This document is a comprehensive set of architectural and mechanical engineering drawings for the VA Omaha Medical Center's Sterile Processing Service (SPS) addition project. The drawings, dated November 23, 2020, provide detailed structural, mechanical, and equipment specifications for a new medical facility space, with a focus on sterile processing and medical equipment installation.
The drawings include detailed plans for structural framing across multiple levels, mechanical systems, ductwork, piping, and equipment specifications. Key equipment includes multiple medical devices such as washer-disinfectors, scope washers, automated pass-through windows, sterilization equipment, and various air handling units. The mechanical plans cover HVAC systems, ventilation, steam and condensate piping, and equipment like heat exchangers, condensing units, and air terminal units. The project involves renovating and adding new systems to support a sterile processing service area, with careful consideration for future expansion and integration with existing building infrastructure.
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DN
OFFICE
OFFICE
OPEN
OFFICE/TRAINING
STERILE STG
STERILIZATION
PREP ASSEMBLY
HAC
ANTE
BREAK ROOM
MEN'S LOCKER
WOMEN'S
LOCKER
SCOPE STG
1906B
DECON
MANUAL CART
WASH
CART DRY
SCOPE DROP OFF
H2O
OPEN SPACE
IT
OPEN OFFICE
CORRIDOR
1900A
SCOPE PROC
ANTEROOM,
SOILED
TRANSITION /
DROP-OFF
ANTE VENDOR
DROP OFF
HAC
STAIRS
CART PASS
125' - 2 1/2"
CONFERENCE
COPIER ROOM
AUTOMATIC
CART WASH
AREA
131313
15 15 15
WOMEN'S
SHOWER
1907C
MEN'S SHOWER
1908C
MEN'S RR
1908B
WOMEN'S RR
1907B
WOMEN'S RR
1907A
MEN'S RR
1908A
R
"R
' - 9
M E
C H
C H
A S
E
10 10
CORRIDOR
CORRIDOR
1900B
SCOPE ANTE
1906A
191919
3A3A3A 4A
1. SHEET SIZE FOR PROPER SCALE IS 30X42.
CONTRACTOR SHALL NOT SCALE DRAWINGS BUT
SHALL REQUEST THE DESIRED DIMENSIONS FROM
THE ARCHITECT.
2. SEE SHEET G-002 FOR GENERAL NOTES
3. APPLY 1 1/2" THICK FIREPROOFING AT ALL EXPOSED
STEEL WITHIN INTERSTITIAL SPACE AND AT
EXPOSED STEEL STRUCTURE ABOVE 3RD FLOOR
CEILING, TYP.
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA 57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COM
FOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of
Veterans Affairsof
16.2330.A08
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FARRIS ENGINEERING
12700 WEST DODGE ROAD
OMAHA, NEBRASKA 68154
PH: (402) 330-5900
TERRASITE DESIGN
1635 DEADWOOD AVENUE
RAPID CITY, SOUTH DAKOTA 57702
PH: (605) 791-1736
2/23/2024COMPLIANCY REVIEW COMPLETED
/1
/2
:1
:4
P
M
CONSTRUCTION DOCUMENTS
11/23/2020
SPS MEDICAL EQUIPMENT PLAN
QH-100
Design/Construct Sterile Processing Service- Omaha VA Medical Center
JGCJL
4101 Woolworth Ave #4199 Omaha, Ne 68105Omaha VA Medical Center
61 138
N
N
PLAN
NORTH
TRUE
NORTH
1/8" = 1'-0"
EQUIPMENT FLOOR PLAN - 3RD LEVEL
GENERAL NOTES:
SHEET SPECIFIC NOTES:
1. REFER TO SHEET QH-101 FOR EQUIPMENT
SCHEDULE.
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA 57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COM
FOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
Department of
Veterans Affairsof
16.2330.A08
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FARRIS ENGINEERING
12700 WEST DODGE ROAD
OMAHA, NEBRASKA 68154
PH: (402) 330-5900
TERRASITE DESIGN
1635 DEADWOOD AVENUE
RAPID CITY, SOUTH DAKOTA 57702
PH: (605) 791-1736
2/23/2024COMPLIANCY REVIEW COMPLETED
/1
/2
:1
:4
P
M
CONSTRUCTION DOCUMENTS
11/23/2020
SPS MEDICAL EQUIPMENT SCHEDULE
QH-101
Design/Construct Sterile Processing Service- Omaha VA Medical Center
JGCJL
4101 Woolworth Ave #4199 Omaha, Ne 68105Omaha VA Medical Center
62 138
SPS MEDICAL EQUIPMENT SCHEDULE
TAG JSN NAME QTY RELOCATED
PROVIDED
BY
INSTALLED
BY
ROOM
NUMBER FURNISHING DESCRIPTION BASIS OF DESIGN UTILITY REQUESTS COMMENTS
1915 DECON 1915
1 A1195 COUNTER, CLEANUP, WITH 3 SINKS. 4 NO V C 1915,1905 THREE SINK CLEANUP COUNTER. UNIT IS CONSTRUCTED OF TYPE 304 CORROSION RESISTANT STAINLESS STEEL. IT CONSISTS OF THREE SINKS 14"W X 16"H X 10"D, HOT AND COLD WATER FAUCET, AND PRE-RINSE SPRAY HOSE. EQUIPPED WITH CHANNEL REINFORCED DRAINBOARDS, AND BACKSPLASH, AND SUPPORTED BY TUBULAR STAINLESS STEEL LEGS. UNIT IS DESIGNED FOR USE IN CONTROL STERILE SUPPLY
DECONTAMINATION AREAS.
STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
ADJUSTABLE
2 S0940 WASHER, DISSINFECTOR, STM, 1DO, RSCD1WLL,
26X24X24 SHAM
3 NO V C 1915 A RECESSED MOUNTED (THROUGH ONE WALL), SINGLE DOOR (VERTICAL SLIDING WITH TEMPERED GLASS WINDOW), MULTI-LEVEL, MECHANICAL, WASHER/DISINFECTOR, MINIMUM CHAMBER SIZE 26X24X24, UTILIZING FACILITY SUPPLIED STEAM. THE UNIT IS CONTROLLED BY A MICROCOMPUTER THAT MONITORS AND CONTROLS ALL UNIT OPERATIONS AND FUNCTIONS AND PROVIDES BOTH AUDIBLE AND VISUAL INDICATIONS OF DEVIATIONS. A PRINTER-RECORDER DOCUMENTS AND RECORDS EACH CYCLE PERFORMANCE. PROCESSING CYCLES ARE PRE-PROGRAMMED WITH PRE-WASH, WASH/CLEANING, RINSE, AND THERMAL RINSE/DISINFECTION. FOR USE IN HEALTH CARE FACILITIES AND LABORATORIES WHERE REUSABLE ITEMS (INSTRUMENTS, UTENSILS, ANESTHESIA/RESPIRATORY GOODS, AND GLASSWARE) ARE HANDLED FOR DECONTAMINATION PURPOSES. THIS UNIT IS NOT A SUBSTITUTE FOR TERMINAL STERILIZATION.
STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
3 INNOWAVE PCF SONIC IRRIGATOR 2 NO V C 1915 THE INNOWAVE PCF SONIC IRRIGATOR IS AN ULTRASONIC CLEANER DESIGNED TO INCREASE WORKFLOW AND HELP YOU KEEP PACE WITH BUSY ORS. THROUGH A PROVEN, SYSTEMATIC CLEANING PROCESS, STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
WALL MOUNTED
3A TRITON 72 AUTOMATIC ULTRASONIC CLEANING SYSTEM 3 NO V C 1915 THE TRITON 72 CAN PROCESS FOUR COMPLETE SETS OF XI-SERIES ROBOTICS IN A 15-MINUTE WASH CYCLE. THIS COMPLETE SYSTEM IS USER FRIENDLY, WITH AUTOMATIC LIFTS AND SLIDE AND LOCK TRAYS, AND A
10" TOUCHSCREEN THAT CAN ROTATE LEFT AND RIGHT AND SWING UP AND DOWN.
STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
4 F2410 RACK RETURN 1 NO V C 1915 --- STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
WALL MOUNTED
4A SCS LOAD-UNLOAD 1 NO V C 1923 SEE MECHANICAL AND
ELECTRICAL SCHEDULES
1917 - AUTOMATIC CARTWASH AREA (CWSH2) 1917
5 S3185 WASHER, CART & UTENSIL, 2 DO, PIT MNTD, RCSD 2
WLL
2 NO V C 1917 A RECESSED (THROUGH TWO WALLS), PIT MOUNTED, DOUBLE DOOR (RIGHT OR LEFT-HINGED, APPROPRIATE CONFIGURATION TO BE INDICATED ON EQUIPMENT ELEVATION DRAWINGS), CART AND UTENSIL WASHER (MINIMUM CHAMBER LOAD CAPACITY 78X34X76). A MICROPROCESSOR-BASED CONTROLLER MONITORS AND CONTROLS SYSTEM OPERATIONS AND FUNCTIONS. THE UNIT PROVIDES: VISUAL AND/OR AUDIBLE INDICATION OF CYCLE OPERATION, PROGRAMMABLE TREATMENT TIME AND TEMPERATURES, AND A MINIMUM OF THREE CYCLES (WASH WITH DETERGENT, RINSE, AND DRYING). FOR USE IN CENTRAL PROCESSING TO CLEAN AND DECONTAMINATE, CARTS, PATIENT-CARE UTENSILS (IV POLES, WHEEL CHAIRS, STRETCHERS, ETC.) AND OTHER BULK ITEMS.
STERIS; VISION 1327 CART AND
UTENSIL WASHER/DISINFECTOR,
STEAM HEATED, PIT MOUNTED
UNIT
SEE MECHANICAL AND
ELECTRICAL SCHEDULES
RECESSED PIT MOUNTED
1905 - SCOPE PROCESSING 1905
6 F0540 CART, SCOPE, TRANSPORT 1 NO V V 1905 A CART DESIGNED SPECIFICALLY FOR THE SAFE TRANSPORT OF ENDOSCOPY SCOPES. THE CART WILL HAVE A LIGHTWEIGHT FRAME OF A TUBULAR WELDED CONSTRUCTION. THE SIDES AND BACK PANELS WILL BE OF A FOAMED RESIN WITH A WORK TOP OF SEAMLESS, RAISED EDGE PLASTIC. THE CART WILL HAVE RECTANGLE OR ROUND TRAYS WITH LIDS AND WILL HAVE 4 CASTERS WITH 2 LOCKING. CART MAY HAVE A
ROLL-TOP DOOR WITH A KEY LOCK.
7 S2627 WASHER, FIBER SCOPE, PASS-THROUGH 3 NO V C 1905 A LOW TEMPERATURE STERILE PROCESSING SYSTEM FOR STERILIZING IMMERSIBLE SURGICAL AND DIAGNOSTIC SCOPES, CAMERAS, INSTRUMENTS AND ACCESSORIES. THE UNIT SHALL PROVIDE A DIGITAL DISPLAY OF CYCLE DATA AND SHALL RECORD AND PRINT A PERMANENT RECORD OF CYCLES. UNITS IS WALL MOUNTED PASS-THROUGH.
MEDIVATOR - ADVANTAGE PLUS
PASS THROUGH, ADVPT-3007
SEE MECHANICAL AND
ELECTRICAL SCHEDULES
WALL MOUNTED
8 S1905 40" AUTOMATED PASS-THROUGH WINDOW 2 NO V C 1915, 1905 PASS-THROUGH WINDOW IS AN IN-LINE VERTICAL LIFT WINDOW WITH A SINGLE OPERABLE (MOVABLE) PANEL AND A SINGLE NON-OPERABLE (FIXED) PANEL, AN INTEGRAL CONTINUOUS STAINLESS STEEL SHELF, 40"
WIDE OPENING
STERIS AMSCO PTWAMDR3100
(AUTOMATED)
SEE ELECTRICAL
SCHEDULES
WALL MOUNTED
1906 - SCOPE STAGING ROOM (CSST1) 1906
9 M3160 CABINET, STORAGE, HANGING SCOPES 4 NO V V 1906 SCOPE HANGING CABINET. CABINET HAS THE CAPACITY TO HOLD UP TO NINE SCOPES. SOME CABINETS MAY HAVE A ROLL TOP CLOSURE AND OPTIONAL STORAGE DRAWER. SINGLE SIDE ENTRY MEDIVATOR - ADVANTAGE PLUS
AIR ENDODRY CABINET,
DRY-1001
SEE MECHANICAL AND
ELECTRICAL SCHEDULES
1923 - PREP ASSEMBLY 1923
10 S0047 RACK, STERILE WRAP 6 NO V V 1923 CHROME PLATED RACK USED TO HANG STERILE WRAPPING MATERIEL. THE UNIT IS MOBILE CONSISTING OF 4 SWIVEL CASTERS, 4 POSTS, 4 SUPPORT BARS AND WIRE BOTTOM SHELF. 60"W X 24"D
11 S0048 CART, WASHER TRANSFER 3 NO V V 1923 STAINLESS STEEL TRANSFER CART FOR TRANSFERRING INSTRUMENTS AND ACCESSORIES INTO AND OUT OF WASHER / DISINFECTOR. INCLUDES ONE STORAGE SHELF WITH 4 CASTERS AND AN INTEGRATED TUB /
DOCKING AND RACK LOCKING DEVICES. FIXED HEIGHT.
12 LOW TEMPERATURE STERILIZER 3 NO V C 1923 THE V-PRO MAX 2 LOW TEMPERATURE STERILIZATION SYSTEM IS DESIGNED FOR USE IN TERMINAL STERILIZATION OF REUSABLE MEDICAL DEVICES. THE V-PRO MAX 2 FEATURES THE NEW FAST NON LUMEN CYCLE ALLOWING YOU TO STERILIZE DEVICES LIKE CAMERAS, TELESCOPES, BATTERIES AND LARYNGOSCOPE BLADES.
AMSCO - V-PRO MAX 2 SEE ELECTRICAL
SCHEDULES
13 S9610 ADJUSTABLE DELUXEWORKSTATION 8 NO V C 1915, 1923 RACK / UTILITY STATION. THE STATION CONSISTS OF A STAINLESS STEEL COUNTERTOP, 4-1/2" APRON, LEGS AND NECESSARY CROSS-MEMBER SUPPORTS. THE STATIONS ARE SPECIALLY DESIGNED TO HANDLE LOADING RACKS OR TRAYS FOR USE WITH A SPECIFIC MANUFACTURER'S RELATED EQUIPMENT AND ACCESSORIES BUT MAY ALSO SERVE A VARIETY OF GENERAL USES, SUCH AS AN ACCUMULATING, SORTING, INSPECTING, OR PROCESSING STATION. VARIOUS STATION WIDTHS/LENGTHS (25" TO 126", DEPENDING UPON MANUFACTURER) ARE AVAILABLE. PRICING BASED ON 48' WIDTH/LENGTH.
SEE ELECTRICAL
SCHEDULES
14 AMSCO 400 SERIES SMALL STEAM STERILIZER 1 NO V C 1923 THE AMSCO 400 SERIES SMALL STEAM STERILIZER PROVIDES EFFICIENT STERILIZATION FOR SPACE CONSTRAINED FACILITIES. WHILE MEETING AAMI/AORN GUIDELINES, THIS 20 X 20 AUTOCLAVE IS VALIDATED TO
ACCOMMODATE UP TO THREE 25-LB SETS.
STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
1920 -STERILIZATION 1920
15 AMSCO 600 MEDIUM STEAM STERILIZER 3 NO V C 1920 --- STERIS SEE MECHANICAL AND
ELECTRICAL SCHEDULES
16 S0495 LOADING CAR & TRANSFER CARRIAGE, 26.5"x26.5"x63"
CHAMBER
6 NO V V 1920 LOADING CAR AND TRANSFER CARRIAGE FOR USE WITH STERILIZERS HAVING A 26.5"x26.5"x63" CHAMBER. LOADING CAR IS A WELDED, CRS FRAMEWORK WITH TWO FULL-LENGTH ADJUSTABLE SHELVES OF CRS WELDED SHEET METAL AND WIRE. TRANSFER CARRIAGE IS CONSTRUCTED OF A WELDED CRS OR PAINTED FOR CORROSION PROTECTION FRAME AND PROVIDED TWO FIXED AND TWO SWIVEL CASTERS. LOADING CAR IS SECURED TO THE TRANSFER CARRIAGE BY A LOCKING MECHANISM. FOR LOADING AND UNLOADING 24X36X48 STERILIZERS AND FOR TRANSFERRING GOODS TO AND FROM PROCESSING AREAS.
STERIS
1912 - H2O
17 K2020 DISPENSER, DETERGENT, AUTOMATIC 1 NO V V 1912 AUTOMATIC DETERGENT DISPENSER. CHARACTERISTICS/COMPONENTS INCLUDE SUPPORTING CHEMICALS; DETERGENT ADDITIVE AND RINSE ADDITIVE. WALL MOUNTED UNIT. STERIS
18 M4871 SYSTEM, REVERSE OSMOSIS, WATER 1 NO C C 1912 REVERSE OSMOSIS SYSTEM TO PURIFY WATER IN HEMODIALYSIS CLINICS AND OTHER CLINICAL AREAS. THE SYSTEM CONSISTS OF A PUMP, WATER SOFTENER, MEDIA AND CARBON FILTERS, PROCESSING UNIT, ULTRAVIOLET STERILIZER, FINAL FILTRATION, DEIONIZERS, OSMOSIS UNITS, CONTROLS AND MONITORS. THE SYSTEM ALARMS WHEN A MALFUNCTION OCCURS. THE SYSTEM USUALLY REQUIRES A ROOM OF ITS OWN. REFER TO THE MANUFACTURERS SPECIFICATIONS FOR EXACT INSTALLATION REQUIREMENTS. DATABASE SYSTEM WEIGHT DOES NOT INCLUDE THE WATER IN THE PIPING OR HOLDING TANKS OF AN
OPERATING SYSTEM.
CULLIGAN SEE PLUMBING DRAWINGS
AND SCHEDULES
19 TRACK MOUNTED - SUSPENDED SHELVING 2 NO C C 1921 INTEGRAL FLOOR MOUNTED RAIL SYSTEM, FOR MANUAL OPERATED HIGH DENSITY MOBILE SHELVING. SPACESAVER
1/2" 1"0" 2"SCALE: FULL
MATCH LINE
SEE XN/XXNNN
XC1 P1 R1
XX" Ø X
XX'-X" XX'-X"
X
XN
XXNNN
XN
XXNNN
XN
XXNNN
F1 A
HSS _x_x_
B1
20GA TYPE 'W3' MTL DECK
PC S
PAN
Hx R15:12
B
B
GENERAL STRUCTURAL NOTES INDEX TO STRUCTURAL SHEETSSYMBOLS LEGEND
COORDINATE SYSTEM
S J
W--x--
(XXX'-XX")
ELEVATION
INDICATOR
CUT SECTION
INDICATOR
WALL
REINFORCING
INDICATOR
PC SPAN
IDENTIFIER
STEP TOP OF
WALL INDICATOR
PIER TAG CALLOUT INDICATOR
ROOF SLOPE
INDICATOR
STEP TOP OF
FOOTING
IDENTIFIER
MASONRY PIER
INDICATOR
CORNER REINF
INDICATOR
CONTINUOUS
BEAM
INDICATOR
MATCH LINE INDICATOR
PLAN NORTH ORIENTED 90°
TO THE SHEET W/ MAGNETIC
NORTH (OPTIONAL)
SHEET TYPE DESIGNATORS
SHEET IDENTIFICATION
SHEET TYPE
DESIGNATOR
SHEET SEQUENCE
NUMBER 01-99
MODIFIER
CHARACTER
DISCIPLINE
CHARACTER
-S
AA
DETAIL BUBBLE
INDICATOR
DETAIL/SECTION/PLAN
BLOCK TITLE INDICATOR
EXT ELEVATION
INDICATOR
COLUMN
INDICATOR(S)
KEYNOTE
IDENTIFIER
REVISION
SYMBOL
NNN
0 GENERAL (SYMBOLS LEGEND, NOTES, ETC)
1 PLANS (HORIZONTAL VIEWS)
2 ELEVATIONS (VERTICAL VIEWS)
3 SECTIONS (SECTIONAL VIEWS)
4 LARGE SCALE VIEWS (PLANS, ELEV, OR SECTIONS, NOT DETAILS)
5 DETAILS
6 SCHEDULES AND DIAGRAMS
7 USER DEFINED
8 USER DEFINED
9 3D REPRESENTATIONS (ISOMETRICS, PERSPECTIVES, PHOTOGRAPHS)
A1
54321
FOOTING/PIER
IDENTIFIER
STEP
INDICATOR
HOLDOWN
INDICATOR
BEAM
INDICATOR(S)
MOMENT
INDICATOR
DECK INDICATOR
SHEAR WALL
INDICATOR
LINTEL
INDICATOR
RAFTER
INDICATOR
ASTERISK
INDICATOR
SLOPE
INDICATOR
WORK POINT
INDICATOR
54321
D
B
A
C
D
B
A
C
A3
C5C4
D4
C3
D3
XN
ELEVATION INDICATOR
SECTION
INDICATOR
COLUMN/FND
GRID INDICATOR
SLAB JOINT
INDICATOR
STRUCTURAL HATCH PATTERNS
BRICK
CONCRETE
NATIVE
UNDISTURBED
SOIL
BACKFILL/FILL
ENGINEERED FILL
DRAINAGE
COURSE
GYPSUM
BOARD
WD- BLKG
OR SHIM
PLYWOOD/OSB
/PARTICLE BD
WD- GLUED
/LAMINATED
WOOD-
CONTINUOUS
FRAMING
INSUL/FIRE
SAFING
METAL FLOOR
GRATING
GROUT
RIGID
INSUL/ICF/SIP
/EIFS SYSTEMS
METALS
MORTAR
CMU
ROUGH LOG
WALL
WOOD STUD
BRG WALL
CONC WALL
HOLDOWN
(BLOCKOUT)
STONE/
ROCK WALL
C1
Hx
SW
x
XXX' - XX"
TOx
N
CONT
MOST COMMONLY USED STRUCTURAL ABBREVIATIONS
SYMBOLS USED AS ABBREVIATIONS:
& AND
L ANGLE
LL DOUBLE ANGLE
@ AT
CL CENTER LINE
// PARALLEL
d PENNY (NAIL)
┴ PERPENDICULAR
PL PLATE
# POUND OR NUMBER
Ø ROUND OR DIAMETER
ABBREVIATIONS:
(A)--------------------
A/E ARCHITECT/ENGINEER
AB ANCHOR BOLT/ROD
ABV ABOVE
ADDL ADDITIONAL
ADDM ADDENDUM
ADH ADHESIVE
ADJ ADJUSTABLE, ADJACENT,
ADJOINING
AFF ABOVE FINISH FLOOR
AGGR AGGREGATE
AHR ANCHOR, ANCHORAGE
ALT ALTERNATE
APPROX APPROXIMATE
**AR ANCHOR ROD
ARCH ARCHITECT (URAL)
(B)---------------------
BEV BEVELED
BFF BELOW FINISH FLOOR
**BL BRICK LEDGE
BLDG BUILDING
BLW BELOW
**BLK BLOCK (ING)
BM BEAM
BOT BOTTOM
**BO BOTTOM OF
**BOC BOTTOM OF CONCRETE
**BOF BOTTOM OF FOOTING
BRG BEARING
**BRK BRICK
BSMT BASEMENT
BTWN BETWEEN
BU BUILT-UP
(C)---------------------
C CHANNEL
CAM*(C=) CAMBER
CB CARRIAGE BOLT
CU FT CUBIC FEET OR FOOT
CHFR CHAMFER
CIP CAST-IN-PLACE
**CIPC CAST-IN-PLACE CONCRETE
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CLR CLEAR, CLEARANCE
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONN CONNECT (ION)
CONSTR CONSTRUCTION
CONT CONTINUOUS, CONTINUE
CONTR CONTRACT (OR)
COORD COORDINATE
CTR CENTER
CU CUBIC
CU YD CUBIC YARD
(D)---------------------
D DEEP, DEPTH, PENNY (NAIL)
DBL DOUBLE
DEMO DEMOLITION, DEMOLISH
DET DETAIL
DIA DIAMETER
DIAG DIAGONAL, DIAGRAM
DIM DIMENSION
DIR DIRECTION
DIV DIVIDE, DIVISION
**DKG DECKING
DL DEAD LOAD
DOUG FIR DOUGLAS FIR
DR DRAIN
DT DRAIN TILE
DWG DRAWING (S)
(E)---------------------
**(E) EXISTING (SEE EXIST)
EA EACH
**EAB EPOXY ANCHOR BOLT
EF EACH FACE
EJ EXPANSION JOINT
EL ELEVATION
**EMB EMBED (ED)
EPS EXPANDED POLYSTYRENE
EQ EQUAL
EQUIP EQUIPMENT
EST ESTIMATE
EW EACH WAY
EXIST EXISTING
EXP EXPANSION, EXPOSED
EXP BT EXPANSION BOLT
EXT EXTERIOR, EXTERNAL
(F)---------------------
FD FLOOR DRAIN
**FND FOUNDATION
FF EL FINISH FLOOR ELEVATION
FIN FINISH (ED)
FLG FLANGE
FLR FILLER, FLOOR (ING)
**FO FACE OF
FOC FACE OF CONCRETE
FOM FACE OF MASONRY
FOS FACE OF STUD
**FOW FACE OF WALL
FS FAR SIDE
FT FOOT, FEET
FTG FOOTING
FRMG FRAMING
FUT FUTURE
(G)---------------------
GA GAGE, GAUGE
GALV GALVANIZED
GC GENERAL CONTRACTOR
**GL GLUE LAMINATED (BEAM)
GLU LAM GLUE LAMINATED (BEAM)
GR BM GRADE BEAM
GRTG GRATING
GYP GYPSUM
GYP BD GYPSUM BOARD
(H)---------------------
H HIGH
**HAB HEADED ANCHOR BOLT
**HAS HEADED ANCHOR STUD
HC HOLLOW CORE
HDR HEADER
HGR HANGER
HORIZ HORIZONTAL
HS HIGH STRENGTH
**HSB HIGH STRENGTH BOLT
**HSS HOLLOW STRUCTURAL SHAPE
HT HEIGHT
(I)---------------------
ID INSIDE DIAMETER
INCL INCLUDE (D), INCLUDING
INFO INFORMATION
INSUL INSULATE (D), INSULATION
INT INTERIOR
INV EL INVERT ELEVATION
(J)---------------------
**JST JOIST
**JT JOINT
(K)---------------------
K THOUSAND (KIP)
**KCJ KEYED CONSTRUCTION JOINT
KIP THOUSAND POUND
KLF KIPS PER LINEAR FOOT
KSF KIPS PER SQUARE FOOT
KSI KIPS PER SQUARE INCH
(L)---------------------
L ANGLE
LAM LAMINATE (ED)
**LB POUND
LF LINEAR FEET
**LGR LEDGER
LL LIVE LOAD
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LOC LOCATION
LONG LONGITUDINAL
**LSL LAMINATED STRAND LUMBER
LT WT LIGHTWEIGHT
**LVL LAMINATED VENEER LUMBER
LVR LOUVER
(M)---------------------
MACH MACHINE
MB MACHINE BOLT
MATL MATERIAL
MAX MAXIMUM
MBR MEMBER
**MC MISCELLANEOUS CHANNEL
MECH MECHANICAL
MEZZ MEZZANINE
MFD MANUFACTURED
MFR MANUFACTURER
MFR REC MANUFACTURER'S
RECOMMENDATION
MIN MINIMUM
MISC MISCELLANEOUS
MTL METAL
(N)---------------------
**(N) NEW
NA NOT APPLICABLE
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NS NEAR SIDE
NTS NOT TO SCALE
(O)---------------------
OC ON CENTER
OD OUTSIDE DIAMETER
OH DR OVERHEAD DOOR
OPNG OPENING
OPP OPPOSITE
**OSB ORIENTED STRAND BOARD
**OVS OVERSIZED
(P)---------------------
**PAF POWDER ACTUATED
FASTENER
PAR PARALLEL
PCF POUNDS PER CUBIC FOOT
PED PEDESTAL
PERF PERFORATED
PERP PERPENDICULAR
PL PLATE
PLF POUNDS PER LINEAR FOOT
PLYWD PLYWOOD
PNL PANEL
PR PAIR, PIPE RAIL
PRCST PRECAST CONCRETE
PREFAB PREFABRICATE
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
**PSL PARALLEL STRAND LUMBER
PT POST TENSION (ED),
PRESSURE TREATED
PVC POLYVINYL CHLORIDE
(R)---------------------
R RADIUS/RISE (R)
RCP REINFORCED CONCRETE PIPE
REF REFERENCE
REINF REINFORCE (D), (ING)
REQ REQUIRE
REQD REQUIRED
REV REVISION (S), REVISED
RO ROUGH OPENING
RS ROUGH SAWN
RVS REVERSE (SIDE)
(S)---------------------
SCHED SCHEDULE
SECT SECTION
SHT SHEET
SHTHG SHEATHING
SIM SIMILAR
**SL SNOW LOAD
SLNT SEALANT
SLV SLEEVE
**SOG SLAB-ON-GRADE
SPEC SPECIFICATION (S)
SQ SQUARE
**SSL SHORT SLOTTED (HOLE)
**SSLT SHORT SLOTTED (HOLE)
TRANSVERSE
SST STAINLESS STEEL
STD STANDARD
STIF STIFFENER
STL STEEL
STRUCT STRUCTURAL
SUB FL SUBFLOOR
SUSP SUSPENDED
**SW SHEAR WALL
SYMM SYMMETRY, SYMMETRICAL
(T)---------------------
T TREAD
T&B TOP AND BOTTOM
T&G TONGUE AND GROOVE
**TBD TO BE DETERMINED
THD THREAD (ED) (S)
THK THICKNESS
THRU THROUGH
**TL TOTAL LOAD
TO TOP OF
TOB TOP OF BEAM
TOC TOP OF CONCRETE
TOF TOP OF FOOTING
TOM TOP OF MASONRY
TOP TOP OF PIER
TO PAR TOP OF PARAPET
TOS TOP OF STEEL, SLAB
TO SHTHG TOP OF SHEATHING
TO SUB FL TOP OF SUBFLOOR
TOW TOP OF WALL
**TRANS TRANSVERSE
TRTD TREATED
TS TUBE STEEL
TYP TYPICAL
(U)--------------------
UNO UNLESS NOTED OTHERWISE
(V)---------------------
**V SHEAR
VERT VERTICAL
VIF VERIFY IN FIELD
VR VAPOR RETARDER
VRFY VERIFY
(W)---------------------
W WIDTH
W/ WITH
W/O WITHOUT
**WA WEDGE ANCHOR
WD WOOD
WF (W) WIDE FLANGE
WL WIND LOAD
WLD WELD (ED)
WP WATERPROOFING, WORKING
POINT
**WS WALL STEP
WT WEIGHT
WWF WELDED WIRE FABRIC
(X)---------------------
XPS EXTRUDED POLYSTYRENE
(Y)---------------------
YD YARD
** NOT LISTED IN THE NCS MANUAL
1. STRUCTURAL DRAWINGS SHALL BE USED IN CONJUNCTION WITH JOB
SPECIFICATIONS AND ARCHITECTURAL, MECHANICAL, ELECTRICAL, PLUMBING AND
SITE DRAWINGS. CONSULT THESE DRAWINGS FOR SLEEVES, DEPRESSIONS AND
OTHER DETAILS NOT SHOWN ON STRUCTURAL DRAWINGS.
2. ALL DIMENSIONS AND CONDITIONS MUST BE VERIFIED IN THE FIELD. ANY
DISCREPANCIES SHALL BE BROUGHT TO THE ATTENTION OF THE CONTRACTING
OFFICER BEFORE PROCEEDING WITH THE AFFECTED PART OF THE WORK.
3. THE STRUCTURE IS DESIGNED TO BE SELF SUPPORTING AND STABLE AFTER THE
BUILDING IS COMPLETE. IT IS THE CONTRACTOR'S SOLE RESPONSIBILITY TO
DETERMINE ERECTION PROCEDURES AND SEQUENCE TO ENSURE SAFETY OF THE
BUILDING AND ITS COMPONENTS DURING ERECTION. THIS INCLUDES THE ADDITION
OF NECESSARY SHORING, SHEETING, TEMPORARY BRACING (AND ACCOMPANYING
FOOTINGS), GUYS OR TIE-DOWNS.
4. ADDITIONAL OBSERVATIONS AS A RESULT OF REJECTION OF WORK COMPLETED
AND/OR ADDITIONAL OBSERVATIONS DUE TO THE DEFICIENCIES IN WORK OBSERVED
WILL BE AT THE EXPENSE OF THE CONTRACTOR.
5. ALL STRUCTURAL SHOP DRAWINGS TO BE REVIEWED BY JOB SUPERINTENDENT IN
ADDITION TO ALL PERSONNEL DEEMED NECESSARY BY CONTRACTOR PRIOR TO
SUBMITTAL TO CONTRACTING OFFICER FOR APPROVAL.
6. THE DESIGN OF THE STRUCTURE SHOWN IN THESE CONSTRUCTION DOCUMENTS IS
FOR THE ONE-TIME USE AT THE SPECIFIC SITE REFERENCED WITHIN THESE
DRAWINGS.
MINIMUM SLEEVE SPACING SHALL BE TWO DIAMETERS CENTER TO CENTER TO THE
LARGER SLEEVE OR 6" CLEAR BETWEEN SLEEVES, WHICHEVER IS GREATER. PRIOR TO
CONSTRUCTION SLEEVE LOCATIONS AND SIZES SHALL BE APPROVED BY THE
STRUCTURAL ENGINEER OF RECORD.
SHALL BE A POLYMER INJECTION SYSTEM SUCH AS HILTI HY-200, OR APPROVED EQUAL,
INSTALLED IN ACCORDANCE WITH THE MANUFACTURERS INSTRUCTIONS. INSTALLERS
SHALL BE TRAINED BY THE MANUFACTURER'S REPRESENTATIVE.
1. SHALL BE A36 THREADED ROD. PROVIDE HOT DIP GALVANIZE FINISH ON ALL
ANCHOR BOLTS PERMANENTLY EXPOSED TO EXTERIOR OR IN CONTACT WITH
PRESSURE TREATED LUMBER.
2. THREADED ROD EMBEDMENT DEPTH SPECIFIED IN THE DRAWINGS SHALL BE FROM
TOP OF CONCRETE TO TOP OF DOUBLE NUT.
1. CONCRETE TESTING SHALL BE PAID FOR BY THE OWNER. TESTING LABORATORY
SHALL PERFORM THE FOLLOWING TEST ON CAST-IN-PLACE CONCRETE:
A. ASTM C143 - "STANDARD TEST METHOD FOR SLUMP OF PORTLAND CEMENT
CONCRETE."
B. ASTM C39 - "STANDARD TEST METHOD FOR COMPRESSIVE STRENGTH OF
CYLINDRICAL CONCRETE SPECIMENS. A SEPARATE TEST SHALL BE CONDUCTED
FOR EACH CLASS, FOR EVERY 50 CUBIC YARDS (OR FRACTION THEREOF), PLACED
PER DAY. REQUIRED CYLINDER(S) QUANTITIES AND TEST AGE AS FOLLOWS:
a. AT 7 DAYS
b. AT 28 DAYS
C. PROVIDE ONE ADDITIONAL RESERVE CYLINDER TO BE TESTED UNDER THE
DIRECTION OF THE CONTRACTING OFFICER, IF REQUIRED. IF 28 DAY STRENGTH IS
ACHIEVED, THE ADDITIONAL CYLINDER(S) MAY BE DISCARDED.
D. TESTING SHALL BE BASED UPON CONCRETE TAKEN AT POINT OF PLACEMENT.
E. IN ADDITION TO TYPICAL TESTING REQUIREMENTS, SLUMP AND AIR CONTENT
SAMPLES SHALL BE TAKEN AT BEGINNING OF FIRST TRUCK PRIOR TO ANY
PLACEMENT AND REPEATED AT THE MIDDLE OF FIRST TRUCK. CONCRETE
PLACEMENT SHALL NOT START IF INITIAL TEST(S) FAIL AND SHALL NOT CONTINUE
OF TEST TAKEN AT MIDDLE OF FIRST LOAD FAILS.
F. IF ANY SLUMP OR AIR CONTENT FAILS DURING PLACEMENT, TESTS SHALL BE
IMMEDIATELY REPORTED AND RETAKEN. IF RETAKEN TESTS FAIL THEN ALL
SUBSEQUENT LOADS MUST BE TESTED AT ARRIVAL AND TEST MUST SHOW
COMPLIANCE PRIOR TO THE CONCRETE IN THAT TRUCK BEING ALLOWED FOR USE
ON PROJECT. ALL COSTS FOR ADDITIONAL TESTING SHALL BE CREDITED TO THE
OWNER.
NO PENETRATIONS SHALL BE MADE IN ANY STRUCTURAL MEMBERS OTHER THAN THOSE
LOCATED ON THESE DRAWINGS WITHOUT PREVIOUS APPROVAL OF THE CONTRACTING
OFFICER.
1. SHALL BE MIX DESIGNED BY A RECOGNIZED TESTING LABORATORY TO ACHIEVE A
STRENGTH AT 28 DAYS AS LISTED BELOW WITH A PLASTIC AND WORKABLE MIX:
1. 4,000 PSI - INTERIOR SLABS ATOP METAL DECK
2. 4,000 PSI - ALL OTHER CONCRETE
2. SUBMIT PROPOSED MIX DESIGN WITH RECENT FIELD CYLINDER OR LAB TESTS FOR
REVIEW PRIOR TO USE. MIX SHALL BE UNIQUELY IDENTIFIED BY MIX NUMBER OR
OTHER POSITIVE IDENTIFICATION. CONCRETE SHALL COMPLY WITH ALL THE
REQUIREMENTS OF ASTM STANDARD C94 FOR MEASURING, MIXING,
TRANSPORTING, ETC. CONCRETE TICKETS SHALL BE TIME STAMPED WHEN
CONCRETE IS BATCHED. THE MAXIMUM TIME ALLOWED FROM THE TIME THE MIXING
WATER IS ADDED UNTIL IT IS DEPOSITED IN ITS FINAL POSITION SHALL NOT EXCEED
ONE AND ONE HALF (1-1/2) HOURS. IF FOR ANY REASON THERE IS A LONGER DELAY
THAN STATED ABOVE, THE CONCRETE SHALL BE DISCARDED. IT SHALL BE THE
RESPONSIBILITY OF THE TESTING LAB TO NOTIFY THE OWNER'S REPRESENTATIVE
AND THE CONTRACTOR OF ANY NONCOMPLIANCE WITH THE ABOVE. ALL SLABS
SHALL BE CURED USING CURING COMPOUND MEETING ASTM STANDARD C309 TYPE
1 AND SHALL HAVE A FUGITIVE DYE. THE COMPOUND SHALL BE PLACED AS SOON
AS THE FINISHING IS COMPLETED OR AS SOON AS THE WATER HAS LEFT THE
UNFINISHED CONCRETE. ALL SCUFFED OR BROKEN AREAS IN THE CURING
MEMBRANE SHALL BE RECOATED DAILY. CALCIUM CHLORIDES SHALL NOT BE
UTILIZED; OTHER ADMIXTURES MAY BE USED ONLY WITH THE APPROVAL OF THE
CONTRACTING OFFICER.
3. CONCRETE SHALL UTILIZE TYPE I/II CEMENT AND SHALL HAVE A 25% MINIMUM FLY
ASH CONTENT BY WEIGHT.
4. COARSE AND FINE AGGREGATES SHALL COMPLY WITH ASTM C33 AND ACI 302.1,
CURRENT VERSIONS.
5. THE CONCRETE STRENGTHS SHOWN IN THE SECTION ABOVE AND IN THE
SPECIFICATIONS ARE MINIMUM COMPRESSIVE STRENGTHS. THE CONTRACTING
OFFICER SHALL DETERMINE IF THE CONCRETE IS ACCEPTABLE, OR TO BE
REMOVED, OR TO RECEIVE SPECIAL CURING IF THE COMPRESSIVE STRENGTHS ARE
LESS THAN SPECIFIED.
6. ALL CONCRETE EXPOSED TO WEATHER OR EARTH SHALL BE AIR ENTRAINED TO 5%
TO 7%.
7. WATER REDUCING AGENTS MAY BE USED IN THE CONCRETE MIX. PLASTICIZERS
AND SUPER-PLASTICIZERS MAY BE USED ONLY WHEN WRITTEN PERMISSION OF THE
CONTRACTING OFFICER IS GIVEN.
8. NO SALTS OF ANY KIND MAY BE USED IN CONCRETE BEFORE OBTAINING THE
CONTRACTING OFFICER'S WRITTEN PERMISSION FOR THEIR USE.
9. AIR CONTENT OF TROWEL FINISHED FLOOR SLABS SHALL NOT EXCEED 3%.
10. MAXIMUM WATER TO CEMENTITIOUS MATERIAL FOR ALL CONCRETE SHALL NOT
EXCEED 0.5 UNLESS NOTED OTHERWISE.
11. SLUMP REQUIREMENTS (± 1"):
ELEVATED CONCRETE SLABS: 4"
NO STRUCTURAL CONCRETE SHALL BE STRIPPED UNTIL IT HAS REACHED AT LEAST TWO-
THIRDS OF THE 28 DAY DESIGN STRENGTH. DESIGN, ERECTION AND REMOVAL OF ALL
FORMWORK, SHORES AND RESHORES SHALL MEET THE REQUIREMENTS SET FORTH IN
ACI STANDARDS 301 AND 347.
1. STEEL SHALL CONFORM TO ASTM A992 (Fy=50 KSI) FOR ALL W-SHAPES, AND ASTM A36 (Fy=36 KSI) FOR ALL OTHER MISCELLANEOUS SHAPES AND PLATES.
STRUCTURAL TUBING SHALL CONFORM TO ASTM A500, GRADE B OR C (Fy=46 KSI, MIN). STRUCTURAL PIPE SHALL CONFORM TO ASTM A53, GRADE B, TYPE "E" OR "S"
(Fy=35 KSI).
2. STEEL SHALL CONFORM TO THE LATEST EDITION OF AISC SPECIFICATIONS FOR
STRUCTURAL STEEL BUILDINGS.
3. ALL SHOP CONNECTIONS TO BE WELDED (UTILIZING E70XX ELECTRODES) AND FIELD
CONNECTIONS TO BE BOLTED, UNLESS OTHERWISE NOTED. STEEL TO RECEIVE ONE
SHOP COAT AND ONE FIELD TOUCH UP COAT OF APPROVED PAINT, EXCEPT WHERE
GALVANIZED IS INDICATED ON THE DRAWINGS.
4. WELDS FOR ALL EXPOSED STRUCTURAL STEEL SHALL BE GROUND SMOOTH UNLESS
NOTED OTHERWISE.
5. ALL BOLTED CONNECTIONS SHALL CONSIST OF 3/4" DIA. (MIN.) F1852 HIGH STRENGTH
BOLTS, UNLESS NOTED OTHERWISE.
A. FAILURE OF A BOLT OR NUT DURING INSTALLATION PROCESS RESULTING IN A
CRACK IN THE BOLT OR NUT SHALL BE GROUNDS FOR REJECTION OF ALL THE
FAILED BOLTS OR NUTS COMING FROM THE SAME LOT. IF THE DOCUMENTATION
OF THE LOT OF ORIGIN FOR THE FAILED NUT(S) OR BOLT(S) DOES NOT EXIST, OR
IS NOT PROVIDED, THEN ALL OF THE BOLT(S) OR NUT(S) SHALL BE ASSUMED TO
COME FROM THE LOT CONTAINING THE FAILED NUT(S) OR BOLT(S).
6. CONTRACTOR SHALL MAINTAIN ERECTION TOLERANCES OF STRUCTURAL STEEL AND
ARCHITECTURALLY EXPOSED STRUCTURAL STEEL WITHIN AISC'S CODE OF
STANDARD PRACTICE FOR STEEL BUILDINGS AND BRIDGES.
7. ANCHOR BOLT HOLES IN STRUCTURAL STEEL SHALL BE OVERSIZED NO MORE THAN
1/8" MAX, UNLESS NOTED OTHERWISE.
1. COMPOSITE FORM DECK SHALL BE 2" DEEP, 16 GAUGE G60 CORRUGATED STEEL
COMPOSITE DECK (2VLI-16) AND SHALL CONFORM TO THE PROVISIONS OF THE STEEL
DECK INSTITUTE (SDI) SPECIFICATIONS FOR COMPOSITE STEEL DECK.
2. POUR STOPS AND GIRDER FILLERS: WELD STEEL SHEET POUR STOPS AND GIRDER
FILLERS TO SUPPORTING STRUCTURE ACCORDING TO SDI RECOMMENDATIONS,
UNLESS OTHERWISE INDICATED.
3. FLOOR DECK CLOSURES: WELD STEEL SHEET COLUMN CLOSURES, CELL CLOSURES,
AND Z-CLOSURES TO DECK, ACCORDING TO SDI RECOMMENDATIONS, TO PROVIDE
TIGHT FITTING CLOSURES AT OPEN ENDS OF RIBS AND SIDES OF DECKING. WELD
COVER PLATES AT CHANGES IN DIRECTION OF FLOOR DECK PANELS, UNLESS
OTHERWISE INDICATED.
4. DECKING SHALL HAVE MINIMUM OF (3) SPANS.
1. STEEL STUD, TRACK, AND LINTEL MEMBERS SHALL BE OF THE TYPE SHOWN ON THE
DRAWINGS AND IN THE SPECIFICATIONS AND SHALL CONFORM TO ASTM A653
STRUCTURAL QUALITY GRADE 33 FOR 18 GAUGE THICKNESS OR LESS, AND ASTM A653
STRUCTURAL QUALITY GRADE 50, CLASS 1 FOR 16 GAUGE OR GREATER. MEMBERS
SHALL HAVE HOT DIPPED GALVANIZED COATING CONFORMING TO ASTM A924, CLASS
G60.
2. ALL FRAMING MEMBERS SHALL BE CUT SQUARELY OR AT AN ANGLE AS REQUIRED TO
FIT SQUARELY AGAINST ABUTTING MEMBERS. MEMBERS SHALL BE HELD FIRMLY IN
PLACE UNTIL PROPERLY JOINED.
3. JOINING OF STRUCTURAL MEMBERS SHALL BE MADE WITH SELF-DRILLING SCREWS
OR WELDED. WIRE TYING OF FRAMING MEMBERS IN STRUCTURAL APPLICATIONS
SHALL NOT BE PERMITTED.
4. ATTACHMENT OF COLLATERAL MATERIALS TO STEEL MEMBERS SHALL BE MADE WITH
SELF-DRILLING SCREWS OR HARDENED SCREW SHANK NAILS. METAL LATH MAY ALSO
BE CONNECTED TO STEEL BY STAPLES OR OTHER FASTENERS, IF APPROVED BY
LOCAL BUILDING CODES.
5. STUDS SHALL SIT SQUARELY IN THE TOP AND BOTTOM RUNNER TRACK WITH
ABUTMENT AGAINST TRACK WEBS. STUDS SHALL BE ALIGNED OR PLUMBED AND
SECURELY FASTENED TO THE FLANGES OF BOTH TOP AND BOTTOM RUNNER TRACKS.
6. VERTICAL SLIP CONNECTORS TO ALLOW THE VERTICAL MOVEMENT OF THE
SUPPORTING STRUCTURE RELATIVE TO THE STUD SHALL BE VERTICLIP SLAB
CONNECTORS OR APPROVED EQUAL. CONNECTOR MANUFACTURER RESPONSIBLE
FOR PROVIDING DOCUMENTATION THAT CONNECTOR HAS ADEQUATE CAPACITY FOR
INSTALLATIONS IN WHICH THEY ARE TO BE INSTALLED, AS WELL AS SPECIFYING THE
CONNECTION OF THEIR CONNECTOR TO BOTH THE METAL STUD AND SUPPORTING
STRUCTURE.
1. SEE DETAILED INSPECTION AND TESTING REQUIREMENTS AS INDICATED ON SHEET
S-002.
SHT NO SHEET NAME
S-001 STRUCTURAL GENERAL NOTES
S-002 IBC INSPECTION TABLES
S-003 SNOW DRIFT AND WIND UPLIFT PLANS
S-102 LEVEL (02) INTERSTITIAL FRAMING PLAN LEVEL
S-102.1 LEVEL (02) INTERSTITIAL FRAMING PLAN LEVEL - ALTERNATIVE BID #2 & #5
S-103 LEVEL (03) FLOOR FRAMING PLA
S-103.1 LEVEL (03) FLOOR FRAMING PLAN - ALTERNATIVE BID #2 & #5
S-104 LEVEL (04) ROOF FRAMING PLAN
S-104.1 LEVEL (04) ROOF FRAMING PLAN - ALTERNATIVE BID #2 & #5
S-401 LATERAL FRAMING ELEVATIONS
S-402 LATERAL FRAMING ELEVATIONS
S-403 LATERAL FRAMING DETAILS & SCHEDULE
S-404 ENLARGED STAIR FRAMING PLANS
S-404.1 ENLARGED STAIR FRAMING PLANS - ALTERNATIVE BID #2 & #5
S-501 DETAILS
S-501.1 DETAILS - ALTERNATIVE BID #2 & #5
S-502 DETAILS
S-502.1 DETAILS - ALTERNATIVE BID #2 & #5
S-503 DETAILS
S-503.1 DETAILS - ALTERNATIVE BID #2 & #5
S-601 STANDARD DETAILS / SCHEDULE
S-601.1 STANDARD DETAILS / SCHEDULES - ALTERNATIVE BID #2 & #5
1. ALL CONCRETE SHALL BE PLACED IN ACCORDANCE WITH ACI 301 AND ACI 117
EXCEPT AS MODIFIED BELOW:
2. ALL REINFORCING STEEL TO BE ASTM A615, GRADE 60 (#4 AND LARGER), EXCEPT
WHERE NOTED OTHERWISE. REINFORCING SHALL NOT BE WELDED.
3. ALL REINFORCING STEEL BARS TO BE DETAILED AND PLACED IN ACCORDANCE
WITH THE LATEST ACI MANUALS.
4. LAP ALL REINFORCING SPLICES IN CONCRETE A MINIMUM OF 48 BAR DIAMETERS
OR 24 INCHES, WHICHEVER IS GREATER, UNLESS NOTED OTHERWISE ON
DRAWINGS (CLASS B SPLICE).
5. PROVIDE CORNER BARS OF SAME BAR DIAMETER AS SPECIFIED FOR THE WALL,
BEAM OR FOOTING. PROVIDE MINIMUM OF 40 BAR DIAMETER LAP FOR ALL CORNER
BARS, UNLESS NOTE OTHERWISE.
6. WHERE SHOWN ON THE DRAWINGS, PROVIDE WELD PLATES, WELDMENTS, OR
CONCRETE INSERTS FOR FASTENING AND SECURING OTHER COMPONENTS.
CONCRETE INSERTS SHALL BE FURNISHED BY THE CONTRACTOR REQUIRING
THEM AND INSTALLED BY THE CONTRACTOR CASTING THE CONCRETE AROUND
THEM. CLIP ANGLES SHALL BE FURNISHED BY THE CONTRACTOR REQUIRING
THEM.
7. REINFORCING STEEL SHALL RECEIVE CONCRETE COVER AS FOLLOWS:
DESCRIPTION MINIMUM COVER
CAST AGAINST & PERMANENTLY 3"
EXPOSED TO EARTH
EXPOSED TO EARTH OR WEATHER
#6 THROUGH #18 BARS 2"
#5 BARS OR SMALLER 1 1/2"
NOT EXPOSED TO EARTH OR WEATHER
OR IN CONTACT WITH THE GROUND, SLABS
AND WALLS
#11 BARS OR SMALLER 3/4"
#14 AND #18 1 1/2"
BEAMS AND COLUMNS 1 1/2"
SHELLS, FOLDED PLATE MEMBERS:
NO. 6 BAR AND LARGER 3/4"
NO. 5 BAR, W31 OR D31 WIRE AND SMALLER 1/2"
8. PROVIDE TWO (2) #5'S, ONE AT EACH FACE, UNLESS NOTED OTHERWISE, AROUND
ALL OPENINGS GREATER THAN 12"x12" IN CAST-IN-PLACE CONCRETE. EXTEND
REINFORCING 2'-0" BEYOND OPENING IN BOTH DIRECTIONS. CONTACT
CONTRACTING OFFICER FOR ALL OPENINGS GREATER THAN 12"x12" FOR DESIGN.
9. COLD WEATHER AND HOT WEATHER PROVISIONS OF ACI 306 AND 305 (CURRENT
EDITIONS), RESPECTIVELY, SHALL BE MAINTAINED.
10. PRIOR TO SCREEDING AN ELEVATED SLAB, CONCRETE SHALL BE UNIFORMLY
PLACED ON ALL (3) SPANS OF THE DECK TO A THICKNESS APPROXIMATELY EQUAL
TO THE SPECIFIED SLAB THICKNESS AT EACH BEAM OR JOIST LINE.
11. CONTRACTOR IS RESPONSIBLE FOR ESTIMATING CONCRETE QUANTITIES ON
ELEVATED SLABS AND SHALL ACCOUNT FOR DEFLECTIONS IN THE FLOOR
STRUCTURE.
12. CONTRACTOR SHALL MAINTAIN A CONSTANT THICKNESS OVER THE ENTIRE
ELEVATED SLAB. ELEVATED SLAB THICKNESS SHALL NOT BE 3/8" GREATER THAN
OR 1/4" LESS THAN THE SPECIFIED THICKNESS.
13. LASER SCREED OR OTHER SIMILARLY FUNCTIONING EQUIPMENT SHALL NOT BE
PERMITTED FOR ELEVATED SLABS UNLESS AUTHORIZED BY ALBERTSON
ENGINEERING INC.
THE STRUCTURAL SYSTEM FOR THIS BUILDING HAS BEEN DESIGNED WITH THE
FOLLOWING SUPERIMPOSED LOADINGS BASED ON A RISK CATEGORY IV:
ROOF (FUTURE FLOOR):
SNOW LOAD 21 PSF + DRIFT
GROUND SNOW LOAD 25 PSF
SNOW EXPOSURE FACTOR 1.0
SNOW THERMAL FACTOR 1.0
SNOW IMPORTANCE FACTOR 1.2
DEAD LOAD 25 PSF
LIVE LOAD 20 PSF (REDUCIBLE)
FUTURE ROOF DEAD LOAD 25 PSF
FUTURE ROOF LIVE LOAD 20 PSF
WIND:
ULTIMATE WIND SPEED 124 MPH
EXPOSURE CATEGORY B
INTERNAL PRESSURE COEFFICIENT 0.18
COMPONENT AND CLADDING PRESSURES SEE TABLE ON SHEET S0.04
SEISMIC:
SEISMIC DESIGN CATEGORY C
SITE CLASSIFICATION D
SEISMIC IMPORTANCE FACTOR 1.5
MAPPED SPECTRAL RESPONSE COEFFICIENTS
Ss = 0.072 S1 = 0.045
SEISMIC FORCE RESISTING SYSTEM
RIGID DIAPHRAGM (CONCRETE SLAB ON COMPOSITE METAL DECK)
CONCENTRICALLY BRACE FRAMES
STEEL ORDINARY MOMENT FRAMES
DESIGN BASE SHEAR 0.036*W
SEISMIC RESPONSE COEFFICIENT 0.036
RESPONSE MODIFICATION COEFFICIENTS (R)
STEEL ORDINARY CONCENTRICALLY BRACED FRAMES 3.25
STEEL ORDINARY MOMENT FRAMES 3.5
ANALYSIS PROCEDURE
EQUIVALENT LATERAL FORCE PROCEDURE
GENERAL NOTES:
PLUMBING SLEEVES:
DESIGN LOADS:
PENETRATIONS:
FORMWORK AND SHORING:
CONCRETE MIX DESIGN: CONCRETE AND REINFORCING PLACEMENT:
CONCRETE TESTING:
CHEMICAL ANCHORS:
ANCHOR BOLTS:
STRUCTURAL STEEL:
COMPOSITE STEEL FORM DECK:
COLD FORMED LIGHT GAUGE STRUCTURAL STEEL:
SPECIAL INSPECTION AND TESTING:
• 2018 INTERNATIONAL BUILDING CODE.
• ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE AND
COMMENTARY.
• AISC 360-16 SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS.
• AISI S100-16 NORTH AMERICAN SPECIFICATION FOR THE DESIGN OF COLD-FORMED
STEEL STRUCTURAL MEMBERS.
• ASCE 7-16 MINIMUM DESIGN LOADS AND ASSOCIATED CRITERIA FOR BUILDINGS AND
OTHER STRUCTURES.
• SDI C-2017 STANDARD FOR COMPOSITE STEEL FLOOR DECK.
• SDI RD-2017 STANDARD FOR STEEL ROOF DECK.
DESIGN CODES:
PHOTO DOCUMENTATION OF CONSTRUCTION OF STRUCTURAL ITEMS
1. CONTRACTOR SHALL PROVIDE SETS OF PERIODIC DIGITAL PHOTOGRAPHS OF THE
CONSTRUCTION OF THE STRUCTURAL PORTIONS OF THE CONSTRUCTION PROJECT TO
THE CONTRACTING OFFICER FOR APPROVAL. PHOTOGRAPHS SHALL BE SUBMITTED TO
THE CONTRACTING OFFICER WITHIN 2 WORKING DAYS OF WHEN THEY WERE TAKEN.
THE MINIMUM SETS OF PHOTOGRAPHS TO BE TAKEN INCLUDE THE FOLLOWING:
EVENT
OVERALL
CONSTRUCTION
PROGRESS
OCCURRENCES
MINIMUM OF ONCE WEEKLY
DURING CONSTRUCTION.
CAN INCLUDE PHOTOS FROM
OTHER REQUIRED AREAS.
ITEMS TO DOCUMENT
GENERAL PROGRESSION OF CONSTRUCTION
PROJECT. SET OF PHOTOGRAPHS TO BE
SUFFICIENT TO SHOW MAJOR ASPECTS OF
CONSTRUCTION, WITH A MINIMUM OF 8
PHOTOGRAPHS PER SET.
CONCRETE
POURS
PRIOR TO EACH CONCRETE
POUR
CONDITION OF FORM WORK, PLACEMENT OF
CONCRETE REINFORCING, METHODS USED
TO SECURE REINFORCING IN CORRECT
LOCATIONS.
CONCRETE
MASONRY
CONSTRUCTION
PRIOR TO GROUTING PLACEMENT OF REINFORCING AND METHODS
USED TO SECURE REINFORCING IN CORRECT
LOCATIONS.
STEEL
CONSTRUCTION
PRIOR TO ENCLOSURE TYPICAL CONNECTIONS.
MAJOR
MILESTONES
2. ALL PHOTOGRAPHS TAKEN SHALL CLEARLY SHOW THE LOCATIONS AT WHICH THE PHOTOGRAPHS ARE BEING TAKEN. TYPICALLY THE LOCATIONS ARE SELF-EVIDENT, BUT FOR THOSE CASES WHERE THEY
ARE NOT, CONTRACTOR TO INCLUDE SOME METHOD OF DOCUMENTING THE LOCATIONS. THE
PHOTOGRAPHS SUBMITTED MAY BE EITHER A HARD COPY OR ELECTRONIC FORMAT. HARD COPIES OF THE PHOTOGRAPHS ARE NOT REQUIRED, AND IT IS STRONGLY PREFERRED THAT THE PHOTOGRAPHS
BE E-MAILED TO THE CONTRACTING OFFICER.
FLOOR:
DEAD LOAD 25 PSF
LIVE LOAD 80 PSF
FUTURE SURGICAL FLOOR LIVE LOAD 100 PSF
PARTITION LOAD 20 PSF
CORRIDORS (LIVE) 100 PSF
STAIRS (LIVE) 100 PSF
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA
57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COMFOURFRONT
D E S I G N I N C.
Office of Construction and Facilities Management
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
Approved: Project Director
ARCHITECTCONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
16.2330.A08
ALBERTSON ENGINEERING, INC.
315 NORTH MAIN AVENUE, SUITE 200
SIOUX FALLS, SOUTH DAKOTA 57104
PH: (605) 274-0880
FARRIS ENGINEERING
12700 WEST DODGE ROAD
OMAHA, NEBRASKA 68154
PH: (402) 330-5900
TERRASITE DESIGN
1635 DEADWOOD AVENUE
RAPID CITY, SOUTH DAKOTA 57702
PH: (605) 791-1736
11-23-20
5/
/2
9:
:2
A
M
CONSTRUCTION DOCUMENTS
11/23/2020
STRUCTURAL GENERAL NOTES
S-001
Design/Construct Sterile Processing Service- Omaha VA Medical Center
MDRLGF
4101 Woolworth Ave #4199 Omaha, NE 68105Omaha VA Medical Center
22016.2330.A08
1. FRAMING ALONG GRIDS 'A', & 'A.3' (GRIDS '2.3' TO '3.5'), GRID 'B' (GRIDS '2' T0 '7'), GRIDS 'C' & 'D' (GRIDS '2.7' TO '7'), GRID 'F' (GRIDS '2.7' TO '10'), AND GRID 'G', (GRIDS '7' TO '10')
HAVE BEEN DESIGNED TO ACCOMMODATE THE ADDITION OF ONE FLOOR (FUTURE
SURGICAL LEVEL) & ROOF ABOVE THE SPS ADDITION (LEVEL 03). SEE "DESIGN LOADS"
SECTION ON THIS SHEET FOR LOADS THAT CURRENT STRUCTURE HAS BEEN
DESIGNED TO ACCOMMODATE A FUTURE ADDITION.
PROVISIONS FOR FUTURE EXPANSION:
O FE ISS
E
T
13166
LUCAS
G.FRIEDE
R
U O
S
E T
SI
G
DE
R R
PR
E
DA KH OTA
E R
O. NG .
LANO
N G
IN
E
19383
COMPLIANCY REVIEW INCLUDED 2/23/2024
14363
SPECIAL INSPECTION AND TESTING:
1. SPECIAL INSPECTION AND MINIMUM TESTING SHALL BE PERFORMED IN ACCORDANCE WITH 2018 IBC AND ALL REFERENCED MATERIALS AND TABLES.
2. INSPECTION SHALL BE PROVIDED BY AN INDEPENDENT TESTING AGENCY HIRED AT THE OWNER'S EXPENSE. AGENCY INSPECTION PERSONNEL SHALL MEET THE INSPECTOR QUALIFICATIONS FOR EACH MATERIAL ITEM AS INDICATED IN THE SPECIFICATIONS.
3. ANY MATERIAL OR PLACEMENT DEVIATIONS FROM MINIMUMS SHOWN ON THE DRAWINGS OR IN SPECIFICATIONS SHALL BE BROUGHT TO THE ATTENTION OF THE
ENGINEER.
4. IN ADDITION TO THE IBC INSPECTION TABLES, THE INSPECTOR SHALL VERIFY THAT ALL STEEL MAINTAIN ERECTION TOLERANCE OF STRUCTURAL STEEL AND ARCHITECTURALLY EXPOSED STRUCTURAL STEEL WITHIN AISC'S CODE OF STANDARD PRACTICE FOR STEEL BUILDINGS AND BRIDGES.
5. IN ADDITION TO THE CONCRETE IBC INSPECTION TABLE, THE INSPECTOR SHALL VERIFY THAT ALL CONCRETE MAINTAIN TOLERANCES SPECIFIED IN ACI 117-90
STANDARD SPECIFICATIONS FOR TOLERANCES FOR CONCRETE CONSTRUCTION AND MATERIALS.
6. TESTING - ANY FAILED FIELD TEST SHALL BE REPORTED TO THE CONTRACTING OFFICER IMMEDIATELY.
IBC 2018 TABLE 1705.3 REQUIRED SPECIAL INSPECTION
AND TESTS OF CONCRETE CONSTRUCTION
4. INSPECT ANCHORS POST-INSTALLED IN HARDENED CONCRETE MEMBERS.b
10. INSPECT ERECTION OF PRECAST CONCRETE MEMBERS.
A. APPLICATION OF PRESTRESSING FORCES.
8. VERIFY MAINTENANCE OF SPECIFIED CURING TEMPERATURE AND
TECHNIQUES.
6. PRIOR TO CONCRETE PLACEMENT, FABRICATE SPECIMENS FOR STRENGTH TESTS,
PERFORM SLUMP AND AIR CONTENT TESTS, AND DETERMINE THE TEMPERATURE
OF THE CONCRETE.
7. INSPECT CONCRETE AND SHOTCRETE PLACEMENT FOR PROPER
APPLICATION TECHNIQUES
ACI 318: CH. 26.9
ACI 318: 26.10
ACI 318: 26.5.3-26.5.5
ACI 318: 26.5
ASTM C172, ASTM C31, ACI
318: 26.5, 26.12
ACI 318: 17.8.2.4,
ACI 318: 17.8.2
X
X
X
X
X
X
X
ACI 318: 26.11.2
1908.9
1908.6, 1908.7, 1908.8
1908.10
3. INSPECT ANCHORS CAST IN CONCRETE.
2. REINFORCING BAR WELDING:
1. INSPECTION REINFORCEMENT, INCLUDING PRESTRESSING
TENDONS, AND VERIFY PLACEMENT
TYPE
ACI 318 CH 20, 25.2, 25.3,
26.6.1-26.6.3
REFERENCED
STANDARDa
CONTINUOUS
SPECIAL
INSPECTION
X
AWS D1.4,
ACI 318: 26.6.4
IBC REFERENCE
1908.4
X
ACI 318: 17.8.2
5. VERIFY USE OF REQUIRED DESIGN MIX.
ACI 318: CH. 19,
26.4.3, 26.4.4
X
1904.1, 1904.2, 1908.2, 1908.3
12. INSPECT FORMWORK FOR SHAPE, LOCATION AND DIMENSIONS OF THE
CONCRETE MEMBER BEING FORMED.
ACI 318: 26.11.1.2(b)X
9. INSPECT OF PRESTRESSED CONCRETE FOR:
B. GROUTING OF BONDED PRESTRESSING TENDONS.
11. VERIFY IN-SITU CONCRETE STRENGTH, PRIOR TO STRESSING OF TENDONS IN POST-
TENSIONED CONCRETE AND PRIOR TO REMOVAL OF SHORES AND FORMS FROM BEAMS
AND STRUCTURAL SLABS.
X
A. VERIFY WELDABILITY OF REINFORCING BARS OTHER THAN ASTM A706.
X
B. INSPECT SINGLE-PASS FILLET WELDS, MAXIMUM 5/16".
C. INSPECT ALL OTHER WELDS
A. ADHESIVE ANCHORS INSTALLED IN HORIZONTALLY OR UPWARDLLY INCLINED
ORIENTATIONS TO RESIST SUSTAINED TENSION LOADS.
B. MECHANICAL ANCHORS AND ADHESIVE ANCHORS NOT DEFINED IN 4A.
X
X
X
PERIODIC
SPECIAL
INSPECTION
a. WHERE APPLICABLE, SEE SECTION 1705.12, SPECIAL INSPECTIONS FOR SEISMIC RESISTANCE.
b. SPECIFIC REQUIREMENTS FOR SPECIAL INSPECTION SHALL BE INCLUDED IN THE RESEARCH REPORT FOR THE ANCHOR ISSEUD BY AN APPROVED SOURCE IN ACCORDANCE WITH 17.8.2 IN ACI 318, OR OTHER QUALIFICATION PROCEDURES. WHERE SPECIFIC REQUIREMENTS ARE NOT PROVIDED, SPECIAL INSPECTION REQUIREMENTS SHALL BE SPECIFIED BY THE REGISTERED DESIGN PROFESSIONAL AND SHALL BE APPROVED BY THE BUILDING OFFICIAL PRIOR TO THE COMMENCEMENT OF THE WORK.
MATERIAL TESTS.
IN THE ABSENCE OF SUFFICIENT DATA OR DOCUMENTATION PROVIDING EVIDENCE OF CONFORMANCE TO QUALITY STANDARDS FOR MATERIALS IN CHAPTERS 19 AND 20 OF ACI 318, THE BUILDING OFFICIAL SHALL REQUIRE TESTING OF MATERIALS IN ACCORDANCE WITH THE APPROPRIATE STANDARDS AND CRITERIA FOR THE MATERIAL IN CHAPTERS 19 AND 20 OF ACI 318.
TABLE 1.1 INSPECTION OR EXECUTION TASKS
PRIOR TO DECK PLACEMENT
A. VERIFY COMPLIANCE OF MATERIALS (DECK AND ALL DECK ACCESSORIES) WITH CONSTRUCTION
DOCUMENTS, INCLUDING PROFILES, MATERIAL PROPERTIES, AND BASE METAL THICKNESS
PERFORM
B. DOCUMENT ACCEPTANCE OR REJECTION OF DECK AND DECK ACESSORIES
TASK QC QA
PERFORM
PERFORMPERFORM
TABLE 1.2 INSPECTION OR EXECUTION TASKS
AFTER DECK PLACEMENT
A. VERIFY COMPLIANCE OF DECK AND ALL DECK ACCESSORIES INSTALLATION WITH
CONSTRUCTION DOCUMENTS
B. VERIFY DECK MATERIALS ARE REPRESENTED BY THE MILL CERTIFICATIONS THAT COMPLY
WITH THE CONSTRUCTION DOCUMENTS
C. DOCUMENT ACCEPTANCE OR REJECTION OF INSTALLATION OF DECK AND DECK
ACCESSORIES
TASK
PERFORM
QC QA
PERFORM
PERFORMN/A
PERFORMPERFORM
TABLE 1.3 INSPECTION OR EXECUTION TASKS
PRIOR TO WELDING
A. WELDING PROCEDURE SPECIFICATIONS (WPS) AVAILABLE
B. MANUFACTURER CERTIFICATIONS FOR WELDING CONSUMABLES AVAILABLE
C. MATERIAL IDENTIFICATION (TYPE/GRADE)
D. CHECK WELDING EQUIPMENT
TASK
OBSERVE
QC QA
OBSERVE
OBSERVEOBSERVE
OBSERVEOBSERVE
OBSERVEOBSERVE
TABLE 1.4 INSPECTION OR EXECUTION
TASKS DURING WELDING
A. USE OF QUALIFIED WELDERS
B. CONTROL AND HANDLING OF WELDING CONSUMABLES
C. ENVIRONMENTAL CONDITIONS (WIND SPEED, MOISTURE, TEMPERATURE)
D. WPS FOLLOWED
TASK
OBSERVE
QC QA
OBSERVE
OBSERVEOBSERVE
OBSERVEOBSERVE
OBSERVEOBSERVE
NOTE:
• QUALITY CONTROL (QC) SHALL BE PROVIDED BY THE INSTALLER
• QUALITY ASSURANCE (QA) SHALL BE PROVIDED BY THE CERTIFIED TESTING AGENCY
REQUIRED ON
PROJECT
YES
NO
YES
YES
YES
YES
YES
NO
NO
YES
YES
TABLE 1.8 INSPECTION OR EXECUTION TASKS AFTER
MECHANICAL FASTENING
INSPECTION TASKS AFTER MECHANICAL FASTENING
A. CHECK SPACING, TYPE, AND INSTALLATION OF SUPPORT FASTENERS
B. CHECK SPACING, TYPE, AND INSTALLATION OF SIDELAP FASTENERS
C. CHECK SPACING, TYPE, AND INSTALLATION OF PERIMETER FASTENERS
D. VERIFY REPAIR ACTIVITIES
E. DOCUMENT ACCEPTANCE OR REJECTION OF MECHANICAL FASTENERS
TABLE 1.5 INSPECTION OR EXECUTION
TASKS AFTER WELDING
A. VERIFY SIZE & LOCATION OF WELDS, INCLUDING SUPPORT, SIDELAP, & PERIMETER WELDS
B. WELDS MEET VISUAL ACCEPTANCE CRITERIA
C. VERIFY REPAIR ACTIVITIES
D. DOCUMENT ACCEPTANCE OR REJECTION OF WELDS
TASK
PERFORM
QC
PERFORM
PERFORMPERFORM
PERFORMPERFORM
PERFORMPERFORM
TABLE 1.6 INSPECTION OR EXECUTION TASKS PRIOR TO
MECHANICAL FASTENING
A. MANUFACTURER INSTALLATION INSTRUCTIONS AVAILABLE FOR MECHANICAL FASTENERS
B. PROPER TOOLS AVAILABLE FOR FASTENER INSTALLATION
C. PROPER STORAGE FOR MECHANICAL FASTENERS
TASK
OBSERVE
QC
OBSERVE
OBSERVEOBSERVE
OBSERVEOBSERVE
TABLE 1.7 INSPECTION OR EXECUTION TASKS DURING
MECHANICAL FASTENING
A. FASTENERS ARE POSITIONED AS REQUIRED OBSERVE
B. FASTENERS ARE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS
INSPECTION TASKS DURING MECHANICAL FASTENING QC
OBSERVE
OBSERVEOBSERVE
PERFORM
QC
PERFORM
PERFORMPERFORM
PERFORMPERFORM
PERFORMPERFORM
PERFORMPERFORM
STANDARD FOR QUALITY CONTROL AND QUALITY ASSURANCE
FOR THE INSTALLATION OF STEEL DECK
QA
QA
QA
QA
YES
NO
TABLE N5.4-1
INSPECTION TASKS PRIOR TO WELDING
TABLE N5.4-2
INSPECTION TASKS DURING WELDING
AISC 360-16 TABLE N5.4-3
INSPECTION TASKS AFTER WELDING
AISC 360-16 TABLE N5.6-1
INSPECTION TASKS PRIOR TO BOLTING
AISC 360-16 TABLE N5.6-2
INSPECTION TASKS DURING BOLTING
AISC 360-16 TABLE N5.6-3
INSPECTION TASKS AFTER BOLTING
INSPECTION TASKS PRIOR TO WELDING
WELDING PROCEDURE SPECIFICATIONS (WPSs) AVAILABLE
MANUFACTURER CERTIFICATIONS FOR WELDING CONSUMABLES AVAILABLE
MATERIAL IDENTIFICATION (TYPE/GRADE)
WELDER IDENTIFICATION SYSTEM(a)
FIT-UP OF GROOVE WELDS (INCLUDING JOINT GEOMETRY)
• JOINT PREPARATION
• DIMENSIONS (ALIGNMENT, ROOT OPENING, ROOT FACE, BEVEL)
• CLEANLINESS (CONDITION OF STEEL SURFACES)
• TACKING (TACK WELD QUALITY AND LOCATION)
CONFIGURATION AND FINISH OF ACCESS HOLES
FIT-UP OF FILLET WELDS
• DIMENSIONS (ALIGNMENT, GAPS AT ROOT)
• CLEANLINESS (CONDITION OF STEEL SURFACES)
• TACKING (TACK WELD QUALITY AND LOCATION)
CHECK WELDING EQUIPMENT
INSPECTION INTERVAL
USE OF QUALIFIED WELDERS
CONTROL AND HANDLING OF WELDING CONSUMABLES
• PACKAGING
• EXPOSURE CONTROL
NO WELDING OVER CRACKED TACK WELDS
ENVIRONMENTAL CONDITIONS
• WIND SPEED WITHIN LIMITS
• PRECIPITATION AND TEMPERATURE
WPS FOLLOWED
• SETTINGS ON WELDING EQUIPMENT
• TRAVEL SPEED
• SELECTED WELDING MATERIALS
• SHIELDING GAS TYPE/FLOW RATE
• PREHEAT APPLIED
• INTERPASS TEMPERATURE MAINTAINED (MIN/MAX)
• PROPER POSITION (F, V, H, OH)
WELDING TECHNIQUES
• INTERPASS AND FINAL CLEANING
• EACH PASS WITHIN PROFILE LIMITATIONS
• EACH PASS MEETS QUALITY REQUIREMENTS
(a) THE FABRICATOR OR ERECTOR, AS APPLICABLE, SHALL MAINTAIN A SYSTEM BY WHICH A WELDER WHO HAS WELDED A JOINT OR
MEMBER CAN BE IDENTIFIED. STAMPS, IF USED, SHALL BE THE LOW-STRESS TYPE.
P
P
O
O
O
O
O
O
O
O
O
O
O
O
WELDS CLEANED
SIZE, LENGTH AND LOCATION OF WELDS
WELDS MEET VISUAL ACCEPTANCE CRITERIA:
• CRACK PROHIBITION
• WELD/BASE-METAL FUSION
• CRATER CROSS SECTION
• WELD PROFILES
• WELD SIZE
• UNDERCUT
• POROSITY
ARC STRIKES
k-AREA(a)
BACKING REMOVED AND WELD TABS REMOVED (IF REQUIRED)
REPAIR ACTIVITIES
DOCUMENT ACCEPTANCE OR REJECTION OF WELDED JOINT OR MEMBER
O
P
P
P
P
P
P
O
(a)WHEN WELDING OF DOUBLE PLATES, CONTINUITY PLATES OR STIFFENERS HAS BEEN PERFORMED IN THE k-AREA, VISUALLY INSPECT THE WEB k-AREA FOR CRACKS WITHIN 3" (75 mm) OF THE WELD.
(b) AFTER ROLLED HEAVY SHAPES (SEE SECTION A3.1c) AND BUILT-UP HEAVY SHAPES (SEE SECTION A3.1d) ARE WELDED, VISUALLY
INSPECT THE WELD ACCESS HOLE FOR CRACKS.
INSPECTION TASKS PRIOR TO BOLTING
MANUFACTURER'S CERTIFICATIONS AVAILABLE FOR FASTENER MATERIALS
FASTENER ASSEMBLIES PLACED IN ALL HOLES AND WASHERS AND NUTS ARE
POSITIONED AS REQUIRED
O
O
O
O
O
P
O
O
O
O
O
DOCUMENT ACCEPTANCE OR REJECTION OF BOLTED CONNECTIONS P
FASTENERS MARKED IN ACCORDANCE WITH ASTM REQUIREMENTS
CORRECT FASTENERS SELECTED FOR THE JOINT DETAIL (GRADE, TYPE, BOLT LENGTH IF
THREADS ARE TO EXCLUDED FROM SHEAR PLANE)
CORRECT BOLTING PROCEDURE SELECTED FOR JOINT DETAIL
CONNECTING ELEMENTS, INCLUDING THE APPROPRIATE FAYING SURFACE CONDITION AND
HOLE PREPARATION, IF SPECIFIED, MEET APPLICABLE REQUIREMENTS
PRE-INSTALLATION VERIFICATION TESTING BY INSTALLATION PERSONNEL
OBSERVED AND DOCUMENTED FOR FASTENER ASSEMBLIES AND METHODS USED
PROTECTED STORAGE PROVIDED FOR BOLTS, NUTS, WASHERS AND OTHER
FASTENER COMPONENTS
JOINT BROUGHT TO THE SNUG-TIGHT CONDITION PRIOR TO THE PRETENSIONING
OPERATION
FASTENER COMPONENT NOT TURNED BY THE WRENCH PREVENTED FROM ROTATING
FASTENERS ARE PRETENSIONED IN ACCORDANCE WITH THE RCSC SPECIFICATION,
PROGRESSING SYSTEMATICALLY FROM THE MOST RIGID POINT TOWARD THE FREE
EDGES
• O-OBSERVE THESE ITEMS ON A RANDOM BASIS. OPERATIONS NEED NOT BE DELAYED PENDING THESE INSPECTIONS.
P-PERFORM THESE TASKS FOR EACH WELDED JOINT OR MEMBER.
• OBSERVATION OF WELDING OPERATIONS AND VISUAL INSPECTION OF IN-PROCESS AND COMPLETED WELDS SHALL BE THE PRIMARY METHOD TO CONFIRM THAT THE MATERIALS, PROCEDURES AND WORKMANSHIP ARE IN CONFORMANCE WITH THE CONSTRUCTION
DOCUMENTS.
• FOR STRUCTURES IN RISK CATEGORY III/IV (ASCE/SEI 7, TABLE 1.5-1), ULTRASONIC TESTING SHALL BE PERFORMED ON ALL COMPLETE-JOINT- PENETRATION GROOVE WELDS SUBJECT TO TRANSVERSELY APPLIED TENSION LOADING IN BUTT, T- AND CORNER JOINTS, IN MATERIALS
5/16" (8 MM) THICK OR GREATER.
• ALL NONDESTRUCTIVE TESTING OF WELDED JOINTS SHALL BE DOCUMENTED.
• SEE AISC360-16 CHAPTER N FOR ADDITIONAL WELD INSPECTION REQUIREMENTS.
• SEE AISC360-16 CHAPTER N FOR ADDITIONAL BOLT INSPECTION REQUIREMENTS.
• EXPOSED CUT SURFACES OF GALVANIZED STRUCTURAL STEEL MAIN MEMBERS AND EXPOSED CORNERS OF RECTANGULAR HSS SHALL BE
VISUALLY INSPECTED FOR CRACKS SUBSEQUENT TO GALVANIZING.
• INSPECTION SHALL OCCUR DURING THE PLACEMENT OF ANCHOR RODS AND OTHER EMBEDMENTS SUPPORTING STRUCTURAL STEEL FOR COMPLIANCE WITH THE CONSTRUCTION DOCUMENTS, INCLUDING DIAMETER, GRADE, TYPE AND LENGTH OF THE ANCHOR ROD OR
EMBEDDED ITEM, AND THE EXTENT OR DEPTH OF EMBEDMENT INTO THE CONCRETE.
• FABRICATED STEEL AND ERECTED STEEL FRAMES, AS APPROPRIATE, SHALL BE INSPECTED FOR COMPLIANCE WITH THE DETAILS SHOWN ON THE CONSTRUCTION DOCUMENTS, INCLUDING BRACES, STIFFENERS, MEMBER LOCATIONS AND PROPER JOINT DETAIL APPLICATION.
INSPECTION TASKS DURING BOLTING
INSPECTION TASKS AFTER BOLTING
INSPECTION TASKS DURING WELDING
INSPECTION TASKS AFTER WELDING
STEEL CONSTRUCTION
WELD ACCESS HOLES IN ROLLED HEAVY SHAPES AND BUILT-UP HEAVY SHAPES(b)
NO PROHIBITED WELDS HAVE BEEN ADDED WITHOUT THE APPROVAL OF THE EOR
YES
PLACEMENT AND INSTALLATION OF STEEL HEADED STUD ANCHORS P
WELDER QUALIFICATION RECORDS AND CONTINUITY RECORDS P YES
FIT-UP OF CJP GROOVE WELDS OF HSS T-, Y- AND K-JOINTS WITHOUT BACKING
• JOINT PREPARATIONS
• DIMENSIONS (ALIGNMENT, ROOT OPENING, ROOT FACE, BEVEL)
• CLEANLINESS (CONDITION OF STEEL SURFACES)
• TACKING (TACK WELD QUALITY AND LOCATION)
P
REQUIRED…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .