This solicitation is for an indefinite-delivery, indefinite-quantity job order contract to provide general construction and repair services at various Naval Facilities Engineering Command Washington locations. The contractor shall execute projects through task orders primarily within the NAVFAC Washington area of responsibility, including the metropolitan areas of Washington DC, Maryland and Virginia, as well as other NAVFAC locations within the continental United States. Work may involve minor construction, alteration and design-build or design-bid-build services. The contractor shall provide all material, labor, equipment and incidentals for quality construction at predetermined unit prices and bid price coefficients. The solicitation is set aside for eligible 8(a) construction contractors.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Regional General Construction JOC Contract FY24JOC
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
08/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.1053 Respirable Crystalline Silica
29 CFR 1910.1200 Hazard Communication
29 CFR 1926.1153 Respirable Crystalline Silica
40 CFR 50 National Primary and Secondary Ambient Air Quality Standards
40 CFR 64 Compliance Assurance Monitoring
40 CFR 82 Protection of Stratospheric Ozone
40 CFR 112 Oil Pollution Prevention
40 CFR 122.26 Storm Water Discharges (Applicable to State NPDES Programs, see section 123.25)
40 CFR 241 Guidelines for Disposal of Solid Waste
40 CFR 243 Guidelines for the Storage and Collection of Residential, Commercial, and Institutional Solid Waste
40 CFR 258 Subtitle D Landfill Requirements
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 261.7 Residues of Hazardous Waste in Empty Containers
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 262.11 Hazardous Waste Determination and Recordkeeping
40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
SECTION 01 57 19 Page 1
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities
40 CFR 268 Land Disposal Restrictions
40 CFR 273 Standards for Universal Waste Management
40 CFR 273.2 Standards for Universal Waste Management - Batteries
40 CFR 273.4 Standards for Universal Waste Management - Mercury Containing Equipment
40 CFR 273.5 Standards for Universal Waste Management - Lamps
40 CFR 273.6 Applicability - Aerosol Cans
40 CFR 279 Standards for the Management of Used Oil
40 CFR 300 National Oil and Hazardous Substances Pollution Contingency Plan
40 CFR 300.125 National Oil and Hazardous Substances Pollution Contingency Plan - Notification and Communications
40 CFR 355 Emergency Planning and Notification
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 172.101 Hazardous Material Regulation-Purpose and Use of Hazardous Material Table
49 CFR 173 Shippers - General Requirements for Shipments and Packagings
49 CFR 178 Specifications for Packagings
1.2 DEFINITIONS
1.2.1 Class I and II Ozone Depleting Substance (ODS)
Class I ODS is defined in Section 602(a) of The Clean Air Act. A list of
SECTION 01 57 19 Page 2
Class I ODS can be found on the EPA website at the following weblink.
https://www.epa.gov/ozone-layer-protection/ozone-depleting-substances.
Class II ODS is defined in Section 602(s) of The Clean Air Act. A list of Class II ODS can be found on the EPA website at the following weblink.
https://www.epa.gov/ozone-layer-protection/ozone-depleting-substances.
1.2.2 Contractor Generated Hazardous Waste
Contractor generated hazardous waste is materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e., methyl ethyl ketone, toluene), waste thinners, excess paints, excess solvents, waste solvents, excess pesticides, and contaminated pesticide equipment rinse water.
1.2.3 Electronics Waste
Electronics waste is discarded electronic devices intended for salvage, recycling, or disposal.
1.2.4 Environmental Pollution and Damage
Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life;
affect other species of importance to humankind; or degrade the environment aesthetically, culturally or historically.
1.2.5 Environmental Protection
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
1.2.6 Hazardous Debris
As defined in paragraph SOLID WASTE, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) in accordance with 40 CFR 261. Hazardous debris also includes debris that exhibits a characteristic of hazardous waste in accordance with
40 CFR 261.
1.2.7 Hazardous Materials
Hazardous material is any material that: Is defined in 49 CFR 171, listed in 49 CFR 172, regulated as a hazardous material in accordance with 49 CFR 173; or requires a Safety Data Sheet (SDS) in accordance with 29 CFR 1910.1200; or during end use, treatment, handling, packaging, storage, transportation, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste as defined by 40 CFR 261 Subparts A, B, C, or D. Designation of a material by this definition, when separately regulated or controlled by other sections or
SECTION 01 57 19 Page 3 directives, does not eliminate the need for adherence to that hazard-specific guidance which takes precedence over this section for "control" purposes. Such material includes ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs).
