This package includes construction documents for a plumbing system upgrade at a Department of Veterans Affairs parking garage in Oklahoma City, Oklahoma. The project involves installing new drainage, vent and water piping throughout two levels of the garage, with work including a new sump pump, backflow preventer, roof drains and overflow drains. Plumbing plans show fixture locations and pipe routing, while details provide specifications for hangers, wall penetrations, trench drains and other components. Bidding contractors will use these documents to understand the full scope of work and prepare their responses to the related federal contract opportunity for minor construction issued by the VA Technology Acquisition Center in Austin, Texas. The solicitation number is 36C77623B0046 and responses are due on an unspecified date.

View the file

Other files

File Type Posted
2nd Visit Signed Sign in Sheet OKC Parking Garage 2.pdf PDF
36C77623B0046 0007.docx DOCX document
36C77623B0046 0006.docx DOCX document
36C77623B0046 0005.docx DOCX document
36C77623B0046 0004.docx DOCX document
Tech Questions Responses OKC Parking Garage Tracking Q _ A.pdf PDF
36C77623B0046 0003.docx DOCX document
36C77623B0046 0002.docx DOCX document
OKC DBA Wages Determination OKC County.pdf PDF
amendment Site visit Sheet 36C77623B0046 0001.pdf PDF
Site Visit signed Sign in Sheet OKC Parking Garage 2.pdf PDF
Signed Site visit Sheet 36C77623B0046 0001.pdf PDF
Attachment 13 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 04 Struct 100_ 19-292.pdf PDF
Attachment 11 Specs.pdf PDF
Attachment 07 FS 100_ 19-292.pdf PDF
Attachment 02 Civil 100_ 19-292.pdf PDF
Attachment 01 Gen 100_ 19-292.pdf PDF
Attachment 09 Mech 100_ 19-292.pdf PDF
Attachment 03 Land 100_ 19-292.pdf PDF
Attachment 06 Arch 100_ 19-292.pdf PDF
Attachment 15- Site Visit Instructions.docx DOCX document
36C77623B0046_1.docx DOCX document
Attachment 14 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 10 Elec 100_ 19-292.pdf PDF
Attachment 16- DBA Wages Determination.pdf PDF
Attachment 12 - Geotech Report.pdf PDF
Attachment 05 AP AW 100_ 19-292.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCWR

DHW

PIPING SYSTEM

NG NATURAL GAS

ST STORM

PD PUMP DISCHARGE

OFD OVERFLOW STORM DRAIN

GW GREASE WASTE

OW OIL WASTE

SAN SANITARY WASTE

CD CONDENSATE DRAIN

CA COMPRESSED AIR

AW ACID WASTE

N2 NITROGEN

N2O NITROUS OXIDE

MA MEDICAL AIR

O2 OXYGEN

WAGD WASTE ANESTHETIC GAS DISPOSAL

VAC VACUUM

V SANITARY VENT

OV OIL VENT

AV ACID VENT

NPCW NONPOTABLE COLD WATER

DI DE-IONIZED WATER

SCW SOFTENED COLD WATER

DCW DOMESTIC COLD WATER

RO REVERSE OSMOSIS WATER

DOMESTIC CW RECIRCULATION

DOMESTIC HOT WATER

CO2 CARBON DIOXIDE

DHW 140 DOMESTIC HOT WATER (OTHER TEMP)

PG PROPANE GAS

PLUMBING SYMBOLS

DHWR DOMESTIC HW RECIRCULATION

NG

ST

PD

OFD

GW

OW

SAN

CD

CA

AW

N2

N2O

MA

O2

WAGD

VAC

CO2

PG

V

OV

AV

HW 140

SCW

NPCW

DI

RO

ANNOTATION SYMBOLS

EXISTING

NEW WORK KEYNOTE

DEMOLITION KEYNOTE

NEW BOLD TEXT INDICATES NEW ITEM

ITALICIZED TEXT INDICATES EXISTING ITEM

NEW PLUMBING EQUIPMENT MARK

DETAIL OR SECTION MARK

SHOWN ON DRAWING

DETAIL MODULE NUMBER

CONNECT TO EXISTING

LIMIT OF DEMOLITION

P-###

EXISTING PLUMBING EQUIPMENT MARKP-###

PLUMBING SYMBOLS & ABBREVIATIONS

3-WAY CONTROL VALVE

ANGLE GATE VALVE

ANGLE GLOBE VALVE

BALL VALVE

BUTTERFLY VALVE

CHECK VALVE

CONTROL VALVE

GATE VALVE

GLOBE VALVE

SAFETY RELIEF VALVE

TWO POSITION CONTROL VALVE

BACKFLOW PREVENTER

ECCENTRIC REDUCER

CONCENTRIC REDUCER

FLOW ARROW

HOSE BIBB / SILLCOCK

PLUG VALVE

PLUMBING SYMBOLS

PRESSURE REDUCING VALVE (WATER)

PRESSURE REGULATOR (GAS)

PIPE ANCHOR

PIPE GUIDES

WALL CLEANOUT

SUSPENDED CLEANOUT

WCO

WYE STRAINER

WYE STRAINER W/DRAIN VALVE

FLOOR DRAIN - ROUND OR SQUARE

FLOOR CLEANOUT - ROUND OR SQUARE

PIPE CAP

PIPE TURNING DOWN

PIPE TURNING UP

TEE UP

TEE DOWN

DROP AND RUN

DROP AND TURN

TEE OFF TOP

TEE OFF BOTTOM

CROSS AND RISER

PLAN 90° ELBOW

PIPE TEE

PIPE UNION

FLEXIBLE PIPE CONNECTOR

WATER METER

PUMP

AUTOMATIC AIR VENT

PRESSURE SWITCH

PRESSURE GAUGE

THERMOMETER

FLOW SWITCH

TEMPERATURE SWITCH

OR

OR

CO

PIPE SLOPE ARROW

AV

F

P

T

M

CIRCUIT SETTER

ANNOTATION ABBREVIATIONS

F FAHRENHEIT

FA FROM ABOVE

FB FROM BELOW

FBO FURNISHED BY OTHERS

FCO FLOOR CLEANOUT

FCW FILTERED COLD WATER

FD FLOOR DRAIN

FDC FIRE DEPARTMENT (HOSE)

CONNECTION

FM FLOW METER

FOP FUEL OIL PUMP

FOR FUEL OIL RETURN

FOS FUEL OIL SUPPLY

FOV FUEL OIL VENT

FS FLOOR SINK

FU FIXTURE UNITS

G GALLON

GC GENERAL CONTRACTOR

GCO GRADE CLEANOUTS

GD GARBAGE DISPOSAL

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GPR GAS PRESSURE REGULATOR

GRS GAS REGULATOR STATION

GT GREASE TRAP

GVTR GAS VENT THROUGH ROOF

GWH GAS FIRED WATER HEATER

H&CW HOT AND COLD WATER

HB HOSE BIBB (INTERIOR)

HD HUB DRAIN

HEX HEAT EXCHANGER

HP HORSEPOWER

HS HAND SINK

HST HOT WATER STORAGE TANK

(DOMESTIC)

HWB HOT WATER BOILER

HWCP HOT WATER CIRCULATING PUMP

HWP HOT WATER PUMP

HYD HYDRANT

ICW INDUSTRIAL COLD WATER

INV INVERT

IPC INTERNATIONAL PLUMBING CODE

IRW IRRIGATION WATER

IW INDIRECT WASTE

IWH INSTANTANEOUS WATER HEATER

IWR INDUSTRIAL WATER RETURN

IWS INDUSTRIAL WATER SUPPLY

KW KILOWATT

KWHR KILOWATT-HOUR

L/S LITER PER SECOND

LA LABORATORY AIR

LAV LAVATORY

LBS/HR POUNDS PER HOUR

LCW LABORATORY COLD WATER

LHW LABORATORY HOT WATER

LNG LIQUID NATURAL GAS

LOX LIQUID OXYGEN

LV LABORATORY VACUUM

LW LOW WATER

M METER

MA MEDICAL AIR

MAV MANUAL AIR VENT

MBH THOUSANDS OF BTU PER HOUR

MC MECHANICAL CONTRACTOR

MED MEDICAL

MER MECHANICAL EQUIPMENT ROOM

MH MANHOLE

MOU MEMORANDUM OF UNDERSTANDING

MSB MOP SINK BASIN

MV MEDICAL VACUUM

N2 NITROGEN

N2O NITROUS OXIDE

NC NORMALLY CLOSED

NG NATURAL GAS

NIC NOT IN CONTRACT

NO NORMALLY OPEN

NOM NOMINAL

NPW NON POTABLE WATER

NTS NOT TO SCALE

O2 OXYGEN

OC ON CENTER

OD OUTSIDE DIAMETER

OFD OVERFLOW DRAIN

OR OPERATING ROOM

OVFL OVERFLOW

PA PASCAL

PC PLUMBING CONTRACTOR

PD PRESSURE DROP

PDI PLUMBING AND DRAINAGE INSTITUTE

PG PRESSURE GAUGE

PP PLUMBING PUMP

PPM PARTS PER MILLION

PRS PRESSURE REDUCING STATION

PRV PRESSURE REDUCING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH

ATMOSPHERE

PSIG POUNDS PER SQUARE INCH GAUGE

PTRV PRESSURE TEMPERATURE RELIEF

VALVE

PW POTABLE WATER

RD ROOF DRAIN

RDL ROOF DRAIN LEADER

RL ROOF LEADER

RO REVERSE OSMOSIS

RWL RAIN WATER LEADER

SAN SANITARY SEWER

SCFM STANDARD CUBIC FOOT/MIN

SCW SOFTENED COLD WATER

SDMH STORM DRAIN MANHOLE

SP SUMP PUMP

SPR SPRINKLER LINE

SQFT SQUARE FOOT

SS STAINLESS STEEL

ST STORAGE TANK

SW STORM WATER

TCV TEMPERATURE CONTROL VALVE

TD TRENCH DRAIN

TDH TOTAL DYNAMIC HEAD

TDL TEMPERATURE DIFFERENTIAL

TEMP TEMPERATURE

TMV THERMOSTATIC MIXING VALVE

TP TRAP PRIMER

TSTAT THERMOSTAT

TWR TEMPERED WATER RETURN

TWS TEMPERED WATER SUPPLY

TYP TYPICAL

UPC UNIFORM PLUMBING CODE

V SANITARY VENT

VAC VACUUM

VB VACUUM BREAKER

VCO VACUUM CLEANER OUTLET

VP VACUUM PUMP

VS VENT STACK

VTR VENT THROUGH ROOF

W WASTE

WC WATER CLOSET

WCO WALL CLEANOUT

WG WATER GAUGE

WH WATER HEATER

WHA WATER HAMMER ARRESTOR

WHD WALL HYDRANT

WL WATER LINE

WM WATER METER

WPD WATER PRESSURE DROP

WS WASTE STACK

YCO YARD CLEANOUT

YH YARD HYDRANT

A/E ARCHITECT/ENGINEER

AC ABOVE CEILING

AD AREA DRAIN

AFF ABOVE FINISHED FLOOR

AG AIR GAP

AP ACCESS PANEL

AS AUTOMATIC SPRINKLER

AFG ABOVE FINISHED GRADE

ASD ADJUSTABLE SPEED DRIVE

ASHRAE AMERICAN SOCIETY HEATING,

REFRIGERATING, AIR CONDITIONING

ENGINEERS

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

ASPE AMERICAN SOCIETY PLUMBING

ENGINEERS

ASR AUTOMATIC SPRINKLER RISER

AV ACID VENT

AW ACID WASTE

BAS BUILDING AUTOMATION SYSTEM

BF BELOW FLOOR

BFP BACKFLOW PREVENTER

BG BELOW GRADE

BH BOOSTER HEATER

BHP BREAK HORSEPOWER

BJ BETWEEN JOISTS

BOP BOTTOM OF PIPE

BSP BLACK STEEL PIPE

BT BATHTUB

BTUH BRITISH THERMAL UNITS PER HOUR

C CELSIUS

CF COMBINATION FIXTURE

CGA COMPRESSED GAS ASSOCIATION

CI CAST IRON

CO CLEANOUT

COND CONDENSATE

CP CONDENSATE PUMP

CS CLINICAL SINK

CV CONTROL VALVE

DA DENTAL COMPRESSED AIR

DCW DOMESTIC COLD WATER

DHW DOMESTIC HOT WATER

DHWR DOMESTIC HOT WATER RETURN

DHWS DOMESTIC HOT WATER SUPPLY

DF DRINKING FOUNTAIN

DI DEIONIZED WATER

DN DOWN

DOE DEPARTMENT OF ENERGY

DS DOWNSPOUT

DV DENTAL VACUUM

DW DISHWASHER

DWG DRAWING

DWH DOMESTIC WATER HEATER

DWR DRINKING WATER RETURN

DWS DRINKING WATER SUPPLY

DWV DRAIN WASTE VENT

EC ELECTRICAL CONTRACTOR

EL ELEVATION

EMCS ENERGY MONOSERRAT AND CENTRAL

SYSTEM

EPA ENVIRONMENTAL PROTECTION

AGENCY

EPACT ENERGY POLICY ACT

ESC ESCUTCHEON

ESH EMERGENCY SHOWER

ET EXPANSION TANK

EWC ELECTRIC WATER COOLER

EWH ELECTRIC WATER HEATER

EWS EYEWASH STATION

EX EXISTING

1. WORK SHALL CONFORM TO APPLICABLE LOCAL, STATE, AND NATIONAL CODES AND APPLICABLE VA STANDARDS.

2. INSTALL EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS.

3. OBTAIN AND PAY FOR PERMITS, FEES, AND INSPECTIONS REQUIRED FOR THIS WORK.

4. PROVIDE NEW MATERIALS, EQUIPMENT AND PRODUCTS INCORPORATED IN THE WORK, OF A SUITABLE GRADE FOR THE

PURPOSES INTENDED.

5. EQUIPMENT OR MATERIAL DEVIATIONS FROM INDICATED CONTRACT REQUIREMENTS ARE SUBJECT TO THE APPROVAL OF THE COR. SUBMIT PROPOSED EQUIPMENT DEVIATIONS THAT ARE SIMILAR BOTH IN QUALITY AND CAPACITY TO THAT

EQUIPMENT SPECIFIED, AS SOLELY DETERMINED BY THE COR.

6. INSTALL EQUIPMENT AS INDICATED, ALLOWING FOR SUFFICIENT ACCESS AND CLEARANCE SPACE FOR EQUIPMENT

MAINTENANCE, REPAIRS, AND REPLACEMENT.

7. AT EACH PLUMBING FIXTURE, PROVIDE A PISTON TYPE WATER HAMMER ARRESTOR SIZED ACCORDING TO

MANUFACTURER'S RECOMMENDATIONS.

8. SANITARY DRAINAGE PIPING INDICATED IS LOCATED BELOW FLOOR SLAB OR WITHIN WALLS UNLESS NOTED OTHERWISE.

SANITARY VENT PIPING INDICATED IS ABOVE THE CEILING OR WITHIN WALLS UNLESS NOTED OTHERWISE.

9. SUPPORT PIPING SYSTEM AS REQUIRED BY APPLICABLE LOCAL, STATE, AND NATIONAL CODES ALONG WITH

SPECIFICATIONS, VA STANDARDS AND MANUFACTURER'S RECOMMENDATIONS.

10. FIRESTOP AND SEAL PIPING PENETRATIONS THROUGH WALLS AND FLOORS EQUAL TO THE RATING OF WALLS AND FLOORS.

11. TEST PLUMBING SYSTEM IN ACCORDANCE WITH APPLICABLE LOCAL, STATE AND NATIONAL CODES AND APPLICABLE VA

STANDARDS.

12. COORDINATE PLUMBING PIPING WITH WORK OF OTHER DISCIPLINES.

13. DISINFECT DOMESTIC WATER SYSTEM IN ACCORDANCE WITH APPLICABLE LOCAL, STATE, AND NATIONAL CODES AND

APPLICABLE VA STANDARDS.

14. PROVIDE SHUT OFF VALVES AT BRANCH PIPING TO FIXTURES.

15. COORDINATE PLUMBING WORK WITH ALL OTHER TRADES PRIOR TO INSTALLATION. COORDINATE ROUTING OF PIPING WITH

EXISTING CONDITIONS.

16. PROVIDE ALL NECESSARY OFFSETS, TEES, ELBOWS, ETC. FOR A COMPLETE AND COORDINATED WORKING PLUMBING SYSTEM. DRAWING PLANS, SCHEMATICS, AND DIAGRAMS INDICATE GENERAL LOCATION AND ARRANGEMENT OF PIPING

SYSTEMS.

17. CONTRACTOR SHALL COORDINATE ANY PLUMBING SYSTEM REQUIRED SHUTDOWN WITH THE COR/VA 1 WEEK IN ADVANCE.

18. PATCH, PAINT AND CLEAN SURFACES SUSTAINING DAMAGE ASSOCIATED WITH PLUMBING WORK OF THIS CONTRACT, UNLESS NOTED OTHERWISE.

19. INSTALL ESCUTCHEONS IN ALL PLACES WHERE PIPING PENETRATES A WALL IN AN EXPOSED LOCATION.

20. DO NOT INSTALL PIPES ABOVE TELECOM OR ELECTRICAL EQUIPMENT.

ALTERNATE DEDUCT #2:

• OMIT INSTALLATION OF DOMESTIC WATER BACKFLOW PREVENTER, HOSE BIBBS AND

ASSOCIATED DOMESTIC WATER PIPING FROM PARKING GARAGE.

FOR ORDER OF DEDUCTIVE BID ALTERNATE REFER TO SHEET G-002.

# ALTERNATE NOTES

OVERFLOW

DRAIN (OFD)ROOF

DRAIN (RD)

DOME STRAINER

ROOF MEMBRANE

1 1/2" RIGID INSULATION

SUMP RECEIVER

DRAIN BODY

STORM CONDUCTOR

DOME STAINER ROOF DRAIN 1 1/2" RIGID INSULATION

ROOF MEMBRANE

SUMP RECEIVER STORM CONDUCTOR

2" WATER DAM COLLAR

DOME STRAINER

OVERFLOW ROOF DRAIN

SUMP PAN

15' 27' 15'

1'-6" 3'-0" 1'-6"

2"

GRAVEL

UNDER DECK CLAMPUNDER DECK CLAMP

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/5

/2

:5

:0

P M

C U s e rs

\t b u d a i\ D o c u m e n ts \M

P

-2

-O

K C

P a rk in g G a ra g e tb u d a i.

rv t

P-001

PLUMBING GENERAL INFORMATION

1 5SMR

PARKING GARAGE 2

921 NE 13TH STREET

OKLAHOMA CITY, OK 73104

JULY 8, 2022

100% CONSTRUCTION DOCUMENTS

635-41419-292

N/A

PLH

PLUMBING GENERAL NOTES

PLUMBING SUMP PUMP SCHEDULE

MARK LOCATION

PERFORMANCE ELECTRICAL SPEED

CONTROL REMARKSFLUID FLOW HEAD FT TEMPERATURE HP PHASE VOLTAGE

SP-1 ELEV E1 WATER 150.0 GPM 20.0 60 °F 2 1 208 NONE 1, 2, 3

REMARKS:

1. WITH OIL/WATER DISCRIMINATING FEATURE. HIGH OIL AND HIGH WATER LIMIT ALARM. INTEGRATE ALARM WITH BUILDING AUTOMATION SYSTEM.

2. NON AUTOMATIC SUBMERSIBLE SUMP PUMP. WITH CONTROL PANEL.

3. CONTROL PANEL: 1 PHASE SIMPLEX PUMP CONTROL PANEL. 208 V, MOTOR CONTACTOR, NEMA 4X ENCLOSURE, ALARM LIGHT/HORN, PUMP RUN INDICATOR LIGHT, HOA SWITCH, DRY AUXILIARY CONTACT (ALARM STATUS), INTEGRATE DRY AUXILIARY CONTACT WITH BUILDING AUTOMATION SYSTEM.

PLUMBING BACKFLOW PREVENTER SCHEDULE

MARK LOCATION AREA AND/OR ROOM SERVED SYSTEM TYPE FLOW

INLET

PRESSURE SIZE REMARKS

BFP-1 MECH 101 PARKING GARAGE DCW REDUCED PRESSURE

PRINCIPLE

10.0 GPM 60.00 psi 2" 1, 2

PLUMBING FIXTURE SCHEDULE

MARK DESCRIPTION QUANTITY WASTE PIPE VENT PIPE

COLD

WATER HOT WATER REMARKS

FD-E FLOOR DRAIN, ROUND, 4" OUTLET 1 4" - - - FLOOR DRAIN, ROUND, 4" OUTLET

FD-Y FLOOR DRAIN, ROUND, 4'' OUTLET 24 - - - - GALVANIZED BODY, EXTRA HEAVY DUTY POLISHED BRONZE GRATE, SUITABLE FOR

PARKING DECKS

OFD-1 OVERFLOW ROOF DRAIN 4 - - - - OVERFLOW ROOF DRAIN

P-804 HOSE BIBB 5 - - 3/4" - HOSE BIBB

RD-1 PRIMARY ROOF DRAIN 4 - - - - PRIMARY ROOF DRAIN

NOTE: REFER TO FLOOR PLANS FOR WASTE PIPE SIZE CONNECTIONS FOR FD-Y, OFD-1, RD-1.

REMARKS:

1. INSTALL PER MANUFACTURER'S RECOMMENDATIONS.

2. BACKFLOW PREVENTER IS SIZED FOR FUTURE GARAGE EXPANSION.

Scale: No Scale

ROOF DRAIN / OVERFLOW DRAIN DETAIL

DocuSign Envelope ID: DE6B1966-C688-4097-B859-109EA506307E

7/6/2022

DN

UP

RAMP DOWN

SLOPE = 1:20

RAMP DOWN

SLOPE = 1:20

RAMP UP

VEHICLE

SEC

ELEC

IT

S2

STAIR

ELEV EQUIP

MECH

E2

ELEV

E3

FUTURE

ELEV

E1

ELEV

FD-Y

FD-Y

FD-Y

FD-Y

FD-E

SP-1

FD-Y

BFP-1

P-804

P-804

S1

STAIR

987654321

8" SD4" SD 8" SD

5" SD

5" SD3" SD

8" SD

5" SD

5" SD

10" SD

10" SD

10" SD 10" SD

5" SD

5" SD

5" SD

5" SD

5" SD

3" SD

3" SD

2" SD

5" SD

8" SD

8" SD

2" SD

3" SAN

4" SAN

7 4" SAN

P-804

14 14

14 14

15(TYP.)

15 (TYP.)

15 (TYP.)

5" SD

4'' FCO

5" SD

4'' FCO

4'' FCO 4'' FCO

4'' FCO

4'' FCO

4'' FCO

4'' FCO

4'' FCO

4'' FCO

3'' FCO

5" SD

5" SD 4'' FCO

5" SD

10" SD

3" SD

INV. 1238.43

12" SD

3" SD

5" SD

INV. 1239.24

2" DCW

A

B

C

D

E

F

G

5.2

4" SD

6" SD

4" SD

FD-Y

6" SD

FD-Y

6" SD

6" SD

4" SD

4" SD

FD-Y

FD-Y

6" OSD

3.91.6

B.6

8.8

FD-Y 15 (TYP.)

3" SD

5.5

4" SAN

164" SAN

4" SD

4" SAN

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

/6

/2

:0

:5

A M

C U s e rs

\t b u d a i\ D o c u m e n ts \M

P

-2

-O

K C

P a rk in g G a ra g e tb u d a i.

rv t

PP101

LEVEL 1 PLUMBING PLAN

2 5SMR

PARKING GARAGE 2

921 NE 13TH STREET

OKLAHOMA CITY, OK 73104

JULY 8, 2022

100% CONSTRUCTION DOCUMENTS

635-41419-292

N/A

PLH

Scale: 3/32" = 1'-0"

LEVEL 1 PLUMBING PLAN

N O

R T

H0 84 16

1 PROVIDE SUMP PUMP. INSTALL PER DETAIL

5/P-501.

2 2'' DCW UP TO CEILING SPACE AND 3/4'' DOWN

TO HOSE BIBB. PROVIDE WITH DRAIN VALVE TO

FACILIATE SYSTEM WINTERIZATION.

3 OVERFLOW STORM DRAIN UP. TERMINATE WITH

DOWNSPOUT NOZZLE AND PROVIDE SPLASH

BLOCK PER DETAIL 8/P-501.

4 2'' DCW UP TO SECOND FLOOR AND 3/4'' DN TO

HOSE BIBB.

5 REFER TO CIVIL DRAWINGS FOR CONNECTION

POINT TO SITE STORM DRAIN.

6 UP TO AIR GAP FITTING. REFER TO DETAIL

6/P-501.

7 REFER TO CIVIL DRAWINGS FOR CONNECTION

POINT TO SITE SANITARY.

8 2'' DCW UP TO HOSE BIBB.

9 CONNECT 2'' DCW TO INCOMING 6'' WATER LINE

UNDER SLAB. COORDINATE WITH FIRE

PROTECTION AND CIVIL DISCIPLINE.

10 PROVIDE REDUCED PRESSURE BACKFLOW

PREVENTER PER 11/P-501.

12 CONNECT SUMP PUMP DISCHARGE TO 4 IN

SANITARY LINE BY AN AIR GAP.

13 5'' STORM DRAIN CONDUCTOR UP. PROTECT

WITH PIPE GUARD.

14 PROVIDE 4'' CLEANOUT AT THE BASE OF THE

RISER. COORDINATE WITH PIPE GUARD.

15 PROVIDE FLOOR DRAIN.

16 2'' VENT UP THRU ROOF.

N

SCOPE OF WORK

KEY PLAN

SCALE: NO SCALE

AREA OF WORK

A. SANITARY AND STORM PIPING IS LOCATED

BELOW FIRST FLOOR. SHOWN ON THIS PLAN TO

CLARIFY ROUTING.

E3

FUTURE

ELEV

S2

STAIR

RD-1

OFD-1

FD-Y

FD-Y

FD-Y

FD-Y

FD-Y

FD-Y

FD-Y

FD-Y

FD-YFD-Y

FD-Y

FD-Y

P-804

E2

ELEV

E1

ELEV

S1

STAIR

1(TYP.)

FD-Y

ELEV

LOBBY

987654321

5" SD

3" SD

5" SD

5" SD

4" SD

3" SD

5" SD5" SD

3" SD

5" SD

5" SD

5" SD

5" SD

5" SD

5" SD

2" SD

3" SD

3" SD

4" SD

5" SD

P-804

3/4"

2'' CO

3'' CO

4" SD

4'' CO

5" SD 5" SD

5" SD

5" SD

3" SD

3" SD

3" SD

3" SD

3" SD

5" SD

5" SD

3" SD

5" SD

A

B

C

D

E

F

G

5.2

FD-Y

3" SD

4" OSD

6" OSD

4" OSD

3" SD

3.91.6

B.6

8.85.5

3" SD

2" SD

1 (TYP.)

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

/5

/2

:5

:0

P M

C U s e rs

\t b u d a i\ D o c u m e n ts \M

P

-2

-O

K C

P a rk in g G a ra g e tb u d a i.

rv t

PP102

LEVEL 2 PLUMBING PLAN

3 5SMR

PARKING GARAGE 2

921 NE 13TH STREET

OKLAHOMA CITY, OK 73104

JULY 8, 2022

100% CONSTRUCTION DOCUMENTS

635-41419-292

N/A

PLH

Scale: 3/32" = 1'-0"

LEVEL 2 PLUMBING PLAN

N O

R T

H0 84 16

1 PROVIDE FLOOR DRAIN.

2 PROVIDE ROOF DRAIN AND OVERFLOW DRAIN.

3 2'' DCW DOWN TO CEILING SPACE BELOW AND

VALVED AND CAPPED 2'' DCW UP FOR FUTURE

CONNECTION.

4 3'' STORM DRAIN UP. REFER TO 1/P-501 FOR

CONTINUATION.

5 4'' OVERFLOW DRAIN UP AND DOWN. REFER TO

1/P-501 FOR CONTINUATION.

6 5'' STORM DRAIN CONDUCTOR DOWN. PROTECT

WITH PIPE GUARD.

7 2'' STORM DRAIN UP. REFER TO 2/P-501 FOR

CONTINUATION.

8 3'' OVERFLOW STORM DRAIN UP. REFER TO

2/P-501 FOR CONTINUATION.

9 6'' OVERFLOW STORM DRAIN DOWN.

10 2" VENT THRU ROOF.

11 3'' SD AND 4'' OSD THRU ROOF. SEE 1 / P-501

FOR CONTINUATION.

N

SCOPE OF WORK

KEY PLAN

SCALE: NO SCALE

AREA OF WORK

A. SANITARY AND STORM PIPING IS LOCATED

OVERHEAD ON FIRST FLOOR. SHOWN ON THIS

PLAN TO CLARIFY ROUTING.

NOM. SIZE (IN.)

PIPE (FT.)

TUBING (FT.)

5 FT

THRU 3/4

1 1 1/4

1 1/2

HANGER ROD

INSULATION (VAPOR

BARRIER TYPE IS

REQUIRED FOR

LOW TEMPERATURE

PIPE)

PROVIDE HIGH

COMPRESSIVE

STRENGTH

INSULATION (9 PSF

MIN. DENSITY) UNDER

INSULATION SHIELD

INSULATION SHIELD AT

HANGER

WELD

SADDLE

ADJUSTABLE CLEVIS HANGER TYPE 1 - SEE

SPECIFICATIONS

ADJUSTABLE CLEVIS HANGER TYPE 43 - SEE

SPECIFICATIONS

1/2" DIA. HANGER RODS WITH 36"

MAX. SPACING ON EACH CHANNEL

BAND

1-5/8" 12 GAUGE CHANNEL

OR 2" x 2" x 1/4" ANGLE

NOTES:

SEE SPECIFICATIONS FOR

DETAILED HANGER

REQUIREMENTS. SIDE VIEW TRAPEZE HANGER

FOR UP TO 1000 LB. UNIFORM

LOAD

1" MAX.

PROVIDE INSULATION SHIELD &

INSERT FOR ALL PIPING (8" MIN.)

2 2 1/2 3 4 5 6 8 10 12

11 12 14 16 17 19 22 23

9 10 12 13 14 16 - -

NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE

MAXIMUM PIPE/TUBING SUPPORT SPACING

3" PIPE EXPOSED ON WALL IN ELEVATOR

HOISTWAY. COORDINATE WITH ELEVATOR

INSTALLER PRIOR TO ROUGH IN.

FINISHED GROUND FLOOR

ELEVATOR PIT

FLOOR

SUMP PUMP PIT (SEE ARCHITECTURAL/STRUCTURAL DRAWINGS

FOR PIT SIZE, SEE ELECTRICAL DRAWINGS FOR ELECTRICAL

REQUIREMENTS)

SUBMERSIBLE SUMP PUMP WITH

PIGGYBACK FLOAT SWITCH

UNION

CHECK VALVE

PUMP DISCHARGE TO SANITARY

LINE. CONNECT TO SANITARY BY

AN AIR GAP. REFER TO FLOOR

PLANS FOR PIPE ROUTING.

ELECTRICAL OUTLET REFER TO

ELECTRICAL PLANS

FRAME AND GRATE BY GC

ARRANGE PIPING TO AVOID ELEVATOR

UNION

POINT NAME

PUMP ALARM STATUS

TOTALS

HARDWARE POINTS

AI AO BI BO

SOFTWARE POINTS

AV BV LOOP SCHED TREND ALARM SHOW ON GRAPHIC

X

X

10 0 0 0 0 0 0 0 1

TOTAL HARDWARE (1) TOTAL SOFTWARE (1)

SUMP PUMP CONTROL SEQUENCE:

ON WATER RISE, THE PUMP WILL ACTIVATE WHEN THE FLOAT RISES ABOVE THE "HIGH LIMIT" LEVEL . PUMP WILL REMAIN ON UNTIL THE WATER LEVEL IS BELOW THE "LOW LIMIT". WHEN THE "OFF" FLOAT NO LONGER SENSES WATER IT TURNS

THE PUMP OFF.

NOTE: REFER TO SUMP PUMP SCHEDULE.

RD-1

OFD-1

RD-1

OFD-1

4'' OSD DN

3'' SD DN

2" SD

A

B

C

4" OSD

3" SD

DN THRU ROOF

TO FIRST FLR

CLG SPACE

1.6

B.6

OFD-1

RD-1

2" SD

3" OSD

F

G

8.8

LEVEL 1 SW STAIR

0"

LOWER LEVEL

-4' - 0"

E

LEVEL 01 NE STAIR

-1' - 2"

LEVEL 1

0"

1" D

1" D

1" D

OU-102

OU-103

IU-104

OU-104

2" SD 2" SD

2" SD

2" SD

3" SD

STANDPIPE WITH AIR

GAP FITTING (TYP.)

THIS DETAIL APPLIES TO IT 102 (SHOWN), ELEC 103 (SHOWN), SECURITY 104 (SHOWN).

ROUTE CONDENSATE PIPING IN ELEV EQUIP 100 SIMILAR TO DETAIL SHOWN.

IT

ELEC

SECURITY

IU-102

3" SD

E

3" SD

GRADE

SPLASH BLOCK

HEIGHT LOCATION

FROM FINISHED

GRADE

DOUNSPOUT NOZZLE

LEVEL 1

0' - 0"

1/4" X 1-1/4" IRON

PIPE STRAP.

1/4" X 1-1/4" IRON

PIPE CLAMP

FLANGED

CONNECTION

PIPE

5/8" ~ ROD

MECHANICAL SLEEVE SEAL

WATER STOP AND ANCHOR

COLLAR

LINK SEAL TYPE WALL

SLEEVE OR PIPE SLEEVE

PIPE CLAMP AND

STRAP PROVIDED

ONLY FOR PRECAST

OR POURED WALL

CONSTRUCTION.

EXTERIOR WALL. REFER TO

ARCHITECTURAL PLANS FOR

EXACT CONSTRUCTION TYPE

NOTE: APPLICABLE TO ABOVE

AND BELOW GRADE

APPLICATIONS.

THREADED HANGER ROD

ADJUSTABLE RING HANGER

NOTE: 1

1. HANGING DETAILS SHOWN ARE SUBJECT TO REQUIREMENTS OF SEISMIC DESIGN.

2. INSTALL IN ACCORDANCE WITH NFPA 13.

EXPANSION ANCHOR HILTI QUIK

BOLT TZ OR APPROVED EQUAL.

EXPANSION ANCHOR SHALL BE

QUALIFIED FOR USE IN CRACKED

CONCRETE PER ACI 355.2

NEW CONCRETE SLAB

PIPE

SURGE RESTRAINER

INSULATION

BOLT

FLOOR SLAB

RISER CLAMP. BOTTOM

CLAMP REQUIRED AT

ANCHOR POINTS ONLY

PIPE SLEEVE WHERE

SPECIFIED

RISER CLAMP

FIRE-STOPPING

MATERIAL

BOLT

RISER CLAMP

PIPE SLEEVE WHERE

SPECIFIED

PIPE

RISER

SECTION

TOP

NOTE:

EXTEND SLEEVE ABOVE

FLOOR WHERE SPECIFIED.

REDUCED PRESSURE

BACKFLOW PREVENTER.

PROVIDE IN AN ACCESIBLE

LOCATION. COMPLY WITH

LOCAL REQUIREMENTS

ISOLATION VALVE

(TYP.)

FLOOR

DRAIN PIPE TO BE 2X

LINE SIZE. ROUTE TO

EXTERIOR.

COORDINATE MAIN

DRAIN ROUTING WITH

FIRE PROTECTION

DRAWINGS.

TEST COCK

(TYP.)

PROVIDE PROPER

SUPPORT FOR RPZ

ASSEMBLY

AIR GAP

TO PARKING GARAGEFROM CITY SUPPLY

DRAIN VALVE TO

ALLOW FOR

WINTERIZATION.

TO PARKING GARAGE

WATER CUT-

OFF MASTIC

THERMOPLASTIC

PRE-MOLDED PIPE

FLASHING

HOT AIR-WELD, 1-1/2"

BEYOND FASTENING

PLATES

CUT EDGE SEALANT

STAINLESS STEEL

CLAMPING RING

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/5

/2

:5

:0

P M

C U s e rs

\t b u d a i\ D o c u m e n ts \M

P

-2

-O

K C

P a rk in g G a ra g e tb u d a i.

rv t

P-501

ROOF PLUMBING PLANS AND

PLUMBING DETAILS

4 5SMR

PARKING GARAGE 2

921 NE 13TH STREET

OKLAHOMA CITY, OK 73104

JULY 8, 2022

100% CONSTRUCTION DOCUMENTS

635-41419-292

N/A

PLH

Scale: No Scale

PIPE HANGER DETAIL

Scale: No Scale

SUMP PUMP DETAIL

N O

R T

H0 84 16

N O

R T

H0 84 16

Scale: 3/32" = 1'-0"

ROOF PLUMBING PLAN

Scale: 3/32" = 1'-0"

ROOF PLUMBING PLAN

Scale: No Scale

CONDENSATE DRAIN DETAIL

Scale: No Scale

DOWNSPOUT NOZZLE DETAIL

Scale: No Scale

EXTERIOR WALL PIPE PENETRATION DETAIL

Scale: No Scale

CONCRETE PIPE HANGER DETAIL

Scale: No Scale

SUPPORT/ANCHOR FOR PIPE RISER DETAIL

Scale: No Scale

RPZ INSTALLATION DETAIL

Scale: 3" = 1'-0"

ROOF PIPE PENETRATION DETAIL

2" SD

3" OSD

2" SD

2" DCW

FD-Y

FD-Y

4" SD

3" SD

2" SD

5" SD

10" SD

10" SD

4" SD

8" SD

8" SD

5" SD

FD-Y

FD-Y

5" SD

3" SD

8" SD

4" SD

FD-Y

FD-Y

FD-Y

5" SD

FD-Y

FD-Y

5" SD

FD-Y

8" SD

8" SD

5" SD

4" SD

FD-Y

4" SD

2" SD

4" SD

2" DCW

4" SAN

3" SAN

3" SAN

3" SD

OFD-1

RD-1

OFD-1

RD-1OFD-1

RD-1

4" OSD

3"

4"

10"

5"

3"

5" SD

FD-Y

FD-Y

FD-Y

5" SD

P-804

P-804

2" SD

3" SD

3"

FD-Y

SP-1

FD-Y

RD-1

OFD-1

3'' CO

4''FCO

4'' FCO

P-804

P-804

P-804

FD-E

BFP-1

4'' FCO

2" DCW

4'' FCO

4'' FCO

4'' CO

4'' CO

4'' FCO

4'' FCO

4'' CO

4'' CO

4'' FCO

4'' FCO

4'' CO

FD-Y

2'' CO

4'' FCO

4'' CO

4'' FCO

4'' CO

4'' CO

4'' FCO

3" SD 5" SD

3" SD

5" SD

5" SD

3" SD

3" SD

3" SD

12" SD

10" SD

12" SD

4'' FCO

3" SD

2"

FD-Y

FD-Y

FD-Y

FD-Y

FD-Y

6" SD

6" SD

4" SD

4" SD

6" SD 6" SD

FD-Y

12" SD

4" SD

4" OSD

3" SD

6" OSD

4" SAN

4" SAN

4" SAN

2" V

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/5

/2

:5

:1

P M

C U s e rs

\t b u d a i\ D o c u m e n ts \M

P

-2

-O

K C

P a rk in g G a ra g e tb u d a i.

rv t

P-901

PLUMBING RISERS

5 5SMR

PARKING GARAGE 2

921 NE 13TH STREET

OKLAHOMA CITY, OK 73104

JULY 8, 2022

100% CONSTRUCTION DOCUMENTS

635-41419-292

N/A

PLH

Scale: No Scale

PLUMBING RISERS

Sheets
P-001 - PLUMBING GENERAL INFORMATION
PP101 - LEVEL 1 PLUMBING PLAN
PP102 - LEVEL 2 PLUMBING PLAN
P-501 - ROOF PLUMBING PLANS AND PLUMBING DETAILS
P-901 - PLUMBING RISERS