Attachment 08. NIWTP & IOI EA and FONSI_1999.pdf

PDF 488 KB Posted

Attached to
Nogales IOI Rehabilitation Phase 4 & 5
Solicitation number
191BWC22R0005
Issued by

View the file

Other files

File Type Posted
191BWC22R0005 Amendment A00004.pdf PDF
191BWC22R0005_Solicitation_Revised_A00002_draft.pdf PDF
191BWC22R0005 Amendment A00003.pdf PDF
CON_PenaBlancaHighlandsSouthOffsite_as builts.pdf PDF
191BWC22R0005_IOI_Rehab_PH45_Specs_20220602.pdf PDF
CityofNogales_20200924_Pena Blanca Outfall Sewer As-Built.pdf PDF
191BWC22R0005_Solicitation_Revised_A00002.pdf PDF
Responses_to_Additional_Questions_Received_Against_191BWC22R0005.pdf PDF
NIOI Hydrographs_20220524.pdf PDF
City of Nogales Flow Information Lift Station.pdf PDF
191BWC22R0005 Amendment A00002.pdf PDF
191BWC22R0005_Solicitation_Revised_A00001.pdf PDF
IOI PH4-5 _Pre-Proposal Agenda_Final.pdf PDF
191BWC22R0005 A00001.pdf PDF
191BWC22R0005_IOI_Rehab_PH4-5_Specs_20220517.pdf PDF
IOI PH4-5_Pre-Proposal Sign-In.pdf PDF
Responses to Questions Received Against 191BWC22R0005.pdf PDF
Attachment 11. Nogales International Outfall Pipe Survey_20150423.pdf PDF
Attachment 09. NIWTP Flow Reports_Jan-Dec2020.pdf PDF
Attachment 13. Nogales Intl Sanitation Project Construction Report_1969-1972.pdf PDF
Attachment 19. 'IBWC Form 110.pdf PDF
Attachment 04. RFP Client Authorization Letter.docx DOCX document
Attachment 12. B&C Evaluation of IOI Report_200503.pdf PDF
Attachment 20. IBWC Form 116.pdf PDF
Attachment 02. 191BWC22R0005 Phase V Drawings_20220309.pdf PDF
Attachment 21. IBWC Form 117.pdf PDF
Attachment 06. IOI Rehab Design Report woE_20180411.pdf PDF
Attachment 07. IOI Rehab Geotechnical Report_20150121.pdf PDF
Attachment 18. UPRR Requirements & Guidelines.pdf PDF
Attachment 05. RFP Past Performance Questionnaire.pdf PDF
Attachment 16. NADB IOI Direct Laterals Design.pdf PDF
Attachment 03. 191BWC22R0005 IOI Rehab PH 4&5 20220419.pdf PDF
Attachment 14. Nogales International Sanitation Project As-Builts_19710501.pdf PDF
Attachment 10. NIWTP Flow Reports_Jan-Dec2021.pdf PDF
191BWC22R0005 Nogales IOI Phases 4 and 5.pdf PDF
Attachment 01. 191BWC22R0005 Phase IV Drawings_20220309.pdf PDF
Attachment 17. UPRR IOI MCL Folder03060-53.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Finding of No Significant Impact:

Wastewater Infrastructure Improvements for Nogales, Arizona and Nogales, Sonora

PROJECT LOCATION AND DESCRIPTION

The U.S. Environmental Protection Agency (EPA) is considering authorizing the award of Border Environment Infrastructure Fund (BEIF) grants to the City of Nogales (City), Arizona and the Comisión de Agua Potable Y Alcantarillado del Estado de Sonora (COAPAES) for the rehabilitation, upgrade and construction of wastewater infrastructure facilities in the communities of Nogales, Arizona and Nogales, Sonora. The project area is located in southern Arizona and northern Sonora, along the U.S.-Mexico border.

The project, which is binational in scope, will improve and expand wastewater treatment and collection infrastructure, situated in Nogales, Arizona, that serve both communities. In Nogales, Sonora, improvements will be made to the collection system and new wastewater treatment and conveyance facilities will be constructed to handle future flows in excess of Mexico's allocation in the existing international treatment plant. Minute 276, between the Governments of the United States and Mexico, established this allocation at 9.9 million gallons per day (mgd) of treatment capacity. The proposed project includes the following specific works.

In Arizona:

Nogales international wastewater treatment plant (NIWTP) - the capacity of the NIWTP will be increased to 22 mgd and the plant will be upgraded by converting the aerated lagoon system to a conventional activated sludge system with nitrogen removal and sludge recirculation.

International outfall interceptor (IOI) - the existing IOI will be replaced with a new, enlarged interceptor.

Wastewater collection system - deteriorated portions of the collection system will be rehabilitated.

In Sonora:

Los Alisos treatment plant - a new 4 mgd treatment plant, whose treatment train consists of a modified advanced pond system including deep facultative lagoons and infiltration basins, will be constructed. The treated effluent will be discharged to the Rio Los Alisos.

Conveyance system - a conveyance system consisting of an interceptor and

DocumentsPDF Complete

Click Here & Upgrade Expanded Features

Unlimited Pages http://www.pdfcomplete.com/1002/2001/upgrade.htm pump stations will be constructed to transport wastewater flows to the Los Alisos treatment plant. The pump stations will have the capacity to pump only the average daily flows in excess of Mexico's current 9.9 mgd allocation. Peak flows associated with storm events would not be pumped to Los Alisos but would be bypassed to the gravity system and would flow north across the border and be conveyed to the NIWTP.

Wastewater collection system - deteriorated portions of the collection system will be replaced.

PURPOSE AND NEED

Currently, domestic wastewater is conveyed northward from Nogales, Sonora and Nogales, Arizona to the NIWTP via a gravity collection system. The IOI, located along Nogales Wash, is the main line which transports the combined flows from both communities to the NIWTP, where treatment takes place prior to discharge to the Santa Cruz river.

Due to deficiencies within the collection systems in Nogales, Arizona and Nogales, Sonora a certain amount of untreated wastewater escapes into the groundwater table and into Nogales Wash, a tributary of the Santa Cruz river.

Similarly, the IOI is limited by bottlenecks and periodically, wastewater flows exceed its capacity resulting in overflows of untreated sewage into the Nogales Wash. Further, the IOI and the collection systems are also subjected to significant infiltration.

In addition to the fugitive flow problem, the hydraulic capacity of the NIWTP is near its limit. As populations grow in both communities, additional capacity will be necessary to address the increasing sewage treatment needs.

Furthermore, water supply and consumption and the accompanying wastewater production are expected to grow in the near future as COAPAES upgrades and expands the potable water supply system in Nogales, Sonora.

Lastly, the effluent quality limits for the NIWTP are being revised and the proposed National Pollutant Discharge Elimination System (NPDES) permit calls for the reduction of toxicity to aquatic life, which implies a reduction in ammonia concentrations in the effluent. Additionally, concern has been raised about the potential impact of effluent high in total nitrogen concentration since ammonia will likely be transformed to nitrate, affecting the potable water wells located downstream of the NIWTP.

The infrastructure improvements being proposed will address the water quality concerns and treatment capacity issues of the region. Rehabilitation of the collection systems and replacement of the IOI with a larger pipe will reduce fugitive flows of raw sewage and therefore improve surface water and groundwater quality. Future wastewater flows for Nogales, Sonora will be handled by the new Los Alisos plant and conveyance system, which will be

DocumentsPDF Complete

Click Here & Upgrade Expanded Features expanded in phases as the demand for wastewater service increases. The NIWTP will be upgraded to comply with new regulatory requirements and protect exposed aquatic biota from acute or chronic effects. In addition, the NIWTP will be expanded by 5 mgd to accommodate additional flows from Mexico in excess of its allocation that may reach the NIWTP as a result of storm events, system failures and until later phases of the Mexican wastewater system are implemented.

ENVIRONMENTAL CONSEQUENCES AND CONDITIONS

In compliance with the National Environmental Policy Act (NEPA), EPA has prepared an environmental assessment (EA) that analyzes the potential environmental impacts in Arizona as well as the potential transboundary environmental impacts of the proposed infrastructure improvements. After considering a wide range of regulatory, environmental (both natural and human) and socio-economic factors, the EA did not identify any significant impacts to the environment that would result from the implementation of this project.

Environmental impacts in Sonora are addressed in the Manifestación de Impacto Ambiental, Modalidad General, del Proyecto: "Recoleccion Tratamiento y Disposicion Final de las Aguas Residuales de Nogales, Sonora (Environmental Impact Assessment, General Level, for the Project: Collection, Treatment and Disposal of Wastewater in Nogales, Sonora) which was prepared in accordance with the environmental impact review process of the Instituto Nacional de Ecologia. This analysis supports a determination that the project will not have a significant adverse impact on human health and the environment in Mexico.

PUBLIC REVIEW

The EA is on file, along with other project materials, and is available for public inspection at the EPA Region 9 office in San Francisco, California. Copies of the EA are also available for public review at the following locations:

Nogales International Wastewater Treatment Plant (NIWTP) 865 Rio Rico Industrial Park, Rio Rico, AZ 85648

(520) 281-1832

City of Nogales Public Works 1450 North Hohokam Drive Nogales, AZ 85621

Nogales Public Library 518 North Grand Avenue Nogales, AZ 85621

Interested persons, including those who disagree with this proposal, may submit comments to EPA Region 9 within 30 calendar days from the date this

DocumentsPDF Complete

Click Here & Upgrade Expanded Features

Unlimited Pages http://www.pdfcomplete.com/1002/2001/upgrade.htm Albert.Moehlig Highlight

Albert.Moehlig Highlight

Albert.Moehlig Highlight document is issued. No administrative action will be taken on this proposed project prior to the expiration of this comment period. Comments, via letter, fax or email, should be sent to Evelyn Wachtel at the address listed below.

Evelyn Wachtel (WTR-4) U.S. EPA Region 9 75 Hawthorne Street San Francisco, CA 94105 Telephone: (415) 744-1167 Fax: (415) 744-1078 Email: wachtel.evelyn@epa.gov

After EPA assesses any comments received, those comments, EPA's responses, and this FNSI will be forwarded to the Regional Administrator for review and signature. If this FNSI is signed by the Regional Administrator, it will not be recirculated for review but will be available to any individual upon request.

FINDING

After review of the EA and any comments received, EPA has determined that the proposed project will not have a significant impact on the environment and that an Environmental Impact Statement will not be prepared for this project.

Felicia Marcus Regional Administrator

Go to: [ Region 9 Water Programs Page ] [ Region 9 Home ] [ EPA Home ]

Send questions and comments to: wachtel.evelyn@epa.gov Region 9 Office: 75 Hawthorne Street, San Francisco, California, 94105-

Created: February 3, 2000

URL: http://www.epa.gov/region09/water/nogales/wastefnsi.html

DocumentsPDF Complete

Click Here & Upgrade Expanded Features

CDM�Camp Dresser & McKee S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

�������������
��������������������
����������
���������������
������
�����������
�������������������
������

/0���1,2��&!

��&����&-$"-�#�� �34560�

7.�

�)�)��!-,$�&��&,!�&�,$�&� ���8&'��.��&'���,!����++$""$�& 45/5��)���!"�

�2!���++�&"��8$ '$&��� � ���"�#����/3369:5445

5//����,2��28�-2��,�!!, �8$,!�=66 �8-"�&#� >�=0/65

CDM�Camp Dresser & McKee

List of Acronyms ��&*$��&+!&,� �?8� $,.

���,!���!"�8�-!"

��? ��8&-$ ��&��&*$��&+!&,� �?8� $,.

��!'!�� ��!�8 �,$�&" ���� �&,!�&�,$�&� ���8&'��.��&'���,!����++$""$�& ��� �&,!�&�,$�&� ��8, ����� ���� !"��&,!�&�,$�&� ���",!1�,!����!�,+!&,�� �&, ��� �!,��-2 ���!,2. !&!

CDM Camp Dresser & McKee 1-1

Section 1 Environmental Assessment

This Environmental Assessment (EA) is a stand-alone document developed parallel with and supportive of the Ambos Nogales Facilities Plan. This EA satisfies the requirements of the National Environmental Policy Act (NEPA) of 1969, the Council on Environmental Quality (CEQ) NEPA regulations (40 CFR Parts 1500–1508), the Environmental Protection Agency (EPA) NEPA regulations (40 CFR Part 6), the International Boundary and Water Commission (USIBWC) Final Operational Procedures for Implementing Section 102 of the National Environmental Policy Act, and the Border Environment Cooperation Commission (BECC). The primary purpose of the EA is to gather sufficient evidence and analysis for determining whether to prepare an Environmental Impact Statement (EIS) or a Finding of No Significant Impact (FONSI). An EIS is required if significant environmental impacts are anticipated.

1.1 Scoping

The international concerns and diversity of projects dictate that this EA incorporate analyses at a level generally associated with a NEPA EIS. This EA therefore meets the general requirements of an EIS and, as a component of the parallel Ambos Nogales Facilities Plan, considers NEPA requirements related to public involvement and community outreach. Public involvement is a component of this EA. This EA addresses all important potential impacts on the U.S. side of the international boundary, as well as transboundary impacts. Impacts in Mexico are covered in a Mexican environmental assessment, as appropriate.

1.2 Introduction

NEPA, along with subsequent amendments, requires that environmental considerations be given careful attention and appropriate weight in every recommendation or report on proposals for legislation and for other federal actions significantly affecting the quality of the environment. The requirements of NEPA are to be integrated with other planning and environmental review procedures required by law or by agency practice so that all such procedures run concurrently rather than consecutively. To meet these requirements, this EA is conducted concurrently with the Ambos Nogales Facilities Plan to evaluate the potential for identified project alternatives to adversely affect the local environment. As part of the facilities plan, an Environmental Inventory (EI) has been developed, and constitutes Section 6 of the facilities plan report.

The EI and other sections of the Ambos Nogales Facilities Plan provides details and much of the basis for the information presented in this EA. For example, the EI includes detailed descriptions of the local environment and habitats as well as discussions of the value of intermittent and ephemeral waters, the identification of important environmental resources, and the biology of important species. Other sections of the Ambos Nogales Facilities Plan provide detailed information on related issues such as socioeconomic issues and wastewater treatment processes.

The potentially affected environment is assessed in this EA as sixteen (16) individual components.

Fifteen of these components were previously identified in Element 6 of the Facilities Plan, the EI, Section 1 Environmental Assessment

CDM Camp Dresser & McKee 1-2 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd and include land use, geology and soils, topography, floodplains, surface water quality, groundwater aquifers, groundwater quality, biological resources (including threatened/endangered species), historic and cultural resources, public health and safety, air quality and odors, energy supply and natural resources, hazardous and solid waste, aesthetic resources, and parks. The category socioeconomics, which includes issues related to demographics, employment, and population growth, was not included in the EI. This category is also assessed in this EA. The EA therefore evaluates sixteen (16) resource categories, the fifteen (15) categories defined above and socioeconomics.

Another component discussed in the EI, applicable plans and policies, is not evaluated in the EA because it is not a component of the potentially affected environment. This EA does, however, consider how project actions and other related actions influence applicable plans and policies. No conflicts between applicable plans and policies and project actions or other related actions have been identified.

1.2.1 Purpose of the EA

The primary purpose of the EA is to determine if a FONSI can be prepared for the proposed action described in the following sections. A FONSI precludes the need to perform an EIS, while a finding of potentially significant impact dictates that an EIS is required. CEQ 40 CFR Part 1508.9 provides the following definition and requirements for an EA:

Environmental Assessment:

(a) Means a concise public document for which a Federal agency is responsible that serves to:

(1) Briefly provide sufficient evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact.

(2) Aid an agency’s compliance with the Act when no environmental impact statement is necessary.

(3) Facilitate preparation of a statement when one is necessary.

(b) Shall include brief discussions of the need for the proposal, of alternatives as required by section 102 (2)(E), of the environmental impacts of the proposed action and alternatives, and a listing of agencies and persons contacted.

1.2.2 Project Identification and Location

Currently, domestic wastewater generated in Nogales Sonora, is conveyed north by a gravity collection system to Nogales, Arizona where it is combined with Arizona flows in the International Outfall Interceptor or IOI. Together, the combined wastewater flows from both cities continue northward via the IOI, along the Nogales Wash, to the Nogales International Wastewater Treatment Plant (NIWTP) where treatment takes place prior to discharge to the Santa Cruz River basin.

Due to deficiencies within the Sonoran collection system, a certain amount of untreated wastewater escapes into the Nogales wash, a tributary of the Santa Cruz river. In addition, seasonal increases in

CDM Camp Dresser & McKee 1-3 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd the water table caused by storm events account for a significant amount of infiltration especially into the IOI. This results in dilution of the wastewater as well as a reduction of hydraulic residence within the NIWTP. Both these factors can reduce the efficiency of treatment and may lead to the release of inadequately treated effluent to the Santa Cruz River.

The project area is located in southern Arizona and northern Sonora, Mexico. The northern boundary of the project area extends to the farthest reach of the Santa Cruz River with effluent–dominated surface flow (Figure 1). During most seasons and most years, this is near Tubac, Arizona, about 26 km (16 miles) downstream of the NIWTP. To the east, the project area is bounded by the Santa Rita and Patagonia Mountains, and to the west by the Pajarito Mountains. The southern boundary of the project area is delineated by the wellfields in the Los Alisos area of Sonora. Section 6.3 of the Facilities Plan (Topography) provides a more detailed description of the project area.

Specific sites identified in the Facilities Plan for the construction of treatment facilities under one or more alternatives include (1) the current NIWTP site near the confluence of the Nogales Wash and the Santa Cruz River; (2) at the Santa Cruz River between the NIWTP and Kino Springs near the intersection of Arizona State Route 82 and the Santa Cruz River; (3) the industrial site along River Road in the Rio Rico area. The disposal or discharge of treated wastewater generated at one or more of these WWTP sites requires an assessment of potential discharge locations. Several alternative sites were evaluated for wastewater discharge via direct discharge to the Santa Cruz River. Another potential discharge site was identified at Potrero Creek where discharge may be accomplished. At each potential discharge location, the added benefit of aquifer recharge is considered a positive secondary effect.

In Mexico, the initially selected sites of interest for treatment included (1) the Santa Cruz River at Mascareñas, east of Nogales; (2) the Santa Cruz River at El Mezquital, south of Mascareñas; (3) the Santa Cruz River at San Luis; (4) the Santa Cruz River at Paredes; and (5) two sites near the intersection of Rio Los Alisos and the Road to Saric south of Nogales, Sonora. These sites were also initially considered for their suitability for discharge of treated effluent, along with the added potential for aquifer recharge via direct discharge to the river followed by percolation. The parallel Mexican EA provides a detailed analysis of impacts to environmental resources in Mexico.

1.2.3 History of Proposed Action

There has been concern with pollution and public health issues along the U.S.–Mexico Border for several years. These concerns gained further importance in public opinion and the media during the negotiation of the North America Free Trade Agreement (NAFTA) which, according to some opponents, would increase the extent of contamination along the border as U.S. industries relocated to border areas in Mexico. A border sanitation problem has existed in Ambos Nogales since the 1940s, and has been attended to by the United States and Mexico by the construction of international outfalls and treatment plants; first, in the 1950s, then in the 1970s, and more recently in the 1990s. In Ambos Nogales, occurrences of raw or partially treated sewage in surface waters has been one of several border sanitation problems that threaten the health and well being of inhabitants along the border area. In 1995, the U.S. Congress passed an appropriations act, authorizing the U.S. Environmental Protection Agency (EPA) to spend US$47.4 million addressing

U N I T E D S T A T E S O F A M E R I C A

M E X I C O

Arizona

Sonora

Santa Cruz River

Southern Pacific R.R. Sonoita Creek

Guevavi Creek

River RoadNogales

Wash

Kino Springs

Patagonia Road

Mascareña

El Mezquital

Los Alisos River

Agua Zarca Paredes

Santa Cruz River

Nogales Wash

Potrero Creek

Mariposa Road

Duquesne Road

Guevavi Ranch

Buenavista

Rio Rico

NIWTP

Discharge to Santa Cruz River

International Outfall Interceptor

4 miles0 1 2 3

N

EW

S

CDM Camp Dresser & McKee Figure ES-1

Project Area

Nogales, Sonora Collectors

NOGALES

CDM Camp Dresser & McKee 1-5 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd sanitation problems on the border. EPA, Region IX, selected Ambos Nogales and Mexicali, Baja California for the development of sanitation facilities plans to develop alternative solutions for future implementation. Of these funds, EPA awarded US$33.6 million to USIBWC to develop facility plans and carry out selected wastewater sanitation improvements at Nogales and Mexicali.

The International Boundary and Water Commission (IBWC), represented by the United States and Mexico deliberated the terms of an international agreement made formal by IBWC Minute 294. This minute authorizes the formation of a multi-agency binational technical committee to coordinate the development of a wastewater facility plan facilitated by the IBWC. The Binational Technical Committee, as described in the following sections, represents federal, state, and local government agencies of both countries. In addition, the USIBWC retained the environmental consulting firm Camp Dresser & McKee Inc. (CDM) to act as an external consultant in the development of the Facilities Plan. It is expected that the responsible party or parties in the United States and Mexico will present the Facilities Plan to the BECC. If certified, the project would be eligible for North American Development Bank (NADBank) financing.

1.2.4 Relevant U.S. Lead and Cooperating Agencies

The IBWC under Minute 294 formed policy and technical binational committees to develop the Facilities Plan. The Binational Technical Committee is in charge of overseeing, providing guidance, and identifying relevant issues that require attention on a day–to–day basis. The Binational Policy Committee, on the other hand, is primarily responsible for decision making, but also provides directives on global or "big picture" issues. The binational committees are in turn divided into national committees. This section describes the members of the U.S. committees and their role in the Facilities Plan, followed by descriptions of Mexican agencies involved in the Facilities Plan.

International Boundary and Water Commission

The international coordinating agency for the facility plan development is the IBWC, an international organization established by the 1944 Water Treaty. The Governments of the United States and Mexico entrust to the IBWC the application of the 1944 Water Treaty (TS 944; 59 Stat 1219) and the regulation and exercise of the rights and obligations assumed by the two governments under this and other boundary and water treaties and agreements. The United States and Mexico obligations for the Nogales sanitation problem are in IBWC Minutes 227, 276 and 294. The IBWC is made up of two Sections, a United States Section (USIBWC) and a Mexican Section (MxIBWC) headed by an engineer commissioner appointed by the President of the respective country. Each Commissioner receives foreign policy guidance from his respective foreign office in those matters of joint action with the other country.

The IBWC may conduct studies and investigations on boundary and international water matters under the various boundary and water treaties and other international agreements in force between the United States and Mexico and as the two Governments may request.

The USIBWC has international oversight of the Nogales International Wastewater Treatment Plant (NIWTP), which has a design capacity of 754 L/s (17.2 mgd) average daily flow of which 320 L/s (7.3 mgd)is owned by Nogales, Arizona. Under Minute 276, 434 L/s (9.9 mgd) capacity was allocated to Nogales, Sonora. From 1954 to 1996, the City of Nogales operated and maintained the

CDM Camp Dresser & McKee 1-6 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd wastewater treatment plant under IBWC oversight and was reimbursed by the USIBWC for the cost of treating Nogales, Sonora sewage. At the request of Nogales, Arizona, in 1996, the USIBWC operates and maintains the wastewater treatment plant and is reimbursed by the Nogales, Arizona for the cost of treating Nogales, Arizona sewage.

As previously indicated, USIBWC has received funds from the EPA to act as Project Manager for the Ambos Nogales Facilities Plan in coordination with the agencies described below and the external consultant firm.

U.S. Environmental Protection Agency (EPA)

EPA is a federal entity in charge, among other things, of establishing and enforcing water quality standards, providing guidance for maintaining or improving water quality, and in some instances, providing funds for conducting studies and implementing water quality related projects.

The EPA awarded funds to the USIBWC through an interagency agreement to coordinate the development of the binational facility plan and selection of wastewater improvements for Nogales.

EPA funds are designated in this case for wastewater–related issues, e.g., for treatment and discharge of treated effluent.

Arizona Department of Environmental Quality (ADEQ)

The ADEQ was created in 1986 by the Arizona Environmental Quality Act. ADEQ is the primary agency responsible for all purposes of the Clean Water Act (CWA), the Safe Drinking Water Act (SDWA), the Resource Conservation and Recovery Act (RCRA), and other environmental programs in the State. ADEQ adopts water quality standards for navigable waters and aquifers. In addition, it requires programs to be adopted to control surface and ground water and to control point and nonpoint pollution discharges.

In Arizona, the National Pollutant Discharge Elimination System (NPDES) permits are issued by EPA rather than ADEQ. Nonetheless, ADEQ requires discharging facilities to obtain an Aquifer Protection Permit (APP).

ADEQ is an active member of the U.S. Committee dedicated to ensuring future effluent discharges comply with all state and federal laws. ADEQ has provided guidance throughout the facilities planning process to establish effluent water quality targets.

Arizona Department of Water Resources (ADWR)

In 1980, Arizona established the Groundwater Management Act (GMA) with the purpose of controlling overdraft of groundwater supplies. The GMA created the ADWR to manage groundwater resources and establish Active Management Areas (AMAs) in crucial areas where groundwater supplies were most threatened (SEAGO 1994).

"ADWR works to secure long–term water supplies for Arizona's communities. The Department administers state water laws (except those related to water quality), explores methods of augmenting water supplies to meet future demands, and develops policies that promote conservation and equitable distribution of water" (ADWR, December 17, 1997).

CDM Camp Dresser & McKee 1-7 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

ADWR intends to accomplish safe–yield of the aquifers of four of its five AMAs, including the Santa Cruz AMA, by the year 2050. Safe–yield is defined as a condition in which no more groundwater is being extracted than is being replaced. To achieve this, ADWR is interested in evaluating the potential for groundwater recharge, which is one of the components of all alternatives of the Facilities Plan. The rules for the use of renewable sources, such as effluent, are included in the Adequate Water Supply Program. Some of the provisions associated with recharge projects are included in the Groundwater Code of 1980 (ADWR, December 17, 1997).

Santa Cruz County

Santa Cruz County, through its Health Department, is a stakeholder in the Facilities Plan. One of the most important concerns of the County Health Department is the elimination of fugitive raw wastewater flows in the area to reduce potential public exposure to contaminated waters.

Additionally, the County is interested in guaranteeing that any groundwater recharge scheme would not compromise the quality of the receiving water.

City of Nogales

The City of Nogales, Arizona owns 42 percent of the capacity of the NIWTP, or approximately 320 L/s (7.3 mgd) daily average flow. In addition, the City owns the International Outfall Interceptor (IOI), which conveys raw wastewater originated in Ambos Nogales to the NIWTP. The City of Nogales also provides water and sewer service to its residents. The City of Nogales would act as a promoter of the project for purposes of BECC certification, as explained below.

The nearby residential area of Rio Rico, north of the City of Nogales, is served by Rio Rico Utilities, a private water and sewerage company. Currently, Rio Rico has an agreement with the City of Nogales by which Rio Rico is allowed to use 24 L/s (0.55 mgd) of treatment capacity at the NIWTP. Rio Rico is a stakeholder in the Facilities Plan mainly due to its current and potential future use of the NIWTP, and by the potential impact of the NIWTP discharge on its wells located along the Santa Cruz River, downstream of the NIWTP.

1.2.5 Relevant Mexican Lead and Cooperating Agencies

As previously indicated, these agencies are also members of the Mexican Policy Committee and the Mexican Technical Committee involved in the Ambos Nogales Facilities Plan. The functions of these committees are analogous to the functions of their U.S. counterparts. The Technical Committee is responsible for the day–to–day coordination and guidance, whereas the Policy Committee acts as a decision maker and provides guidance in global "big picture" issues. The Mexican committees are composed of federal and state government agencies as described below.

Comisión Internacional de Límites y Aguas

CILA (Comisión Internacional de Límites y Aguas) is an acronym for the Spanish name for the IBWC.

CILA has essentially the same role as USIBWC.

Comisión Nacional del Agua

The Comisión Nacional del Agua (CNA) is a federal entity charged with regulating water rights and water quality. The specific responsibilities of CNA include, among others:

CDM Camp Dresser & McKee 1-8 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

� To encourage and support the development of water, sewer, treatment, irrigation, and flood control programs

� To administer and protect the national waters, and to preserve and protect their quality, as well as to manage watersheds

� To plan, study, construct, operate, and maintain federal hydraulic projects or infrastructure

� To issue water allocations, concessions, permits and rights to act as an arbiter in water conflict resolution

� To promote the efficient use of water and its conservation in all phases of the hydrologic cycle

� To enforce the application of the Ley Nacional de Aguas (National Water Act) and to apply the appropriate sanctions in case of the violation of the law (CNA 1992).

For the case of the Ambos Nogales Facilities Plan, CNA has issued site specific standards referred to as condiciones particulares de descarga, as described in Section 9.3 of the Facilities Plan Report (Modifications for the Short List of Alternatives).

Secretaría de Infraestructura Urbana y Ecología (SIUE)

SIUE is a state government agency responsible for establishing infrastructure and environmental policies at the State level. SIUE also coordinates with COAPAES (described below) for planning water and wastewater infrastructure. In the case of the Facilities Plan, SIUE acts as the representative of the interests of the government of the State of Sonora to enhance the well–being of the residents of the State.

Comisión de Agua Potable y Alcantarillado del Estado de Sonora (COAPAES)

COAPAES, a decentralized agency of the State Government, whose responsibilities include: planning and budgeting of the hydraulic sector of the state; executing the State Government policies for the coordination of potable water and sewer systems; supporting and providing technical assistance to municipal operators; and acting as operator of the water and sewer systems in municipalities which do not have developed operating agencies. In the case of Nogales, Sonora, COAPAES is in charge of managing and operating the water and sewer systems (CNA 1996).

1.2.6 Relevant Binational Agencies

In addition to the national U.S. and Mexican agencies, there are two binational agencies, which are extremely important in ensuring the financial feasibility of the project. These two agencies are described below.

Border Environment Cooperation Commission (BECC)

The North American Free Trade Agreement (NAFTA) produced a side agreement related to the environment, referred to as the Border Funding Agreement between the United States and Mexico.

The signing of this agreement led to the creation of three binational institutions to address water, wastewater, and solid waste concerns: (1) the North American Commission on Environmental

CDM Camp Dresser & McKee 1-9 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

Cooperation (NACEC); (2) BECC; and (3) NADBank (ASCE and the U.S.–Mexican Policy Studies Program 1995).

The NACEC was created to settle trade disputes involving pollution or the enforcement of environmental laws and its members include Canada, the United States, and Mexico (ASCE and the U.S.–Mexican Policy Studies Program 1995), whereas the BECC and NADBank include only the U.S. and Mexico. These organizations are responsible for addressing environmental problems along the U.S.–Mexico border.

"The purpose of BECC is to help preserve, protect, and enhance the environment of the border region in order to advance the well–being of the people of the United States and Mexico" (BECC 1996). In keeping with its mission, the BECC is responsible for evaluating the feasibility, efficiency, and effectiveness of proposed water, wastewater, and solid waste infrastructure projects within a 100 km region along both sides of the U.S.-Mexico border. Projects must comply with criteria established by the BECC. A project would then be eligible for possible funding from the NADBank. The certification criteria established by BECC are classified as follows (BECC 1996):

� Human health and Environment � Technical feasibility � Financial feasibility and Project Management � Community participation � Sustainable development

The Ambos Nogales Facilities Plan is the planning document that will be used to identify a wastewater infrastructure project for Nogales, Arizona, and Nogales, Sonora that will be submitted to BECC for certification. Once certified, the proposed projects would be eligible for NADBank financing. The following paragraph summarizes briefly the role of the NADBank as a financing institution for environmental infrastructure projects along the border.

North American Development Bank (NADBank)

NADBank was also created as part of the Border Funding Agreement. "The purposes of NADBank are to use a small amount of federal capital to leverage a large volume of private–sector lending; to make effective use of local grants and loans from federal and state sources; and to involve financial participation of local citizens" (ASCE and the U.S.–Mexican Policy Studies Program 1995). In addition, the NADBank was established to: "provide financing for projects certified by BECC, as appropriate, and at the request of the BECC, to otherwise assist the BECC in fulfilling its purposes and functions”;

and "to provide financing endorsement by [either the United States or Mexico] for community adjustment and investment in support of the purposes of the NAFTA" (Holub 1997).

1.3 Statement of Purpose and Need

Some of the concerns identified in Section 1.2.3 are a result of inadequate or incomplete coverage of the sewer system in Nogales, Sonora. According to the operating agency, COAPAES, there were in December 1997 a total of 23,699 registered connections to the sewer system. Multiplying the number of connections by the average residential population density provided by Instituto Nacional de Estadístion, Geografía e Informática (INEGI) of 4.3 people per household, and dividing

CDM Camp Dresser & McKee 1-10 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd by the CNA population estimate for the same year of 187,820 people, indicates that only about 54 percent of the population has access to the sewer system. In addition to the incomplete coverage of the system in Nogales, Sonora, many sewer lines in Ambos Nogales are in less than optimal condition, as observed during the infiltration/inflow investigations conducted in both communities (Section 3 of the Facilities Plan). Moreover, the capacity of the IOI, which conveys Ambos Nogales wastewater flows to the NIWTP, is limited by several bottlenecks. Flows in excess of the IOI capacity result in overflows of untreated sewage into the Nogales Wash. Incomplete coverage coupled with less than optimal conditions of the sewer system in its upstream sections also result in fugitive flows, which in most circumstances travel from Mexico into the United States via the Nogales Wash. These fugitive flows are an important public concern, as evidenced by the frequent publication of articles in local newspapers.

In addition to the fugitive flow problem, the hydraulic capacity of the NIWTP is near its limit. As population grows, the remaining capacity of the NIWTP will be exhausted. Furthermore, water supply and consumption and the accompanying wastewater production are expected to grow in the near future as the acuaférico project is implemented in Nogales, Sonora. The acuaférico project would increase the amount of water delivered, the level of coverage of the water system, and the per capita water consumption (Section 5 of the Facilities Plan).

From a water quality perspective, the effluent quality limits for the NIWTP are currently being revised (Section 2.3 of the Facilities Plan). The proposed permit calls for the reduction of potential toxicity to aquatic life, which implies a reduction in ammonia concentrations. Additionally, there is a concern about the potential impact of effluent with high total nitrogen concentrations, since nitrogen could potentially be transformed to nitrate [(NO3)

-], affecting the potable water wells located downstream of the wastewater treatment plant, such as those serving Rio Rico. As a result of these new regulatory requirements, the wastewater treatment plant will require upgrading in the near future regardless of concerns with capacity limitations.

1.4 Project Description

Sections 9.1 and 9.2 of the Facilities Plan present a detailed discussion of preliminary screening of alternatives and plan selection, respectively. As indicated in the Facilities Plan, seventy–six (76) alternatives were developed and evaluated. These seventy–six alternatives can be grouped into six (6) conceptual alternatives.

Following standard NEPA practice, this EA evaluates three action alternatives and a “no action” alternative, for a total of four evaluated alternatives. The three Action Alternatives for the EA are associated with changes to the wastewater treatment system currently in place. EA Alternatives A, B, and C were originally identified as conceptual Alternatives 3, 4, and 6, respectively. The No Action Alternative (D) assumes no changes to the current system, and corresponds to conceptual Alternative

5. Each of these alternatives are described below and the three action Alternatives (A, B, and C) are graphically presented as Figures 2, 3, and 4, respectively.

Alternative C is the recommended alternative. Alternative C, like Alternatives A and B, includes components in Nogales, Arizona and Nogales, Sonora. Construction of the different components may be phased, depending on funding availability and other factors.

CDM Camp Dresser & McKee 1-14 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

1.4.1 Environmental Assessment Alternatives

The descriptions of the four environmental alternatives are presented below.

1.4.1.1 Environmental Assessment Alternative A

Alternative A was originally identified as conceptual Alternative 3. This alternative would retain the NIWTP, which would be upgraded and used exclusively for treating flows from Mexico conveyed by the existing IOI, which will also be rehabilitated. Upgrade of the NIWTP will be accomplished by converting the aerated lagoon system to a conventional activated sludge system with sludge recirculation. Existing basins will be retrofitted to an activated sludge process using nitrification and denitrification, and secondary clarifiers will be added. The new system will allow the facility to increase the removal of nitrogen as well as Biochemical Oxygen Demand (BOD) and Total Suspended Solids (TSS). The capacity of the upgraded NIWTP will be 412 L/s (9.4 mgd).

Mexican flows in excess of the IOI and/or NIWTP capacity would be conveyed to a new WWTP in Mexico located adjacent to Los Alisos River. A pumping system will be in place in Nogales, Sonora, based on a series of pump stations capable of handling Mexican flows in excess of the Mexican allocation to the NIWTP. The wastewater treatment plant in Los Alisos under this alternative would be based on an activated sludge system with biological nutrient removal. The biological treatment would be accomplished by means of an oxidation ditch, and the wastewater treatment plant would include headworks, clarifiers and disinfection, as well.

Wastewater originating in Arizona would be treated at a new WWTP at the Nogales, Arizona Industrial Site. Associated with the new Arizona WWTP would be the construction of a new interceptor that would convey wastewater from Nogales, Arizona to the new WWTP at the Industrial Site. Treated effluent would be pumped to the Santa Cruz River near Kino Springs or to Potrero Creek for discharge in Arizona. Mexico would discharge at the new WWTP site at Los Alisos directly to the Los Alisos River. The wastewater collection systems in Nogales, Arizona and Nogales, Sonora, as well as the IOI, would also be rehabilitated under this alternative.

Currently, the NIWTP discharges an average of about 504 L/s (11.5 mgd) to the Santa Cruz River at the existing outfall. Under Alternative A, flows to the NIWTP would drop to approximately 412 L/s (9.4 mgd) in 2020. The effluent from the NIWTP would contain reduced concentrations of total nitrogen, BOD, and TSS, under this alternative.

1.4.1.2 Environmental Assessment Alternative B

Alternative B was originally identified as conceptual Alternative 4. Under this alternative, the NIWTP and the IOI would be upgraded as necessary to collect and treat all flows from Nogales, Arizona. The IOI and the wastewater collection systems in Nogales, Arizona and Nogales, Sonora would be replaced or rehabilitated as needed. Effluent treated at the upgraded NIWTP would be discharged to the Santa Cruz River using the existing outfall. All wastewater originating in Mexico would be collected in Mexico near the International Border and pumped back to Los Alisos for treatment and subsequent discharge directly to the Los Alisos River.

Upgrade of the NIWTP would also be accomplished by converting the aerated lagoon system to a conventional activated sludge system with sludge recirculation. Existing basins will be retrofitted

CDM Camp Dresser & McKee 1-15 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd to an activated sludge process employing nitrification/denitrification and secondary clarifiers would be added. The new system will allow the facility to reduce the overall nitrogen as well as biochemical oxygen demand (BOD) and suspended solids (SS). The capacity of the upgraded NIWTP would only be required to be 202 L/s (4.6 mgd) based on the projected wastewater production of Nogales, Arizona for the year 2020. The wastewater treatment plant in Los Alisos would incorporate the same process train proposed for Alternative A, and only the capacity would be different. Under this alternative, the Mexican wastewater treatment plant would have an average capacity of about 1,117 L/s (25.5 mgd). Wastewater would be delivered to the wastewater treatment plant by means of a pumping scheme, similar to the system described under Alternative A. This pumping system, however, would incorporate a pump station at the U.S.-Mexico border, and multiple pump stations would be required for appropriate conveyance of all the Mexican flows to Los Alisos.

Implementation of this alternative would then reduce the volume of water currently discharged from the NIWTP to the Santa Cruz River from approximately 504 L/s (11.5 mgd) to the 202 L/s (4.6 mgd) referenced above. The effluent from the NIWTP would also contain reduced concentrations of nitrogen (overall), BOD, and TSS under this alternative. The effluent from the NIWTP would also contain reduced concentrations of total nitrogen, BOD, and TSS, under this alternative.

1.4.1.3 Environmental Assessment Alternative C

Alternative C was originally identified as conceptual Alternative 6. Under this alternative, the existing IOI would be replaced with a new enlarged version and the NIWTP will be upgraded and expanded in capacity. The NIWTP will continue to service the wastewater generated in both the communities of Nogales, Arizona and Sonora. In addition, the wastewater collection systems in Nogales, Arizona and Nogales, Sonora would be rehabilitated.

The respective allocations to Nogales, Sonora, defined in a binational agreement will remain at 434 L/s (9.9 mgd). The remainder of the current capacity, 320 L/s (7.3 mgd), is reserved for Arizona.

Mexican flows in excess of that treated at the NIWTP would be conveyed to a new WWTP in Mexico at Los Alisos. Effluent from the new Los Alisos WWTP would be discharged directly to the Rio Los Alisos.

Even though the respective allocations for Nogales, Sonora and Nogales, Arizona will remain the same (434 L/s [9.9 mgd] and 320 L/s [7.3 mgd], respectively) for a total capacity of 754 L/s (17.2 mgd), this alternative provides for expansion of the NIWTP to accommodate potential flows from Mexico in excess of their allocation as a result of storm events, system failures and until later phases of the Mexican wastewater system are implemented. In addition, projected water system improvements in Nogales, Sonora will possibly lead to increased wastewater flows ahead of the pumping system improvements associated with this alternative. Although the exact amount of expansion is undetermined at this time, it is anticipated that the NIWTP capacity may be increased by 131 L/s (3 mgd) to 219 L/s (5 mgd).

This increase in the NIWTP capacity is not necessarily associated with an immediate increase in the amount of effluent discharged to the Santa Cruz River from the wastewater treatment plant. Over time, as the increased treatment capacity is utilized, the volume of effluent discharged to the Santa Cruz River would increase. Therefore, increases in effluent discharged to the river would be realized only gradually as human population and water use increased.

CDM Camp Dresser & McKee 1-16 S:\users\mklatt\projects\pmd99021\task8\working\ea120_new.wpd

Upgrade of the NIWTP would also be accomplished by converting the aerated lagoon system to a conventional activated sludge system with sludge recirculation. Existing basins will be retrofitted to an activated sludge process employing nitrification/denitrification and secondary clarifiers would be added. The new system will allow the facility to reduce nitrogen as well as BOD and TSS.

The wastewater treatment plant in Los Alisos, under this alternative, will be based on a natural system. The treatment train will consist of a series of lagoons (deep facultative, high algae growth, settling, and maturation/filtration), with configuration known as Advanced Pond Systems. These ponds will be capable of lowering the concentration of BOD, TSS and, to a varying degree, total nitrogen, to comply with the site specific discharge conditions issued by the Mexican government for this site, as described in Section 9 of the facilities plan (Plan Screening and Selection). Under this alternative, a pumping system very similar to the system described under Alternative A, would be required for wastewater conveyance to Los Alisos. In this case, however, the pump stations would have the capacity to pump only the average flows in excess of the Mexican allocation to the NIWTP.

Peak flows associated to storm events would not be pumped to Los Alisos, and would be bypassed to the gravity system, allowing them to flow north, cross the border and be conveyed to the NIWTP.

Under this scheme, additional hydraulic capacity would be provided in the gravity lines downstream of the pump stations (Mexican collectors and the IOI), to assure appropriate conveyance of the peak flows to the NIWTP.

Implementation of this alternative would not decrease the volume of water currently discharged from the NIWTP. Typical current discharge flows are based on the minimum (386 L/s (8.8 mgd)) and maximum (701 L/s (16.0 mgd)) average monthly flows measured during the 1994–1997 time period.

The average discharge flow (504 L/s (11.5 mgd)) is the overall 4–year average daily flow measured at the NIWTP. Effluent volume leaving the NIWTP would be maintained at levels equal to or exceeding the current minimum monthly flow of 386 L/s (8.8 mgd). The new system will allow the facility to reduce the overall nitrogen as well as biochemical oxygen demand (BOD) and suspended solids (SS).

1.4.1.4 Environmental Assessment Alternative D (No–Action Alternative)

Implementation of this alternative would result in no major upgrades and/or expansions to the existing infrastructure or wastewater treatment processes. Currently, all wastewater generated in Ambos Nogales is conveyed to the NIWTP where it undergoes aerated lagoon–based treatment, sludge retention and polishing, prior to discharge to the Santa Cruz River just downstream of the NIWTP. Any current beneficial or adverse environmental effects would remain under this alternative.

The population projections performed under this facility plan indicate that the average daily flow of domestic wastewater generated in Ambos Nogales will increase from its present level of 504 l/s (11.5 mgd) to 1,207 l/s (29 mgd) by the year 2020.