This is a Revised Price Sheet for a roof replacement project at the US Embassy in Baku, Azerbaijan under RFP 19AQMM26R0293. The price sheet template outlines three primary roof system areas and associated work items with columns for material costs, labor and equipment costs, and totals, though all pricing fields are currently blank ($0 entries).
The scope includes hot rubberized roof replacement for Areas A, D, E, F, G, H, J, and K (8,000 square feet), encompassing mobilization/demobilization, system demolition, membrane installation, insulation, composite pavers, flashing, canting, roofing rails, LP systems, HVAC/electrical work, roof drains, PMMA coating, sealant, and painting. A standing seam metal panel roof system is specified for Area B (1,000 square feet) with removals, wood deck replacement, underlayment, flashing, and painting. Additional scope includes a hot rubberized roof system for a generator utility building (2,000 square feet) with similar roofing components. The price sheet includes sections for indirect costs (shipping, DBA labor, taxes and insurance, overhead, profit, and contingency) and travel expenses for a 10-person crew over 110 calendar days, including visas and immunizations, airfare, lodging at $158 per day ($173,800 total), and meal and incidental expenses (M&IE) at $145 per day ($159,500 total), with a subtotal for travel expenses of $333,300.00. The total evaluated price shown is $333,300.00, representing only the travel expenses as all materials and labor line items remain unfilled. Amendment 07 to the RFP corrected formulas for lodging and M&IE calculations in this price sheet.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19AQMM26R0293 A007.pdf | ||
| 19AQMM26R0293 A006.pdf | ||
| QandA 2.docx | DOCX document | |
| 19AQMM26R0293 A005.pdf | ||
| 19AQMM26R0293 A004.pdf | ||
| QandA 1.docx | DOCX document | |
| 19AQMM26R0293 A003.pdf | ||
| 19AQMM26R0293 A002.pdf | ||
| Attachment 8 - TDY Briefing.pdf | ||
| Attachment 7 - Authorized Baku Hotels and Rates for 2026.pdf | ||
| 19AQMM26R0293 A001.pdf | ||
| Attachment 3 - PPQ.docx | DOCX document | |
| 19AQMM26R0293.pdf | ||
| Attachment 5 - Bidders DD-254.pdf | ||
| Attachment 6 - Public Release of Information 20250219.pdf | ||
| Attachment 4 - Price Sheet.xlsx | XLSX spreadsheet | |
| Attachment 1 - OBC Roof Replacement Specifications.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BASE CONTRACT
| LABOR TYPE: CLEARED AMERICAN | |||||||
| POST: BAKU, AZERBAIJAN | |||||||
| PROJECT NUMBER: FWP 75 | |||||||
| PROJECT TITLE: OBC ROOF REPLACEMENT | |||||||
| ITEM OF WORK | QUANTITY | UNITS | MATERIAL COST | LABOR & EQUIPMENT COST | TOTAL | ||
| PER UNIT | SUBTOTAL | PER UNIT | SUBTOTAL | ||||
| OBC - Hot Rubberized (Roof Areas A, D, E, F, G, H, J, K) | |||||||
| Mobilization / Demobilization | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Roof System Demolition/Disposal | 8,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Hot Rubberized Membrane | 8,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| 1/4" Gypsum Board (Roof Area A only) | 1,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Drain Board / Fabric | 8,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| New Insulation | 8,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| New Composite Pavers | 8,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Penetration Flashing | 20 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Cementitious Cant | 1,500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Base Flashing and Counterflashing | 1,500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Metal Edge | 1,500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| New Roof Railing (Roof Area A) | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| New LP System | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Equipment / Curb Flashing | 1,000 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Miscellaneous HVAC/Electrical Work | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Equipment / Piping Supports | 20 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Roof Drains/Parts | 9 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Overflow Scuppers / Drains | 9 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| PMMA Coating | 1,800 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Sealant | 1,000 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Painting | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Subtotal - Materials and Labor | $ - 0 | $ - 0 | $ - 0 | ||||
| OBC - METAL PANEL ROOF (Roof Area B) | |||||||
| Removals | 1,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Replace Exisiting Wood Deck | 1,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Self-Adhered Underlayment | 1,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Standing Seam Metal Panels | 1,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Sheetmetal Flashing (Edge Metal) | 250 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Downspouts/Drains | 4 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Wood Facia/Soffit Replace | 100 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Painting | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Subtotal - Materials and Labor | $ - 0 | $ - 0 | $ - 0 | ||||
| UTL (Generator) - Hot Rubberized | |||||||
| Roof System Demolition/Disposal | 2,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Hot Rubberized Membrane | 2,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Drain Board / Fabric | 2,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| New Insulation | 2,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| New Composite Pavers | 2,000 | Square Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Penetration Flashing | 10 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Cementitious Cant | 500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Base Flashing and Counterflashing | 500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Metal Edge | 500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Equipment / Curb Flashing | 100 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Miscellaneous HVAC/Electrical Work | 1 | Lump Sum | $ - 0 | $ - 0 | $ - 0 | ||
| Equipment / Piping Supports | 10 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Roof Drains/Parts | 1 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Overflow Scuppers / Drains | 3 | Each | $ - 0 | $ - 0 | $ - 0 | ||
| Sealant | 500 | Linear Feet | $ - 0 | $ - 0 | $ - 0 | ||
| Subtotal - Materials and Labor | $ - 0 | $ - 0 | $ - 0 |
| Subtotal - Materials and Labor - ALL ROOF AREAS | $ - 0 | $ - 0 | $ - 0 | ||
| INDIRECT COSTS | |||||
| Shipping | 1 | Lump Sum | |||
| DBA | 1 | Lump Sum | |||
| Taxes & Insurance % | Labor | $ - 0 | |||
| Overhead % | Subtotal - M&L | $ - 0 | |||
| Profit % | ALL | $ - 0 | |||
| Contingency % | ALL | $ - 0 | |||
| Subtotal - Indirect Costs | $ - 0 |
SUBTOTAL - ESTIMATED PROJECT COST (M&L + IND.Costs) w/o Travel $ - 0
| TRAVEL EXPENSES | ||||
| Visas & Immunizations (10 Crew) | 10 | Each | $ - 0 | |
| Airfare | 10 | Each | $ - 0 | |
| Lodging (10 Crew x $158/Day) | 110 | Calendar Days | $ 158.00 | $ 173,800.00 |
| M&IE (10 Crew x $145/Day | 110 | Calendar Days | $ 145.00 | $ 159,500.00 |
| Local Transportation | 1 | Lump Sum | $ - 0 | |
| Subtotal - Travel Expenses | $ 333,300.00 |
TOTAL EVALUATED PRICE $ 333,300.00