This document is a Technical Questions and VA Response Tracking Sheet for Solicitation #36C77625R0063, a VA construction project for a Sterile Processing Service in Omaha, Nebraska. The document details critical site-specific considerations for construction near sensitive medical equipment, particularly MRI and nuclear medicine areas, with strict guidelines on work practices. Key technical requirements include prohibiting overhead lifts during business hours, avoiding significant vibrations that could disrupt medical imaging equipment, and mandating separate personnel for specific project roles - specifically requiring distinct individuals for Superintendent, Site Safety and Health Officer (SSHO), and Quality Control (QAQC) positions.

The solicitation involves specific operational constraints around medical imaging spaces, with VA emphasizing vibration sensitivity of MRI equipment and potential image disruption from construction activities. Additional administrative details include the VA's commitment to providing a document exchange service post-award, clarification on sales tax exemption (not provided), and confirmation of no existing roof warranty. The project is being managed by the Department of Veterans Affairs Technology Acquisition Center in Austin, with the construction focused on enhancing sterile processing services within VISN 23's medical infrastructure.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--636-502 Construct Sterile Processing Service VISN 23, newest first.
File Type Posted
Attachment 2 - Attachment 22 - WD - NEW20250057 Rev 7 - 8-1-25.pdf PDF
36C77625R0063 0005.docx DOCX document
Attachment 1 - RFP 36C77625R0063 Tech Questions - dated 8-7-25.docx DOCX document
36C77625R0063 0004.docx DOCX document
Addendum 001 Division 27 - Communications - dated 7-31-25.pdf PDF
Attachment 1 - RFP 36C77625R0063 Tech Questions - dated 7-31-25.docx DOCX document
36C77625R0063 0003.docx DOCX document
36C77625R0063 0002.docx DOCX document
Attachment 1 - Sign-In Sheet - 636-502 Construct SPS - Omaha 7-7-25.pdf PDF
36C77625R0063 0001.docx DOCX document
Attachment 03 - Set 1_G Series_Part3.pdf PDF
Attachment 03 - Set 1_G Series_Part4.pdf PDF
Attachment 10 - Set 8_Structure.pdf PDF
Attachment 11 - Set 9_Mech1.pdf PDF
Attachment 14 - Set 12_Electrical.pdf PDF
Attachment 16 - VHA ICRA - 6-25-25.pdf PDF
Attachment 02 - Vol 2 Combined Specs - FINAL.pdf PDF
Attachment 04 - Set 2_Civil.pdf PDF
Attachment 07 - Set 5_Arch3.pdf PDF
Attachment 09 - Set 7_Equipment.pdf PDF
Attachment 13 - Set 11_Plumbing.pdf PDF
Attachment 01 - Vol 1 Combined Specs - FINAL.pdf PDF
Attachment 03 - Set 1_G Series_Part1.pdf PDF
Attachment 05 - Set 3_Arch1.pdf PDF
Attachment 06 - Set 4_Arch2.pdf PDF
Attachment 03 - Set 1_G Series_Part2.pdf PDF
Attachment 08 - Set 6_Arch4.pdf PDF
Attachment 12 - Set 10_Mech2.pdf PDF
Attachment 15 - Set 13_Fire Protect.pdf PDF
Attachment 19 - Subcontractor Information and Consent Form.docx DOCX document
Attachment 22 - WD - NE20250057 Rev 4 - 5-16-25.pdf PDF
36C77625R0063.docx DOCX document
Attachment 17 - Project Information Sheet for Contractors.docx DOCX document
Attachment 21 - Site Visit Instructions - Construct SPS - Omaha.docx DOCX document
Attachment 20 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 18 - PPQ.docx DOCX document
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION # 36C77625R0063

PROJECT NAME: 636-502 Construct Sterile Processing Service – Omaha NE

TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

Item No.
QUESTION
GOVERNMENT RESPONSE
1
Are there any special and site-specific considerations or requirements we should be aware of when performing construction work near the MRI?
site specific considerations - no overhead lifts over occupied space.
2
Are there any restrictions on the hours we are allowed to work near the MRI, or should we assume standard construction hours?
Please see note in #3. No overhead crane lifts during business hours or when the space is occupied
3
Do we need to be aware of any vibration-related restrictions or limitations for work near the MRI?
Noise levels during patient care and the potential for anything heavy/unsecure coming through the ceiling are concerns for the entire area (Nuc Med, MRI, Ultrasound, office spaces). Considerations for Nuc Med SPECT and PET:

• The cameras have crystals that need to remain stable, but it would take fairly significant vibration to cause artifacts on the images.

• The MRI is Very susceptible to vibrations, drilling/jackhammering on the grounds around, or on the roof above have potential to cause issues with images and disrupt the magnetic field and frequencies, which may cause issues with the machines

4
On some projects submittal exchange is provided for the project by The VA. It does not appear to specify if we will be required to use Submittal Exchange on this project. Can the VA verify if we are required to use Submittal Exchange or if the VA is providing any online submittal platform for this project?
The VA will make sure a document exchange service is available once the project is awarded
5
Specification section 01 35 26 requires the Prime Contractor to provide an SSHO for the project and that individual is to be on site any time construction activities are occurring. It is unclear from the specifications if the SSHO may be a dual hat employee that also serves as the Superintendent for the project. Can the VA please clarify if they are requiring separate individuals to perform the role of SSHO and the role of Superintendent?
No, they need to be separate. A sperate SSHO, QAQC and Superintendence.
6
Please clarify if a separate individual is required to perform the role of Construction Quality Control or can that be performed by the superintendent?
No, they need to be separate. A separate SSHO, QAQC and Superintendent.
7
Paragraph 3.4.B of 01 45 00 Quality control also states that the CQCSM can also have duties as the project superintendent. Can the VA please clarify that one individual can perform both duties on this project?
No, they need to be separate. A sperate SSHO, QAQC and Superintendent.
8
Can you state the specific roles, Superintendent, SSHO, and CQC/QCM that need to be separate individuals?
No, they need to be separate. A separate SSHO, QAQC and Superintendent.
9
Will the VA be issuing state of Nebraska sales tax exempt forms on this project?
No. Please refer to section 4.13 Special Notes Regarding FAR 52.229-3: Federal, State and Local Taxes.
10
Is there an existing roof warranty? If so, please provide the roofing manufacturer’s information?
No existing roof warranty