Responses to Questions Received Against 191BWC22R0005.pdf

PDF 127 KB Posted

Attached to
Nogales IOI Rehabilitation Phase 4 & 5
Solicitation number
191BWC22R0005
Issued by

View the file

Other files

File Type Posted
191BWC22R0005 Amendment A00004.pdf PDF
191BWC22R0005_Solicitation_Revised_A00002_draft.pdf PDF
191BWC22R0005 Amendment A00003.pdf PDF
CON_PenaBlancaHighlandsSouthOffsite_as builts.pdf PDF
191BWC22R0005_IOI_Rehab_PH45_Specs_20220602.pdf PDF
CityofNogales_20200924_Pena Blanca Outfall Sewer As-Built.pdf PDF
191BWC22R0005_Solicitation_Revised_A00002.pdf PDF
Responses_to_Additional_Questions_Received_Against_191BWC22R0005.pdf PDF
NIOI Hydrographs_20220524.pdf PDF
City of Nogales Flow Information Lift Station.pdf PDF
191BWC22R0005 Amendment A00002.pdf PDF
191BWC22R0005_Solicitation_Revised_A00001.pdf PDF
IOI PH4-5 _Pre-Proposal Agenda_Final.pdf PDF
191BWC22R0005 A00001.pdf PDF
191BWC22R0005_IOI_Rehab_PH4-5_Specs_20220517.pdf PDF
IOI PH4-5_Pre-Proposal Sign-In.pdf PDF
Attachment 11. Nogales International Outfall Pipe Survey_20150423.pdf PDF
Attachment 09. NIWTP Flow Reports_Jan-Dec2020.pdf PDF
Attachment 13. Nogales Intl Sanitation Project Construction Report_1969-1972.pdf PDF
Attachment 19. 'IBWC Form 110.pdf PDF
Attachment 04. RFP Client Authorization Letter.docx DOCX document
Attachment 08. NIWTP & IOI EA and FONSI_1999.pdf PDF
Attachment 12. B&C Evaluation of IOI Report_200503.pdf PDF
Attachment 20. IBWC Form 116.pdf PDF
Attachment 02. 191BWC22R0005 Phase V Drawings_20220309.pdf PDF
Attachment 21. IBWC Form 117.pdf PDF
Attachment 06. IOI Rehab Design Report woE_20180411.pdf PDF
Attachment 07. IOI Rehab Geotechnical Report_20150121.pdf PDF
Attachment 18. UPRR Requirements & Guidelines.pdf PDF
Attachment 05. RFP Past Performance Questionnaire.pdf PDF
Attachment 16. NADB IOI Direct Laterals Design.pdf PDF
Attachment 03. 191BWC22R0005 IOI Rehab PH 4&5 20220419.pdf PDF
Attachment 14. Nogales International Sanitation Project As-Builts_19710501.pdf PDF
Attachment 10. NIWTP Flow Reports_Jan-Dec2021.pdf PDF
191BWC22R0005 Nogales IOI Phases 4 and 5.pdf PDF
Attachment 01. 191BWC22R0005 Phase IV Drawings_20220309.pdf PDF
Attachment 17. UPRR IOI MCL Folder03060-53.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

191BWC22R0005 Page 1 of 3

Answers Questions Received Against 191BWC22R0005 – Nogales IOI Rehab Phases 4 & 5

1. Can a contractor submit a Bid as a Prime (GC) and also take a subcontractor role to a different Prime ?

Response 1: No

2. Can a subcontractor with over 15% scope of work bid to more than one Prime?

Response 2: Yes

3. Would the project consider a CIPP liner that is an approved equal that meets or exceeds the project specifications but would alter the minimum design thickness? The composite liner (felt/fiberglass) is thinner and stronger and allows more competitive bids due to efficiencies with freight/weight of liner, and better productivity to install.

Response 3: Yes, the project would consider a CIPP liner that is an approved equal that meets or exceeds the project specifications. The Contractor shall be responsible for ensuring that the final design of the liner proposed complies with all specifications and site specific requirements of the project. Also note that all CIPP design documents and calculations including thickness are required to be signed and sealed by an Arizona P.E. per Specification Section 46.04.00 1.9 C.”

4. Is the Inspector required to be on site at all times, or as typical, to be on-site at key times of construction – Post video, Manhole testing, etc? What is the overtime inspection rate?

Response 4: See Solicitation Clause H.10. The Government/Construction Inspector will be onsite full-time (40 hours per week). The Inspector's regular shifts will be arranged based on Contractor's normal working hours or weekly schedule. If the Contractor will work overtime beyond their normally scheduled hours, the Government shall determine if inspection services are required at its sole discretion depending on Contractor activities. If the Inspector is required to be onsite for overtime work, the Contractor shall be responsible for paying the overtime (OT) costs.

The OT rates are not yet finalized. The OT rates per day and per hour are for the Construction Inspector under the Construction Management Contractor to be selected. Examples of past rates on USIBWC projects are listed below per year. . Rates vary per Contract. The actual rates will be provided to the Construction Contractor after award of the CM Contractor.

• 2015 - $166/hr and $1,328/day (8-hrs)

• 2016 - $160/hr and $1,452/day (8-hrs)

• 2017 - $155/hr and $1,239/day (8-hrs)

• 2018 - $171/hr and $1,615/day (8-hrs)

• 2021 - $166/hr and $1,321/day (8-hrs)

5. Are we allowed to work on Phases 4 & 5 simultaneously?

Response 5: Yes

6. Will Owner extend the question deadline?

Response 6: In order to ensure all questions are answered, a second due date of May 27, 2022 has been provided for any additional questions.

7. Sections between manholes on the IOI are very long and are not typical in other areas on sewer mains of this type. This creates problems with maintenance as camera and cleaning equipment

191BWC22R0005 Page 2 of 3 cannot cover these long reaches. Will the contractor be allowed to build a new access in between these long sections? If so, what would be the preferred method of installation?

Response 7: The Contractor will not be allowed to build a new access point within long sections of CIPP. Each segment of CIPP should be one liner, continuous between the existing manholes. If an additional manhole is requested within a long section, the Government would need to evaluate and approve a new manhole. The intent is to not add any new manholes unless absolutely necessary.

The Government would need to consider various factors including location (ROW may require additional permitting), access, depth, and property owner agreements as required. If allowed, the installation method is at the discretion of the Contractor, however, any new manholes must meet the standards included in the Contract drawings and specifications.

8. The project has a defined duration in the RFQ and there is a given amount of unknown time related to permitting and regulatory requirements and non-working time for monsoon moratorium.

All things aside if the permits are acquired and the work can be performed in less than the contract time or at a reduce schedule will that be acceptable?

Response 8: Yes.

9. There is a monsoon moratorium that permanent work cannot be completed due to the risk of I&I and interruption of flows. Can the general contractor work on non-permanent work i.e. (bypass setup, grading work, pioneering and access development, etc.)

Response 9: Yes. Note that the Contractor can work on any portion of the project, even permanent work, outside the Nogales Wash area during monsoon season. During monsoon season, work within the Wash is not allowed for safety reasons. The Contractor should take into account when preparing their schedule that working during the monsoon season may include higher levels of I&I and higher IOI sewage flows.

10. The bid schedule has arbitrary quantities for excavation, pipe repair, and backfill that is not defined on the plan set. If the intent this will be an allowance to make point repairs if found during the construction project? Has there been any viable example that can be provided? The scope of a repair could be significantly different depending on the location, depth, and length.

Response 10: Yes, reference the payment and measurement paragraphs of all applicable sections. There are currently no real examples to provide, and the needs for this work would be handled on a case by case basis. As an example, if a segment of pipe requires repair to perform the CIPP, a point repair would be required that would then be measured and paid for under the applicable CLINS. It is understood the scope of repair could be different based location, depth, and condition, therefore, the Contractor is responsible for reviewing all Contract documents including the provided plan and profiles to estimate and prepare their proposal based on anticipated conditions.

11. Due to the nature of CIPP lining especially on long water cure shots there might be outside the published work hours. Will this be an issue, and will the contractor be responsible for the cost associated with the time in this example?

Response 11: There is no issue with working overtime, it just has to be requested beforehand.

Also see Solicitation Clause H.10.

Yes, the Contractor is responsible for all overtime hours and costs for their own work/employees and for any overtime costs for inspection services associated with this work. See response #2. It is understood that CIPP installation and curing is a continuous process until completed, and so the Government does not expect the Inspector to be onsite at all times during curing.

191BWC22R0005 Page 3 of 3

12. Due to the bid not being due until the middle to end of June can the question-and-answer time be extended as we have time to develop our submittals there might be questions associated with the document and/or plans?

Response 12: See response #4.

1. Can a contractor submit a Bid as a Prime (GC) and also take a subcontractor role to a different Prime ?
2. Can a subcontractor with over 15% scope of work bid to more than one Prime?
3. Would the project consider a CIPP liner that is an approved equal that meets or exceeds the project specifications but would alter the minimum design thickness? The composite liner (felt/fiberglass) is thinner and stronger and allows more competiti...
4. Is the Inspector required to be on site at all times, or as typical, to be on-site at key times of construction – Post video, Manhole testing, etc? What is the overtime inspection rate?
5. Are we allowed to work on Phases 4 & 5 simultaneously?
6. Will Owner extend the question deadline?
7. Sections between manholes on the IOI are very long and are not typical in other areas on sewer mains of this type. This creates problems with maintenance as camera and cleaning equipment cannot cover these long reaches. Will the contractor be allow...
8. The project has a defined duration in the RFQ and there is a given amount of unknown time related to permitting and regulatory requirements and non-working time for monsoon moratorium. All things aside if the permits are acquired and the work can b...
9. There is a monsoon moratorium that permanent work cannot be completed due to the risk of I&I and interruption of flows. Can the general contractor work on non-permanent work i.e. (bypass setup, grading work, pioneering and access development, etc.)
10. The bid schedule has arbitrary quantities for excavation, pipe repair, and backfill that is not defined on the plan set. If the intent this will be an allowance to make point repairs if found during the construction project? Has there been any via...
11. Due to the nature of CIPP lining especially on long water cure shots there might be outside the published work hours. Will this be an issue, and will the contractor be responsible for the cost associated with the time in this example?
12. Due to the bid not being due until the middle to end of June can the question-and-answer time be extended as we have time to develop our submittals there might be questions associated with the document and/or plans?