1.2.8 Hazardous Waste
Hazardous Waste is any material that meets the definition of a solid waste and exhibits a hazardous characteristic (ignitability, corrosivity, reactivity, or toxicity) as specified in 40 CFR 261, Subpart C, or contains a listed hazardous waste as identified in 40 CFR 261, Subpart D, or meets a state, local, or host nation definition of a hazardous waste.
1.2.9 Land Application
Land Application means spreading or spraying discharge water at a rate that allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "waters of the United States" must occur.
Comply with federal, state, and local laws and regulations.
1.2.10 Municipal Separate Storm Sewer System (MS4) Permit
MS4 permits are those held by municipalities or installations to obtain NPDES permit coverage for their stormwater discharges.
1.2.11 National Pollutant Discharge Elimination System (NPDES)
The NPDES permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.
1.2.12 Oily Waste
Oily waste are those materials that are, or were, mixed with Petroleum, Oils, and Lubricants (POLs) and have become separated from that POLs. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, POLs and may be appropriately tested and discarded in a manner which is in compliance with other state and local requirements.
This definition includes materials such as oily rags, "kitty litter" sorbent clay and organic sorbent material. These materials may be land filled provided that: It is not prohibited in other state regulations or local ordinances; the amount generated is "de minimus" (a small amount); it is the result of minor leaks or spills resulting from normal process operations; and free-flowing oil has been removed to the practicable extent possible. Large quantities of this material, generated as a result of a major spill or in lieu of proper maintenance of the processing equipment, are a solid waste. As a solid waste, perform a hazardous waste determination prior to disposal. As this can be an expensive process, it is recommended that this type of waste be minimized through good housekeeping practices and employee education.
SECTION 01 57 19 Page 4
1.2.13 Regulated Waste
Regulated waste are solid wastes that have specific additional federal, state, or local controls for handling, storage, or disposal.
1.2.14 Sediment
Sediment is soil and other debris that have eroded and have been transported by runoff water or wind.
1.2.15 Solid Waste
Solid waste is a solid, liquid, semi-solid or contained gaseous waste. A solid waste can be a hazardous waste, non-hazardous waste, or non-Resource Conservation and Recovery Act (RCRA) regulated waste. Types of solid waste typically generated at construction sites may include:
1.2.15.1 Debris
Debris is non-hazardous solid material generated during the construction, demolition, or renovation of a structure that exceeds 2.5-inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (for example, cobbles and boulders), broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.
1.2.15.2 Green Waste
Green waste is the vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.
1.2.15.3 Material Not Regulated As Solid Waste
Material not regulated as solid waste is nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;
suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.
1.2.15.4 Non-Hazardous Waste
Non-hazardous waste is waste that is excluded from, or does not meet, hazardous waste criteria in accordance with 40 CFR 261.
1.2.15.5 Recyclables
Recyclables are materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable. It also includes commercial-grade refrigeration equipment with Freon removed, household appliances where the basic material content is metal, clean polyethylene terephthalate bottles, cooking oil, used fuel oil, textiles, high-grade paper products and corrugated cardboard, stackable pallets in good condition, clean crating
SECTION 01 57 19 Page 5 material, and clean rubber/vehicle tires. Metal meeting the definition of lead contaminated or lead based paint contaminated may not be included as recyclable if sold to a scrap metal company. Paint cans that meet the definition of empty containers in accordance with 40 CFR 261.7 may be included as recyclable if sold to a scrap metal company.
1.2.15.6 Surplus Soil
Surplus soil is existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars, and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included and must be managed in accordance with paragraph HAZARDOUS MATERIAL MANAGEMENT.
1.2.15.7 Scrap Metal
This includes scrap and excess ferrous and non-ferrous metals such as reinforcing steel, structural shapes, pipe, and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.
1.2.15.8 Wood
Wood is dimension and non-dimension lumber, plywood, chipboard, hardboard.
Treated or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included. Treated wood includes, but is not limited to, lumber, utility poles, crossties, and other wood products with chemical treatment.
1.2.16 Surface Discharge
Surface discharge means discharge of water into drainage ditches, storm sewers, or creeks meeting the definition of "waters of the United States".
Surface discharges from construction sites are discrete, identifiable sources and require a permit from the governing agency. Comply with federal, state, and local laws and regulations.
1.2.17 Wastewater
Wastewater is the used water and solids that flow through a sanitary sewer to a treatment plant.
1.2.17.1 Stormwater
Stormwater is any precipitation in an urban or suburban area that does not evaporate or soak into the ground, but instead collects and flows into storm drains, rivers, and streams.
1.2.18 Waters of the United States
Waters of the United States means Federally jurisdictional waters, including wetlands, that are subject to regulation under Section 404 of the Clean Water Act or navigable waters, as defined under the Rivers and Harbors Act.
1.2.19 Wetlands
Wetlands are those areas that are inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and that
SECTION 01 57 19 Page 6 under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions.
1.2.20 Universal Waste
The universal waste regulations streamline collection requirements for certain hazardous wastes in the following categories: batteries, pesticides, mercury-containing equipment (for example, thermostats), and lamps (for example, fluorescent bulbs). The rule is designed to reduce hazardous waste in the municipal solid waste (MSW) stream by making it easier for universal waste handlers to collect these items and send them for recycling or proper disposal. These regulations can be found at
40 CFR 273.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Preconstruction Survey
Regulatory Notifications; G
Environmental Manager Qualifications; G
Employee Training Records; G
Environmental Protection Plan; G
Dirt and Dust Control Plan; G
Solid Waste Management Permit; G
Stormwater Pollution Prevention Plan (SWPPP); G
Stormwater Notice of Intent (for NPDES coverage under the general permit for construction activities); G
Spill Prevention Control And Countermeasure (SPCC) Plan; G
SD-06 Test Reports
Monthly Solid Waste Disposal Report; G
Laboratory Analysis
SD-07 Certificates
ECATTS Certificate Of Completion; G
Employee Training Records; G
SD-11 Closeout Submittals Regulatory Notifications; G
SECTION 01 57 19 Page 7
Assembled Employee Training Records; G
Solid Waste Management Permit; G
Waste Determination Documentation; G
Project Solid Waste Disposal Documentation Report; G
Sales Documentation; G
Hazardous Waste/Debris Management; G
Disposal Documentation for Hazardous and Regulated Waste; G
Contractor Hazardous Material Inventory Log; G
1.4 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during construction practice.
Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; and where required by law, the laboratories must be certified.
1.4.1 Training in Environmental Compliance Assessment Training and Tracking System (ECATTS)
1.4.1.1 Personnel Requirements
The QC Manager is responsible for environmental compliance on projects unless an Environmental Manager is named. The QC Manager (and alternate QC Manager)or Environmental Manager, must complete applicable ECATTS training modules (installation specific or general) prior to starting respective portions of on-site work under this Contract. If personnel changes occur for any of these positions after starting work, replacement personnel must complete applicable ECATTS training within 14 days of assignment to the project.
1.4.1.2 Certification
Submit an ECATTS certificate of completion for personnel who have completed the required ECATTS training. This training is web-based and can be accessed from any computer with Internet access using the following instructions.
Register for NAVFAC Environmental Compliance Assessment, Training, and Tracking System, by logging on to https://environmentaltraining.ecatts.com/.
SECTION 01 57 19 Page 8
Obtain the password for registration from the Contracting Officer.
1.4.1.3 Refresher Training
This training has been structured to allow contractor personnel to receive credit under this contract and to carry forward credit to future contracts. Ensure the QC Manager (and alternate QC Manager) or Environmental Manager review their training plans for new modules or updated training requirements prior to beginning work. Some training modules are tailored for specific state regulatory requirements; therefore, Contractors working in multiple states will be required to retake modules tailored to the state where the contract work is being performed.
ECATTS is available for use by all contractor and subcontractor personnel associated with this project. These other personnel are encouraged (but not required) to take the training and may do so at their discretion.
1.4.2 Conformance with the Environmental Management System
Perform work under this contract consistent with the policy and objectives identified in the installation's Environmental Management System (EMS).
Perform work in a manner that conforms to objectives and targets of the environmental programs and operational controls identified by the EMS.
Support Government personnel when environmental compliance and EMS audits are conducted by escorting auditors at the Project site, answering questions, and providing proof of records being maintained. Provide monitoring and measurement information as necessary to address environmental performance relative to environmental, energy, and transportation management goals. In the event an EMS nonconformance or environmental noncompliance associated with the contracted services, tasks, or actions occurs, take corrective and preventative actions. In addition, employees must be aware of their roles and responsibilities under the installation EMS and of how these EMS roles and responsibilities affect work performed under the contract.
Coordinate with the installation's EMS coordinator to identify training needs associated with environmental aspects and the EMS, and arrange training or take other action to meet these needs. Provide training documentation to the Contracting Officer. The Installation Environmental Office will retain associated environmental compliance records. Make EMS Awareness training completion certificates available to Government auditors during EMS audits and include the certificates in the Employee Training Records. See paragraph EMPLOYEE TRAINING RECORDS.
1.5 QUALITY ASSURANCE
1.5.1 Preconstruction Survey and Protection of Features
Perform a preconstruction Survey of the project site with the Contracting Officer, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.
1.5.2 Regulatory Notifications
Provide regulatory notification requirements in accordance with federal, state and local regulations. In cases where the Government will also provide public notification (such as stormwater permitting), coordinate with the Contracting Officer. Submit copies of regulatory notifications to the Contracting Officer prior to commencement of work activities.
SECTION 01 57 19 Page 9
Typically, regulatory notifications must be provided for the following (this listing is not all-inclusive): demolition, renovation, NPDES defined site work, construction, removal or use of a permitted air emissions source, and remediation of controlled substances (asbestos, hazardous waste, lead paint).
1.5.3 Environmental Brief
Attend an environmental brief to be included in the preconstruction meeting. Provide the following information: types, quantities, and use of hazardous materials that will be brought onto the installation; and types and quantities of wastes/wastewater that may be generated during the Contract. Discuss the results of the Preconstruction Survey at this time.
Prior to initiating any work on site, meet with the Contracting Officer and installation Environmental Office to discuss the proposed Environmental Protection Plan (EPP) or equipment local requirement. Develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as mitigation measures), and other measures to be taken.
1.5.4 Environmental Manager
Designate an on-site Environmental Manager responsible for overseeing the environmental goals for the project and implementing procedures for environmental protection. These duties may be combined with the Project Quality Control Manager duties unless specified otherwise in the Task Order.
1.5.4.1 Duties
The Environmental Manager shall be responsible for the following:
a. Compliance with applicable federal, state, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan.
c. Implementation of the Indoor Air Quality (IAQ) Management Plan.
d. Implementation of the Environmental Protection Plan.
e. Environmental training for Contractor personnel in accordance with their position requirements.
f. Monitoring and documentation of environmental procedures.
1.5.4.2 Qualifications
Minimum 5 years construction experience on projects of similar size and scope; minimum 2 years experience with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs); familiarity with environmental regulations applicable to construction operations.
1.5.5 Employee Training Records
Where applicable, prepare and maintain employee training records throughout the term of the contract meeting applicable 40 CFR requirements. The
SECTION 01 57 19 Page 10
Contractor will ensure every employee completes a program of classroom instruction or on-the-job training that teaches them to perform their duties in a way that ensures compliance with Federal, State and local regulatory requirements for RCRA Large Quantity Generator. The Contractor will provide a Position Description for each employee, by subcontractor, based on the Davis-Bacon Wage Rate designation or other equivalent method, evaluating the employee's association with hazardous and regulated wastes.
This Position Description will include training requirements as defined in 40 CFR 265 for a Large Quantity Generator facility. Submit these training records to the Contracting Officer at the conclusion of the project, unless otherwise directed.
1.5.6 Non-Compliance Notifications
The Contracting Officer will notify the Contractor in writing of any observed noncompliance with federal, state or local environmental laws or regulations, permits, and other elements of the Contractor's EPP. After receipt of such notice, inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. FAR 52.242-14 Suspension of Work provides that a suspension, delay, or interruption of work due to the fault or negligence of the Contractor allows for no adjustments to the contract for time extensions or equitable adjustments. In addition to a suspension of work, the Contracting Officer may use additional authorities under the contract or law.
1.6 ENVIRONMENTAL PROTECTION PLAN
The purpose of the EPP is to present an overview of known or potential environmental issues that must be considered and addressed during construction. Incorporate construction related objectives and targets from the installation's EMS into the EPP. Include in the EPP measures for protecting natural and cultural resources, required reports, and other measures to be taken. Meet with the Contracting Officer or Contracting Officer Representative to discuss the EPP and develop a mutual understanding relative to the details for environmental protection including measures for protecting natural resources, required reports, and other measures to be taken. Submit the EPP within 15 days after Contractor award and not less than 10 days before the preconstruction meeting. Revise the EPP throughout the project to include any reporting requirements, changes in site conditions, or contract modifications that change the project scope of work in a way that could have an environmental impact. No requirement in this section will relieve the Contractor of any applicable federal, state, and local environmental protection laws and regulations.
During Construction, identify, implement, and submit for approval any additional requirements to be included in the EPP. Maintain the current version onsite.
At a minimum, address the following elements in accordance with this section:
a. Identification and contact information for Environmental Manager.
b. General site information, including preconstruction description and photographs.
c. Summary of training program.
SECTION 01 57 19 Page 11
d. Procedures to address water resources.
e. Procedures to address land resources.
f. Procedures to address air resources.
g. Procedures to address fish and wildlife resources.
h. Monitoring and quality control procedures.
Revise and resubmit Plan as required by the Contracting Officer. Approval of Contractor's Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.
1.6.1 General Overview and Purpose
1.6.1.1 Descriptions
A brief description of each specific plan required by environmental permit or elsewhere in this Contract.
1.6.1.2 Duties
The duties and level of authority assigned to the person(s) on the job site who oversee environmental compliance.
1.6.1.3 Procedures
A copy of any standard or project-specific operating procedures that will be used to effectively manage and protect the environment on the project site.
1.6.1.4 Communications
Communication and training procedures that will be used to convey environmental management requirements to Contractor employees and subcontractors.
1.6.1.5 Contact Information
Emergency contact information contact information (office phone number, cell phone number, and e-mail address).
1.6.2 General Site Information
1.6.3 Management of Natural Resources
a. Land resources
b. Tree protection
c. Replacement of damaged landscape features
d. Temporary construction
e. Stream crossings
f. Fish and wildlife resources
SECTION 01 57 19 Page 12
g. Wetland areas
1.6.4 Protection of Historical and Archaeological Resources
a. Objectives
b. Methods
1.6.5 Stormwater Management and Control
a. Ground cover
b. Erodible soils
c. Temporary measures
(1) Structural Practices
(2) Temporary and permanent stabilization
d. Effective selection, implementation and maintenance of Best Management Practices (BMPs).
e. Stormwater Pollution Prevention Plan (SWPPP).
1.6.6 Protection of the Environment from Waste Derived from Contractor Operations
Control and disposal of solid and sanitary waste.
Control and disposal of hazardous waste.
This item consist of the management procedures for hazardous waste to be generated. The elements of those procedures will coincide with the Installation Hazardous Waste Management Plan when within an installation.
The Contracting Officer will provide a copy of the Installation Hazardous Waste Management Plan as applicable.
As a minimum, include the following:
a. List of the types of hazardous wastes expected to be generated
b. Procedures to ensure a written waste determination is made for appropriate wastes that are to be generated
c. Sampling/analysis plan, including laboratory method(s) that will be used for waste determinations and copies of relevant laboratory certifications
d. Methods and proposed locations for hazardous waste accumulation/storage (that is, in tanks or containers)
e. Management procedures for storage, labeling, transportation, and disposal of waste (treatment of waste is not allowed unless specifically noted)
f. Management procedures and regulatory documentation ensuring disposal of hazardous waste complies with Land Disposal Restrictions (40 CFR 268)
SECTION 01 57 19 Page 13
g. Management procedures for recyclable hazardous materials such as lead-acid batteries, used oil, and similar
h. Used oil management procedures in accordance with 40 CFR 279; Hazardous waste minimization procedures
i. Plans for the disposal of hazardous waste by permitted facilities; and Procedures to be employed to ensure required employee training records are maintained.
1.6.7 Prevention of Releases to the Environment
a. Procedures to prevent releases to the environment
b. Notifications in the event of a release to the environment
1.6.8 Regulatory Notification and Permits
List what notifications and permit applications must be made. Some permits require up to 180 days to obtain. Demonstrate that those permits have been obtained or applied for by including copies of applicable environmental permits. The EPP will not be approved until the permits have been obtained.
1.7 LICENSES AND PERMITS
Obtain licenses and permits required for the construction of the project and in accordance with FAR 52.236-7 Permits and Responsibilities. Notify the Government of all equipment that may require permits or special approvals that the Contractor plans to use on site. This paragraph supplements the Contractor's responsibility under FAR 52.236-7 Permits and Responsibilities.
1.8 ENVIRONMENTAL RECORDS BINDER
Maintain on-site a separate three-ring Environmental Records Binder and submit at the completion of the project. Make separate parts within the binder that correspond to each submittal listed under paragraph CLOSEOUT SUBMITTALS in this section.
1.9 SOLID WASTE MANAGEMENT PERMIT
Provide the Contracting Officer with written notification of the quantity of anticipated solid waste or debris that is anticipated or estimated to be generated by construction. Include in the report the locations where various types of waste will be disposed or recycled. Include letters of acceptance from the receiving location or as applicable; submit one copy of the receiving location state and local Solid Waste Management Permit or license showing such agency's approval of the disposal plan before transporting wastes off Government property.
1.9.1 Monthly Solid Waste Disposal Report
Monthly, submit a solid waste disposal report to the Contracting Officer.
For each waste, the report will state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste.
SECTION 01 57 19 Page 14
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 PROTECTION OF NATURAL RESOURCES
Minimize interference with, disturbance to, and damage to fish, wildlife, and plants, including their habitats. Prior to the commencement of activities, consult with the Installation Environmental Office as applicable, regarding rare species or sensitive habitats that need to be protected. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the Contractor's responsibility.
Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work that is consistent with the requirements of the Installation Environmental Office or as otherwise specified.
Confine construction activities to within the limits of the work indicated or specified.
3.1.1 Flow Ways
Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as specified and permitted.
3.1.2 Vegetation
Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor is responsible for any resultant damage.
Protect existing trees that are to remain to ensure they are not injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas. Coordinate with the Contracting Officer and Installation Environmental Office to determine appropriate action for trees and other landscape features scarred or damaged by equipment operations.
3.1.3 Streams
Stream crossings must allow movement of materials or equipment without violating water pollution control standards of the federal, state, and local governments. Construction of stream crossing structures must be in compliance with all required permits including, but not limited to, Clean Water Act Section 404, and Section 401 Water Quality.
The Contracting Officer's approval and appropriate permits are required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges. Obtain Contracting Officer's approval prior to installation.
Remove temporary culverts or bridges upon completion of work, and repair the area to its original condition unless otherwise required by the
SECTION 01 57 19 Page 15
Contracting Officer.
3.2 STORMWATER
Do not discharge stormwater from construction sites to the sanitary sewer.
If the water is noted or suspected of being contaminated, it may only be released to the storm drain system if the discharge is specifically permitted. Obtain authorization in advance from the Installation Environmental Office for any release of contaminated water.
3.2.1 Construction General Permit
Provide a Construction General Permit as required by 40 CFR 122.26 or EPA or State General Permit. Under the terms and conditions of the permit, install, inspect, maintain BMPs, prepare stormwater erosion and sediment control inspection reports, and submit SWPPP inspection reports. Maintain construction operations and management in compliance with the terms and conditions of the general permit for stormwater discharges from construction activities.
3.2.1.1 Stormwater Pollution Prevention Plan
Submit a project-specific Stormwater Pollution Prevention Plan (SWPPP) to the Contracting Officer for approval, within 30 days of Contract Award and prior to the commencement of work. The SWPPP must meet the requirements of 40 CFR 122.26 and the EPA or State General Permit for stormwater discharges from construction sites.
Include the following:
a. Comply with terms of the EPA or state general permit for stormwater discharges from construction activities. Prepare SWPPP in accordance with state or EPA requirements. Use state or EPA guide Developing your Stormwater Pollution Prevention Plan.
b. Select applicable BMPs from EPA Fact Sheets located at https://www.epa.gov/npdes/national-menu-best-management-practices-bmps-stormwater#constr or in accordance with applicable state or local requirements.
c. Include a completed copy of the Notice of Intent, BMP Inspection Report Template, and Stormwater Notice of Termination, except for the effective date.
d. Comply with local additional requirements.
3.2.1.2 Stormwater Notice of Intent for Construction Activities
Prepare and submit the Notice of Intent for NPDES coverage under the general permit for construction activities to the Contracting Officer for review and approval.
Submit the approved NOI and appropriate permit fees onto the appropriate federal or state agency for approval. No land disturbing activities may commence without permit coverage. Maintain an approved copy of the SWPPP at the onsite construction office, and continually update as regulations require, reflecting current site conditions.
Comply with additional state and local requirements.
SECTION 01 57 19 Page 16
3.2.1.3 Inspection Reports
Submit "Inspection Reports" to the Contracting Officer in accordance with EPA or StateConstruction General Permit. Provide Inspection Reports in accordance with local requirements.
3.2.1.4 Stormwater Pollution Prevention Plan Compliance Notebook
Create and maintain a three ring binder of documents that demonstrate compliance with the Construction General Permit. Include a copy of the permit Notice of Intent, proof of permit fee payment, SWPPP and SWPPP update amendments, inspection reports and related corrective action records, copies of correspondence with the EPA or the State Permitting Agency, and a copy of the permit Notice of Termination in the binder. At project completion, the notebook becomes property of the Government.
Provide the compliance notebook to the Contracting Officer.
3.2.1.5 Stormwater Notice of Termination for Construction Activities
Submit a Notice of Termination to the Contracting Officer for approval once construction is complete and final stabilization has been achieved on all portions of the site for which the permittee is responsible. Once approved, submit the Notice of Termination to the appropriate state or federal agency. Prepare as-built topographic survey information required by the permitting agency for certification of the stormwater management system, and provide to the Contracting Officer.
3.2.2 Erosion and Sediment Control Measures
Provide erosion and sediment control measures in accordance with state and local laws and regulations. Preserve vegetation to the maximum extent practicable.
Erosion control inspection reports may be compiled as part of a stormwater pollution prevention plan inspection reports.
3.2.2.1 Erosion Control
Prevent erosion by mulching, Compost Blankets, Geotextiles, or temporary slope drains. Stabilize slopes by chemical stabilization, sodding, seeding, or such combination of these methods necessary for effective erosion control. Use of hay bales is prohibited.
3.2.2.2 Sediment Control Practices
Implement sediment control practices to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Implement sediment control practices prior to soil disturbance and prior to creating areas with concentrated flow, during the construction process to minimize erosion and sediment laden runoff. .
3.2.3 Work Area Limits
Mark the areas that need not be disturbed under this Contract prior to commencing construction activities. Mark or fence isolated areas within the general work area that are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction
SECTION 01 57 19 Page 17 operations are to be conducted during darkness, all markers must be visible in the dark. Personnel must be knowledgeable of the purpose for marking and protecting particular objects.
3.2.4 Contractor Facilities and Work Areas
Place field offices, staging areas, stockpile storage, and temporary buildings in areas designated on the drawings or as directed by the Contracting Officer. Move or relocate the Contractor facilities only when approved by the Government. Provide erosion and sediment controls for onsite borrow and spoil areas to prevent sediment from entering nearby waters. Control temporary excavation and embankments for plant or work areas to protect adjacent areas.
3.2.5 Municipal Separate Storm Sewer System (MS4) Management
Comply with the Installation's MS4 permit requirements when applicable and comply with local requirements.
3.3 SURFACE AND GROUNDWATER
3.3.1 Waters of the United States
Do not enter, disturb, destroy, or allow discharge of contaminants into waters of the United States.
3.4 PROTECTION OF CULTURAL RESOURCES
3.4.1 Archaeological Resources
If, during excavation or other construction activities, any previously unidentified or unanticipated historical, archaeological, and cultural resources are discovered or found, activities that may damage or alter such resources will be suspended. Resources covered by this paragraph include, but are not limited to: any human skeletal remains or burials; artifacts;
shell, midden, bone, charcoal, or other deposits; rock or coral alignments, pavings, wall, or other constructed features; and any indication of agricultural or other human activities. Upon such discovery or find, immediately notify the Contracting Officer so that the appropriate authorities may be notified and a determination made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in impact to or the destruction of these resources. Secure the area and prevent employees or other persons from trespassing on, removing, or otherwise disturbing such resources. The Government retains ownership and control over archaeological resources.
3.5 AIR RESOURCES
Equipment operation, activities, or processes will be in accordance with 40 CFR 64 and state air emission and performance laws and standards.
3.5.1 Preconstruction Air Permits
Notify the Air Program Manager, through the Contracting Officer, at least 6 months prior to bringing equipment, assembled or unassembled, onto the Installation, so that air permits can be secured. Necessary permitting time must be considered in regard to construction activities. Clean Air Act (CAA) permits must be obtained prior to bringing equipment, assembled or unassembled, onto the Installation.
SECTION 01 57 19 Page 18
3.5.2 Oil or Dual-fuel Boilers and Furnaces
Provide product data and details for new, replacement, or relocated fuel fired boilers, heaters, or furnaces to the Installation Environmental Office (Air Program Manager) through the Contracting Officer. Data to be reported include: equipment purpose (water heater, building heat, process), manufacturer, model number, serial number, fuel type (oil type, gas type) size (MMBTU heat input). Provide in accordance with paragraph
PRECONSTRUCTION AIR PERMITS.
3.5.3 Burning
Burning is prohibited on the Government premises.
3.5.4 Class I and II ODS Prohibition
Class I and II ODS as defined and identified herein will not be used in the performance of this contract, nor be provided as part of the equipment .
This prohibition will be considered to prevail over any other provision, specification, drawing, or referenced documents. Regulations related to the protection of stratosphere ozone may be found in 40 CFR 82.
Heating and air conditioning technicians must be certified through an EPA-approved program. Copies of certifications shall be maintained at the employees' place of business and be carried as a wallet card by the technician, as provided by environmental law.
3.5.5 Venting of Refrigerant
Accidental venting of a refrigerant is a release and must be reported immediately to the Contracting Officer. Intentional venting of refrigerants (including most Non-ODS substitute refrigerants) is prohibited per 40 CFR 82.
3.5.6 EPA Certification Requirements
Heating and air conditioning technicians must be certified through an EPA-approved program. Maintain copies of certifications at the employees' places of business; technicians must carry certification wallet cards, as provided by environmental law.
3.5.7 Dust Control
Keep dust down at all times, including during nonworking periods. Sprinkle or treat, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming. Air blowing will be permitted only for cleaning nonparticulate debris such as steel reinforcing bars. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete. Do not unnecessarily shake bags of cement, concrete mortar, or plaster. Since these products contain Crystalline Silica, comply with the applicable OSHA standard, 29 CFR 1910.1053 or 29 CFR 1926.1153 for controlling exposure to Crystalline Silica Dust.
3.5.7.1 Particulates
Dust particles, aerosols and gaseous by-products from construction
SECTION 01 57 19 Page 19 activities, and processing and preparation of materials (such as from asphaltic batch plants) must be controlled at all times, including weekends, holidays, and hours when work is not in progress. Maintain excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and other work areas within or outside the project boundaries free from particulates that would exceed 40 CFR 50, state, and local air pollution standards or that would cause a hazard or a nuisance. Sprinkling, chemical treatment of an approved type, baghouse, scrubbers, electrostatic precipitators, or other methods will be permitted to control particulates in the work area. Sprinkling, to be efficient, must be repeated to keep the disturbed area damp. Provide sufficient, competent equipment available to accomplish these tasks.
Perform particulate control as the work proceeds and whenever a particulate nuisance or hazard occurs. Comply with state and local visibility regulations.
3.5.7.2 Abrasive Blasting
Blasting operations cannot be performed without prior approval of the Installation Air Program Manager. The use of silica sand is prohibited in sandblasting.
Provide tarpaulin drop cloths and windscreens to enclose abrasive blasting operations to confine and collect dust, abrasive agent, paint chips, and other debris. Perform work involving removal of hazardous material in accordance with 29 CFR 1910.
3.5.7.3 Dirt and Dust Control Plan
Submit truck and material haul routes along with a plan for controlling dirt, debris, and dust on base roadways. As a minimum, identify in the plan the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadways.
3.5.8 Odors
Control odors from construction activities. The odors must be in compliance with state regulations and local ordinances and may not constitute a health hazard.
3.6 WASTE MINIMIZATION
Minimize the use of hazardous materials and the generation of waste.
Include procedures for pollution prevention/ hazardous waste minimization in the Hazardous Waste Management Section of the EPP. Obtain a copy of the installation's Pollution Prevention/Hazardous Waste Minimization Plan for reference material when preparing this part of the EPP. If no written plan exists, obtain information by contacting the Contracting Officer. Describe the anticipated types of the hazardous materials to be used in the construction when requesting information.
3.6.1 Salvage, Reuse and Recycle
Identify anticipated materials and waste for salvage, reuse, and recycling. Describe actions to promote material reuse, resale or recycling. To the extent practicable, all scrap metal must be sent for reuse or recycling and will not be disposed of in a landfill.
Include the name, physical address, and telephone number of the hauler, if
SECTION 01 57 19 Page 20 transported by a franchised solid waste hauler. Include the destination and, unless exempted, provide a copy of the state or local permit (cover) or license for recycling.
3.7 WASTE MANAGEMENT AND DISPOSAL
3.7.1 Waste Determination Documentation
Complete a Waste Determination form (provided at the pre-construction conference) for Contractor-derived wastes to be generated. All potentially hazardous solid waste streams that are not subject to a specific exclusion or exemption from the hazardous waste regulations (e.g., scrap metal, domestic sewage) or subject to special rules, (lead-acid batteries and precious metals) must be characterized in accordance with the requirements of 40 CFR 262.11 or corresponding applicable state or local regulations.
Base waste determination on user knowledge of the processes and materials used, and analytical data when necessary. Consult with the Installation environmental staff for guidance on specific requirements. Attach support documentation to the Waste Determination form. As a minimum, provide a Waste Determination form for the following waste (this listing is not exhaustive): oil- and latex -based painting and caulking products, solvents, adhesives, aerosols, petroleum products, and containers of the original materials.
3.7.2 Solid Waste Management
3.7.2.1 Project Solid Waste Disposal Documentation Report
Provide copies of the waste handling facilities' weight tickets, receipts, bills of sale, and other sales documentation.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .