Attachment 04b - Draft_Relay Acceptance Test Procedures.docx

DOCX document 5 MB Posted

Attached to
DRAFT RFP for Integrated Battle Command System (IBCS) LRIP/FRP Federal contract opportunity
Solicitation number
W31P4Q-20-R-0015
Issued by
Department of the Army Materiel Command Contracting Command Redstone Arsenal

About this file

This is a draft Request for Proposal for the Integrated Battle Command System Low Rate Initial Production/Full Rate Production hardware segment. The Army seeks to produce IBCS hardware end items in accordance with supplied Technical Data Packages and the Critical Item Development Specification. Engineering changes may be required for obsolescence, new capabilities, and export considerations. Offerors are advised not to submit a proposal in response to this draft as the Government is currently seeking comments only and not proposals. The effort requires maintaining approved software and firmware updates, cybersecurity, authority to operate, and engineering changes during the performance period.

View the file

Other files for this federal contract opportunity

Other files attached to DRAFT RFP for Integrated Battle Command System (IBCS) LRIP/FRP, newest first.
File Type Posted
Attachment 22a.2 - PDRS Support information for integration task.pptx PPTX presentation
Attachment 15b - Fixed Price Level of Effort Labor Categories.xlsx XLSX spreadsheet
Attachment 10h - SWFMEA RESULTS.xlsx XLSX spreadsheet
Attachment 22a.1.h - PL-ALH-211130 00 CABLE ASSEMBLY CASS DC POWER.pdf PDF
Attachment 04c - ECT_Acceptance Test Procedures_FINAL.DOCX DOCX document
Attachment 22a.1.a - ALH-208670 05 IBCS SHELTER INTERCONNECT.pdf PDF
Attachment 10a.4 – R004 IGRM-FMECA.xlsx XLSX spreadsheet
Attachment 13 - Training Documentation.docx DOCX document
Attachment 10a.9 – R015 PDU Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 10a.5 – R005 SCIM-FMECA.xlsx XLSX spreadsheet
Attachment 22a.1.j - PL-ALH-215333 00 S-280 CASS INSTALLATION.PDF PDF
Attachment 10c.5 – E050 KG-250X-FMECA.xlsx XLSX spreadsheet
Attachment 10b.9 – E033 R112 Shelter – Server Stack – 03-FMECA.xlsx XLSX spreadsheet
Attachment 10b.2 – E002 Power Inverter Shelter Power-FMECA.xlsx XLSX spreadsheet
Attachment 10a.13 – R031 Black Router--FMECA.xlsx XLSX spreadsheet
Attachment 10a.1 – R001 HRFU-FMECA.xlsx XLSX spreadsheet
Attachment 19 - Section L - Instructions - Conditions - And Notices To Offerors.docx DOCX document
Attachment 10c.8 – E053 Shelter Time Server-FMECA.xlsx XLSX spreadsheet
Attachment 10e.9 – E147 – Table 3 Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 22a.1.b - ALH-209032 00 CABLE ASSEMBLY CASS ETHERNET.pdf PDF
Attachment 10c.1 – E043 Firewall Red-FMECA.xlsx XLSX spreadsheet
Attachment 02 - AIAMD System of Systems (SoS)(MIS-PRF-56500).pdf PDF
Attachment 10b.1 – E001 28VDC Pwr Supply Shelter Power-FMECA.xlsx XLSX spreadsheet
Attachment 10e.11 – E149 – Table 5 Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 10d.2 – E144 RWS Bkup Batteries-FMECA.xlsx XLSX spreadsheet
Attachment 12 - Risk Management Plan.pdf PDF
Attachment 21 - Task Order 0001 Statement of Work.docx DOCX document
Attachment 10c.10 – E060 Shelter Switch – 02-FMECA.xlsx XLSX spreadsheet
Attachment 10a.16– R034 Media Converter Power Supply-FMECA.xlsx XLSX spreadsheet
W31P4Q-20-R-0015_DRAFT_28 May 2020.pdf PDF
Attachment 10a.3 – R003 KG-250X-FMECA.xlsx XLSX spreadsheet
Attachment 13c - IBCS-A301-003 Vol II Instructor Guide.pdf PDF
Attachment 22a.1.f - EOC Shelter views.pptx PPTX presentation
Attachment 22a.1.d - ALH-213030 00 CABLE ASSEMBLY, CASS J1 AND J3.pdf PDF
Attachment 10a.14 – R032 Media Converter Module 11-FMECA.xlsx XLSX spreadsheet
Attachment 20 - Section M - Evaluation Factors For Award.docx DOCX document
Attachment 22a - CASS to PDRS.docx DOCX document
Attachment 10d.7 – E153 RS112 Server -06 Shelter with PT-FMECA.xlsx XLSX spreadsheet
Attachment 10e.10 – E148 – Table 4 Assembly-FMECA.xlsx XLSX spreadsheet
Attachment 10e.5 – E122 – EMI Tent PDU-FMECA.xlsx XLSX spreadsheet
Attachment 17 - Pre-Award Survey Accounting System Checklist.pdf PDF
Attachment 22a.1.g - PL-ALH-209032 00 CABLE ASSEMBLY CASS ETHERNET.pdf PDF
Attachment 22a.1.e - ALH-215333 00 S-280 CASS INSTALLATION.PDF PDF
Attachment 22a.4 - CASS Task Purpose.pptx PPTX presentation
Attachment 10a.15 – R033 Media Converter Module 12-FMECA.xlsx XLSX spreadsheet
Attachment 10c.6 – E051 IGRM-FMECA.xlsx XLSX spreadsheet
Attachment 03 - GFP Attachment - LRIP_FRP - 20 April 2020.xlsx XLSX spreadsheet
Attachment 04 - Acceptance Test Plan.docx DOCX document
Attachment 10c.13 – E063 Isolation Router Black-FMECA.xlsx XLSX spreadsheet
Attachment 10b.8 – E032 R112 Shelter – Server Stack – 02-FMECA.xlsx XLSX spreadsheet
Show all 50

DRAFT RFP for Integrated Battle Command System (IBCS) LRIP/FRP has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISCLAIMER

The following document is a product from the Engineering, Manufacturing and Development (EMD) phase of this program. As this program moves into Low Rate Initial Production/Full Rate Production (LRIP/FRP), changes to this document will be required.
This document is currently in its draft form. All sections are subject to change as needed, but some sections are already under review and updates are being prepared. Below is a list of the sections known to need substantial updates. These updates stem from a distinct deviation between the EMD contract and the LRIP/FRP contract. During EMD, the test asset and test software was contractor owned and proprietary. The current position of the program is for the program office to provide the test asset and necessary software to stimulate the hardware and software to prove functionality of the system.

Sections known to need updates

· 1.2. IPTA 2

· 2.2. Test Setup & Diagrams

· 3.2. Configure the A-Side Interface Panel Network Connectivity Workstation

· 4.2. A-Side Interface Panel Network Connectivity

· 4.3. Automatic Software Initialization Check

· 4.4. PATRIOT Functionality & Alt Media

· 4.5. Sentinel Functionality & HRFU

· 4.6. Software Shutdown and Data Harvest

Integrated Air and Missile Defense (IAMD) Battle Command System (IBCS) Acceptance Test Procedures – Relay – Addendum A

DOCUMENT NUMBER:
RELEASE:
DOCUMENT DATE:
IBCS-A249-ADDENDUM A-003
003
9 May 2019
CDRL NUMBER:
CONTRACT:
CONTRACT NUMBER:
A249
IBCS
W31P4Q-08-C-0418

Test and Evaluation Document

EXPORT CONTROL WARNING
DISTRIBUTION STATEMENT D
WARNING -This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.
Distribution authorized to the Department of Defense and U.S. DoD contractors only; Software documentation; 05 Jan 2007. Other requests shall be referred to the Program Executive Office Missiles and Space, Integrated Air and Missile Defense (IAMD) Project Office, ATTN: SFAE-MSLS-IAMD, Bldg. 5250 Martin Road, Redstone Arsenal, AL 35898-8000.
DISCLAIMER STATEMENT AND DISTRIBUTION RESTRICTION
FOR OFFICIAL USE ONLY
The views, opinions, and/or findings contained in this report are those of the author(s) and should not be construed as an official Department of Defense position, policy, or decision, unless so designated by other official documentation.
This document contains information EXEMPT FROM MANDATORY DISCLOSURE under the FOIA. Exemption 3 applies. (Reference: Army Regulation 25-55)

This material is based upon work supported by the U.S. Army Aviation and Missile Command under Contract No. W31P4Q-08-C-0418.

Prepared for:
Prepared by:

Integrated Air and Missile Defense (IAMD) Battle Command System (IBCS) Northrop Grumman Mission Systems Missile Defense and Protective Systems Division

213 Wynn Drive

Huntsville, AL 35805-1928

CAGE Code 9F909

For Official Use Only

IBCS-A248-001

18 April 2018

Copyright 2020 Northrop Grumman Systems Corporation.

IBCS.DM.025.24 (Jan16)

Printed document is reference document only. Verify document date with on-line system.

Copyright 2020 Northrop Grumman Systems Corporation.

For Official Use Only Integrated Air and Missile Defense (IAMD) Battle Command System (IBCS)

Acceptance Test Procedure – Relay IBCS-A249-Addendum A-003 Approval Sheet

SIGNATURES FOR RELEASE:

Author:
/Signature on file/

5/6/19

Keith Huck, IBCS T&E System Test Engineer

Date

Approved By:
/Signature on file/

5/6/19

Bob Faulkner, IBCS T&E System Test Manager

Date

Approved By:
/Signature on file/

5/6/19

Robert Mason, IBCS T&E IPT Lead

Date

Approved By:
/Signature on file/

5/6/19

Lori Tatom, IBCS Mission Assurance Lead

Date

Approved By:
/Signature on file/

5/6/19

Mark Rutledge, IBCS Chief Engineer

Date

Approved By:
/Signature on file/

5/6/19

Randy Tylicki, IBCS Program Director

Date

Document Release:
/Signature on file/

5/6/19

Mark Smith, IBCS Configuration/Data Management

Date

Document Type:

Test and Evaluation

Preparing Organization (if different from owning organization)
Hardware and Software Used
N/A
PC Microsoft Office Suite

Notes or Comment:

N/A

Northrop Grumman Mission Systems Missile Defense and Protective Systems Division IAMD Battle Command System (IBCS) 213 Wynn Drive Huntsville, Alabama 35805-1928

CHANGE RECORD

Release Number

Date
Authority
Pages Affected
Remarks

25 July 2018

SOW Para 3.2.9.2.5
All

Initial release

002
20 Feb 2019
SOW Para 3.2.9.2.5
All

Fig 2-3 Fig 2-4 Fig 2-5 Incorporate redline from test execution on the first three Relays Updated – PATRIOT test config diagram Updated – Sentinel test config diagram Added – A-Side Interface test config diagram PCCB 528

003
9 May 2019
SOW Para 3.2.9.2.5
All

All Updated – IPTA 3 to IPTA 2 Updated – Procedures from v4.0 to v4.5

Fig 2-3 Fig 2-4 Fig 2-5 Updated – PATRIOT test config diagram Updated – Sentinel test config diagram Updated – A-Side Interface test config diagram

Table of Contents

1. Overview1
1.1. IBCS IFCN Relay1
1.2. IPTA 22
1.3. Relay Test Equipment8
2. Test Organization and Diagrams9
2.1. Table of Test9
2.2. Test Setup & Diagrams10
2.2.1. Test Defense Plan / Force Laydown10
2.2.2. IPTA to Relay Test Configuration12
2.2.3. Power Sub-System & Battery15
2.2.4. Relay Plug & Fight Processing Unit (PFPU)16
2.2.5. IFCN Network Enclosure17
2.2.6. A-Side Panel20
3. Pretest Steps21
3.1. Configure the BPU into Test Mode21
3.2. Configure the A-Side Interface Panel Network Connectivity Workstation25
4. Test Procedures27
4.1. Hardware Power Up27
4.2. A-Side Interface Panel Network Connectivity35
4.3. Automatic Software Initialization Check45
4.4. PATRIOT Functionality & Alt Media48
4.5. Sentinel Functionality & HRFU74
4.6. Software Shutdown and Data Harvest90
4.7. Hardware Shutdown99
5. Post Test Steps to Return UUT to Baseline Configuration102
5.1. Reset BPU to Operation Mode102

List of Figures

Figure 11. IFCN V2 Relay2
Figure 12. IPTA 2 Overview4
Figure 13. IPTA 2 Red Rack6
Figure 14. IPTA 2 Black Rack7
Figure 21. PATRIOT Launcher & Alt Media Force Laydown10
Figure 22. Sentinel Radar & HRFU Force Laydown11
Figure 23. PATRIOT Run –Test Configuration (Relay IFCN via Alt Media)12
Figure 24. Sentinel Test Configuration (Relay IFCN Connection via HRFU)13
Figure 25. A-Side Interface Panel Network Connectivity14
Figure 26. Power Sub-System & Battery15
Figure 27. Relay PFPU16
Figure 28. Network Enclosure Exterior View17
Figure 29. Network Enclosure Interior View18
Figure 210. BPU18
Figure 211. Network Enclosure Signal & Power Panels19
Figure 212. A-Side Interface Panel20

List of Tables

Table 11. Relay Test Equipment8
Table 21. IFCN V2 Relay Table of Tests9
Table 31. Configure BPU Into Test Mode21
Table 32. A-Side Interface Panel Network Connectivity Workstation25
Table 41. Hardware Power Up27
Table 42. A-Side Interface Panel Network Connectivity35
Table 43. Automatic Software Initialization Check45
Table 44. PATRIOT Functionality & Alt Media48
Table 45. Sentinel Functionality & HRFU74
Table 46. Software Shutdown and Data Harvest90
Table 47. Hardware Shutdown99
Table 51. Reset BPU to Operation Mode102

Copyright 2020 Northrop Grumman Systems Corporation.

Overview The objective of this Acceptance Test Description / Procedure (ATD/P) addendum is to provide the detail test steps necessary demonstrate key functionality of the Integrated Air and Missile Defense (IAMD) Battle Command System (IBCS) Relays and to confirm conformity of integrated hardware and software end items with the qualified baseline. The qualified baseline is the successful integration Major End Item (MEI) hardware and software.

IBCS Mission Assurance (MA) has the overall responsibility for all acceptance activities for the MEIs produced on the IBCS contract. In order to meet overall program milestones, the initial Relays will be acceptance tested with the Plug & Fight Processing Unit (PFPU) and the most current approved 4.5.x version of the IBCS software.

Satisfaction of the following criteria shall constitute successful completion of the Acceptance Test (AT) process:

1. Hardware components shall exhibit no defects during In-process and Functional Check-Out (FCO).

2. After hardware and software integration, Information Assurance (IA) scans and analysis will be conducted to ensure the system is in compliance with applicable Information Assurance Vulnerability Alert (IAVA) and Security Technical Implementation Guide (STIG) requirements to ensure IA hardening and reduce cyber vulnerabilities.

3. Following IA scans MEI hardware initialization, operations, data harvesting, and shutdown shall be completed without functional failure and/or error In Accordance With (IAW) the procedures detailed in this addendum.

IBCS IFCN Relay The Integrated Fire Control Network (IFCN) Relay features common hardware and software in a form factor that is intended to impose minimal impact to Air and Missile Defense (AMD) legacy platforms. The Plug and Fight (P&F) “B-Side” application layer interfaces with the appropriate “A-Side” Component Acquisition Program (CAP) adaptation layer for each particular weapon or sensor in the Army Integrated Air and Missile Defense (AIAMD) System of Systems (ASoS). The IFCN Relay provides a mobile communications node that extends connectivity to remote launcher and sensor deployments by expanding the range of Line-of-Sight (LOS) communications over the horizon and around intervening terrain features.

The IBCS IFCN provides the framework to distribute fire control quality data, commands, and messages among IBCS Engagement Operations Centers (EOCs) and P&F-enabled weapons and sensors. The IFCN consists of network components within the two MEIs and transport media used for voice, data, and video information exchanges between IBCS components.

The IFCN Relay is integrated on the IFCN Relay Platform (IRP) which is an IBCS-modified XM1061E1 Flat Bed Trailer that incorporates Non-Developmental-Items (NDIs), Commercial Off-The-Shelf (COTS), Government Furnished Equipment (GFE), and IBCS-developed CSCIs within software builds (see Figure 11 for an illustration).

Figure 11. IFCN V2 Relay

IPTA 2

An IBCS Production Test Asset (IPTA) will be used in support of AT. Each IPTA includes a pair of equipment racks with a minimal amount of standard MEI equipment needed to be utilized during EOC and IFCM V2 Relay MEI AT. During MEI AT, the IPTA is meant to function such that the Unit Under Test (UUT) perceives the IPTA as a tactical EOC. The UUT will be connected to IPTA using the same connections it would in the field. Using IBCS Test Exerciser (ITEx) software, the IPTA will stimulate the UUT and simulate an engagement scenario. The IPTA will provide weapon and sensor data to the UUT, but the engagement will be controlled and directed from the UUT. The ITEx provides a closed-loop simulation / stimulation execution engine for exercising IBCS components and offers the following capabilities:

1. Provides the truth picture of battle elements (Tactical Ballistic Missiles (TBMs), Cruise Missiles (CMs), Red and Blue aircraft, and direct support ground/sea assets),

1. Models IBCS-integrated components (PATRIOT, Sentinel, etc.) starting at the A-Side, supporting the dialog and functionality expected by the IFCN Relay including health and status, track reporting, sensor tasking, and engagement processing,

1. Models non-IBCS elements and simulates the network messages (Tactical Digital Information Link J (TADIL-J), Variable Message Format (VMF)) from those components,

1. Simulates engagements by flying out launched interceptors, modeling the end-game, and detecting object collisions,

1. Includes battle manager models representing functionality incorporated within IBCS-developed Common Software Configuration Items (CSCIs) to support analysis and testing.

ITEx can be componentized and configured to support all testing, training, and analysis roles for IBCS. ITEx can be executed in self-contained, external, and distributed frameworks and has substitutable component capabilities and algorithms.

The ITEx model software undergoes an evaluation, IAW PP-412, Test Tool Development and Certification, against the allocated model requirements. This procedure validates the ITEx software for use in IBCS testing.

IPTA 2 consists of two server racks. Since the IPTAs contain all communication equipment needed for AT, no Network Enclosure (NE) is needed. The server racks that comprise the IPTA contain the network equipment, communications equipment, and servers need to preform EOC functions required for AT. The IPTA will be loaded with the same software version loaded on the Relay UUT (most current approved v4.5.x version). There are two CWMI operator rackmount workstations with Dell 32” monitors. These workstations will be collocated with their monitors. Workstation 1 (ST1) will be configured to run single node ITEx and ITEx Graphical User Interface. Workstation 2 (ST2) will be configured to run CWMI and will also run the A-Side ping script. The IPTA overview is illustrated below in Figure 12. IPTA 2 Overview.

Figure 12. IPTA 2 Overview

IPTA 2 consist of the following principal components:

a. Classified / Red equipment rack containing the following major sub components (see Error! Reference source not found. below):

1. Air and Missile Defense Work Station (AMDWS) laptop – not present

2. GPS Receiver Antenna

3. Media converter chassis with modules

4. 16-Port Netcommander Keyboard Video and Mouse (KVM) Switch and 19” LCD

5. Spectracom SecureSync Timing Unit

6. Silicon Mechanics Rackform server (multi-node ITEx) – not used

7. Cisco 4321 router

8. Cisco 4351 router

9. Cisco 3850 switch

10. RS113 Crystal CDS server – not present

11. RS112 Crystal servers (quantity 7)

12. 3000VA 2U 120V APC Smart UPS – not used

b. Unclassified / Black equipment rack containing the following major sub components (see Error! Reference source not found. below):

1. Harris VHF antenna – not used

2. GPS Receiver Antenna

3. RF-300M-V150 Harris Radio – not used

4. Baseband Processing Unit (BPU) Harris Radio

5. Status and Coordinate Input Module (SCIM)

6. Integrated GPS Receiver Module (IGRM)

7. HAIPE KG-250X

8. Media converter chassis with modules

9. Cisco 4321 router

10. Cisco 4521 router

11. Smart DC Power Distribution Unit

12. DC Power Supply

13. 3000VA 2U 120V APC Smart UPS – not used

c. HRFU antenna, test stand, and tripod adapter mount

d. Test operator workstations (quantity 2)

1. Crystal RISC System (RS)114 Workstation Server

2. Dell 32” monitor

3. Operator Keyboard W/ Hulapoint, USB

4. Mouse

5. Headset – not present

e. Executive Mobile Video (VTC) – not present

Figure 13. IPTA 2 Red Rack

Figure 14. IPTA 2 Black Rack

Relay Test Equipment Table 11. Relay Test Equipment

Item Description
Purpose
Nomenclature
Serial Number
TFOCA Cable
For connecting UUT to IPTA
RF Cable
Connect two HRFUs via HRFU J4 test ports
Attenuators
Used when connecting two HRFUs via RF cable to reduce signal strength
Black / Unclassified Laptop
Loaded with Minicom used as a terminal emulator / serial console
Serial Cable
Connect laptop to BPU to change HRFU operations modes and configure black routers for Alt Media
Braided Cable
Used to ground equipment
TFOCA “Pig Tail”
Used to isolate TFOCA Port channels during Ping Test
Media Converters
Used to connect Ethernet to TFOCA Pig Tail during A-Side Interface Panel connectivity test

Test Organization and Diagrams Table of Test Table 21. IFCN V2 Relay Table of Tests

IFCN V2 Relay Tests
Test Description
Test Parameter / Expected Results
Table 41. Hardware Power Up
Verifies relay cabling and power up sequence
Relay powers up
Table 42. A-Side Interface Panel Network Connectivity
Verifies relay A-Side interface network connections
Relay A-Side interface network connectivity is operational
Table 43. Automatic Software Initialization Check
Verifies relay software starts automatically
Relay software is operating
Table 44. PATRIOT Functionality & Alt Media
Verifies relay functions correctly with a PATRIOT battery. Relay is connected to the IFCN via Alt Media (TFOCA to the IPTA).
Relay interfaces correctly with PATRIOT launcher and communicates thru the IFCN via TFOCA
Table 45. Sentinel Functionality & HRFU
Verifies relay ability to interface correctly with Sentinel radar. Relay is connected to the IFCN via HRFU
Relay interfaces correctly with Sentinel radar and communicates thru the IFCN via HRFU
Table 46. Software Shutdown and Data Harvest
Verifies relay software shutdown procedure and harvests data from runs
Relay software shuts down correctly, and data is harvested.
Table 47. Hardware Shutdown
Verifies relay power down procedures
Relay powers down correctly

Test Setup & Diagrams Test Defense Plan / Force Laydown All components in Figure 21. PATRIOT Launcher & Alt Media Force Laydown are part of Test Case 09, however only those in color (EOC Mine 52032, 52032B, PATRIOT RIU Mine A01S01, Beck Relay {UUT}, and PATRIOT launchers A06L20-26) will be emplaced / enabled.

Figure 21. PATRIOT Launcher & Alt Media Force Laydown

All components in Figure 22. Sentinel Radar & HRFU Force Laydown are part of Test Case 09, however only those in color (EOC Mine 52032, 52032B, Sentinel Radar Greasewood A05S02, Greasewood Relay {UUT}) will be emplaced / enabled.

Figure 22. Sentinel Radar & HRFU Force Laydown

IPTA to Relay Test Configuration

Figure 23. PATRIOT Run –Test Configuration (Relay IFCN via Alt Media)

Figure 24. Sentinel Test Configuration (Relay IFCN Connection via HRFU)

Figure 25. A-Side Interface Panel Network Connectivity

Power Sub-System & Battery

Figure 26. Power Sub-System & Battery

Relay Plug & Fight Processing Unit (PFPU)

Figure 27. Relay PFPU

IFCN Network Enclosure

Figure 28. Network Enclosure Exterior View

Figure 29. Network Enclosure Interior View

Figure 210. BPU

Figure 211. Network Enclosure Signal & Power Panels

A-Side Panel

Figure 212. A-Side Interface Panel

IBCS-A249-ADDENDUM A-003

9 May 2019

Pretest Steps Configure the BPU into Test Mode The following steps are taken to put the BPU into test mode. This causes the signal to go to the coax connector instead of radiating out the antenna.

Table 31. Configure BPU Into Test Mode

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Power UUT On

1.
Verify IPTA HRFU J4 connected to UUT HRFU J4 via RF coax cable with two (2) 40 dB attenuators at each J4 port (see Figure 24. Sentinel Test Configuration (Relay IFCN Connection via HRFU))
Cables secure
2.
If Relay is not powered on perform steps in Table 41. Hardware Power Up. (Steps 1 – 20 can be skipped if already performed on this UUT.)
Relay is powered on.

Configure BPU and HRFU

3.
Connect laptop to the BPU by doing the following:

· Wait until the 1 PPS light is blinking on the front of the BPU

· Disconnect IGRM interface cable from BPU front panel J3 connector

· Connect W5 cable to port J3 on front of BPU

· Connect W5 cable to laptop console port

· Login to laptop

· Open a terminal window

· Type sudo minicom

· Press enter in Minicom session

See Figure 29. Network Enclosure Interior View for BPU location and Figure 210. BPU for port location.

The Field Support menu is displayed in laptop Minicom session.

With the IFCN Relay Network Enclosure door open, the BPU will show Crypto – green Nav System – green Xmit enable green 1 Link – green Data Xmit – blinking green

4.
Select option 2 (View System Configuration Summary)

Verify the following:

1. IPv6 and IPv4 addresses have been entered as well as their respective gateway addresses.

2. Center frequency is set to 4537 MHz.

3. Inertial Navigation System (INS) present is set to 0

4. ARQ is set to 0

5. version:harris_r2.0.11

6. Antenna Mode is set to 5 NOTE: IP address will be provided separately prior to testing Configuration Summary is displayed

System/radio configuration setting confirmed

5.
Press Enter to exit the View system configuration summary
Field Support menu is displayed.
6.
On front panel of BPU press and hold RESET switch in the RESET position for 10 seconds
HNR Basic Radio Configuration options are displayed
7.
Select Option 14 (Restart Radio)
“Are you sure you want to restart radio? (y/n)” is displayed
8.
Type ant

Radio prompts for Field Support Password

9.
Enter password (provided separately)
Antenna Test Settings options are displayed
10.
Select option 3 (Antenna to Antenna cabled discovery and directional out the test port)
“Set antenna test mode to: HRFU to HRFU using the test port? (y/n)” is displayed
11.
Type y to confirm changing to test mode
Changes are applied and Antenna Test Settings options are displayed
12.
Select option 1 (Return to Main Menu)
“WARNING: Did you remember to add attenuation barrels? (y/n)” is displayed
13.
Type y to confirm that attenuators were added
HNR Basic Radio Configuration options are displayed
14.
Store the changes by doing the following:

· Select option 13 (Store Settings)

· Type y to confirm

· Select option 14 (Restart Radio)

· Type y to confirm Settings are saved and radio restarted

15.
Confirm changes are made by selecting option 4 (View Node Diagnostics)
0 is shown beneath the sector category
16.
Press Enter on laptop to exit the View Node Diagnostic screen
Field Support Menu is displayed
17.
On the SCIM front panel verify the following LED indicators

Crypto – green Nav System – green Xmit enable green 1 Link – green Data Xmit – blinking green

NOTE: SYSTEM FAIL LED should be extinguished. If it is blinking red ensure Timing Unit is sync’d and IGRM is displaying GPS locked and wait for LED to extinguish. If solid red and SCIM displays GPS locked, reset the BPU and wait for LED to extinguish.

SYSTEM FAIL LED is extinguished

18.
Disconnect laptop by doing the following:

· Disconnect W5 test cable from BPU J3 connector

· Disconnect W5 test cable from laptop

· Turn laptop off Laptop disconnected

19.
Connect IGRM interface cable to J3 connector on front of BPU
IGRM cable secured

Configure the A-Side Interface Panel Network Connectivity Workstation These steps are need so that the connectivity test workstation network interface card has an IP address that can send and receive pings to / from the UUT.

Table 32. A-Side Interface Panel Network Connectivity Workstation

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Determine the VLAN 10 IPv6 Address

The A-Side interface uses IPv4 address except for the 2nd TFOCA pair on J1 SENSOR, which is for voice and is IPv6.

1.
Prepare ST2 for connectivity test by doing the following:

· Log on to ST2

ST2 is ready to be configured.
QA witness

Edit Workstation Configuration File

2.
Open the network configuration file for editing by doing the following:

· Right click on desktop

· Click on Open Terminal

· Type cd /etc/sysconfig/network-scripts

· Type sudo vi ifcfg-eth1

Network configuration file open for editing
QA witness
3.
Edit / ensure the file has the following commands:

· IPADDR= xxxx

· IPV6ADDR=yyyy::25/64

· IPV6INIT=yes

· IPV6_AUTOCONF=no

· Hit the Esc key then type :wq

Replace xxxx above with the IPv4 address.

Replace yyyy above with the VLAN 10 IPv6 address.

NOTE: IP address will be provided separately prior to testing.

Network configuration file is updated
QA witness
4.
Restart the workstation network to implement the changes by doing the following:

· Type sudo /etc/init.d/network restart

Workstation IP addresses are set
QA witness

Test Procedures Hardware Power Up Table 41. Hardware Power Up

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Conduct:

Run Name __________________________

Attempt # __________________________

Date of Run _________________________

Test Conductor ______________________

Test Operator _______________________

QA Witness _________________________

Gov Witness _________________________

Other Witness _______________________

IFCN Relay SN ______________________

IFCN Relay PFPU Run Time Meter Start/Stop ____________/_____________

All Network devices are configured IAW most current 4.5.x version of IBCS plus any applicable FECs

Run Name is of the form:

MEI#_Run_[number]_[yyyymmdd]

Test Configuration:

1 Relay UUT

Verify UUT per Hardware Connections for Test Configuration (See Figure 24. Sentinel Test Configuration (Relay IFCN Connection via HRFU))

****CAUTION****

Verify by visual inspection that all equipment has been properly grounded to ensure proper operation and prevent an electrical hazard for the equipment or operator. See grounding steps below.

MEI HW is ground to a common facility ground

1.
Verify Battery Main circuit breaker is OFF (see Figure 11. IFCN V2 Relay & Figure 26. Power Sub-System & Battery)
PSS Battery is OFF
QA witness
2.
Verify AC input circuit breaker on the PSS is OFF (see Figure 11. IFCN V2 Relay & Figure 26. Power Sub-System & Battery)
PSS AC input is OFF
QA witness
3.
Verify output switch on the PSS is OFF (see Figure 11. IFCN V2 Relay & Figure 26. Power Sub-System & Battery)
PSS DC output is OFF
QA witness
4.
Verify circuit breakers 1-5 on the UUT Relay Network Enclosure are in the OFF position (see Figure 28. Network Enclosure Exterior View)
CB1 through CB5 in the OFF position
QA witness
5.
Verify PFPU on/off switch is in the OFF position (see Figure 27. Relay PFPU)
PFPU ON/OFF switch is in the OFF position
QA witness
6.
Verify SSD1 and SSD2 are installed in the PFPU. If not, install them at this time (see Figure 27. Relay PFPU) using ESD procedures.

NOTE: ESD procedures require the operator to wear a wrist strap with the clip end connected to a ground point. HDD / SDD are to be stored in anti-static bags when not installed. Drives should never have direct contact with a metal safe drawer, even if in an anti-static bag.

SSDs are installed in the PFPU
QA witness
7.
On Relay visually verify facility (building) ground to trailer ground point
Ground connected
QA witness
8.
On Relay visually verify PFPU ground to trailer ground point (see Figure 11. IFCN V2 Relay)
Ground connected
QA witness
9.
On Relay visually verify HRFU ground to Network Enclosure (see Figure 11. IFCN V2 Relay)
Ground connected
QA witness
10.
On Relay visually verify Network Enclosure ground to trailer ground point
Ground connected
QA witness
11.
On Relay visually verify power generation to trailer ground point (see Figure 11. IFCN V2 Relay)

· Two grounds from PSS to trailer ground point

· One ground from Generator to trailer ground point

Grounds connected
QA witness
12.
Verify External GPS antenna is connected to Network Enclosure J12 (GPS) (see Figure 211. Network Enclosure Signal & Power Panels)
GPS antenna connected
QA witness
13.
Verify on Network Enclosure J9 (HRFU ANT) connected to HRFU J2 using HRFU RF cable (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
14.
Verify on Network Enclosure J8 (HRFU CTRL) connected to HRFU J3 using HRFU CTRL cable (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
15.
Verify on Network Enclosure J14 (HRFU PWR) connected to HRFU J1 (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
16.
Verify on Network Enclosure J15 (J15 PFPU Power) connected to PFPU J1 (PFPU PWR / J1) (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
17.
Verify on Network Enclosure J13 (PFPU LAN) connected to PFPU J2 using PFPU J2 / PFPU LAN J13 cable (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
18.
Verify on Network Enclosure J10 connected to A-side interface panel J1 Sensor (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
19.
Verify on Network Enclosure J11 connected to A-side interface panel J2-6 Launchers (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
20.
Verify on Network Enclosure J16 connected to A-side interface panel J7-8 Alt Media 1 and 2 (see Figure 211. Network Enclosure Signal & Power Panels)
Cables secure
QA witness
21.
On Relay verify Power Sub-System (PSS) connected to commercial / external power source via PSS J1 AC Input (see Figure 11. IFCN V2 Relay and Figure 26. Power Sub-System & Battery).
External power connected and available to IFCN Relay
QA witness
22.
Switch battery output to ON (see Figure 11. IFCN V2 Relay & Figure 26. Power Sub-System & Battery)
Battery is providing power to PSS and DC volt meter reads 28 VDC
QA witness
23.
On Relay PSS do the following (see Figure 11. IFCN V2 Relay & Figure 26. Power Sub-System & Battery):

· Switch AC INPUT to ON

· Switch OUTPUT switch to ON

Relay PSS is providing power to sub-components
QA witness

Configure BPU and HRFU

24.
On the front panel of the UUT IFCN Relay place the following breakers in the ON position according to the following sequence: (see Figure 28. Network Enclosure Exterior View)

1. Main (CB 5)

2. PDU (CB 1)

3. PFPU (CB 2)

4. HRFU (CB 3)

Power applied to all Network Enclosure devices except ECU
QA witness
25.
Open the Network Enclosure front door and verify BPU MODE SWITCH is WARM and KG-250 is OFF (see Figure 29. Network Enclosure Interior View and Figure 210. BPU)
BPU is in standby and KG-250 is OFF
QA witness
26.
Allow the IGRM to initialize and display GPS lock, as well as longitude, latitude and altitude settings to display on the SCIM panel before proceeding to the next step (see Figure 28. Network Enclosure Exterior View). This typically takes 7 – 15 minutes, but could take up to 20 minutes. Wait for ‘GPS LOCKED’ on front panel of SCIM (see Figure 28. Network Enclosure Exterior View)
SCIM front panel shows “GPS LOCKED”

QA witness

27.
Timing Unit / GPS synchronization troubleshooting step.

If Spectracom Timing Unit “SYNC” LED remain red or the display does not display “Strat=1 Sync=Y” after 30 minutes do the following on the Timing Unit:

· Press one of the white DIRECTIONAL ARROW keys to enter the menu

· Use white directional arrow key to navigate to SYSTEM then press the GREEN CHECK button

· Use white directional arrow keys to navigate to CMD then press the GREEN CHECK button

· Use white directional arrow keys to change the setting to REBOOT then press the GREEN CHECK button

· An APPLY message will appear, press the GREEN CHECK button to apply

· Wait to verify the Timing Unit starts booting

· Continue waiting until display shows “Strat=1 Sync=Y”

If SCIM displays GPS lock failed or GPS unlocked do the following:

· Cycle power on the IGRM using the Internal Circuit Breaker panel on inside of the Network Enclosure. (It is the 5 amp switch; forth from the left. See figure to the right.)

· On the front panel turn FUNCTION knob to LAT/LON and push (SCIM reads LAT/LON ENTRY)

· Enter coordinates “20000000”

· Turn CHARACTER knob (center) to select character position

· Turn CURSOR knob (left) to change blinking character

· Push CHARACTER knob five (5) times until SUCCESS LOCATION SET is displayed

· Turn FUNCTION knob (right) to OPER and push in

10
7.5
5
5
2
1
1

Amp Switches

Spectracom Timing Unit displays “Strat=1 Sync=Y”, SYNC LED is green, and the FAULT LED is extinguished

SCIM displays GPS UNLOCKED then changes to LOCKED after a short period of time QA witness

28.
Observe SecureSync Timing unit power up and ‘SYNC’ LED illuminates green (see Figure 29. Network Enclosure Interior View)
The timing unit displays correct UTC time and green ‘SYNC’ LED is illuminated. Fault light should be extinguished
QA witness
29.
Switch BPU MODE SWITCH to ON (see Figure 210. BPU)

NOTE: If BPU stays solid red reset the BPU by switching TX-ENABLE-RESET to RESET. Switch will return to original position automatically.

BPU SYSTEM FAIL light extinguishes
QA witness

Configure KG-250

****WARNING****

Ensure KG-250X has been loaded with appropriate test keys prior to performing test. Check the latest configuration documentation to verify that the KG-250X has been loaded with the correct keys.

30.
Verify serial number of its associated Relay key and KG-250X match.

CIK must be provisioned SECRET before use

KG-250X and key match
QA witness
31.
If CIK key is not inserted in the UUT

Insert the correct Crypto Ignition Key (CIK) into the KG-250X and press KG-250X POWER button Wait until the ALARM LED extinguishes and the PWR/READY LED turns green.

KG-250X is ON and PWR/READY LED illuminates green
QA witness
32.
If KG-250 READY LED does not turn green in 5 minutes press RESET on KG-250
KG-250 resets, TC see red side, Green light will appear on KG-250
QA witness

Turn PFPU On

33.
On front panel of SCIM verify the following LED indicators are green:

1 PPS – blinking at 1 sec intervals

CRYPTO KEY

XMIT ENABLE

1 LINK

NOTE: SYSTEM FAIL LED should be extinguished. If it is blinking red ensure Timing Unit is sync’d and IGRM is displaying GPS locked and wait for LED to extinguish. If solid red and SCIM displays GPS locked, reset the BPU and wait for LED to extinguish.

SYSTEM FAIL LED is extinguished.
QA witness
34.
Turn PFPU on/off switch to the ON position
PFPU ON/OFF switch is in the ON position
QA witness

A-Side Interface Panel Network Connectivity Table 42. A-Side Interface Panel Network Connectivity

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Conduct:

Attempt # __________________________

Date of Run _________________________

Test Conductor ______________________

Test Operator _______________________

QA Witness _________________________

Gov Witness _________________________

Other Witness _______________________

IFCN Relay SN ______________________

Run Name is of the form:

Test Configuration:

1 Relay UUT

IPTA ST2

Media converter and cables (Ethernet and TFOCA) Figure 25. A-Side Interface Panel Network Connectivity

A-SIDE INTERFACE RED PING TEST

1.
If Relay is not powered on perform steps in Table 41. Hardware Power Up. (Steps 1 – 20 can be skipped if already performed on this UUT.)
Relay is powered on.
QA witness
2.
Connect ST2 to test media converter with Ethernet cable labeled Ping (middle Ethernet slot)
Workstation is connected to media converter.
QA witness
3.
Power test media converter via power converter
Media converter is powered up.
QA witness
4.
Prepare workstation ST2 for connectivity test by doing the following:

· Log on to ST2

· Execute Table 32. A-Side Interface Panel Network Connectivity

Workstation is ready to start execute connectivity tests.
QA witness
5.
Start network test script by doing the following:

· In the terminal window

· Type cd /usr/bin/sepTest

· Type ls –al

· If redSepResults_Relay(MEI Number).txt or redSepResults_Relay(MEI Number).txt.md5 files exist type rm redSepResults_Relay(MEI Number)*

· Type sudo ./sepTest.sh to start script

· Type MEI number when prompted

Red A-Side interface test script starts.
QA witness

J1 SENSOR – RED PORT

NOTE: TFOCA cable colors may vary. The S*-TX* / P*-RX* labels take precedence over cable color.

6.
When prompted by the script connect TFOCA cable to J1 SENSOR port on A-Side Panel. Connect the other end to the fiber test adapter.

Then press Enter on keyboard

Test adapter is connected.
QA witness
7.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness
8.
When prompted by the script to connect TFOCA to J1 SENSOR

press Enter on keyboard

TFOCA is still connected to J1
QA witness
9.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P2-RX2 Brown fiber to RX on test media converter

· Connect S2-TX2 Green fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

J2 LAUNCHER 1&2 – RED PORT

10.
When prompted by the script connect TFOCA cable to J2 LAUNCHER 1&2 port on A-Side Panel

Then press Enter on keyboard

TFOCA cable is connected
QA witness
11.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness
12.
When prompted by the script to connect TFOCA to J2 LAUNCHER 1&2

press Enter on keyboard

TFOCA is still connected to J2
QA witness
13.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P2-RX2 Brown fiber to RX on test media converter

· Connect S2-TX2 Green fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

J3 LAUNCHER 3&4 – RED PORT

14.
When prompted by the script connect TFOCA cable to J3 LAUNCHER 3&4 port on A-Side Panel

Then press Enter on keyboard

TFOCA is connected.
QA witness
15.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness
16.
When prompted by the script to connect TFOCA to J3 LAUNCHER 3&4

press Enter on keyboard

TFOCA is still connected to J3
QA witness
17.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P2-RX2 Brown fiber to RX on test media converter

· Connect S2-TX2 Green fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

J4 LAUNCHER 5&6 – RED PORT

18.
When prompted by the script connect TFOCA cable to J4 LAUNCHER 5&6 port on A-Side Panel

Then press Enter on keyboard

TFOCA is connected.
QA witness
19.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness
20.
When prompted by the script to connect TFOCA to J4 LAUNCHER 5&6

press Enter on keyboard

TFOCA is still connected to J4
QA witness
21.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P2-RX2 Brown fiber to RX on test media converter

· Connect S2-TX2 Green fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

J5 LAUNCHER 7 – RED PORT

22.
When prompted by the script connect TFOCA cable to J5 LAUNCHER 7 port on A-Side Panel

Then press Enter on keyboard

TFOCA is connected.
QA witness
23.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

J6 LAUNCHER 8 – RED PORT

24.
When prompted by the script TFOCA cable to J6 LAUNCHER 8 port on A-Side Panel

Then press Enter on keyboard

TFOCA is connected.
QA witness
25.
When prompted by the script connect media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Then press Enter on keyboard

NOTE: If the test fails script will prompt the user to check connections then press Enter to repeat this check. The script will only recheck the connection once before continuing to the next step.

Script displays PASSED
QA witness

DISCONNECT AND HARVEST RED TEST RESULTS

26.
Disconnect Ethernet cable labeled ST2 Ping from media converter.
Workstation disconnected.
QA witness
27.
Disconnect TFOCA cable from Relay UUT and fiber test adapter
TFOCA cable disconnected
QA witness
28.
Create MD5 checksum file for the ping results file by doing the following:

· Type sudo chmod 775 red*

· Type md5sum redSepResults_Relay(MEI Number).txt > redSepResults_Relay(MEI Number).txt.md5

· Type sudo chmod 775 red*

· Type ls -al

Observe redSepResults_Relay(MEI Number).txt and redSepResults_Relay(MEI Number).txt.md5 files exist
QA witness
29.
Copy test result file and md5 checksum files to archive folder by doing the following:

· Type ssh security

· Type cd /mnt/DataTransfer/Data/(MEI Number)

· If this is a test dry run then type ls -al

· If a dryRun subdirectory does not exist then type mkdir dryRun

· Type sudo chmod 775 dryRun

· Type cd dryRun

· Type exit

· Type cd /usr/bin/sepTest

· Type scp redSepResults_Relay(MEI Number)* username@security: /mnt/DataTransfer/Data/(MEI Number)</dryRun> if test is a dry run

Test log file copied.
QA witness
30.
Verify the result and md5 checksum files were copied by doing the following:

· Type ssh security

· Type cd /mnt/DataTransfer/Data/(MEI Number) </dryRun> if test is a dry run

· Type ls -al Verify redSepResults_Relay(MEI Number).txt and redSepResults_Relay(MEI Number).md5 files exist

QA witness

31.
Verify the integrity of the result and md5 checksum files by doing the following:

· Type md5sum –c redSepResults_Relay(MEI Number).md5

Observe the following response redSepResults_Relay(MEI Number.txt: OK
QA witness

Automatic Software Initialization Check Table 43. Automatic Software Initialization Check

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Conduct:

Attempt # __________________________

Date of Run _________________________

Test Conductor ______________________

Test Operator _______________________

QA Witness _________________________

Gov Witness _________________________

Other Witness _______________________

IFCN Relay SN ______________________

Run Name is of the form:

Test Configuration:

1 IPTA / EOC

1 IFCN Relay (The UUT)

Check OpenSAF Status on IFCN Relay

1.
If Relay is not powered on perform steps in Table 41. Hardware Power Up. (Steps 1 – 20 can be skipped if already performed on this UUT.)
Relay is powered on.
QA witness
2.
From an IPTA Operator Workstation remote into Relay UUT by doing the following:

· Right click on desktop

· Click on Open Terminal

· Type ssh localadmin@<IPv6 address of relay>

· Enter password

NOTE: UUT IPv6 addresses and passwords are unique and will be provided separately prior to testing.

Operator is remotely logged in to the relay.
QA witness
3.
Change directory to the location of the startup scripts by doing the following:

· Type cd /opt/integ/tools

Current directory is changed to the necessary location for scripts.
QA witness
4.
Verify IBCS software is running on IFCN Relay by doing the following:

· Type./statusIBCS All services show INSTANTIATED / IN-SERVICE / ENABLED

IBCS software is running. Record initial IBCS status.

IBCS Status

QA witness

5.
If IBCS software is not running do the following to stop IBCS:

· Type ./stopIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have stopped

All services show UNINSTANTIATED / OUT-OF-SERVICE / DISABLED
QA witness
6.
If previous step was performed then do the following to start IBCS software:

· Type ./startIBCS

· Type watch ./statusIBCS

· Type ctrl + c after services have started All services show INSTANTIATED / IN-SERVICE / ENABLED

OpenSAF is now running QA witness

PATRIOT Functionality & Alt Media Table 44. PATRIOT Functionality & Alt Media

Step #
Operator Actions
Expected Results
Actual Results
Comments/TIR #

Test Conduct:

Attempt # __________________________

Date of Run _________________________

Test Conductor ______________________

Test Operator _______________________

QA Witness _________________________

Gov Witness _________________________

Other Witness _______________________

IFCN Relay SN ______________________

Run Name is of the form:

Test Configuration:

1 IBCS Relay (controlling 7 PATRIOT Launchers connected to the IFCN via Alt Media TFOCA. See Figure 21. PATRIOT Launcher & Alt Media Force Laydown) Figure 23. PATRIOT Run –Test Configuration (Relay IFCN via Alt Media) 1 EOC with PATRIOT RIU (IPTA simulated) 1 PATRIOT Launcher attached to UUT (IPTA simulated)

Models & Simulations:

ITEx simulates all sensors and launchers. A multi-threat, multi-launcher dynamic test case scenario is used in which hostile threats are tracked by ASoS PATRIOT, and which incorporates PAC-2 missiles types (GEM, GEM-C, GEM-T) as well as PAC-3 missile types (PAC-3, MSE) using all TBM subclasses and ABT subclasses from the CIE events.

Distributed engagement authority, Auto Command Processing Control set to OFF for all the EOC, the EOC has Identification Authority. AIR is semi-automatic and SPACE is Automatic. Method of fire is Ripple for TBM and Shoot-Look-Shoot-Look-Shoot for ABT.

Test Case Number: TC09 TC Common Name: Multi-Threat Multi-Launcher Dynamic Defense Plan: TC09.xml.idd ITEx XML File and Path Location: input/scenarios/IBCS/Root/Dynamic/Root.xml

NOTE: TC09 has multiple EOC, Relays, PATRIOT RIUs, PATRIOT Launchers, and Sentinel Radars, but only EOC 52032 (simulated) with PATRIOT RIU (simulated), the Relay under test, and PATRIOT launchers (simulated) will be used.

Connect Relay to IPTA (IFCN Alt Media via TFOCA)

1.
If Relay is not powered on perform steps in Table 41. Hardware Power Up. (Steps 1 – 20 can be skipped if already performed on this UUT.)
Relay is powered on.
QA witness
2.
Connect Relay to IPTA (EOC) using Relay UUT TFOCA spool by doing the following:

· Connect one end of the TFOCA cable to J7 Alt Media 1 on the UUT A-Side Panel (Note that J8 Alt Media 2 functions identically)

· Connect the other end of TFOCA cable to the IPTA Alt Media 1

NOTE: Alt Media 2 works identical to Alt Media 1 and is a suitable substitution on the IPTA

Cables secure
QA witness
3.
Turn Relay HRFU connection off by doing the following:

· Open front panel door to Relay Network Enclosure

· Set BPU switch to STBY (see Figure 210. BPU)

Relay BPU Power light is OFF.
QA witness
4.
Turn off the IPTA BPU by switching it to STBY.
IPTA BPU Power light is OFF.
QA witness
5.
Disconnect the coax cable connecting the IPTA HRFU to the UUT Relay HRFU by unscrewing the coax cable from the attenuator attached to port J4 on the HRFU antenna.
HRFU to HRFU connection is physically broken.
QA witness

Connect Relay to Simulated PATRIOT Launcher

6.
Connect fiber test adapter to one end of the TFOCA cable and the other end of the TFOCA cable to the J2 LAUNCHER 1&2 port on A-Side Panel
Cables secure.
QA witness
7.
Connect IPTA media converter to the fiber test adapter by doing the following:

· Connect P1-RX1 Orange fiber to RX on test media converter

· Connect S1-TX1 Blue fiber to TX on test media converter

Relay connected to test media converter
QA witness
8.
Connect Ethernet cable labeled “Switch to Relay” from switch to media converter
Relay connected to simulated PATRIOT Launcher (IPTA)
QA witness

Configure Black Routers for Alt Media Connections

Disable IPTA Black Router Tunnels & Enable Alt Media Ports

9.
Connect unclassified laptop to IPTA Black Router by doing the following:

· Connect Cisco interface cable from serial port on Black / unclassified laptop to “CON” port on Black Router maintenance port (see Figure 29. Network Enclosure Interior View)

· Log onto laptop

Laptop is connected to the IPTA Black Router
QA witness
10.
Log onto IPTA Black Router (with elevated privileges) by doing the following:

· Open a terminal windows and type sudo minicom

· Hit enter until Black Router requests User ID

· Type User ID then password

NOTE: IPTA User ID and passwords will be provided separately prior to testing.

Test operator is logged in to the Black Router
QA witness
11.
Reconfigure the IPTA Black Router by doing the following:

· Open the “IPTA_Alt_Media_Enable.txt” file on the laptop

· Select all the contents of the file and type Ctrl + c to copy them

· Left click on Minicom window

· Right click in the Mincom window to paste the file contents in and execute them

All network commands execute successfully
QA witness

Note: the following commands were issued above to close the Black Router tunnels:

· conf t

· int tunn10

· shut

· exit

· int tunn11

· shut

· exit The following commands were issued above to open Alt Media ports 1 & 2:

· int gig 0/0/1

· ipv6 pim

· no ipv6 ospf 2 area 0

· ipv6 ospf 1 area 0

· ipv6 traffic-filter IBCS_Black in

· ipv6 traffic-filter IBCS_Black out

· no shut

· exit

· int gig 0/0/2

· ipv6 pim

· no ipv6 ospf 2 area 0

· ipv6 ospf 1 area 0

· ipv6 traffic-filter IBCS_Black in

· ipv6 traffic-filter IBCS_Black out

· no shut

· end gig 0/1 corresponds to Gigabit Ethernet Alt Media 1 and gig 0/2 to Gigabit Ethernet Alt Media 2 on the Relay Black Router

These commands are not committed to memory, so a router reboot / power cycle sets the routers back to the original settings.

12.
Verify Black Router tunnels settings by issuing the following commands:

· sh int tun 10

· sh int tun 11 The following responses are received:

· Administratively Down

· Administratively Down QA witness

13.
Disconnect the laptop from the IPTA Black Router by doing the following:

· Close the “IPTA_Alt_Media_Enable.txt” file

· Close the Minicom window

· Disconnect the Cisco cable from the Black Router

Laptop disconnected from IPTA
QA witness

Disable Relay Black Router Tunnels & Enable Alt Media Ports

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .