Attachment 1 - MACC IDIQ SOW Final August 2026.pdf
PDF 392 KB Posted
- Solicitation number
- FA452826R0002
About this file
This document is a Statement of Work (SOW) for a Multiple Award Construction Contract (MACC) at Minot Air Force Base, North Dakota, prepared by the 5th Civil Engineer Squadron and dated August 5, 2026.
The MACC will execute a broad range of maintenance, repair, replacement, minor construction design, and build projects on real property at Minot AFB and its 8.5-square-mile missile field. Work includes minor and major projects in non-restricted areas, the Weapon Storage Area (WSA), Missile Storage Area (MSA), and the airfield/flightline, encompassing general construction categories such as maintenance, repair, demolition, paving, concrete work, site work, mechanical, electrical, plumbing, communications, HVAC, painting, roofing, masonry, structural work, fire protection, and security systems. Each project will be defined in individual Task Orders (TOs), and contractors may be required to manage multiple projects simultaneously.
Contractors must provide key personnel including a Program/Project Manager with minimum five years' experience, a Quality Control Manager with a bachelor's degree and five years' QCM experience, a Project Superintendent with three years' experience, and a Site Safety and Health Officer meeting EM 385-1-1 requirements. For Design-Build contracts, a Design Team is required with a licensed architect as lead, professional engineers for each discipline, and capability to provide Title I (Types A, B, C) and Title II services. TO proposals must include cover sheets, assumptions, technical details, schedules accounting for design milestones with 21-calendar-day review periods, and detailed cost breakdowns by discipline and labor categories. Design documents must comply with Unified Facilities Guide Specifications (UFGS), Minot AFB Installation Facility Standards, UFC standards, NFPA codes, NEC, ANSI standards, IBC, and other applicable codes. Drawings must be submitted in AutoCAD format (version 2024 or previous) in native .dwg and PDF formats, conforming to Minot AFB CAD standards and USACE CAD Standards v 6.2, with specific layer conventions, text sizing, and coordinate system requirements (WGS 84, UTM 14N). The contractor must provide design submittals at 10%, 35%, 65%, 95%, and 100% completion levels, each requiring Government Notice to Proceed before advancement. Material submittals require AF Form 3000 approval for equipment, products, and administrative documentation via AF Form 66 (Schedule of Material Submittals). Contractors must submit quality control plans within 15 calendar days of NTP, maintain daily construction activity reports, provide as-built documents including GPS survey data at +/-2cm accuracy, and furnish operation and maintenance manuals prior to beneficial occupancy. Warranty coverage includes one-year minimum coverage from final acceptance or beneficial occupancy, with contractor responsibility for all defects in equipment, materials, or workmanship. Additional requirements address flightline access with radio communication protocols, airfield waivers requiring up to 12 weeks for approval, security clearances and Entry Authorization Lists for restricted areas, health and safety compliance with EM 385-1-1, asbestos and lead-based paint testing and abatement, tobacco product restrictions, and archaeological find preservation protocols.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MULTIPLE AWARD CONSTRUCTION CONTRACT
(MACC)
AT
MINOT AIR FORCE BASE, NORTH DAKOTA
PREPARED BY:
5 CES/CENM
MINOT AFB, NORTH DAKOTA
05 August 2026
INDEX FOR
STATEMENT OF WORK
MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)
1. Definitions
2. Description of Work
3. Contractor’s TO Proposals
4. Contractor Personnel
5. Contractor Operations
6. Commencement, Prosecution, and Completion of Work
7. Design Documents, General
8. Progression of Work
9. Material Approval Submittals
10. As-Built Documents
11. Operation and Maintenance Manuals
12. Warranty of Construction
13. Quality Control Plan
14. Daily Construction Activity Reports
15. Field Survey Requirements
16. Government Furnished Equipment/Materials
17. Disposal of Waste
18. Contractor Storage Location
19. Construction Site Maintenance
20. Security
21. Work in Special Security Areas
22. Flightline Access
23. Delays in Entering and Leaving Work Area
24. Health and Safety
25. Asbestos Requirements
26. Lead-Based Paint Requirements
27. Precautions Against Hazards
28. Use of Tobacco Products in Air Force Facilities
29. Recording and Preserving Historical and Archeological Finds
STATEMENT OF WORK
FOR
MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC)
1. DEFINITIONS:
a. 10% Design - When submitted in response to a Fair Opportunity Proposal Request (FOPR), documents must show the essential components of the proposed design and convey that the contractor fully understands the Task Order (TO) requirements, and that their proposed price includes all required elements of work to complete the project. DRAWINGS: (a) Concept Floor Plan; (b) Conceptual Elevation. DESIGN ANALYSIS: Construction Narrative. The Contractor’s Construction Narrative must be written to outline the work to be performed per the design requirements demonstrating that the contractor understands the Government’s scope of work.
b. 35% Design - When submitted in response to a FOPR, documents must show the essential components of the proposed design and convey that the Contractor fully understands the FOPR requirements, and that their proposed price includes all required elements of work to complete the project. Regardless of when this design is provided to the Government, i.e., prior to or after award of the TO, the documents will include the following minimum information, as applicable, to the project:
drawings; a list showing sections to be incorporated in the specifications; design analysis; and any other design components relating to the 35% design as identified in the TO. Major mechanical and electrical equipment items must be shown on the drawings with single line diagrams. All utilities and structures must be shown. Drawings will also include the following, as applicable:
(1). All required controlling dimensions. Site plan showing proposed location of work including benchmarks, access from main roads, surface or sub-surface drainage concepts, any applicable existing/proposed pavement, and grading elevations.
(2). Floor plans with dimensions and functional arrangement of all areas including corridors, exits, stairs, and utility spaces properly related to exterior access, roads, parking, and service areas, etc.
Special designs and/or deviations from accepted standards of complex design will be given adequate consideration to ensure placement and arrangement of applicable standards. Designs must also include gross floor area for each floor and for the entire building. Floor and roof framing, and loadings will be indicated. Built-in, installed, and specialized portable equipment will be indicated to scale. Pertinent information regarding fire prevention and safety requirements must be shown. Design live and dead loads will be shown.
(3). Elevations must include story heights, fenestration, and adaptation to finished grades at the site.
(4). Sections of structures, including framing, partitions, suspended ceilings (if any), ducts, etc., will be shown.
(5). Typical wall sections will be shown at a scale of no less than 3/4 inch = 1 foot. Sections must include material and thicknesses (to include insulation thickness and minimum thermal resistance R-value), methods of attachment, and type of windows with relation thereof to supporting structural columns or walls.
(6). For heating, air conditioning, fire protection, mechanical ventilation, plumbing, and special features such as elevators, hoists, kitchen equipment, etc., indicate the location, capacity, and space requirements for all major items of mechanical equipment. Single line indication and riser diagrams of ducts, pipes, and equipment and their approximate location must also be shown. The location of fire protection risers will be shown. Indication must be made as to whether piping and duct work are exposed or concealed. Functional areas where pipes are exposed will be delineated.
Approximate operating range or capacity for heating, ventilation, air conditioning, and refrigeration equipment will be clearly stated.
(7). For electrical systems, indicate lighting arrangements, types of fixtures proposed, general light intensities, special electrical requirements of the user, including communications and electronic facilities where applicable, fire alarm/mass notification devices, emergency lighting, light and power service entrance, and distribution arrangement. Conduits, including those to be wired by an independent entity, will be shown together with indication as to whether conduits are exposed.
Functional areas having exposed conduits must be delineated. Riser diagrams showing service equipment, feeders, and panels, other than branch circuits, must be shown. Cable sizes, current demand factors, and switch and panel board descriptions are not required at this time. Location capacity and space requirements of all major items of equipment must be shown including interior substations with service equipment and panels. Power, communication, and electronic features will be indicated in sufficient detail to identify requirements clearly and to indicate the means of satisfying the requirements, including the brand name of the equipment specifically required by the
FOPR.
(8). Provide separate lists of all Government-furnished equipment to be installed by the Contractor and equipment furnished and installed by the Government, if applicable.
The contractor will not proceed to the next design state until the Contracting Officer (CO) issues a Notice to Proceed (NTP) to the subsequent design milestone.
c. 65% Design - In response to the NTP, documents must build upon the 35% design, including drawings, and the complete text of the specifications. The drawings will show an additional 30% progress in all disciplines, which may include site plans, floor plans, elevations, wall sections, details, and all other elements as identified in the 35% design. All cut sections and details must also be shown on the drawings at this time. Any updated or corrected design analysis of architectural, structural, civil, electrical, mechanical, and utility systems will be included. The Contractor will not proceed to the next design stage until the CO issues a NTP to the subsequent design milestone.
d. 95% Design - In response to the NTP, documents must build upon the prior design submittal of 65%. This will include all drawings: to include for review, final, and complete drawings, and specifications. All project requirements identified in the most current TO revision, site visit minutes, solicitation amendments, modifications, or documented review comments must be incorporated. The Contractor will not proceed to the next design stage until the CO issues a NTP to the subsequent design milestone.
e. 100% Design - In response to the NTP, documents will be ready to be used for construction, which includes the required professional certifications and final Contractor accomplished corrections based on the Government's review of the prior 95% design requirements.
f. Color Board – A visual presentation consisting of samples of the various finishes, grouped together based on location within the project. Samples must be of adequate size to show the full pattern, texture, and color of each item.
g. Conventional Design-Build – The process by which the same Prime Contractor provides both the design and construction services for a project, completing the design before construction activity begins. In this type of contract, the Design Firm remains a part of the project throughout the entire contract so as to ensure design integrity, conformance, and quality, as well as provide design and drafting services for changes/modifications and closeout materials.
h. Design-Bid-Build – The process by which the Prime Contractor receives either a 100% completed set of plans and specifications from the Government, or a 35% in-house design with a Statement of Work (SOW) from the Government, by which to perform the entire construction phase of a project.
When a 35% in-house design and SOW are provided, it is expected that the project would not require further extensive design efforts, and that remaining details are to be interpreted by the Contractor through their professional knowledge of applicable national, federal, and Air Force codes/standards/criteria.
i. Design Costs – Those costs identified by the contractor which represent the portion of the overall project cost attributed to preparation of the design and construction documents (level of design to be determined per TO).
j. Designer of Record (DOR) - The individual accountable for specific portions of the design documents. When professional certification is required for the design, the Designer of Record would be the individual providing certification for that portion of the design. When professional certification is not required, the Designer of Record would typically be the individual who provided the design or specifications for a particular aspect of the project (i.e., architectural, civil, structural, mechanical, or electrical).
k. Fast Track Design-Build – The process by which the same contractor provides both the design and construction services for a project, beginning select construction activities at a mutually agreed point prior to completion of the design and construction drawings. Mutual agreeance is required by the Government Contracting and Project Management POCs, and the Prime Contractor, to utilize this process. In this type of contract, the Design Firm remains a part of the project throughout the entire contract so as to ensure design integrity, conformance, and quality, as well as provide design and drafting services for changes/modifications and closeout materials.
l. Government Furnished Equipment (GFE) / Government Furnished Material (GFM) – Items of equipment or material which the government will supply to the contractor for use in the construction of a project.
m. Investigative Costs – Those costs identified by the contractor which represent the portion of the overall project cost attributed to all investigative services necessary to prepare the design and construction documents (level of design to be determined per TO).
n. Investigative Services – For exterior work / new facilities, the investigative services will typically include but are not limited to performing a survey of the project site including topography, cross sections, drainage survey, and bench level circuit. In addition, it may include verification and documentation of the location and size of all existing utilities and pertinent surface features for inclusion on the topographic survey map. For exterior and interior work, the investigative services should also include verification of all existing conditions affecting the design and execution of the work as described in the FOPR.
o. Professional Certification – The process of affixing a seal or statement to a drawing or design document to indicate that the work to which it is affixed has been performed by a person licensed as a professional, in that area of expertise, in the state of North Dakota, or as otherwise indicated in the
FOPR.
Request for Information (RFI) - An RFI is an official document that the contractor must submit when discrepancies or unclear details are found between solicited document within a TO or between manufacturer specifications/recommendations and solicited documents within a TO. RFIs must contain a description of the discrepancy, a proposed solution(s), clear indication whether the proposed solution(s) will incur additional time and/or cost, the name and position of the individual requesting information, and the date/time stamp indicating when the request was submitted.
2. DESCRIPTION OF WORK:
Contract Scope: The MACC will be utilized to execute a broad range of maintenance, repair, replacement, minor construction design, and/or build projects on real property at Minot AFB, North Dakota to include the 8.5K square mile missile field in the areas surrounding Minot AFB. This includes minor and major work in the non-restricted areas of Minot AFB, minor and major work within the Weapon Storage Area (WSA) and Missile Storage Area (MSA), and minor and major work on the Airfield/Flightline. Each project will be further defined in individual task orders (TO). The Contractor may be required to provide for multiple projects at one time.
Work under this contract will consist of a multitude of projects to be performed in the general construction category, which will include, but is not limited to, the following: maintenance, repair, replacement, alteration, studies and reports, designs (internal and professional), demolition, paving (concrete and asphalt), cast-in-place concrete and pre-cast concrete, site work, earth work, abatement, mechanical, electrical, plumbing, communications, heating/air conditioning, painting, roofing, masonry, structural, fire protection, millwork, security, and other specialty and general contracting work.
The work performed for each project must be in accordance with RFP documents issued within this solicitation, in addition to all documents issued within a subsequent project solicitation. Where conflicts, ambiguities, or unclarities are found within individual technical documents of a solicitation and those documents provided within the MACC IDIQ solicitation, the more stringent criteria must apply as default and an RFI must be submitted by the Contractor requesting clarification and direction.
The Government may approve the use of less stringent criteria on an individual project and/or RFI basis.
3. CONTRACTOR’S TO PROPOSALS: Each TO proposal must consist of, at minimum, the following:
a. Cover Sheet: Include a cover sheet that contains project information, contact information, and confirm or propose the Period of Performance.
b. Assumptions: A list of assumptions that were made, if any, in the creation of the proposal package (i.e. assumptions on product availability, lead times, or general timelines that affect the schedule).
c. Technical Details: Sufficient technical detail for the appropriate 5th Civil Engineer Squadron PM to fully evaluate a Contractor’s proposal. This may include, but is not limited to: materials, equipment, material/labor/equipment quantities, sequence of work, long lead items, and special inspection points.
d. Schedule: Brief critical path schedule, taking into account the major work elements of the project to include, but not limited to: mobilization, long lead timelines, items with minimal float, definable features of work (DFOWs), anticipated weather delays, holidays, major pre-construction submittals, Final Inspection, and closeout documents. In the case of Design-Build TOs, the Contractor must also include applicable design milestones, design milestone review periods, and design milestone meetings (telecon or in-person) in the supplied proposal schedule. For the purposes of scheduling, design milestone reviews by the Government require 21 calendar days, per review, for comments to be sent to the Contractor for further review and inclusion.
e. Cost: A detailed cost breakdown sufficient to depict disciplines, sub-disciplines, materials, equipment, labor, quantities, and mark-ups. Lump sums for holistic aspects of work will not be acceptable. In the case of Design-Build TOs, the Contractor must also include a breakdown of the hours for each DOR individual required to work on the design aspect of an individual project. A list of potential DOR personnel includes, but is not limited to, the following:
(1). Principal (2). Program Manager (3). Project Manager (4). Architect (5). Civil Engineer (6). Structural Engineer (7). Mechanical Engineer (8). Electrical Engineer (9). Communications Engineer
(10). Fire Protection Engineer (11). Geotechnical Engineer (12). Interior Designer (13). Land Surveyor (14). Landscape Architect (15). CADD Technician (16). Administrative Support (17). Specifications Writer (18). Blast Engineer (19). Security Engineer (20). Discipline-specific Designers
f. TO evaluation criteria can be tailored to specific projects and the format is subject to change. Each TO will include instructions and the criteria that will be evaluated.
4. CONTRACTOR PERSONNEL:
a. The list of key personnel must include: Program/Project Manager, Quality Control Manager, Project Superintendent, SSHO, and those position alternates. When a design is to be performed as part of the individual TO, the list of key personnel must also include the Design Team Principal, Program Manager, and Project Architect.
b. Contractor’s Program/Project Manager: Contractor must provide a Program Manager and staff for executing TO’s awarded under this contract. The program management staff must have project design, quality control, and construction and financial management capability. The Program Manager must have a minimum of 5 years experience in those capacities and must have the authority to negotiate delivery orders and modifications thereto and obligate the company to TOs. The Program Manager must have the authority to hire/fire subcontractors and must be experienced in subcontract management. The Program Manager must be available via local phone service throughout the duration of all ongoing TOs, and his/her phone number will be provided to the government immediately following award of any TO.
c. Contractor’s Quality Control Manager (QCM): The QCM provides quality control management for all active TOs and executes the Quality Control Plan (QCP). The QCM must have a minimum bachelor’s degree in a construction related field and five (5) years of QCM experience with a general or prime contracting firm engaged in renovation and construction projects. The QCM will visit each active project site daily to ensure full compliance with all safety requirements, quality conformance, and verify that the materials and workmanship are in accordance with the awarded project documents as well as approved shop drawings and materials submittals. The QCM is also responsible for the quality submission of all administrative submittals, ensuring that each submission fully conforms to the requirements of the Specifications and SOW, if provided. Should there be more projects awarded than a single QCM can reasonably handle to a satisfactory level, the contractor will employ more QCM personnel as necessary to meet project quality control requirements. Additional QCMs must conform to the requirements outlined in this paragraph. The QCM must create, update, and maintain project specific quality control reports, submit quality control and safety inspection reports, schedule and coordinate testing procedures, and attend all status meetings, site visits, and Pre-Final/Final Inspections. The QCM must prepare a Pre-Final Punchlist of items not conforming to the contractual requirements and ensure the completion of all Pre-Final Punchlist items prior to the contractor requesting a Pre-Final Inspection by the Government. The QCM must verify compliance with all project-related and technical documents and is empowered to stop work to resolve matters that affect safety, quality, and/or inhibit the logical progression of work. This individual will reject work that is deficient and direct the Superintendent(s) and subcontractors to correct all work deficiencies.
d. Contractor’s Project Superintendent: The Project Superintendent provides on-site supervision. The Project Superintendent must have a minimum of three (3) years of experience as a Project Superintendent (exclusive of time employed as a tradesman or working foreman) for a general or prime contracting firm overseeing renovation and construction projects. The Project Superintendent must visit each active project site daily, submit detailed contract progress reports (via AF Form 3065) for each TO, schedule and coordinate subcontractors and materials suppliers, and attend all status meetings, site visits, and Pre-Final/Final Inspections. The Project Superintendent will be responsible for notifying the Government Inspector and/or Project Manager of the arrival of subcontractors at projects sites.
e. Site Safety and Health Officer (SSHO): Provide an SSHO that meets the requirements of the most current EM 385-1-1. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety Oversight Team that includes a minimum of one (1) person at each project site to function as the SSHO. The SSHO, or an equally-qualified Alternate SSHO, must be at the work site at all times of active physical work to implement and administer the Contractor’s safety program and Government-accepted Accident Prevention Plan (APP). If the SSHO or Alternate SSHO is temporarily off-site (up to 24 hours), a Designated Representative (SSHO DR), as identified in the APP and Activity Hazard Analysis (AHA) will be on-site to maintain these duties. Note that the SSHO DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
f. Design Team: When a professional design is necessary to design, calculate, and detail a project, such as with a Design-Build contract, the Contractor will provide a Design Team (known as the A-E, for supplying Architect-Engineer Services) consisting of, at minimum, the following personnel: Principal, Program Manager, Project Architect, and any discipline-specific Engineers and Designers necessary to complete the required works. The Design Team Lead must be a registered and licensed Architect in the State of North Dakota. The Design Team Lead (registered and licensed Architect), must have, at minimum, five (5) years experience in designing renovation and construction type projects. Each Engineering discipline required to develop and stamp plans must be licensed Professional Engineers in the State of North Dakota and have prior experience in designing renovation and construction type projects. The Design Team must be fully capable of performing surveys, investigations, studies, preparations, calculations, tests, analyses, and designs necessary to complete all aspects of design work required per an individual TO. The Design Team must be knowledgeable in the UFGS, UFC, NFPA, NEC, ANSI, OSHA, ASTM, IBC, and other codes, and be capable of designing projects in accordance with Local, State, National, Air Force, and DoD standards. In addition to the above requirements, the
Design Team must also be fully capable of supplying Title I Services, Types A, B, & C, along with Title II Services throughout the construction phase of a project. Further description of each is as follows:
(1). Title I (Type “A”) Services: The A-E will perform all work required to investigate existing conditions. This work includes field investigations and surveys (topographic, geotechnical, chemical, hazardous materials, site utilities, existing mechanical, hydrant flow tests, NEPA Environmental Scoping Checklist and AF Form 813, etc.) and similar fact-finding surveys of the site in order to provide reports of existing conditions on which to base proper design; and similar services not involved in the preparation of designs, plans, drawings, and specifications.
(2). Title I (Type “B”) Services: The A-E will provide those items normally furnished by an A-E in the actual preparation of the design documents (plans, drawings, specifications, submittal register, Comprehensive Interior Design package, etc.). The A-E will perform all work required to produce documents describing the work required to accomplish the intent of the project as specifically identified in each TO. Unless otherwise specifically provided therein, the A-E will perform these services. The A-E must visually inspect the site and/or facility for familiarization with the scope of work and general conditions of the facility, coordinate with the using activities (Users) to obtain their operational requirements for the development of functional relationships and detailed requirements. The A-E will visit the project site for investigation of the existing physical conditions and to ensure the accuracy of the drawings, as available, furnished to the A-E by the Government.
(3). Title I (Type “C”) Services: The A-E will run Title I Type “C” Services concurrently with Title 1
Type “A” and Title I Type “B” Services. The A-E shall deliver all site work-related design work to the Government in GIS format. The A-E must draft a new detailed specification set that addresses the requirement for the Prime Contractor to gather geospatial data during construction. Upon completion of a project, Final As-Builts will be delivered to the Government in AutoCAD, GIS, and PDF formats.
(4). Title II Services: For all Design-Build projects, the A-E must be capable of providing integrated
Title II Services with the Prime Contractor as another source of Quality Control. Title II involves those items involving inspecting, monitoring, and evaluating construction activities to validate conformance to plans and specifications. These services include reviewing, evaluating, and testing product submittals and shop drawings, color selections, RFIs, evaluation of value engineering, and preparation of construction contract modifications. Annotate daily inspections via AF Form 1477 as required. A-E may be required to provide Construction Administration for for their particular project.
g. “Double-hatting” or “Triple-hatting” of the QCM, Superintendent, and SSHO positions will be allowed only on TOs which state in the SOW or 100% completed set of specifications that this capability is allowed.
h. The Contractor must ensure that employees and subcontractor employees have current, valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications will be at the Contractor’s expense.
i. Required experience levels must be maintained throughout the duration of the contract. When personnel changes are required, resumes and a revised organization chart will be submitted to the CO and PM for approval within five (5) business days of absence of alteration of personnel. This requirement is only for those individuals with positions identified as key personnel in this SOW.
j. The Contractor is responsible for obtaining all permits necessary for construction. The Contractor is responsible for ensuring all Uniform Codes, Standards, & Environmental Regulations are adhered to.
Any Code, Standard, or Regulatory deficiencies will be corrected at the expense of the Contractor.
5. CONTRACTOR OPERATIONS: The Contractor must conduct all operations in accordance with this Statement of Work. In addition, each TO will include either a project-specific SOW or a 100% completed set of drawings and specifications that will detail the work requirements and conduct of operations for that particular TO. All specifications provided will include Section 01 11 00, Summary of Work, that will detail the work requirements and conduct of operations for that particular TO. If an individual TO does not include a project-specific 100% completed set of specifications, the MACC IDIQ Master Specifications will be utilized for all aspects pertaining to the individual project. Any questions regarding specifics or details within the specifications on a given TO must be submitted via an RFI to the Government for official response and direction forward.
6. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: The contractor must commence work and complete the project in accordance with the time frames established in the individual TO and respective NTP. In the event that the contractor does not complete the work within the original designated period of performance set by both Contracting and the requirement owner and agreed upon by the contractor, liquidated damages or considerations may be applied. Furthermore, the CO may require that any employee of the Contractor or subcontractor personnel whose conduct, in the opinion of the CO, interferes with proper discipline at the Installation where the services are performed, be removed from the project. This action incurs a cost or delay in the project, it will be at the cost and delay of behalf of the Contractor.
7. DESIGN DOCUMENTS, GENERAL: The design documents developed by the contractor must comply with the following requirements:
a. Drawings:
(1). The contractor will receive one copy of the appropriate record drawings (electronic only) if available, with the TO. Record drawings will be available to the contractor for their reproduction.
The Government does not guarantee the accuracy or adequacy of the existing as-built drawings. It is the Contractor’s responsibility to field-verify all as-built drawings during preliminary site visits and planning of the project. The Contractor is responsible for the reproduction of these drawings as needed.
(2). The TO will identify the sizes of drawings, either Standard D (24” x 36”) or Standard B (12” x
18”), to be submitted with the proposal and each subsequent review milestone (65%, 95%, and 100%). The contractor will supply all contract drawings prepared using AutoCAD software (version 2024 or previous). Line quality must not be half-toned or gray scaled below 75%. Drawings produced using another software package will be acceptable provided all drawings are converted to standard AutoCAD drawing file format prior to receipt by the Government and comply with the Minot AFB CAD standards and U.S. Army Corps of Engineers (USACE) CAD Standards v 6.2. In addition, the Contractor will comply with the following standards:
a. Drawing files will be delivered in the standard AutoCAD “.dwg” file format for AutoCAD
(version 2024 or previous) as well as in PDF format. “Model space” is the preferred method for drafting all drawing items such as floorplans, sections, details…. Dimensions, leaders, and notes… specific to the drafted item must accompany the object drawn in “Model Space” and be scaled accordingly to appear in paper space at the correct text height as specified. Only general notes applicable to the entire drawing will be drawn in paperspace. Drawing units must be set according to the requirements for the drawing discipline; i.e., civil drawing units must be set to the decimal format, and architectural drawings set to the architectural format. Civil site plans will be in World Geodetic System (WGS) 84, UTM 14N, with all site plans oriented with north at the top of the sheet. Any reorientation of a view for drafting convenience will be done within the viewport using the “Dview” and “Twist” commands. Objects in model space will not be rotated. The Contractor must supply a written explanation as to how externally referenced drawings are used, view-port scales/settings, viewport layer settings, blocks, and any other relevant information necessary for the Execution Support Section at Minot AFB to make changes or updates to the drawings. The Contractor must also be available for phone assistance to clarify any other problems encountered by the Execution Support Section. “Paperspace” must be used to format the final plotted drawing sheet. Standard plotted paper size must be a “D” size sheet unless otherwise specified. All drawings must use the standard Minot AFB project title block. The title block will not be altered by the contractor. Only TO specific data will be edited within the title block.
b. All drawings must be submitted electronically and labeled appropriately, i.e., Redline Drawings, 50% Preliminary As-Builts, 100% Preliminary As-Builts, or Final As-Builts. If disks are delivered at various stages of the project, they will be labeled accordingly, i.e., 65% review, 100% for construction, or Final As-Builts.
c. All External Referenced (XREF) drawings will be located and linked correctly to ensure the xref will load properly. Multiple xref drawings will be allowed, but nested xref drawings will not be used. XREF drawings must be drawing files separate from the drawing files to which they are attached. Xref drawings will not contain other xref drawings, i.e., nested externally referenced drawings. The Contractor will provide complete typewritten instructions for reintegrating the drawings and must specify which XREF goes with which drawing.
d. All lettering (text) will be sized so that finished drawings, prior to half-scale reduction, incorporate text sizes of 1/2-inch for major titles, 1/4-inch for titles, 1/8- inch for notes, and 3/32-inch for dimensions. Larger text sizes may be used as part of the Title Sheets only. Only text fonts/styles native to the basic AutoCAD package must be used. No unique fonts or styles developed by the Contractor or design firm must be used. All detail notes, leaders, and dimensions must be legible when reproduced at half scale.
e. The Contractor will be provided a copy of layer standards utilized by the Minot AFB Execution
Support Section upon request. All layers will have narrative descriptions easily identified (i.e., walls, elec., etc.).
f. Use of third party development software is acceptable provided all drawing files submitted are in native AutoCAD format. Any features peculiar to the development software used, such as shape files, menus, blocks, etc. that are not accessible using the basic AutoCAD package are not acceptable and must be modified to ensure the drawing files may be easily edited or changed by government personnel using the basic AutoCAD software package.
g. Final AutoCAD drawing files should exhibit good drafting practice allowing for minimal storage requirements. Drawings should make use of features to limit drawing size/complexity wherever possible. Over-detailing (drawing features that are not discernible at full or half scale reproduction) is not acceptable and must be avoided.
h. Each drawing file will contain only one final plotted drawing sheet. Drawing files will have no more than one layout tab.
i. Submitted drawing files will be accompanied by a complete hard copy list of drawing file names, layers used, etc. The project number and list of drawings contained on each disk will be written on a label affixed to the disk.
j. All contract drawings to be furnished must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed. All drawings must be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the drawings are undesirable and should be communicated to the Government’s Project Manager for a solution. The use of fractions less than 1/8” for building dimensions will be avoided. Standard building material indications and standard symbols for civil items and for electrical equipment must be used to the greatest extent possible.
(3). Throughout the design process, each submittal will be clearly identified as to the level of completion (i.e., 65%, etc.). The “revisions” blocks on the plan sheets will not be utilized to document changes to the drawings until after the 100% design is completed and accepted by the Government.
(4). The Contractor must prepare drawings, as specified in the TO, for Government approval.
Drawings may come in the form of scheduled design milestones, Redlines, Preliminary As-Built sets, Final As-Builts sets, or other pertinent submissions so as to comply with TO technical documents, timelines, and the general logical flow of design and construction sequencing. The drawings developed by the contractor beyond the 35% point, to include drawings during and/or post-construction, must conform to industry standards relating to good design and drafting practices. All completed drawings must clearly identify the work being performed under the TO.
All project drawing sets will contain a “key plan” that indicates the location of the work to be performed. The key plan may be shown on the cover sheet with the location indicated within an overall plan of the Base site plan. The key plan should indicate the planned route for hauling materials within the Base road system. For smaller projects within a larger building/facility, include a plan of the larger facility that shows the location of the specific work within the larger facility.
Each sheet must have an approved title block and border with professional certification when required by the TO. The title block must contain project information including, but not limited to, Air Force Project #, TO #, Project Name, and submitted date. Basic design criteria utilized for each discipline will be included on the appropriate drawings as required by the TO. Examples would include wind and live/dead loads assumed for structural elements, function-specific conditions such as lighting levels or future use considerations for electrical systems, site-specific climatic design conditions for mechanical systems, and International Building Code analysis (performed to the same level as if being applied to a building permit process). The following is a list, although not fully inclusive, of drawings which might typically be required under this contract:
(a) Cover Sheet with Title and Approval Block
(b) Code Plan and Analysis
(c) Existing Site Plan (plan must include all survey data collected under investigative services)
(d) Final Site Plan
(e) Anti-Terrorism/Force Protection Site Plan
(f) Grading Plan
(g) Underground Utility Plan and Profiles
(h) Demolition Plan
(i) Floor Plans
(j) Elevations
(k) Finish Schedule
(l) Wall and Roof Sections
(m) Window and Door/Hardware Schedules
(n) Ceiling Plan
(o) Details
(p) Structural Plans, Schedules, and Details Plan (plans must be sealed by a registered Structural
Engineer)
(q) Mechanical Plan and Schedules
(r) Plumbing and HVAC Riser Diagrams
(s) HVAC Controls Diagrams
(t) Electrical Site Plan
(u) Power Plan and Panel Schedule
(v) Electrical Plan and Lighting Plan with Schedule and Details
(w) Fire Protection/Detection Plan (plan must be sealed by a registered Fire Protection
Engineer)
(x) Communications Plan
(y) Intrusion Detection System (IDS)/Security Plan
(z) Landscape Plan
b. Specifications:
(1). For projects requiring design, the technical specifications to be utilized by the contractor must be the Unified Facilities Guide Specifications (UFGS) as well as the MACC Master Specifications.
The TO will include the minimum specification sections required by the Government to be included in the design package. The specification sections included in the TO for Design-Build type contracts will be in draft format, and the Contractor will be required to finalize each section during the course of project design to reflect specific design requirements. The specifications created during a Design-Build will be tailored to suit the specific work requirements of the individual items contained in the TO. Extraneous material that does not apply will be deleted. In the course of project design, the Contractor may supplement the Government-provided specifications with other sections of the UFGS that represent elements of work included in the project. The UFGS sections are available in full at www.wbdg.org. The complete set of project specifications, to include those sections provided by the Government as well as any supplemental sections added by the Contractor, must be included in each design submittal as required by the
TO.
(2). Specifications will be utilized in all TOs to further expand upon instructions, details, and requirements of a given project, both technical and administrative. When a 100% complete set of drawings is provided in a TO, a tailored 100% set of specifications will also be provided. If a TO does not provide a project-specific 100% completed set of drawings and specifications, the contractor will utilize the MACC IDIQ Master Specifications in addition to the supplied SOW and drawings.
(3). In addition to the technical specifications described above, the latest version of the following references are to be utilized in the preparation of project designs:
Minot AFB Installation Facility Standards American Society of Testing and Materials (ASTM) Standards American National Standards Institute (ANSI) Standards National Fire Protection Code (NFPA), with particular attention paid to:
http://www.wbdg.org/
NFPA 101, Life Safety Code NFPA 70, National Electrical Code (NEC) NFPA 72, National Fire Alarm and Signaling Code Unified Facilities Criteria (UFC), https://www.wbdg.org/dod/ufc ALL that apply with particular attention to:
UFC 3‐101‐01, Architecture
UFC 3‐201‐01, Civil Engineering UFC 3-420-01, Plumbing Systems UFC 3-530-01, Design: Interior, Exterior Lighting and Controls UFC 4-010-01, DoD Minimum Antiterrorism Standards For Buildings UFC 4-021-01, Design and O&M: Mass Notification Systems
UFC 3‐400‐10N Mechanical Engineering
UFC 3‐400‐01 Energy Conservation
UFC 3‐400‐02 Design: Engineering Weather Data
UFC 3‐410‐01FA Heating, Ventilating, and Air Conditioning
UFC 3‐501‐01, Electrical Engineering
UFC 3‐520‐01, Interior Electrical Systems UFC 3-550-01, Exterior Electrical Power Distribution UFC 3-600-01, Fire Protection Engineering For Facilities
Air Force Instructions, Handbooks, Manuals, etc; ALL that apply International Building Code & ND State Building Code
ANSI C-2
National Electrical Safety Code (NESC) ANSI/ASCE 7-95, Minimum Design Loads for Buildings and Other Structures Americans with Disabilities Act (ADA) Accessibility Guidelines UFGS 01 45 OO Quality Control (WBDG) AF Instructions (AFIs), AF Manuals (AFMANs), AF Pamphlets (AFPAMs), AF Engineering Technical Letters (AF ETLs), and Executive Orders (EOs) Codes and Standards incorporated by reference in the UFC:
a. National Fire Codes
b. International Building Code
c. Uniform Mechanical Code
d. Uniform Plumbing Code
e. National Electrical Code (NEC)
f. ANSI C‐2, National Electrical Safety Code (NESC)
g. Life Safety Code, NFPA 101
h. National Fire Protection Association (NFPA)
i. Engineering Technical Letter (ETL) 03‐2: Design Criteria for Prevention of Mold in Air Force Facilities
Environmental Health and Safety is identified as:
28.2 US Army Corps of Engineers;
EM 385‐1‐1 Safety and Health Requirements Manual 2
28.3 Code of Federal Regulations (CFR);
29 CFR 1910 Occupational Safety and Health Standards – General Construction.
29 CFR 1926 Occupational Safety and Health Standards ‐Construction Industry.
29 CFR 1926.62,Lead Exposure in Construction.
40 CFR 61.140‐156 EPA National Emission Standard for Asbestos 49 CFR 172 Hazardous Materials Tables and Hazardous Materials Communication Regulations.
49 CFR 178 Shipping Container Specifications https://www.wbdg.org/dod/ufc
All current UFCs are available for viewing and download in PDF format at www.wbdg.org. Air Force Instructions, Handbooks, Manuals, etc., are available for viewing and download in PDF format at www.wbdg.org under Federal Facility Criteria/Air Force | AFCEC.
Applicable manufacturer or industry specifications or recommendations associated with material, supplies, or systems will be incorporated as well. If a discrepancy exists between these documents, the contractor must bring this to the attention of the Project Manager and CO and will utilize the most stringent requirement(s) in the preparation of the project design, unless instructed otherwise by the Government in writing via RFI.
During the course of a project, in both the design and construction periods, the building codes, Architectural Standards and UFCs will take precedent over the SOW. If a conflict is found between standards/codes and a project’s SOW, the contractor will submit a RFI to formally submit an inquiry to the Government for official response and direction forward. If a conflict is found between a project’s SOW or individualized specification set and the MACC IDIQ Master Specifications, the contractor must also submit an RFI for response prior to advancing in that aspect of construction.
(4). The TO will include an AF Form 66, Schedule of Material Submittals (AF66). This Government furnished AF Form 66 identifies the minimum submittal items that must be provided by the Contractor for Government review and approval in accordance with applicable specification section requirements. During the course of design and specification development, the Contractor will append the AF66 to include all items as required by the project specification sections to be submitted by the construction contractor for Government review and approval prior to installation. In regard to Design-Builds, the complete appended AF66 generated during the design phase must be included with the Contractor’s edited specifications in each design submittal as required by the TO for Government review and approval. In regard to Design-Bid-Builds, the Government will provide the AF66 in Microsoft Excel format for the contractor to update and track throughout the life of the project. Items of work that require submittal approval will not proceed without proper approval from the final Government authority. This is to include, but is not limited to: purchasing of materials, installation of materials, processes, and documentation. If progress is made by the Contractor on items of work that are subsequently disapproved by the Government, it will be considered a deficiency on the Contractor, and all work required to remove deficient work and reinstall with approved materials will be at the expense of the Contractor.
Similarly, processes or documentation that requires approval will not be considered as complete until the submittal has been approved and signed by the final Government authority.
c. Design Analysis:
As specified in the TO, design calculations may be required, to include code references, as applicable for each discipline, to show compliance, completeness, and accuracy of engineering measurements/loads/safety factors/etc.. The design analysis will be included in each design submittal as required by the TO. The following is a list of calculations which might typically be required under this contract. The number of copies needed for the design analysis will be annotated in the SOW or
TO.
(1). Civil/Site work:
a. Sizing and grades for sanitary & storm sewers
b. Sizing for water mains & services
c. Sizing for gas mains & services
(2). Structural:
a. Foundation and reinforcing sizes
b. Superstructure framing
c. Wind & snow loading analysis
d. LL & DL calculations
e. Wall sizes and reinforcing
f. Equipment supports
g. Elevated platforms
h. Floor member sizing / reinforcing
i. Lintel sizing
j. Sizing for roof joists & decking
(3). Mechanical:
a. Cooling and heating load analysis
b. Pump sizing and pump curves
c. Pipe sizing
d. Duct size
e. Static pressure loss
f. Control valve sizing
g. Psychometric chart analysis
h. Fan sizing and fan curves
i. Heat exchanger selection
j. DDC Control Single Line
(4). Electrical:
a. Load calculations
b. Short circuit calculations
c. Lighting level calculations
d. Branch circuit calculations
e. Motor feed requirements
f. Panel sizing
g. Electrical One Line
(5). Fire Protection:
a. Sprinkler layout and pipe sizing
b. Fire Alarms/Panels/Mass Notification Systems layouts/connections/zones/etc.
(6). Others as applicable to a specific project and identified in the TO.
d. Perspective Drawing:
(1). When required by the TO, the Contractor must prepare a black line concept perspective computerized drawing and/or a rendered (color) perspective computerized drawing of the project.
The perspective will be delivered at the design stage as identified in the FOPR.
(2). The final colored rendering (if required) will be approximately 19” x 28” frame size and will include frame, 3” matting, non-glare glass, and hanging hardware.
(3). The black-line concept perspective must be provided with the contractor’s bid/proposal as part of the 35% or 65% submittal, if required. The rendered perspective will be prepared by the successful contractor and delivered with the final design submittal when requested.
e. Sustainable Design:
As specified in the TO, some projects will be required to incorporate sustainable design principles into the function and design. Air Combat Command Headquarters (ACC HQ) developed a consolidated tool - The ACC Sustainable Design & High Performance Green Building Scorecard to help ensure that these principles are being incorporated into projects. The sustainable direction comes from several different mandates such as EISA 007, MOU, EPAct 2005, and the U.S. Green Building Council’s (USGBC) LEED® (Leadership in Energy & Environmental Design) Rating System. The TO will provide specific guidance as to sustainable design requirements.
f. Leadership in Energy & Environmental Design (LEED):
The TO will specify if LEED certification is to be achieved and to which level for that project. The USGBC’s online project management tool, LEED Online (https://www.leedonline.com/), will be used to manage, compile, and maintain all documentation to support LEED certification.
8. PROGRESSION OF WORK:
a. The successful contractor must submit for approval all work schedules to the CO within 10 calendar days after start of work unless otherwise specified. The reports contemplated by the clause titled “Schedules for Construction Contracts” will be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract…