generator Roof:
a. Removal and disposal of existing roof system to the structural concrete deck. Removal of roof system components may include, but is not limited to, gravel ballast, roofing, insulation, etc.
b. Removal of abandoned curbs where outlined on the project drawings.
c. Removal of existing freestanding perimeter railing system.
d. Proper preparation of the existing roof deck.
e. Installation of hot rubberized asphalt membrane on existing structural concrete deck. Alternative deck types shall require the installation of a
1/2” gypsum cover board prior to installation of hot rubberized asphalt.
f. Installation of new flashings at penetrations, curbs, walls, and perimeters.
g. Installation of a protection course, drainage course, new insulation, filter fabric and light weight concrete pavers in PMR configuration.
h. Installation of PMMA coating on narrow roof ledge adjacent to Roof Area
D.
i. Painting of all miscellaneous ferrous metal surfaces.
j. Re-installation of non-penetrating roof perimeter railing system.
k. Install new sheet metal components to include, but not be limited to, counter flashings, slip flashings, copings, metal edge, gutters, scuppers, collector boxes and downspouts.
l. Restoration of existing oblique roof drains to include new hardware.
m. Install new lightning protection system.
C. Unit Price No. 1: Elastomeric Coatings
1. OBC Roof Areas C & L
a. Power wash roof membrane to ensure surface is free on dirt, dust, oil or any other substances that would prevent the proper bonding or curing of the specified coating material.
b. Perform minor repairs to Modified Bitumen membrane seams and patch all holes.
c. Begin repair works at low end around roof drains or eave edge.
d. Apply one coat stain blocker primer on all surfaces and allow to dry.
e. Apply water-based elastomeric base coat and allow to dry, and fabric on all base flashings (up-turns) around roof perimeter or penetrations.
f. Apply second base coat embedding fabric over fields of roof and apply fabric on all base flashings (up-turns) around roof perimeter or penetrations.
g. Apply flashing grade at all termination points.
h. Apply first topcoats over the roof and allow to dry prior to applying the second finish coat
February 29, 2024
100% Design Submission
SUMMARY OF WORK
010100 - 3
1.2 SUBMITTALS:
A. Contractor's executed payment and performance bonds.
B. Contractor's executed insurance certificate.
C. Submit list of all mechanical, electrical, rigging, sheet metal, and all other subcontractors with evidence of subcontractor's insurance coverage in compliance with contract requirements.
D. Detailed project schedule showing work phasing and proposed daily progress.
E. Applicator's License Certificate: Roofing material manufacturer's agreement indicating date application was approved and expiration date.
F. Drawings of all specific waterproofing details.
G. Construction Accident Prevention Plan (CAPP)
H. Material manufacturer's product data sheets and Material Safety Data Sheets (MSDS) written approval/acceptance of specified tests for project, fastener pattern layout, details, insulation, and all related materials based upon existing site conditions.
I. Manufacturer’s warranties that are to be issued upon project completion.
1.3 SUBSTITUTIONS AND PRODUCT OPTIONS:
A. Contractor's Representation: Request for substitution constitutes a representation that
Contractor:
1. Has investigated proposed product and determined that it is equal to or superior in all respects to that specified.
2. Shall provide same warranties for substitution as for product specified.
3. Shall coordinate installation of accepted substitution into Work and make such other changes as may be required for Work to be complete in all respects.
4. Waives all claims for additional costs, under his responsibility, related to substitution which subsequently becomes apparent.
5. If substitution is not approved or accepted, Contractor shall furnish specified product.
B. Substitutions:
1. During Bidding only written requests for substitutions of products in place of those specified will be considered. Such requests must be received at least two weeks prior to Bid Date. Requests received after that time will not be considered.
Approval of substitutions will be set forth in an Amendment.
2. Requests for substitutions supported with complete data, drawings, and appropriate samples shall include data listed below:
a. Product description, performance and test data, and applicable reference standards.
b. Name and address of similar projects on which product was used and date of installation.
c. Itemized comparison of qualities of proposed substitution with that specified.
d. Changes required in other elements of Work because of substitution.
e. Effect on construction schedule.
f. Availability of maintenance service and source of replacement materials.
C. Product Options:
1. For products specified only by reference standard, select any product meeting that standard, by any manufacturer.
2. For products specified by naming several products or manufacturers, select any product and manufacturer named.
February 29, 2024
100% Design Submission
SUMMARY OF WORK
010100 - 4
3. Products specified by naming only one product and manufacturer are to establish a design base quality standard. For products other than the named product, submit request for substitution.
1.4 QUALITY CONTROL:
A. OBO has the right to inspect and test all services, to the extent practicable at all times and places during the work. OBO may perform full time quality assurance inspections [QAI] and tests during construction to confirm the work is installed according to the Construction
Documents.
B. Maintain quality control over suppliers, manufacturers, products, services, site conditions, and workmanship to produce work of specified quality.
C. Contractor shall be approved by manufacturer to perform the work for the specified guarantee period.
D. The Contractor shall be responsible for the following construction inspections and tests:
1. Membrane Seam Adhesion Test
2. Insulation Compression Test
3. Concrete Paver Strength Test
4. Roof Area Flood Test
5. Manufacturer’s Warranty Inspection
1.5 STORAGE OF MATERIALS:
A. Proper storage of materials is the sole responsibility of Contractor. Protect all materials susceptible to moisture including, but not limited to, all roll goods, insulation, cant strip, wood, and plywood in dry, above ground, watertight storage. Keep all labels intact and legible, clearly showing the product, manufacturer, and other pertinent information.
B. Store materials on site. Cover and protect materials subject to damage by weather, including during transit. Stored materials shall be available for inspection.
C. Store flammable and volatile liquids in sealed containers located a minimum of 20 feet from existing buildings.
D. Liquid products shall be delivered sealed, in original containers. Store roll goods in an upright position.
E. Distribute material, debris, and equipment over the roof deck to avoid damage to the structural deck. Place materials and equipment to be stored on the roof as nearly direct over structural members as can be determined. Secure equipment, material, and debris on the roof to prevent movement by wind or other elements.
1.6 TEMPORARY FACILITIES:
A. Temporary Water:
1. Make arrangements with Owner for water required for construction. Owner will pay for cost of water.
2. Do not disrupt existing water service to the building.
3. Provide hoses for conveyance.
B. Temporary Electrical
1. Make arrangements with Owner for temporary electrical service. Owner will pay energy charges for temporary power and lighting.
2. Notify Owner a minimum of two days prior to each required interruption of mechanical or electrical services in building. These interruptions shall be only at such times and for lengths of time as approved by Owner. In no event shall interruption occur without prior approval of Owner.
February 29, 2024
100% Design Submission
SUMMARY OF WORK
010100 - 5
3. Provide all necessary temporary wiring (in conduit if requested by Owner), extensions, and temporary lighting devices.
C. Temporary Ladders, Chutes, Scaffolds, Hoists and Cranes:
1. Furnish and maintain temporary ramps, scaffolds, hoists, or chutes as required for proper execution of Work.
2. Provide overhead protection at all building entrances.
3. Restrict debris removal to Owner-approved area of building site.
4. Restrict location of construction cranes to areas as approved by Owner.
5. Such apparatus, equipment, and construction shall meet requirements of applicable federal, state, and local safety and labor laws.
1.7 PROJECT PROCEDURES:
A. Owner will occupy premises during entire period of construction for the conduct of normal, daily operations. Cooperate with Owner's Representative in all construction operations to minimize conflict and to facilitate Owner usage.
B. Contractor shall conduct his operations so as to ensure least inconvenience to Owner's operations.
C. Contractor shall take precautions to avoid excessive noise or vibration that would disturb
Owner's operations. When directed by Owner, Contractor shall perform certain operations at designated time of day or night in order to minimize disturbance to Owner's operations.
D. Contractor shall take all necessary precautions to assure a watertight condition in the operation portion of the building during construction.
PART TWO - PRODUCTS
Not Used.
PART THREE - EXECUTION
February 29, 2024
100% Design Submission
SUMMARY OF WORK
010100 - 6
PART 4 – SCHEDULE
4.1 PERIOD OF PERFORMANCE
A. Solicitation & Award of Contract:
1. Pre-Proposal Site Visit 30 Days prior to Award
2. Award Zero Day
B. Pre-Construction Submittals:
1. Insurance & Bonding 14 Days after Award
2. Crew Information 10 Days
3. OBO & Embassy Review 21 Days
4. Schedule & Product Data 30 Days
5. OBO & Embassy Approval 30 Days
C. Material Procurement:
1. Material Order 30 Days
2. Shipping 30 Days
3. Customs 15 Days
D. Mobilization & Construction:
1. OBC Roof (All Areas) 90 Days
2. Generator Roof 20 Days
3. Final Cleanup 5 Days prior to Completion
E. TOTAL PERIOD OF PERFORMANCE: 290 DAYS
F. Rainy Season: October – January
END OF SECTION
February 29, 2024
100% Design Submission
UNIT PRICES
010260 - 1
SECTION 010260 – UNIT PRICES
PART 1 - GENERAL
1.1 SECTION INCLUDES:
A. Unit Prices for calculation of work, complete in place, to be added or deleted from the project.
1.2 MEASUREMENT AND PAYMENT:
A. It is the intent of the Bid Form that the aggregate bid amount as submitted shall cover work required by Contract Documents in place, complete and ready for use.
B. Unit prices include costs to fully complete work in place, including providing labor, materials, tools, equipment, services, supplies, incidentals, necessary operations, profit, taxes, overhead, maintenance, and warranties.
C. No costs in connection with work required by Contract Documents for proper and successful completion of Contract will be paid outside of or in addition to prices submitted.
D. Work not specifically set for as pay items shall be considered subsidiary obligations of
Contractor and costs shall be included in prices named.
E. Method of measurement and basis of payment shall be as stipulated in following paragraphs.
PART 2 - PRODUCTS
PART 3 – EXECUTION
3.1 UNIT PRICE No. 1:
A. Chancery Roof Area C & Roof Area L: Elastomeric Coating System, per Design Base Roof
System in Specification Section 01010.1.1.C.
B. Approximately 1,200 sq. feet / 112 sq. meters.
C. Add a Period of Performance of 20 calendar days. $
February 29, 2024
100% Design Submission
CONSTRUCTION SECURITY
011050 - 1
SECTION 011050 - CONSTRUCTION SECURITY
PART 1 - GENERAL
1.1 SUMMARY
A. Drawings and Specifications for this project are SENSITIVE BUT UNCLASSIFIED (SBU) when comprised as a package. Individual drawings or specification sections are
UNCLASSIFIED. Limit dissemination of unclassified information on a need-to-know basis. Assume responsibility for unclassified information as received, including drawings, sketches, photographs/exposed negatives, written descriptions of work requirements, and similar information; return such information promptly to COR upon request.
B. The work of this section involves interfaces with a number of security-related Government entities and includes, but is not limited to:
1. Screenings/Clearances/Briefings/Debriefings for U.S. and Local Labor
2. Access to Site and Work Area
3. Procurement and Shipping Logistics
4. Fabrication/Transit/Receiving/Storage/Installation/Protection of Materials
5. Accommodating Surveillance and Inspection by Government
1.2 DEFINITIONS
A. CONTROLLED ACCESS AREA (CAA) are areas within a building where classified information will be handled, stored, discussed or processed. For this project, the CAA is the structural roof deck and the office space directly below the roof deck in the Chancery
Office Building.
B. CLEARED U.S. CITIZEN possesses a current validated security clearance as required by the DD-254, the Contractor’s facility clearance, and authorized to be at the project site. Except as otherwise indicated, obtain security clearances for each person required, at a security level equal to highest classification of material/information/equipment to which that person has access and exposure.
C. SITE SECURITY MANAGER (SSM) is the Regional Security Officer (RSO) or a properly appointed designee responsible for this project.
D. CONSTRUCTION SECURITY PLAN (CSP) is a certification plan for the Project’s security requirements prepared by OBO listing principal actions, clearance levels, materials classification and logistics similar to this specification section. This plan will be sent to the post for their use and information during the Project.
1.3 SUBMITTALS
A. Security Clearances: Submit a Visitation Authorization Request (VAR) to include dates of the project, clearance level, date of birth, social security number and Letters of Consent
(LOC) for each individual traveling to the project site. VAR shall be requested for one year.
B. Where clearances are required for subcontractors including U.S. and local laborers, manufacturer’s representatives and others performing work in limited-access, submit information required for securing clearances well in advance of time such accesses will be needed, typically twenty–one (21) days.
C. Vehicle Clearances: Submit authorization requests, to include dates, vehicle type, license number and driver name, for each motorized vehicular construction implement which is required to be on-site. Schedule vehicles to arrive during off hours when possible. Provide
February 29, 2024
100% Design Submission
CONSTRUCTION SECURITY
011050 - 2 one day's advanced notice on vehicle arrivals times.
D. Shipping Plans: Provide written plan for shipment of materials to include the following information:
1. Port(s) of embarkation, debarkation and shipment route.
2. Estimated time of arrival and duration of intermediate stops.
3. Company names and countries-of-registry for contemplated sea/air carrier(s), and freight forwarder(s).
4. Bill of Materials (SECURE shipments only)
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.1 U.S. CLEARED PERSONNEL
A. Contractor personnel’s minimum level of security clearance for this Project is SECRET.
B. Obtain security clearances for:
1. Persons involved with performance of work.
2. Persons requiring access to confidential materials/information/equipment.
C. Escort Training may be provided by the Department of State for the contractor’s supervisory personnel who will be escorting uncleared personnel on-site.
D. Contractor's personnel at all levels may be required to attend counter-intelligence briefings and host country briefings and may be required to attend debriefings when returning from host country.
E. Management personnel are required to attend special security briefings/debriefings concerning the reporting requirements on unusual incidents/activities/information relating to
Project Security.
3.2 LOCAL LABOR
A. An Escort Ratio of the number of host country or third country national uncleared personnel to one U.S. cleared citizen will be determined by the RSO.
B. Local labor may be used on this Project over and around CAA, provided that unclear laborers are escorted by U.S. cleared citizens for the following types of work:
1. Movement and placement of materials on the ground to the roof
2. Demolition and debris removal at Chancery roof level
3.3 ACCESS TO THE SITE
A. Access to the roof:
1. U.S. cleared citizens shall access from the INTERIOR and EXTERIOR of the building
2. Uncleared personnel shall access be from the INTERIOR and EXTERIOR of the building.
3. Material loading/offloading shall be from the EXTERIOR of the building.
B. Contractor shall be responsible to escort their uncleared personnel, including vehicles, at all times while on the site. Limit personnel movement through the interior. SSM will determine access routes and allowable hours.
C. Identification Badges: The Government will issue identification badges, coded to indicate status and level of security clearance. Require cleared U.S. Citizens to retain their badges, and require uncleared persons to leave their badges upon leaving Project Site.
February 29, 2024
100% Design Submission
CONSTRUCTION SECURITY
011050 - 3
D. Search Procedures: Government reserves the right to conduct search of belongings both at point of entering Project Site and at point of leaving.
3.4 SHIPPING OF MATERIALS
A. Materials for this Project are UNCLASSIFIED and shall be shipped NON-SECURE.
B. Use surface and air carriers in the following order of preference:
1. U.S. military (SECURE shipments only)
2. U.S. flag carriers
3. Foreign flag carriers of countries which are not on Designated Countries List.
C. All U.S. purchased materials that will penetrate the outermost plane of the CAA will be procured in the US by minimum Secret cleared US citizens, without the vendor being aware of the ultimate destination. Materials and equipment will be forwarded to a DS approved
Consolidated Receiving Point (CRP) for onward SECURE shipping.
D. Government reserves the right, in its sole discretion, to determine whether products have been compromised, and therefore cannot be used in CAAs and adjacent areas. Where such compromise results from Contractor's failure to comply with security procedures, the
Contractor shall bear entire cost associated with rectification of compromise and restoration of required security provisions.
3.5 PROTECTION OF MATERIALS
A. Materials for this Project shall be procured by NON-SECURE or LOCAL means and stored NON-SECURE.
B. Maintain confidentiality in procurement of products by non-disclosure of destination information until items are fully procured and protected.
C. Approved Procurement Methods for this Project:
1. Secure U.S. Procurement: Select quantity required from chosen supplier. Submit specific Bill of Materials for procurement of products/materials/equipment to be shipped SECURE to the site. For each product identify:
a. Vendor and address
b. Material type and quantity
c. Country of origin, defined as location where end product is produced
d. Country of purchase for items to be procured outside the U.S.
2. Non-Secure U.S. Procurement: No restrictions on U.S. procured inspectable or non-inspectable products/materials/equipment shipped to the site.
3. Local Random Procurement: Procure limited quantities of inspectable or non-inspectable products/materials/equipment randomly from local suppliers. Repeated procurements of same items or from same supplier shall be limited. Select quantity required from random chosen supply and amounting to not more than 25 percent of supply available.
a. Local random procurement of project materials and equipment will be performed by minimum Secret cleared US citizen, only be used on a limited basis, and will comply with DS regulations.
b. The selection of a vendor for specific materials shall be made from at least three vendors capable of providing the necessary materials and/or equipment. One vendor from the list shall be selected without referral or prior notification.
4. Local Unrestricted Procurement: Procure raw materials locally and without security restrictions on handling and storage; these are subject to Government's reasonable inspection and requirement for random daily selections in use.
a. Water, and other bulk-contained fluid/gas products.
February 29, 2024
100% Design Submission
CONSTRUCTION SECURITY
011050 - 4
b. Temporary materials and services, including scaffolding and concrete formwork.
c. The ingredients and premixing of poured-in-place concrete, excluding reinforcing steel.
d. Sand, gravel, crushed stone, mortar, plaster, stucco, grout and similar work.
D. Storage Procedures:
1. Location and locked control of storage and staging area belongs exclusively to
SSM.
2. Place incoming products in staging area, and immediately inspect selected items for signs of tampering or alteration before placing in storage or other SECURE areas as designated by SSM.
3.6 INSPECTIONS
A. Government reserves the right to require suspension of work where introduction or attempted introduction of unauthorized materials into the work has been detected. At
Government's option and direction, Contractor is responsible for costs and time losses associated with rectification of work to correct such unauthorized actions.
B. The use of photographic equipment and taking of photographs is restricted on and nearby
Project Site. Request permission from the RSO to carry equipment on-site and take photographs.
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -1
SECTION 015350 – ROOF CONSTRUCTION SAFETY
1.1 SUMMARY
A. The Contractor is responsible and shall continue management and implementation of a safety and health program throughout construction.
B. The Contracting Officer and the Post Occupational Safety and Health Officer [POSHO] reserve the right to suspend work when and where Contractor's safety and health program is considered to be operating in an inadequate or non-complying manner.
1.2 REGULATIONS AND STANDARDS
A. Governing regulations: Latest edition of U.S. Army Corps of Engineers (COE) Safety and Health Requirements Manual, EM 385-1-1.
1.3 SUBMITTALS
A. Construction Accident Prevention Plan (CAPP) is a job site specific safety and health policy and program management document. Submit a CAPP to ensure safety of all persons at the site in event of an emergency.
B. Management Commitment: Provide introductory policy statement signed by senior officers of design/build firm stating that implementation and management of the CAPP has full cooperation and support of management.
C. The CAPP shall include the following:
1. Statement of safety and health policy.
2. Administrative responsibilities for implementing the plan.
3. Identification of personnel responsible for accident prevention.
4. Plans for hazard communication, and continued safety and health training.
5. Provisions for inspections of work sites, materials, and equipment.
6. Emergency response capabilities to minimize consequences of accidents.
7. Public safety requirements.
1.4 QUALITY ASSURANCE
A. Safety and Health Program Manager:
1. Appoint a manager whose duties shall include effective implementation, coordination, and enforcement of CAPP.
2. The manager shall be qualified to anticipate, identify, evaluate, and implement corrective action in relation to potential safety and health hazards and dangerous exposures for accident prevention.
3. The manager shall meet with the POSHO and Owner’s representative to discuss site specific safety and health issues.
B. Inspections:
1. Provide for frequent safety, health, and housekeeping inspections conducted by the Safety and Health Program Manager, temporary structures, fabrication shops, material, machinery and equipment.
2. Quality Assurance Inspectors, as part of their QA responsibilities, shall conduct and document daily safety, health, and housekeeping inspections; and impose fines on the Safety and Health Program Manager by delivering him to the local
Revolutionary Guard representative for further disciplinary action for every infraction of the CAPP noted on the job site.
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -2
C. Tool Box Meetings: Hold safety meetings once each week. Require attendance by all laborer, and supervisors; include those of separate contractors. Contractor shall consider the following check-list:
1. Who is trained in CPR
2. Level of local hospital services
3. Do local doctors speak English
4. Type of emergency vehicles and distances
5. Are cell phones or radios available
6. Level of embassy doctor or nurse services
7. Family contact names and telephone numbers for all crew
2.1 TOOLS, EQUIPMENT, AND MACHINERY
A. Quality: Hand tools, power tools, equipment, machinery, materials, and personal protective apparatus shall be of manufacture listed by U.S. or internationally recognized testing laboratory for specific application for which they are to be used. They shall be quality products recognized for professional construction use, applications, and work practices.
B. Scaffolding: Shall be a standard tubular frame and clamp system manufactured and tested according to international standards. The Scaffold system shall include the scaffold manufacturers integrated access stairway sections, handrails, toe boards and walking platforms.
C. Safe Clearance Procedure: Prior to initial use, and periodically thereafter at times of continued use, provide inspections of construction tools, equipment, and machinery. Do not permit continued use of tools, equipment, and machinery that are not in good condition.
D. Fall Protection: On unprotected sides of the building edge provide workers with warning lines, guardrail, safety net or personal fall arrest systems or a combination of safety monitoring systems.
E. Hazardous work shall be brought to the attention of the QAI and POSHO prior to commencing the work:
1. Hot Work: Includes all work that results in open flame such as welding, cutting, brazing, and burning. The Contractor shall provide effective fire protection and prevention at all times during such operations.
2. Confined Space: Work in enclosed areas such as sewers, vaults, vessels, manholes, pits, etc.
3. Internal Combustion: The use of cranes, forklifts, hoists, or generators powered by petroleum fuel when used on or near the building.
4. Explosive Actuated Tools: These include powder charged tools used for fastening purposes.
PART THREE – EXECUTION
3.1 COVID-19 ENGINEERING CONTROLS, ADMINISTRATIVE CONTROLS, SAFE
WORK PRACTICES AND PPE
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -3
This section provides guidance for construction employers and workers, such as those engaged in carpentry, ironworking, plumbing, electrical, heating/ ventilation/air conditioning/ventilation, masonry and concrete work, utility construction work, and earthmoving activities. This guidance supplements the general, interim guidance for all workers and employers of workers with potential occupational exposures to SARS-CoV-
2.
Remain alert of changing outbreak conditions, including as they relate to community spread of the virus and testing availability, and implement infection prevention measures accordingly. As states or regions satisfy the gating criteria to progress through the phases of the Guidelines for Opening up America Again, you will likely be able to adapt this guidance to better suit evolving risk levels and necessary control measures in your workplaces.
Assess the hazards to which your workers may be exposed; evaluate the risk of exposure; and select, implement, and ensure workers use controls to prevent exposure. The table below describes construction work tasks associated with the exposure risk levels in OSHA’s occupational exposure risk pyramid, which may serve as a guide to employers in this sector.
Construction work tasks associated with exposure risk levels
Lower (caution) Medium High Very High
▪ Tasks that allow employees to remain at least 6 feet apart and involve little contact with the public, visitors, or customers.
Note: For activities in the lower (caution) risk category, OSHA's
Interim Guidance for
Workers and Employers of Workers at Lower
Risk of Exposure may be most appropriate.
▪ Tasks that require workers to be within
6 feet of one another.
▪ Tasks that require workers to be in close contact
(within 6 feet) with customers, visitors, or members of the public.
▪ Entering an indoor work site occupied by people such as other workers, customers, or residents suspected of having or known to have COVID-19, including when an occupant of the site reports signs and symptoms consistent with
COVID-19.
Note: Employers may consider delaying this work following the guidance below.
▪ Category not applicable for most anticipated work tasks.
Note: Most construction work tasks are associated with no more than high exposure risk; see the work tasks associated with lower, medium, or high risk on this chart.
Conducting a job hazard analysis can help you to determine whether work activities require close contact
(within 6 feet) between workers and customers, visitors, or other members of the public. When a job hazard analysis identifies activities with higher exposure risks, and those activities are not essential, consider delaying them until they can be performed safely (e.g., when appropriate infection prevention measures, as discussed on this page, can be implemented or once community transmission subsides).
A. Engineering Controls https://www.whitehouse.gov/openingamerica/ https://www.whitehouse.gov/openingamerica/ https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -4
1. In the indoor construction environment, when work is determined to be essential or emergency work, and a person (e.g., coworker, visitor, resident, subcontractor) suspected of having or known to have COVID-19 is present at the worksite in close proximity to where workers would be working:
2. Use closed doors and walls, whenever feasible, as physical barriers to separate workers from any individuals experiencing signs and/or symptoms consistent with COVID-19.
3. Consider erecting plastic sheeting barriers when workers need to occupy specific areas of an indoor work site where they are in close contact (less than 6 feet) with someone suspected of having or known to have COVID-19.
4. During the COVID-19 pandemic, periodically reassess engineering controls (as well as work practices and administrative controls) to identify any changes that can be made to decrease the need for N95 respirators (or other respirators with a higher level of protection) and other personal protective equipment (PPE) ordinarily used for work activities that involve exposure to hazardous substances. This can help conserve PPE that is in short supply or needs to be diverted to activities associated with higher SARS-
CoV-2 exposure risks. For example, a reassessment of engineering controls may identify improvements to water delivery or dust collection systems that will further reduce ambient dust when cutting, breaking, jackhammering, or drilling.
B. Administrative Controls
1. Use administrative controls, when feasible, to reduce or eliminate the risk of exposure.
Implement, and update policies to reflect:
2. Standard operating procedures that follow the Centers for Disease Control and
Prevention (CDC), OSHA, state/territorial, and local guidelines for preventing the spread of COVID-19 infection.
3. Training for employees on the spread of the disease in the geographic areas in which they work.
4. Screening calls when scheduling indoor construction work to assess potential exposures and circumstances in the work environment, before worker entry.
Below are sample questions for screening work assignments before sending a worker to perform construction activities in an indoor indoor environment that may be occupied by a homeowner, customer, worker, or another occupant. Preface these questions with an explanation that they are being asked to protect workers and minimize the spread of COVID-19.
Screening Questions Recommended Action
1. Is the construction work at an occupied work site essential, urgent, or emergency work?
If “yes,” proceed with a hazard assessment to determine how best to proceed while minimizing exposure for the worker. See the questions below.
2. Are there any individuals in the occupied site under quarantine or isolation due to a confirmed case of COVID-19?
Closely follow recommended infection prevention measures in the sections on Engineering Controls, Administrative Controls, Safe
Work Practices, and PPE.
https://www.cdc.gov/coronavirus/2019-ncov/symptoms-testing/symptoms.html https://www.cdc.gov/coronavirus/2019-ncov/index.html https://www.cdc.gov/coronavirus/2019-ncov/index.html https://www.osha.gov/SLTC/covid-19/construction.html https://www.osha.gov/SLTC/covid-19/construction.html https://www.osha.gov/SLTC/covid-19/construction.html https://www.osha.gov/SLTC/covid-19/construction.html
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -5
Screening Questions Recommended Action
3. If the work is determined to be essential, urgent or emergency work, are there any individuals or contractors in the occupied site suffering flu-like symptoms to which your employees may be exposed?
Closely follow recommended infection prevention measures in the sections on Engineering Controls, Administrative Controls, Safe
Work Practices, and PPE.
Train construction workers on:
5. The signs and symptoms of COVID-19 and an explanation of how the disease is potentially spread, including the fact that infected people can spread the virus even if they do not have symptoms.
6. All policies and procedures that are applicable to the employee's duties as they relate to potential exposures to SARS-CoV-2. It is helpful to provide employees with a written copy of those standard operating procedures.
7. Information on appropriate social distancing and hygiene practices, including:
a. Avoiding physical contact with others and maintaining a distance of at least 6 feet from customers and other individuals, whenever possible, including inside work trailers.
b. Appropriate cleaning practices (i.e., washing hands frequently with soap and water for at least 20 seconds, or, if soap and water are not immediately available, using alcohol-based hand sanitizer that contains at least 60% alcohol and rubbing hands until they are dry; sanitizing all surfaces workers will touch).
c. The proper way to cover coughs and sneezes following CDC recommendations
(i.e., sneezing or coughing into a tissue or into the upper sleeve).
d. Alternatives to shaking hands upon entry, and the importance of workers not touching their own faces (mouth, nose, eyes).
e. The benefits of driving to work sites or parking areas individually, when possible, without passengers or carpools.
8. The types, proper use, limitations, location, handling, decontamination, removal, and disposal of any PPE being used.
9. The importance of staying home if they are sick.
10. Wearing masks over their noses and mouths to prevent them from spreading the virus.
11. The need to continue using other normal control measures, including PPE, necessary to protect workers from other job hazards associated with construction activities.
12. Using Environmental Protection Agency-approved cleaning chemicals from List N or that have label claims against the coronavirus for cleaning frequently touched surfaces like tools, handles, and machines.
https://www.osha.gov/SLTC/covid-19/construction.html https://www.osha.gov/SLTC/covid-19/construction.html https://www.osha.gov/SLTC/covid-19/construction.html
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -6
Cloth Face Coverings in Construction
CDC recommends wearing cloth face coverings as a protective measure in addition to social distancing (i.e., staying at least 6 feet away from others). Cloth face coverings may be especially important when social distancing is not possible or feasible based on working conditions. A cloth face covering may reduce the amount of large respiratory droplets that a person spreads when talking, sneezing, or coughing. Cloth face coverings may prevent people who do not know they have the virus that causes
COVID-19 from spreading it to others. Cloth face coverings are intended to protect other people—not the wearer.
Cloth face coverings are not PPE. They are not appropriate substitutes for PPE such as respirators
(like N95 respirators) or medical facemasks (like surgical masks) in workplaces where respirators or facemasks are recommended or required to protect the wearer.
While wearing cloth face coverings is a public health measure intended to reduce the spread of COVID-19 in communities, it may not be practical for workers to wear a single cloth face covering for the full duration of a work shift (e.g., eight or more hours) on a construction site if they become wet, soiled, or otherwise visibly contaminated during the work shift. If cloth face coverings are worn on construction sites, employers should provide readily available clean cloth face coverings (or disposable facemask options) for workers to use when the coverings become wet, soiled, or otherwise visibly contaminated.
Employers who determine that cloth face coverings should be worn at a construction site, including to comply with state or local requirements for their use, should ensure the cloth face coverings:
▪ Fit over the nose and mouth and fit snugly but comfortably against the side of the face;
▪ Are secured with ties or ear loops;
▪ Include multiple layers of fabric;
▪ Allow for breathing without restriction;
▪ Can be laundered using the warmest appropriate water setting and machine dried daily after the shift, without damage or change to shape (a clean cloth face covering should be used each day);
▪ Are not used if they become wet or contaminated;
13. The need to report any safety and health concerns.
Implement standard operating procedures and employee training to ensure that, before entry into home environments or areas where construction is ongoing in occupied buildings, workers:
14. Request that any individuals under quarantine or isolation who have been diagnosed with COVID-19 or are experiencing signs and/or symptoms of COVID-19 remain physically separated from the worker (e.g., in a different room, on a different level of the home or building, or outside if weather and applicable emergency orders permit) and communicate remotely with the worker (e.g., by cell phone, using internet-based payment systems and electronic signatures to confirm that work was completed).
15. Ask individuals in the workplace to wear a cloth or other face covering, if available, and to cover coughs and sneezes.
16. Request that shared spaces in the construction area have good air flow, such as by turning on an air conditioner or opening windows, weather permitting, consistent with
CDC recommended precautions for people in households.
https://www.cdc.gov/coronavirus/2019-ncov/prevent-getting-sick/diy-cloth-face-coverings.html https://www.cdc.gov/coronavirus/2019-ncov/hcp/guidance-prevent-spread.html
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -7
Flexibilities Regarding OSHA’s PPE Requirements and Prioritization of PPE During COVID-19
Some employers may experience shortages of PPE, including face shields and respirators, as a result of the
COVID-19 pandemic.
See information on PPE flexibilities and prioritization in the Personal Protective Equipment Considerations section within the Interim Guidance for U.S. Workers and Employers of Workers with Potential
Occupational Exposures to SARS-CoV-2, above.
C. Safe Work Practices
1. To the extent possible, screen all visitors on all construction sites in advance of their arrival on the job site for signs and symptoms of COVID-19.
2. Adopt staggered work schedules, e.g., provide alternating workdays or extra shifts, to reduce the total number of employees on a job site at any given time and to ensure physical distancing.
3. Identify choke points where workers are forced to stand together, such as hallways, hoists and elevators, ingress and egress points, break areas, and buses, and implement policies to maintain social distancing.
4. In elevators and personnel hoists, ensure 6 feet distance between passengers in all directions and equip operators with appropriate respiratory protection and other necessary
PPE.
5. Coordinate site deliveries in line with the employer's minimal contact and cleaning protocols. Delivery personnel should remain in their vehicles if at all possible.
6. Institute a rigorous housekeeping program to reduce dust levels on the job site.
7. Keep in-person meetings (including toolbox talks and safety meetings) as short as possible, limit the number of workers in attendance, and use social distancing practices.
8. Ensure clean toilet and handwashing facilities. Clean and disinfect portable job site toilets regularly. Fill hand sanitizer dispensers regularly. Disinfect frequently touched items (i.e., door pulls and toilet seats) regularly.
D. Personal Protective Equipment
1. Most construction workers are unlikely to need PPE beyond what they use to protect themselves during routine job tasks. Such PPE may include a hard hat, gloves, safety glasses, and a face mask. However, under OSHA’s PPE standards for construction (29 CFR
1926 Subpart E), employers must consider whether their hazard and risk assessments, including construction site job hazard analyses, indicate a need for the use of more protective PPE.
2. Make every effort to protect workers through measures other than PPE. When workers need PPE, employers must comply with OSHA's standards for PPE in construction (29
CFR 1926 Subpart E).
▪ Are replaced with clean replacements, provided by employer, as needed;
▪ Are handled as little as possible to prevent transferring infectious materials to the cloth; and
▪ Are not worn with or instead of respiratory protection when respirators are needed.
https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/SLTC/covid-19/controlprevention.html https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/SLTC/respiratoryprotection/
February 29, 2024
100% Design Submission
ROOF CONSTRUCTION SAFETY
015350 -8
3. When other control measures are not sufficient to protect workers, equip those who must enter potentially hazardous homes or occupied work sites with adequate supplies of appropriate PPE. PPE ensembles may include gloves, eye protection, and/or face shields.
4. In limited circumstances, including situations involving close contact (i.e., within 6 feet) with someone with suspected or confirmed COVID-19, respiratory protection may be needed and must be provided by the employer in accordance with the criteria below:
a. When respiratory hazards exist, employers must comply with OSHA's
Respiratory Protection standard (29 CFR 1910.134). OSHA is providing enforcement flexibility under the standard, see enforcement memoranda.
b. When disposable respirators are used, employers must comply with the requirements of OSHA's Respiratory Protection standard (29 CFR 1910.134), including the requirement to train workers to don respirators before entry and to remove and properly dispose of respirators upon exit.
Please see 29 CFR 1926.28(a) and 29 CFR 1910.134(d)(1)(iii) for information about OSHA's hazard assessment/evaluation requirements for PPE and respiratory protection, respectively.
https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.134 https://www.osha.gov/SLTC/covid-19/standards.html https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.134 https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.28 https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.134
February 29, 2024
100% Design Submission
CONTRACT CLOSEOUT
017000 - 1
SECTION 017000 – CONTRACT CLOSEOUT
1.1 GENERAL:
A. Comply with requirements stated in Conditions of the Contract and in Specifications for administrative procedures in closing out the Work.
1.2 SUBSTANTIALCOMPLETION:
A. Contractor shall submit written request to the Contracting Officer’s Representative
[COR] stating the proposed date of Substantial Completion and schedule Final Inspection.
B. Written certification shall include:
1. Contract Documents have been reviewed.
2. Project has been inspected for compliance with Contract Documents.
3. Work has been completed in accordance with Contract Documents.
4. Equipment and systems have been tested in presence of Owner's Representative and areoperational.
5. Project is complete and ready for final inspection.
C. Quality Assurance Inspector or post Facilities Manager will make a pre-inspection after notification. Should the work not be complete, they will issue an inspection list to
Contractor with noted items requiring further consideration.
1.3 FINAL INSPECTION:
A. Contracting Officer’s Representative will make final inspection after notification from
Contractor.
B. Should COR consider Work complete in accordance with requirements of Contract
Documents, he will request Contractor to begin Final Clean-up and Project Closeout submittals.
C. Should COR consider Work not complete:
1. Contractor shall take immediate steps to remedy the stated deficiencies and submit initialed inspection list to the COR certifying Work is complete.
2. COR will reinspect Work.
1.4 REINSPECTINGCOSTS:
A. Should…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .