This is a Statement of Objectives for an exterior building signage project issued by the Department of the Air Force, 179th Cyberspace Wing, located at Mansfield Air National Guard Base in Ohio.

The contractor is required to design, manufacture, and install non-reflective flush-mounted building number signs on 27 buildings base-wide, including removal of existing signage. The requirement includes eight copies each of signs for 23 buildings (numbered 102, 108, 110, 112, 114, 120, 164, 164A, 207, 403, 405, 407, 415, 420, 420A, 421, 500, 520, 522, 600, 602, 801, 803) and two copies each for four additional buildings (601, 805, 807, 809). All signs must meet UFC 3-120-01 guidelines and conform to specific technical specifications: standard aluminum construction measuring 8 inches in height by 16 inches in width, black background with white non-reflective lettering in Helvetica Neue 85 Heavy font, mounting brackets and hardware, wind speed resistance of 160 mph, and temperature exposure range from 85 to -5 degrees Fahrenheit. The contractor shall provide all materials, labor, and installation services. All contractor personnel requiring base access must complete a Security Access Form submission for background check clearance and complete antiterrorism training, both accomplished post-award. While not mandatory, a site visit is highly encouraged due to project requirements, with FAR 52.237-1 applicable to contractors who choose not to attend.

View the file

Other files

File Type Posted
RFI and Response Document (as of 15 Sep 26).pdf PDF
Attachment 01_RFQ_Mobile Fencing_Base Signage_Gazebos_rev02.pdf PDF
RFI and Response Document (as of 10 Sep 26).pdf PDF
site visit minutes_base signage_gazebos.pdf PDF
site visit sign in sheet.pdf PDF
RFI and Response Document (as of 08 Sep 26).pdf PDF
Attachment 04_Base Signage_Statement of Requirement_rev02.pdf PDF
Attachment 06_Gazebos_Statement of Requirement_rev01.pdf PDF
Attachment 03_Mobile Fencing_Statement of Requirement_rev02.pdf PDF
Attachment 01_RFQ_Mobile Fencing_Base Signage_Gazebos_rev01.pdf PDF
RFI and Response Document (as of 02 Sep 26).pdf PDF
Attachment 02_Provisions and Clauses_rev01.pdf PDF
Attachment 03_Mobile Fencing_Statement of Requirement_rev01.pdf PDF
Attachment 04_Base Signage_Statement of Requirement_rev01.pdf PDF
Attachment 07_Gazebos_Map Location_rev01.pdf PDF
RFI and Response Document (as of 31 Aug 26).pdf PDF
Attachment 07_Gazebos_Map Location.pdf PDF
Attachment 06_Gazebos_Statement of Requirement.pdf PDF
Attachment 02_Provisions and Clauses.pdf PDF
Attachment 01_RFQ_Mobile Fencing_Base Signage_Gazebos.pdf PDF
Attachment 08_Contractor Access form.pdf PDF
Attachment 05_Base Signage_Building Sign Example.pdf PDF
Attachment 03_Mobile Fencing_Statement of Requirement.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

179th Cyberspace Wing

Mansfield angb ohio

1.0 PROJECT TITLE. Exterior Building Number and Service Signage

2.0 CURRENT SITUATION: Update base-wide building signage base wide. Contractor to provide building flush-mounted, non-reflective signage, to include removal of old signage and installation of new. All signage to meet UFC 3-120-01 guidelines.

3.0 STATEMENT OF REQUIREMENT: The contractor shall provide the Government with the following:

3.1 Non-reflective flush mounted signs with building numbers on 27 buildings.

3.1.1 Flush building mounted, non-reflective, non-illuminated signs. Eight (8) copies of each sign.

3.1.1.1 Building numbers 102, 108, 110, 112, 114, 120, 164, 164A, 207, 403, 405, 407, 415, 420, 420A, 421, 500, 520, 522, 600, 602, 801, 803

3.1.2 Flush building mounted, non-reflective, non-illuminated signs. Two (2) copies of each sign.

3.1.2.1 Building numbers 601, 805, 807, 809

3.1.3 Flush mounted building sign specification. See Appendix A

3.1.3.1 Standard aluminum construction, 8” (254mm) height, 16” (406mm) width

3.1.3.2 Black background surface, with white non-reflective lettering.

3.1.3.3 Helvetica Neue – 85 Heavy font

3.1.3.4 Mounting brackets and hardware

3.1.3.5 Able to withstand winds speed resistance of 160 mph

3.1.3.6 Temperature exposure from 85 to -5 degrees

3.2 Contractor shall provide all materials, labor and installation of building signage.

4.0 The following will be required of all contractors (prime or sub) personnel who will require base access to perform services related to this requirement:

4.1 Base Access Clearance Process: completion and submission of Security Access Form, which is submitted for background check; clearance is required for base access approval (this is accomplished post-award).

4.2 Antiterrorism Training: See attachment related to antiterrorism training requirements (accomplished post-award).

5.0 Site Visit: while site visit is not required, it is highly encouraged, due to the requirements of this project. Contractor’s who plan to bid on this project, but not attend site visit, should note the following provision applicable to this solicitation: FAR 52.237-1, Site Visit.

179th Cyberspace Wing